interiew Q's
The following are some sample interview Question s I have taken from the internet, sample
certification Question s,.
1. What is the difference between the stock transfer between two plants belonging to same company
code and those belonging to different company code?
2. What are the fields in Purchasing view?
3. What are the steps in automatic account assignment config.
4. How do you create movement types? What are the steps involved? When will you recommend a
new movement type?
5. What is meant by access sequence? When it is used?
6. How does the PO pick up the pricing schema?
7. What are the steps involved in creating a pricing procedure?
8. What are the types of special stocks available?
9. What are the types of inforecords?
10. What is meant by consignment stock?
11. What are the steps involved in consignment cycle?
12. Tell me about the subcontracting cycle.
13. How is scrap accounted in subcontracting?
14. How are the byproducts taken care of in subcontracting?
15. Tell me about the various movement types and usage.
16. What is meant by scales? Can scales be used in standard purchase order?
17. What is the difference between a contract and a scheduling agreement?
18. How does the system calculate taxes?
19. How does the system calculate nondeductible taxes?
20. What is meant by batches? How can the batches be searched?
21. How is a shelf-life item managed in SAP? What is the full cycle?
22. What are the settings required for quota arrangement?
23. What is meant by MRP Type and lot sizing?
24. Can it be configured in such a way that the external requisitions can also be taken into account
while MRP runs in consumption-based planning if VB is selected as MRP type?
In SAP, a material master record contains all the necessary data required to manage a material.
Material master data includes a description of the material. Description may include things like size,
weight, dimensions etc. Further, this also includes data relating to the control function i.e. industry
sector, material type etc. All the above data can be maintained directly by the user in SAP MM. In
addition to this data, which can be directly maintained by the user. Further, the material master record
also contains some data which is directly maintained by the SAP system such as stock levels, which
are updated on a continous basis.
Q). In SAP what is a component of a module?
The structure of SAP is divided in various modules such as SD, MM, PP, FI, CO etc. Within a module,
there are various components. For example the SD module has the component Sales Order Planning,
SD-SOP. As a general rule the Implementation Guide (IMG), accessed via transaction code [SPRO],
is broken down into modules with the subnodes as components. Thus, individual modules are further
sub-divided into components in SAP.
Q). What is a transaction Code?
In SAP, a transaction code provides a shortcut to a specific function in SAP. The T-code
(transaction code) may be a shortcut to a program or a shortcut to select further data. In SAP,
transactions codes are arranged according to components or modules. For example the T-code ME53
displays the purchase requisition.
Q). What is ASAP?
ASAP stands for Accelerated SAP (ASAP). ASAP is a software tool used for project management in
SAP implementations. Normally, any SAP implementation invloves various phases. ASAP helps in
guiding a SAP implementation project. Thus from the intial stages to the "Go Live" stage, ASAP helps
in streamlining the entire SAP implementation process.
Q). What is the ABAP Workbench?
SAP's graphical programming environment is called ABAP WorkBench. ABAP WorkBench is used to
write ABAP code, design screens, create user interfaces, obtain database information, and debug and
test applications for efficiency. It is essential for developing any ABAP program.
is updated in SAP enabling the billing due list so that goods shipped can be billed.
-----------------------------------------Q). In SAP how does a user execute the MRP run for a material
The entire purpose of MRP is to plan for a material. The MRP can be executed using the transaction
code MD02. MRP Material Requisition Planning can be done for a single material item or a multilevel
plan can be run for a material within a plant. But, what exactly does MRP do. Material Requisition
Planning creates PR purchase requisitions, PO purchase orders, or planned orders for the material.
This is done on the basis of the settings selected in the transactions. To take an example, a particular
material item may be procured externally, in such a case, an MRP run creates requirements for that
material through the respective plant from a sales document.
Such Question s are very popular in SAP interviews both functional as well as technical. I would
suggest you go through the basic material you have on the module you are focusing on. Another
important source of information is SAP help which gives explanations to each and every term.
-------------------------------Q). is What the difference between rescheduling and back order processing?
The Question just requires a candidate to explain the concepts of Rescheduling and Backorder
processing.
Backorder Processing - Backorder processing is the processing of a backorder. Now, a backorder
means a sales order which has not been confirmed in full or has not been confirmed at a certain
delivery date.
Rescheduling - Rescheduling on the other hand is a proposal which can enable confirmed quantities
already assigned to sales orders might be reassigned to other orders. This reassignement may be
required due to an order of higher priority which may require an earlier delivery date.
marketing costs. These cannot be directly attributed to producing the product and so are not included.
The cost of goods sold for a production company will include things like raw materials, energy and
labour used to produce the product. For a retail company such as Marks and Spencer it will be the
total amount they have paid to their suppliers for the products they sell on the shelves.
------------------------------Q) In SAP, is it possible to have a self-defined transaction code?
To start with, yes, self-defined reports, transactions or functions are possible within SAP. There might
be numerous reasons why a company might go in for customized transaction codes or for that matter
reports. To cater to this demand, SAP allows creation of user-defined transaction codes.
Creating a transaction code allows the user to speed up access to specific reports/programs as the
user no longer needs to use transaction code [SA38]. Thus, instead of using T-Code SA38, then
entering the program name or report name and pressing execute, the same can be done directly
through a pre-defined T-Code. The user can then simply use a transaction code, which will
automatically open the program. In SAP custmoized T-codes can be created through transaction code
[SE93].
-----------------------------------Q). What is a functional area in SAP?
In SAP, a functional area is normally assigned to the query. It represents the logical database or tables
with respect to the various linkages/table joins defined. This helpful in defining which tables and fields
the query can reference.
------------------------------Q). In SAP how can a user access object names for which they do not have authorization?
In case a SAP user is trying to execute a transaction code for which he does not have authorization,
he will be given an error message. A user can view the object or transaction which he does not have
authorization using transaction code SU53.
-------------------------------Q). In SAP, what is the transaction code for viewing the update error log?
The "Update Error Log" in SAP can be viewed through Transaction code [SM13].
----------------------------------Q). How does a user access details of a spool in SAP?
A SAP user can access the Spool Administraton Overview Screen through transaction code [SPAD]
while using spools. The screen helps in investigating output devices and request for outputs. A user
can thus access details of a spool from this menu.
-----------------------------------Q): What is a batch input?
SAP provides a facility for updating large amounts of data using a tool. SAP transactions can be
arranged in a specified format and then uploaded into SAP using batch input facility. A user can record
the batch input used for a SAP transaction and then export the batch input recorded to a text file.
Taking an example, in case changes are to be made in finished goods pricing for all the finished
goods, a user can do it easily using the batch input facility.
-----------------------------------Q). What is a variant in SAP?
In SAP, a user can specify various selection parameters while executing a program. These various
selection parameters are called variants in SAP. SAP stores the various selection parameters as
Variants. To take an example, when a query for executing the delivery due list is given, one of the
variants can be shipping points. Such shipping points can be located in a plant or warehouse as have
been defined in the variant i.e. selection parameter.
Q). How can locked entries be viewed in SAP R/3?
In SAP R/3 locked entries can be viewed using the transaction code [SM12]. Transaction [SU01] can
be used to display a list of all the users alongwith the user details. A user can be unlocked in the
system by informinf him/her through the above mentioned transaction code.
Q). What is an IDOC?
IDCO refers to information documents in SAP. Information Documents (IDOCs) are divided into
various categories and types. Each IDOC can be translated into an EDI message, or vice versa, in
order to cater to other systems (R/3, R/2, or third-party software).
SAP R/3 is one of the most popular ERPs today. SAP offers a lot of flexibility to organziations. It can
be implemented to suit business requirement with many customizations. My topic for discussion today
is how Configurable Controls in SAP R/3 can help achieve Sarbanes Oxley Compliance. Controls in
SAP can be classified as Inherent Controls, Configurable Controls, Security Controls, Reporting
Controls and finally Policies and Procedures. An organization which is on SAP can look into the belwo
mentioned SAP configurable controls which will be helpful in Sarbanes Oxley Compliance in the long
run. Configurable Controls in SAP R/3 include 1. Edit Checks
2. Data Entry Validations
3. Document Blocking
4. Tolerance Levels
5. Authorization Groups
6. Payment Blocking
7. Document Types
8. User defined Error / Warning Messages
9. Automatic Posting with predefined posting keys
10. Reason Codes
11. Predefined Master Data
12. SAP Workflow
13. Mandatory and/or System populated fields
---------------------------SAP GUI
SAP Graphical User Interface (GUI)
SAP R/3 has a user interface called the SAP graphical user interface (SAPGUI). The SAPGUI runs on
Windows 3.1/95/98/NT/XP, Motif, OS/2 presentation manager, and Macintosh. Irrespective of the
operating system, all SAPGUIs have the same look and feel. However, SAPGUI interface varies
according to the varsion of SAP / SAPGUI a user is running. In either case there are only very small
changes which SAP has done in tis GUI over the years. A user can configure the GUI according to the
way he wishes. Even the appearance of the menus and screens are configurable.
______________________________________________________________
5. If you use special stock indicators you can create different stock and value updates of a material
for one and the same movement type.
Valuation
Which of the following statements on procuring a material of material type NLAG are
correct?
1. The purchase order must be account assigned.
2. The goods receipt must always be non-valuated.
3. When you enter an invoice, you can change the account assignment as long as the goods
receipt was non-valuated.
4. When the material is for consumption, no document is ever created in Financial Accounting.
Which of the following stock transfers/transfer postings are relevant to valuation?
1. Stock transfer from storage location to storage location within the same plant or company code.
2. Stock transfer from consignment stores of vendor XY to our unrestricted-use stock in storage
location 0001.
3. Transfer posting from stock in quality inspection in storage location 001 to stock in quality
inspection in storage location 0002 within the same plant.
4. Stock transfer of a material from storage location 0001 from plant 0001 to plant 0002. The plants
belong to the same company, however the valuation areas are different (valuation level is plant).
Which of the following statements about valuation classes are true?
1. The valuation class is maintained in the material master record at the storage location level.
With that, a split valuation per storage location is possible.
2. The valuation class is maintained in the material master record at valuation area level. With that,
different account determination is possible for the materials of one material type. For example, you
can have different material stock accounts for different materials of the same material type.
3. The valuation class is a standard class of the classification system. A characteristic of this class
refers to the moving average price or standard price in the accounting view in the material master
record. With that, it is possible to search for materials with similar prices. The search is possible
with direct values, intervals and greater than / less than relationships.
4. The valuation classes will be tied to one or more material types via an account category
reference.
Which of the following statements on price control in the SAP R/3 system are correct?
1. Price control S allows only purchase orders with constant prices. Therefore, for purchased
materials with price control S, you should arrange outline agreements to protect the constant
price.
2. Price control V is recommended for purchased materials.
3. If a goods issue is posted between when you post the goods receipt and when you post the
invoice, and this leads to the total stock being smaller that the quantity to be settled, the system
posts any differences between the purchase order price and the invoice for the quantity consumed
(stock shortage) to a price difference account, irrespective of the price control that the material is
subject to.
4. The importance of price control V depends on whether the material ledger is active or not. If
you are not working with the material ledger, price control V means that you are using the moving
average price. This means that the value of the stock account and the price per price unit is
adjusted for existing stocks.
5. In the case of differences between the purchase order price and the valuation price in the
material master, the difference is posted to a GR/IR clearing account at goods receipt if you are
working with price control S. This is then cleared when the invoice is posted.
2. MRP procedure VV is defined in the material master record; a scheduling agreement exists; a
quota arrangement exists and is defined as relevant to planning; a forecast exists; a planning run
is executed with an appropriate setting for the automatic creation of schedule lines.
3. MRP procedure VV is defined in the material master record; a scheduling agreement exits; a
source list with the scheduling agreement as the supply source is defined as relevant to planning;
a forecast exists; a planning run is executed with an appropriate setting for the automatic creation
of schedule lines.
4. MRP procedure VV is define in the material master record; past consumption values exist; a
scheduling agreement exists; a quota arrangement relevant to planning exists; a forecast exists; a
planning run is executed with an appropriate setting for the automatic creation of schedule lines.
Which MRP procedures are used in consumption-based planning?
1. Forecast-based Planning
2. Material requirements Planning
3. Manual reorder point Planning
4. Systematic materials Planning
5. Time-phased materials Planning
Purchasing
How can a purchasing info record be generated?
1. Manual entry
2. Update from purchase order
3. Update from purchase requisition
4. Update from RFQ
Purchase orders can be outputted (printed or transmitted) in different languages. Where
does the system obtain the information determining the language in which a PO is to be
printed?
1. Customizing setting
2. The language must be specified when you log on to the system. This is then used as the basis
for system printing.
3. You specify the language to be generally used for communication purposes for each vendor in
the vendor master record.
4. The language from the PO header is used.
3. The purpose of the release strategy is to exercise control over the transmission of the purchase
requisition.
In which way can you obtain information on purchase orders issued to a vendor that have
not yet been invoiced?
1. You make use of a list that displays all the purchase orders issued to a certain vendor. You limit
the POs shown on the list to those that have not yet been invoiced by the appropriate definition of
the Scope of List.
2. You make use of a list that displays all the purchase orders issued to a certain vendor. You limit
the POs shown on the list to those that have not yet been invoiced by means of the selection
parameters.
3. The selection parameters and list scopes are predefined by SAP and cannot be changed.
How does the system assign prices to items when creating a purchase order? To what
extent can you use these prices in subsequent purchase orders?
1. You can enter conditions manually. However, you cannot use scale prices.
2. The conditions for the purchase order items are saved as conditions in the info record. The
system then proposes these prices in subsequent purchase orders.
3. Info records that the system created automatically from the purchase order only contain the
reference to the previous purchase order, from which the system determines the conditions.
4. If there is no info record, and if the purchase order item is created with reference to a purchase
requisition item that has a material master record, the system assumes the price from the
purchase requisition.
What does the purchasing document type control?
1. Number assignment
2. Permitted item categories
3. The eligibility of scaled prices in contracts
4. The eligibility of scaled prices in scheduling agreements
5. Which header texts, appendix texts, and item texts are printed
You wish to procure a material using a purchase order. You wish to take delivery of the
material at different times. A graduated discount scale exists for the material. How do you
proceed if you wish to take advantage of the discount arrangement?
A Enter several order items with the same material number and different delivery dates
B Enter one order item with the material number and assign the material to different accounts
C Enter an order item with the material number and create a number of schedule lines
D Enter a number of purchase orders for the material and specify different delivery dates
Invoice Verification
Which options for handling cash discounts are available in R/3?
1. Gross or net posting at the time of goods receipt
2. Gross or net posting at the time of invoice receipt
3. Gross or net posting at the time of purchase order entry
4. Deduction of cash discount during the payment run in Financial Accounting
5. Gross or net posting when the invoice is released
Which of the following statements on purchasing transactions using foreign currencies are
correct?
1. An exchange rate can be entered in the order header. This is only for statistical purposes to be
able to analyze fluctuations.
2. At goods receipt the system uses the current exchange rate.
3. You can configure the system so that it uses the current exchange rate in Invoice Verification.
4. You can configure the system so that it uses the exchange rate from the purchase order in
Invoice Verification.
5. You can configure the system so that it uses the exchange rate from the order header in Invoice
Verification.
What must you take into account if you want to post an invoice before the goods receipt?
What are the consequences of using this procedure?
1. You must set the GR-based invoice verification indicator in the purchase order at the latest.
2. Before you enter the invoice, you must set the GR-based invoice verification indicator in the
vendor master record.
3. The system cannot refer to the quantity to be settled and the corresponding amount. You must
enter this information manually every time.
4. The system identifies a quantity variance and blocks the invoice for payment (provided that the
appropriate tolerance limits are exceeded).
Master Data
Which of the following statements about the material number are true?
1. You can extend the length of the material number to a maximum of 40 characters. You configure
this in Customizing.
2. When you create a material, the system checks if the material number falls within a number
range defined in Customizing, depending on the material type.
3. The system checks the existence of the material number in all transactions that work with
material master records.
4. When you create a new material master record without specifying a material number, the
system always generates a material number automatically.
5. You can use a template to format the material number, which you configure in Customizing. It
applies to all material master records in an R/3 System.
What controls the account group in the vendor master?
1. Account determination
2. Field selection in the vendor master
3. Type of number assignment for vendor master
4. Particular use of vendor master record
Which of the following statements on procuring a material of the material type NLAG are
correct?
A. The purchase order must be acount assigned.
B. The goods receipt must always be unvaluated.
C. when you enter an invoice, you can change the account assignement as long as the goods
receipt was unvaluated.
D. When the material is for consumption, no document is ever created in Financial Acccounting.
ORGANISATIONAL STRUCTURES
1. Which of the following are examples of Organizasional elements in SAP?
(more than one answer can be correct)
1A Company Code
1B Material
1C Vendor
1D Purchase Organisation
1E Plant
MASTER DATA
2. A material master has been created for material 1234 in Plant 1000. You want to extend
the material master to Plant 1100 for Purchasing, Storage and Accounting. Which
transaction would you use?
(more than one answer can be correct)
2A Change Material Master record.
2B Create Material Master record.
2C Extend Material Master record.
2D Display Material Master record.
2E Maintain Material Master record.
PURCHASING
3. You wish to procure a material using a Purchase Order. You wish to take delivery of the
material at different times. A graduated discount scale exists for the material. How do you
proceed if you wish to take advantage of the discount arrangement?
(Only one answer is correct)
3A Enter several order items with the same material number and different delivery dates.
3B Enter one order item with the material number and assign the material to different accounts.
3C Enter an order item with the material number and create a number of schedule lines.
3D Enter a number of purchase orders for the material and specify different delivery dates.
3E Enter an order item with the material number and in the Purchase order header text field you
specify the delivery dates and discount scales.
MATERIALS REQUIREMENTS PLANNING
4. To view the most up to date planning data (available stock, orders, reservations, etc.) on
a material, use the:
(more than one answer can be correct)
4A Stock Overview report.
4B List display of material and accounting documents.
4C MRP list.
4D Stock Requirement list.
4E Standard Analysis for a material
5. A material forecast can be used by the following MRP types:
(Only one answer is correct)
5A Manual Reorder point planning.
5B Automatic reorder point planning.
5C Forecast based planning.
5D Time phased planning.
5E Storage location MRP
6. Materials planning can be set to automatically generate:
(more than one answer can be correct)
6A Contracts.
6B Purchase Requisitions.
6C Purchase Orders.
6D Planned Orders.
6E Delivery Schedules.
7. The following are lot sizing rules available for SAP R/3:
(more than one answer can be correct)
7A Fixed lot size.
7B Replenish to maximum stock level.
7C Weekly lot size.
7D Daily lot size.
7E Economic order quantity.
PURCHASING
8. Purchase Information records can be created or updated from:
(more than one answer can be correct)
8A Purchase Requisitions.
8B Purchase Orders.
8C Quotations.
8D Contracts.
8E Source Lists.
9. Which of the following apply to Purchase Orders?
(more than one answer can be correct)
9A The vendor must be specified in the Purchase Order Header.
9B All materials on a purchase order must be procured through the same purchasing group.
9C All materials on a purchase order must be of the same material group.
9D Discounts and surcharges can be maintained in the document header.
9E Discounts and surcharges can be maintained at line item level.
10. Which of the following is an Account Assignment category?
(more than one answer can be correct)
16. Which of the following document types can appear in the purchase order history for a
purchase order line item?
(more than one answer can be correct)
16A Another purchase order.
16B A goods receipt material document.
16C A service entry sheet.
16D An invoice.
16E A release procedure.
17. in which ways can purchase requisitions be created?
(more than one answer can be correct)
17A From contracts.
17B From source lists.
17C From material requirements planning.
17D Manually.
INVENTORY MANAGEMENT
23. Reservations can be created for:
(more than one answer can be correct)
23A Goods receipt for purchase order.
23B Goods receipt without a purchase order.
23C Goods issue to a cost centre.
23D S****ping.
23E Transfer of stock from quality inspection to unrestricted stock.
24. Stocks can be withdrawn from the stores for consumption to a cost centre:
(Only one answer is correct)
24A From quality inspection stock.
24B From blocked stock.
24C From goods receipt blocked stock.
24D From unrestricted use stock.
24E From In-Transit stock.
25. Normal stock items that are received with reference to a purchase order can be received
into:
(more than one answer can be correct)
25A Quality inspection stock.
25B Block stock.
25C Goods receipt block stock.
25D Unrestricted use stock.
25E In-Transit stock.
26. Which of the following stocks belong to a vendor, but are stored on your companys
premises?
(more than one answer can be correct)
26A Materials provided to a sub contractor.
26B Vendor consignment stock.
26C Returnable transport packaging.
26D Block stock.
26E Stock in transit.
27. Which of the following stock types can be counted through Physical Inventory
procedure?
(more than one answer can be correct)
27A Unrestricted use stock.
MATERIAL VALUATION
29. Which of the following cab possibly influence the valuation price of a moving average
priced material?
(more than one answer can be correct)
29A Goods receipt for a purchase order.
29B Goods Issue to a cost centre.
29C Invoice verification against a purchase order.
29D Stock transfer between two storage locations in the same plant.
29E Transfer posting from unrestricted use stock to quality inspection.
REPORTS
30. Variants can be used to:
(Only one answer is correct)
30A Define default report formats such as column width and sort sequence.
30B Save reports.
30C Automatically execute reports.
GENERAL
32. In the SAP system a user can operate in the following hierarchies.
(more than one answer can be correct)
32A Service level.
32B Application level.
32C Main menu level.
32D Month.
32E Total stock value.
ORGANIZATIONAL STRUCTURES
33. In cross plant procurement a purchase organisation procures material and services for:
(Only one answer is correct)
33A Several purchasing groups.
33B Multiple plants belonging
33C Multiple plants belonging to the same company code.
33D A single plant belonging to different company codes.
33E One specific plant.
CLASSIFICATION
36. The following terminology applies to the classification system:
(more than one answer can be correct)
36A Object value.
36B Class.
36C Item.
36D Object.
36E Characteristic value.
MATERIALS PLANNING
37. The main aim of materials planning is to determine:
(Only one answer is correct)
PURCHASING
42. Which of the following statements are true with regard to RFQs and Quotations?
(more than one answer can be correct)
42A Each RFQ and quotation must have a separate number.
42B An RFQ can be created manually or with reference to purchase order.
42C By comparing vendor quotations, the system can determine a ranking list.
42D Conditions attached to quotations can be saved as info records.
42E Unsuccessful quotations can automatically be rejected.
43. In the SAP system, the reference document used in the purchasing cycle is the:
(Only one answer is correct)
43A Purchase requisition.
43B Info record.
43C Source list.
43D Purchase Order.
43E None of the above.
44. Which of the following statements are true about SAP purchasing documents?
(more than one answer can be correct)
44A All purchasing documents have header items and line items.
INVENTORY MANAGEMENT
57. In the SAP system, which of the following activities are covered by inventory
Management?
(more than one answer can be correct)
57A Goods issues.
57B Goods Receipts.
57C Reservations.
57D Consignment.
57E Subcontracting.
58. A delivery arrives at your warehouse for which no purchase order exists. In the SAP
system, which of the following options are available to you:
(Only one answer is correct)
58A depending on the movement type, the system can generate a purchase order.
58B The item can only be received if the goods are non valuated.
58C You have to return the goods as a PO must be referenced with a goods receipt.
58D Receive the goods to block stock if the value is indicated on the delivery note.
58E The goods are received into GR blocked stock.
PURCHASING
59. A service master record contains the following:
(more than one answer can be correct)
59A A material master number.
59B Text.
59C A base unit of measure.
59D Conditions.
59E A valuation class for account determination.
60. A service entry sheet can be captured against:
(more than one answer can be correct)
60A Purchase requisition.
60B Outline agreement.
60C Purchase Order.
60D Master Service Schedule.
60E Invoice.
______________________________________________________________________________
___________________________
ANSWERS
1. A, D, E
2. B
3. C
4. C
5. B,C,D
6. B,D,E
7. A,B,C,D,E
8. B,C,D
9. A,B,E
10. C
11. A,B,E
12. B,C,D,E
13. A,B,C
14. C
15. A,B,C,E
16. B,C,D
17. C,D
18. E
19. E
20. A
21. B
22. A,B,D
23. B,C
24. D
25. A,B,C,D
26. B,C
27. A,B,C,D
28. D
29. A,C
30. D? (I think E)
31. A,B,D
32. B,C,E
12. Regular Vendor (used in Info Records) is activated per Purchase Organization?
13. Freezing of Book inventory as used in Physical Inventory is only allowed if activated on
Plant / S.Loc level?
14. If the posting Block was set for Physical Inventory document you will not be able to process
material movements until the difference is posted?
15. For invoice verification, a default tax code can be set up per company code?
16. When creating Contracts a Purchase Organization must be specified?
17. One step Transfer postings can done between plants if the plants belong to different company
codes?
18. In external service management a service entry sheet is the same as a goods receipt?
19. If the Source List selection is set in the material master then you must maintain a source list
for the material?
20. If the Quota Arrangement option is set in a material master then you must maintain a quota
arrangement for the material?
21. For valuation, a plant is assigned a chart of accounts?
22. For a Framework requisition (type FO) the validity dates are entered on header level?
23. MRP Area is a grouping of PLANTS?
24. MRP can create reservations?
25. Exchange rates can be changed during invoice verification (ref to PO) but it must be done
before the PO number is typed in?
26. Manual postings to stock (GL) accounts can only be made if the current stock quantity is zero?
27. A material type can be configured to allow pipeline or pipeline mandatory?
28. Goods receipt to GR block stock for valuated material will create a material document?
29. Only one plant / storage location can be used in one Physical Inventory document?
30. Consignment info records can only be created in the currency of the company?
31. The same material (for a specific plant) can be set up for either batch management or split
valuation not both?
32. For MRP to create stock transport requisitions (PR with item category U) a source list must be
set up?
33. When creating a Purchase Requisition for a material the price in the PR is from the material
master?
34. Source lists can be created for a material group?
35. Planned delivery costs is specified in pricing conditions and can not be changed during
invoicing?
36. Field selection can be linked to release indicator (status)?
37. Returnable transport packaging stocks are never valued?
38. Consignment stock can be receipted in block stock?
39. Stock can only go negative if the material is valued as standard price, not moving average
price?
40. Reservations that are flagged for deletion can be un-deleted by simply removing the flag?
41. Purchase requisitions that are flagged for deletion can be un-deleted by simply removing the
flag?
42. Requirements date on a reservation is specified on header level?
43. If the Shelf live expiration date (SLED) is set in the material master but not in the Purchase
Order then it will not be checked during Goods Receipt?
44. End User training takes place during the Go-Live and Support phase of a project?
45. SAP Solution Manager provides the methodology through 3 roadmaps Implementation,
Solution Management & Global?
46. A Parked invoice is visible in the PO History?
47. A Hold document (invoice) is only visible in PO History if the balance is zero?
48. Automatic Invoice reduction can take place if the vendor specific tolerance is set up. Invoice
reduction can only take place for positive differences and not for negative diverences?
49. Subsequent debit / credit will not post to GR/IR account?
50. Unplanned delivery costs will always post either to stock or consumption account?
51. The duplicate invoice check is activated on company code level?
52. Account assignment U can be used in PR and contract but not in Purchase Orders?
53. The same Valuation Grouping code can be linked to multiple plants belonging to different
company codes?
54. Configuration takes place during the realization phase?
55. The project definition activity takes place in Blueprint phase?
56. For missing parts check to function, the availability checking must be activated for a material?
57. A message schema contains message types?
58. A Quote can be accepted or rejected?
59. In the material type configuration a setting is available to indicate if the material can be
managed as consignment stock?
60. Reservations from production are called manual reservations?
______________________________________________________________________________
___________________________
Answers
1. FALSE only on header
2. TRUE Although the overall PO is only in one currency (specified on header) individual items
can have prices in different currencies.
3. FALSE -- Factory calendar is link to Plant
4. FALSE It is set for the system
5. TRUE
6. FALSE it can be both
7. FALSE on MRP type
8. TRUE
9. FALSE only in a PO
10. TRUE
11. TRUE --- only other stock types can be included/excluded, such as Block stock, QI stock, safety
stock, .
12. FALSE per plant
13. TRUE
14. FALSE until the count is entered (not posted)
15. TRUE
16. TRUE (on header level)
17. TRUE it is known as a inter company transfer
18. TRUE service entry sheet + acceptance is the same as goods receipt (movement type 101)
19. TRUE
20. FALSE for quota arrangements the tick on material master only activates the functionality but the
use is optional
21. FALSE the chart of accounts is linked to the company code
22. FALSE there is a FO type for purchase requisitions but no place to enter validity period. It is
normally entered as free text in one of the long text fields
23. FALSE grouping of Plant + Storage Location
24. FALSE only planned orders, PR and delivery schedules
25. TRUE
26. FALSE no manual postings can be made to stock accounts
27. TRUE
28. TRUE but not an accounting document
29. TRUE data is on header level
30. FALSE
31. TRUE