Escolar Documentos
Profissional Documentos
Cultura Documentos
05
5. CONCRETE
5.1 Introduction
Today the concrete, is the most important material for all types of construction
works and has been used for innumerable construction work . Some forms of concrete are
reinforced cement concrete, plain concrete, pre-cast concrete, pre-stressed concrete & many others.
In construction industry, the concrete is mainly used for foundations , columns ,slabs & beams
,staircase , lintels ,doors , window frames , sun shades, storage tanks etc..
Concrete is mainly composed of cement , water and aggregates with or Without
additions known as an admixture to improve strength , durability and other physical properties .
It is used to construct most of the structures in construction field. Concrete can not bare tensile
forces (only compressive forces), so reinforcements are used with it, where required.
Basically concrete is a mixture of cement, fine aggregate (sand), coarse aggregate
(metal), water, and admixtures. Admixtures are used to delay or accelerate the setting time of
cement in concrete. The above mentioned materials are mixed to certain ratios to obtain different
types of concrete for different types of jobs. Also coarse aggregate sizes are varies for different
mixes (ex: lean concrete, r/f concrete, chip concrete).
In a site, concrete can be produced by using a concrete mixture or by hand out side
the sites concrete is produced at the batching plants.
A single truck mixer can contain a maximum volume of 6.5m 3 & there are truck
mixers with different volumes (1m3, 3m3). When ordering concrete, wastages should be
included. All the details regarding the concrete, contains in the delivery sheet. (A copy is kept
45
the site a sample of concrete is taken to do the slump test and cast test cubes before
using.
After three hours from batching a concrete is rejected. If a problem arises in the site and the
concrete is unable to carry on, the batching plant should be informed immediately to stop batching of
concrete.
b)
c)
d)
Be well mixed.
e)
Be well cured.
Be durable.
b)
c)
d)
e)
Be resistant to friction.
46
5.4.2 Aggregates :-
47
48
5.4.3 Water:Water needs to be added to mix due to two reasons .One of them is water is required
for reacting with cement so that the practical are bound together . The other reason is for
making the concrete sufficiently workable to be placed and compacted . However the
amount of water required for the chemical reaction is very small and as such the rest
will remain or evaporate gradually as the concrete hardens , leaving small holes or voids
as they are usually called .Not surprisingly ,voids weaken concrete and so the more water
there in mix , the weaker will be the concrete .There will always be some voids in the
concrete because we must use sufficient water to make the mix workable enough to
obtain full compaction , but it is important not to add more than is necessary .Evaporation
of water will also cause cracks due to shrinkage .
Water for concreting was equal in quality to a good drinking water .Sea water may
be used but it has certain disadvantages such as delayed hardening and subsequent
efflorescence .If sea water is used in reinforced concrete it easily Leeds to corrosion of
he reinforcing steel .
5.5.1 Hand mixing :In this method ,mixing is done manually on a leveled , cleaned and
non-absorbent platform .( When mixing concrete by hand , the mix would not be as
uniform as when mixed by machine ). Hence , it should be done only when small
49
5.5.2 Machine mixing :Normally concrete should be mixed in a mechanical mixer .Machine mixing is
faster than the hand mixing and save the materials and a better mixture is turned out
.The revolving drum type of machine is used for concrete mixing . The capacity of the
machine being chosen to meet the required quantity of concrete on the job and the speed
at which each batch can be laid .There is no advantage to be gained by mixing the
materials dry first so the required amount of water is first added into the drum .This
moistens the drum and removes any fresh mortar or concrete adhering to the sides . The
remaining materials are then measured into the drum in their correct proportions . In
mixing coarse aggregate should be take first , then sand and last cement .In the revolving
state ,When the three materials get thoroughly mixed , water should be added . Mixing
should be continued until there is a uniform distribution of the materials and the mass is
uniform in color and consistency . The fully loaded drum is allowed to mix for about two
minutes by which time the concrete is thoroughly mixed and ready to be laid in
position .The revolving drum can tilt the concrete directly on to a platform to one side of
50
5.6.1 Advantages: Usually of high quality due to well controlled batching in to correct proportions.
No space is required on site for a mixing plant and storage of materials.
Saves lot of time on site operation.
Labor force required is reduced.
5.6.2 Disadvantages: No ways of checking quantity of concrete coming in trucks other than measuring the
deposited area.
A continuous supply of truck mixers may restrict due to heavy traffic on roads.
The truck mixers are basically a mobile mixing, drum mounted on a lorry chassis. It
can be employed in one of three ways:
51
Loaded at the depot with dry batched materials plus the correct quantity of water, the
truck mixer is used to complete the mixing process at the depot before leaving for the site. During
transportation to the site the mix is kept agitated by the revolving drum, on arrival the contents are
remixed before being discharged.
2)
Fully or partially mixed concrete is loaded into the truck mixer at the depot. During
transportation to the site the drum revolving at 1 to 2 revolutions per minute agitates the mix. On
arrival the mix is finally mixed by increasing the drum's revolutions to between 10 and 15
revolutions per minute for a few minutes before being discharged.
3)
When the time taken to deliver the mix to the site may be unacceptable the mixing can
take place on site by loading the truck mixer at the depot with dry batched materials and adding the
water upon arrival on site before completing the mixing operation and subsequent discharge.
All forms of truck mixer carry a supply of water which is normally used to wash out
the drum after discharging the concrete and before returning to the depot.
When using ready mixed concrete the main requirement that should be considered .
Availability of space for parking the truck mixture to unloaded to concrete and the
pump car to pump the concrete to higher positions .
There must be a good water supply to clean the every truck mixture after
unloading the concrete contained .
A good communication system is required between the site staff and the contractor .
The distance between site and the batching plant to where the order for concrete is
given must be minimum.
Ready mixed concrete is not always cheaper than site mixed concrete .Delivery
time can be irregular and the continuity of operations is upset by unavoidable delays and
reject batches .For small
to
get ready-mixed and for slow moving concreting . (Eg: columns concreting in higher
floors).
52
It is not also much economical because the setting time of the concrete is
over . So the contractor has to bring it little by little which make much cost .
construction and should give enough attention to the choice of the method or to its use on
site .If the equipment is used improperly or carelessly, the concrete quality will suffer and
so will sufficiency and productivity.
The method whereby the concrete is transported from the mixture to the point
of placing depend on the type of job being done , the nature of the site, the ground conditions,
the distance to be covered below or
above ground and the cost of labors at the time . On many jobs several
different methods or a combination of methods may be required, for example when concrete has to
be transported both horizontally and vertically. Transporting concrete must be quickly. Sometimes
we used large vehicle as truck mixers and pump car. By using these vehicle , we can reduced
transporting cost of the site .
Various methods are available for transporting concrete , ranging from wheel
barrows to pumps .The methods used for transporting the concrete in our site are as follows;
1. Wheel barrows
To transport concrete within the site, special wheelbarrows are used. It is
used for handing small quantities in concrete over short distance and is especially useful in
areas where inaccessible to other equipment. A wheel barrow can take a comfortable load
of about 0.03 m3 of concrete.
2. Dumper
It is also used for transport concrete in areas where mobile crane or truck mixers cant
carried , but dumper can take a capacity of 0.3m of concrete.
53
4. Truck mixer
Ready mixed concrete is supplied to sites in specially designed truck mixers
which are basically a mobile mixing drum mounted on a lorry chassis .Truck mixer can be
employed in following way .Fully or partially mixed concrete is loaded in to the truck
mixer at the depot .During transporting to the site mix is agitated by the drum revolving at
1 to 2 revolutions per minute . On arrival the mix is finally mixed by increasing the drum
revolutions in between 10 to 15 revolution per minute,
For a few minutes before being discharged. All
supply of water which is normally used to washout the drum after discharging concrete and
before returning to the depot .
Truck mixers are heavy vehicles weighing up to 24 tones when fully loaded
with a turning circle .The site allowance time for the unloading is usually 30 minutes;
allowing for the discharge of a full load in 10 minutes leaving 20 minutes of free time to
permit for a reasonable degree of flexibility in planning and programming to both the
supplier and the user . Truck mixer capacities vary with the different models but 4,5,6 m 3
are common sizes consideration must be given by the contractor as to the best unloading
position .
54
Concrete should place in uniform layers, avoiding large heaps or sloping layers because there
is always a danger of segregation.
If it is a column or wall concreting, pour height should not be exceeded 5 ft to avoid the
formation of air pockets and segregation of materials.
Each layers of concrete should fully compact, before placing the next one.
Concrete which dries out too quickly will not develop its full strength, there fore new
concrete should be protected from the drying winds and sun.
The workability of concrete varies according to type of concrete, location is being
used, type of compaction and type of pouring etc. more mobility and workability is required for
beams and columns it they are consist of reinforcement too closer to each other. Otherwise, it won't
be well bonded firmly. If vibrators are sued for compaction more workability is not necessary, but it
concrete pumps are used for, pouring mobility is needed in a large magnitude.
Fig.4.8.Placing of concrete
55
Voids reduce the contact between the concrete and the reinforcement and other embedded
metals, the required bond will them not be achiever and the reinforced member will not be as
strong as it should be.
Voids produce visual blemishes such as blow holes and honey combing on a struck surfaces.
1) Hand compaction.
2) Mechanical compaction.
5.9.1 Hand compaction:Hand compaction is done by rotting, tamping, hammering or ramming on the out
side of the formwork. Rotting consists of inserting a bar (may be a piece of reinforcing rod)
vertically in to the concrete and moving it up and down until the concrete is thoroughly
worked in to place. Rotting is used only for thin vertical sections for awkward corners, or to
work the material around reinforcement. Special care should be taken to see that concrete is
worked well in to all corners, cavities and around reinforcing bar to prevent their distortion.
5.9.2 Machine Compaction:This process of compaction consists essentially of the elimination of entrapped
air . The modern method is vibration. Main types of vibrators are
Internal immersion or porker vibrators - very common
External vibrators -
56
Surface vibrators -
Care must be taken to ensure that concrete is well compacted against forms and corners
and junctions.
2)
Poker should be inserting quickly and left it in the concrete for about 10 seconds.
3)
Poker must withdraw more slowly and wiggle it about to ensure that the hole which made
by the poker, closes up properly.
4)
Should be avoided the touching the from face and the reinforcement with the poker.
5)
6)
7)
8)
Avoid over compaction, as this will bring the grout to the surface, which effects the
compaction.
Type of cement
Mix proportions
Required strength
57
Curing means keeping the concrete sufficiently damp and prevent of evaporation by
wind, sunny etc. Curing method depend on nature of the work and climatic condition. In our site
there were two methods of curing.
Shading of concrete.
Sprinkling water.
Pounding.
Flooding.
58
5.10.2 Chemical curing walls:Only the concrete walls were cured by this method. An Acrylic based concrete curing
compound was applied evenly on the wall.
59