Project:
Matang New Township
0.20 m
45 tonnes
19 m
(D/B)
Set Criteria:
Pult
ef * W * H
S+ (C1 + C2 + C3)/2
S
ef * W * H
Pult
W + (n2 * Wp)
W + Wp
W + (n2 * Wp)
W + Wp
- (C1+C2+C3)/2
where:
Pult
W
Wp
Wa
n
H
=
=
=
=
=
=
=
=
=
=
s
C1
C2
C3
=
=
=
=
CT = C1+C2+C3
0.026 m
0.017067 m
Psafe
FOS
ef
ef* W * H
900,000 N
450,000 N
2
0.8
16,000 N
18,240 N
5,000 N
0.4
1.2 m
or cap (m)
Pult
W + (n2 * Wp)
W + Wp
0.503
(C1+C2+C3)/2
0.013
-4.63
mm
-46
mm
Therefore:
0.006 m
0.016 m
0.005 m
0.22 in
0.62 in
0.20 in
Hammer Efficiency
Hammer Efficiency, (%)
Poor
Normal
Good
55
70
85
Hydraulic (based on Potential Single Acting
Energy)
Double Acting
65
80
95
Free Fall
40
50
60
Drop (based on Potential
Energy)
Lifted Fall
20
30
40
Single Acting
15
25
35
Diesel (based on rated Energy) Double Acting
20
30
40
*Recommended Hammer Efficiency from Piling Handbook (Traswaja)
Pile Driving Hammer Type
Type of Hammer
Drop Hammer (triggered fall)
Steam or compressed air hammer
Drop Hammer (winch operated)
Diesel Hammer
Power efficiency
1
0.9
0.8
0.6-0.8
Temporary Compression, C = Cc + Cp + Cq
Form of compression
Easy
Driving
(inch)
0.05
Medium
Driving
(inch)
0.10
Hard
Driving
(inch)
0.15
Very Hard
Driving
(inch)
0.20
0.05
0.10
0.15
0.20
3 in/76.2mm packing
under helmet or driving
cap*
0.07
0.15
0.22
0.30
0.03
0.05
0.07
0.10
0.004L
0.008L
0.012L
0.016L
0.003L
0.006L
0.009L
0.012L
0.003L
0.006L
0.009L
0.012L
0.05
0.10 to
0.20
0.15 to
0.25
0.05 to
0.15
Material
Head of Timber Pile
Timber Pile (E =
1,500,000 lb/in2 or
10.342,500 kPa)
Pile Length Cp
Quake Cq
E=
Note: * If these devices are used in combination, the compression should be added together.
Length, L measure in feet
1 feet = 0.3048m & 1 inch = 25.4mm
(Source: A Guide on The Control of The Installation of Driven Pile, 1st Edition, Ir. Dr. Ting W.H., Ir. Chiam T.T., 1976)
Coefficient of restitution
Wood
0.25
Concrete
0.4
Steel
0.5
Pile/cushion Material
Coefficient of restitution
concrete or iron
wooden cushion/steel piles
wooden piles
0.4-0.5
0.3-0.4
0.25-0.3
0.20 m
33 tonnes
30 m
(D/B)
Set Criteria:
Pult
ef * W * H
S+ (C1 + C2 + C3)/2
S
ef * W * H
Pult
W + (n2 * Wp)
W + Wp
W + (n2 * Wp)
W + Wp
- (C1+C2+C3)/2
where:
Pult
W
Wp
Wa
n
H
=
=
=
=
=
=
=
=
=
=
s
C1
C2
C3
=
=
=
=
CT = C1+C2+C3
0.023 m
0.023182 m
Psafe
FOS
ef
ef* W * H
Pult
W + (n2 * Wp)
W + Wp
0.526
(C1+C2+C3)/2
0.011
0.89
mm
mm
Therefore:
0.004 m
0.015 m
0.004 m
0.15 in
0.59 in
0.15 in
0.20 m
33 tonnes
30 m
(D/B)
Set Criteria:
Pult
ef * W * H
S+ (C1 + C2 + C3)/2
S
ef * W * H
Pult
W + (n2 * Wp)
W + Wp
W + (n2 * Wp)
W + Wp
- (C1+C2+C3)/2
where:
Pult
W
Wp
Wa
n
H
=
=
=
=
=
=
=
=
=
=
s
C1
C2
C3
=
=
=
=
CT = C1+C2+C3
0.023 m
0.018182 m
Psafe
FOS
ef
ef* W * H
Pult
W + (n2 * Wp)
W + Wp
0.446
(C1+C2+C3)/2
0.011
-3.21
mm
-32
mm
Therefore:
0.004 m
0.015 m
0.004 m
0.15 in
0.59 in
0.15 in
0.20 m
33 tonnes
30 m
(D/B)
Set Criteria:
Pult
ef * W * H
S+ (C1 + C2 + C3)/2
S
ef * W * H
Pult
W + (n2 * Wp)
W + Wp
W + (n2 * Wp)
W + Wp
- (C1+C2+C3)/2
where:
Pult
W
Wp
Wa
n
H
=
=
=
=
=
=
=
=
=
=
s
C1
C2
C3
=
=
=
=
CT = C1+C2+C3
0.023 m
0.024545 m
Psafe
FOS
ef
ef* W * H
Pult
W + (n2 * Wp)
W + Wp
0.526
(C1+C2+C3)/2
0.011
1.61
mm
16
mm
Therefore:
0.004 m
0.015 m
0.004 m
0.15 in
0.59 in
0.15 in