Escolar Documentos
Profissional Documentos
Cultura Documentos
MEPA
LIBRARY
MEPA
Malta Environment & Planning Authority
Published:
Project no. :
Prepared
6 January 2005
80.4201.01
Jan R0nberg and Carsten Skov
PAGE
TABLE OF CONTENTS
INTRODUCTION
1.1
12
1.3
Acknowledgements
2.1
Summary
2.2
Recommendations
10
3.1
10
3.2
10
3.3
Tourism
11
3.4
11
12
4.1
12
21
5.1
21
5.2
International
24
5.3
6.1
31
6.2
32
35
7.1
35
7.2
Shoreline Extension
36
Creation of Islands
Technical aspects
37
37
7.3
7.3.1
Legislation
24
7.3.2
7.3.3
7.3.4
Environmental aspects
Cost estimates
Social and Economic Benefits and Constraints
A:
B
C:
The Malta Environment and Planning Authority (MEPA) has agreed to commission
Carl Bro International to undertake a Land Reclamation Study in accordance with the
conditions outlined below.
Most of the solid waste generated in the Maltese Islands originates from construction
and demolition and currently only limited waste disposal options are available. It is
frequently recommended to dispose of inert waste at sea, with the possibility of
increasing the present landmass through sea reclamation. The purpose of this Study
is to identify the potential for waste disposal at sea, with respect to construction and
demolition waste in the Maltese Islands, including land reclamation.
4. Predicted amounts of construction waste that will need marine deposition within
the next 20 years.
5. Identification of ways how deposition of construction waste can be carried out at
sea (deep sea deposition, extension of the shoreline, creation of islands,
construction of tourist, recreational and other facilities, etc.), indicating for each
option the environmental, social and economic benefits and constraints.
6. Identification and initial evaluation of potential marine sites, methodologies, etc.,
indicating for each the acceptable options and recommending a preferred option
for implementation.
7. Indicate additional baseline and feasibility studies necessary for further project
preparation, including environmental impact assessments.
The current Project Identification Report presents the results of work conducted
during 2 weeks in November 2004. The consultants worked one week in Malta in
close cooperation with MEPA officials and representatives from other institutions, who
all provided substantial background information for the study. A list of institutions and
individuals met during the identification study is attached as Appendix A.
Chapter 2 of the report includes a summary of the report and the Consultant's
recommendation;
Chapter 3 provides a profile of Malta on specific issues of relevance for the study;
Chapter 4 describes the current coastal activities;
Chapter 5 includes an overview of national and international legislation and
policies concerning land reclamation;
Chapter 6 deals with the current management of excavation, construction and
demolition waste, including estimates on waste amounts that may be used for land
reclamation purposes;
Chapter 7 describes the principles of land reclamation including technical,
environmental and financial aspects;
Chapter 8 identifies and evaluates potential areas for land reclamation along the
Maltese coastline; and
Chapter 9 presents the Consultant's recommendations on further steps to be taken
related to the planning and implementation of a land reclamation project.
The consultants and officials from MEPA and WasteServ have visited major waste
management sites, limestone quarries and a number of areas along the coastline,
where artificial islands might be established in front of the coastline.
Carl Bro International would like to thank all persons and institutions met for their
keen interest in the project. At the operational level, we would like to the officials from
MEPA for the daily liaison and coordination during the visit to Malta.
The natural harbours situated around the islands have been extensively used for
commercial and tourism developments. This is particularly noticeable on the east
and north-eastern coasts of Malta;
Tourism is the key service industry in the Maltese Islands and has grown to
become one of the Islands' most important economic activities. In 1960 tourist
arrivals totalled nearly 20,000, by 1990 these numbers had exceeded 870,000 and
in 1998 tourist arrivals totalled 1.2 million. The majority of tourist developments are
concentrated on the east and north coasts of Malta, including Sliema, Paceville
and Bugibba.
The marine waters along the coastal perimeter are presently used for a series of
commercial and recreational interest. Amongst these are in particular fishing and
fish farming, boating, bathing and diving. Further offshore oil exploration and
commercial ships traffic dominate together with fish trawling.
The national policies and legislation related to coastal environment are moving
from the initial into more regulated stages. While still suffering from a deficit of data
and information on the coastal and marine environment, the policies are directed
towards sustainable usage of the coastal resources. The lack of data however
hampers the effort to adhere to EU environmental legislation in the protection of
species and the habitats that support them.
Excavation works, and construction and demolition activities generate large waste
amounts, much of which comprise soft stone and are essentially inert. Although
some materials are reused or recycled as part of reclamation or landscaping
schemes, the bulk of these wastes is currently deposited in disused quarries
Some of the waste is even illegally dumped / fly-tipped.
The Solid Waste Management Strategy, approved in 2001, includes clear policies
and aims on the reduction of construction and demolition waste. According to the
Strategy, the Building Industry Consultative Council together with representatives
from relevant Government bodies are supposed to undertake a number of tasks,
primarily aimed to recover and recycle materials from excavations, demolition and
construction wastes. Reality shows that until now such activities have had no or
only very limited effect, since the major part of these waste amounts are still being
deposited at disused quarries. It is estimated that the disposal capacity in these
quarries will expire within the next 5 years. The annual need for disposal capacity
is in the order of one million m3.
Tied with the issue of inert waste management is that of land reclamation. Land
reclamation projects have to be justified as they result in a substantial impact on
the natural processes within coastal areas. The engineering works and financial
resources required to fulfil such projects are high. Structural stability is essential as
the reclaimed areas are continuously exposed to wave action and therefore require
appropriate construction materials and operations to ensure the long-term
existence of the reclaimed areas.
The main purpose of any land reclamation is to create high value land, the value of
which is above the construction cost. The value of the land is hence tied to the
subsequent activities to be placed on the land. The Maltese government has
decided, not to provide financial support to any land reclamation projects, but
rather promote private developers to initiate any such reclamation activities, based
on economically self-sustainable projects. The activities foreseen on the reclaimed
land, are hence required to create revenues that enable both land reclamation and
the cost of establishing the activities on the reclaimed land.
The location of a land reclamation project close to the shore is likely to cause
environmental impact in coastal areas which sustain ecologically sensitive benthic
habitats. The impacts will most probably be largest during the implementation of
the land reclamation project, but since any impact depends on the construction,
the construction methods applied and the location, the magnitude of the impact is
at present not assessable. At least three likely types of impacts are envisaged to
arise from land reclamation, namely increased turbidity of the water column,
obliteration of the benthic environment1 on the land reclamation site and
smothering of benthic habitats from the settlement of suspended particles. The
spatial extent of these impacts will amongst others depend on local current
conditions.
Under consideration of various criteria for excluding and highlighting areas, six
relatively large coastal areas have been identified as search areas for potential
land reclamation sites
Under consideration of various criteria for excluding and highlighting areas, the
Consultant has identified six relatively large coastal areas as search areas for
potential land reclamation sites. It is recommended that these six areas - or at
least a selection of them - shall be investigated in further details in parallel with the
execution of a pre-feasibility study, before a principal decision is taken on whether
land reclamation is considered realistic under Maltese conditions. It is
recommended that such investigations and studies be carried out by the
Government prior to the involvement of the private sector in possible land
reclamation projects.
The Maltese Islands are situated roughly in the centre of the Mediterranean sea, lying
some 96 km due south of Sicily and approximately 290 km due east of the North
African coast. They consist of three main islands and several uninhabited islands and
rocks and in total cover an area of some 320 km2
Malta is the largest of the Maltese Islands with a population of more than 340,000, the
next largest with more than 26,000 inhabitants is Gozo, whilst the smallest inhabited
island with less than 10 inhabitants is Comino. Access to the islands of Gozo and
Comino is predominately reliant on a ferry service from Malta, although a helicopter
service also existed between Malta and Gozo until September 2004.
The solid geology of the islands consists almost entirely of marine sedimentary rocks,
predominantly tertiary limestones with some clays and marls. There are also some
minor quaternary deposits of terrestrial origin mentioned in the Waste Management
Subject Plan/1/.
Groundwater is contained within the pores and fissures of tlle impervious rock strata,
forming aquifers which provide important resources of potable water supplies for
human consumption, industrial and agricultural uses as well as the maintenance of
natural watercourses and springs.
The minerals currently of most significance in the Maltese Islands are its limestone
reserves. These comprise softstone quarried mainly from the Lower Globigerina
formation, used as cut building blocks, and hardstone quarried from the Upper and
Lower Coralline formations used for 'marble', aggregates and concrete. The voids
created by mineral extraction operations can be used as sites for waste disposal. On
account of the need to protect groundwater resources, many of these sites may be
restricted to inert only wastes or require some landfill engineering works to be
undertaken prior to the disposal of any wastes.
Tourism is the key service industry in the Maltese Islands and has grown to become
one of the Islands' most important economic activities. In 1960 tourist arrivals totalled
nearly 20,000, by 1990 these numbers had exceeded 870,000 and in 1999 tourist
arrivals peaked at 1.2 million visitors. By 2002 the number has declined slightly to 1.1
million visitors. The majority of tourist developments are concentrated on the east and
north coasts of Malta, including Sliema, Paceville and Bugibba. In 1990 the bed
capacity available for tourists was estimated at over 41,000 with over 7,400 people
employed full time in hotels, complexes and catering establishments. By 1998 the bed
capacity available for tourists was some 46,500.
The following section describes presently ongoing activities along the Maltese
coastline. The activities list is not necessarily exhaustive, but characterises the main
activities in terms of economic and environmental importance. Most of the
background information to this identification study, including different maps on various
coastal topics, has been supplied by MEPA. The maps in question are enclosed in
appendix B without further elaboration.
A.
\\ r,'ck
3
Dlw"lt..:
-'quacllllllr,' ZOIl":
FI,h Farm
511mbalhyrn~lry
Sl'"d Groulld
The fishing industry in Malta is relatively small with more than 65 percent of landings
by weight taken up by large pelagic species. However, at local level, the social
importance of fisheries far outweighs their economic output. This is due to the small-
scale and traditional nature of local fisheries, and to their role in supplying valuable
food items.
Table 4-1
Production
(f'reshIfnmM1)
Exports
Total
PM ctJpitB
supply
supply
2.14
5.47
2.7
1.36
1.92
consumption
Based on local population, excluding processed/preserved fish products (e.g. canned, smoked, fillets,
breaded, etc.)
2427
Primarysector:
525
Secondarysector:
Gross value of fisheriesoutput (2000):
Marine fisheries
As on 18 September 2001, there were a total 1736 licensed fishing vessels (1411 in
Malta and 325 in Gozo). Of the 1736 vessels, only 45 were considered to be industrial
vessels (i.e. over 15 m in length). These industrial vessels were mainly trawlers, longliners (surface- and bottom long lines) and netters (including floating FAD's). The rest
could be considered as multi-purpose, since they undertook all types of fishing,
although on a smaller scale.
Due to their commercial value, the most targeted species were common dolphin fish
(Coryphaena hippurus), northern bluefin tuna (Thunnus thynnus), swordfish (Xiphias
glad ius), stone bass or wreckfish (Polyprion americanus) and species in the Sparidae
and Scorpaenidae families, such as dentex (Dentex dentex), common sea bream or
red porgy (Pagrus pagrus) and black scorpion fish (Scorpaena porcus).
The fishing effort related to trawlers are all located outside the 3 nautical Mile
boundary of the Maltese coast, and primarily between or outside the 12 and 25
Nautical Mile limits, see Figure 4.2. Trawling zones within the 3-mile zone are
withheld.
,
flf
Fi'lhin~ rffM1:
:"oIm:11I~:,k' t l,hl.'f')
(Tr:.m.md
'Jc:h~.
Slla.i.1 Oimiblllioll
uftishing
trrurl:
l\1II:l1I'\4."all'Fidll'n
The offshore aquaculture industry has been developed within the constraints of a
National Aquaculture Plan and policy guidelines that ensure environmental protection
and sustainable development. Aquaculture is essentially based on large-scale
commercial offshore units employing modern technology. The cost of producing
farmed fish is still relatively high. The aquaculture production - which reached 1 746
tons in 2000 - is almost entirely exported (95 percent).
The annual aquaculture production increased dramatically during the 1990's from 60
tonnes in 1991 to a peak of 1800 tonnes in 1998 through the operation of 6
commercial farms. The highest production consisted of 1200 tonnes of sea bream
and 600 tonnes of sea bass. However, due to decreased prices for these two species
throughout the Mediterranean region, production dropped to 1300 tonnes in 2001.
o
o
7 offshore areas are designated for bunkering. The 5 sites closest to the Maltese
coastline are depicted in Figure 4.1. The eastern most site (area 5) is scheduled to be
relocated.
The bunkering sites do not in themselves pose rigorous constraints on the use of the
coastal waters of Malta, since they can be moved by administrative decision.
Offshore Wind Farms
There are at present no offshore wind farms in Maltese waters. The consultants have
not during the present study been presented with information on possible offshore
wind farm activities, other than sketched ideas. Hence reference is made to section
7.2 for further discussion on the possibility of creating offshore wind farms.
Navigation Requirements
Navigation in Maltese coastal waters primarily takes place in connection with:
- Ferries connecting to Gozo island, including the Valletta-Gozo route
- Cruise liners, ships and traffic of other vessels from and to Grand Harbour
- Commercial large vessel traffic to and from Malta Freeport
Apart from obvious requirements for navigation in areas very close to the ports, the
navigation requirements do not immediately seem to pose a significant problem in
relation to the topic of the present study. This would of course depend on the location
and extent of any reclamation, for which reason the issue should be addressed with
MMA, when more details on the extent and location of a possible reclamation site is
known.
Marine Protected Areas
The entrance into the European Union requires the designation of protected habitat
areas and bird protective zones according to the EU-habitat directive and the EU-Bird
protection directive. Marine zones are in the process of being identified, but have not
yet been so. Inland coastal areas have been identified and published in September
2003 as Government
Notice 877 of 2003. Marine candidate areas have been
identified and proposed for habitat areas, as described in section 5.1 Hence protected
areas in the marine environment are not present in the context of EU legislation.
The area between Rdum Majjiesa and Ras ir-Raheb, see Figure 4.5, on the northwestern coast of Malta has been proposed as a candidate site for Marine protected
area.
Moreover, the marine environs of Filfla are essentially a no entry zone for all activities,
except for fishing from moving vessels, are prohibited since 1990.
'1l
r--
r---l
I~;;'~~"
Protected
:ana
:eCClamcmun 5'lti ~
~\'O.\\~\~\'e~\\~'e~\\~\~~~~
~'e~'\\.
Figure 4.7
In 1999 tourist arrivals to the Maltese Islands reached a record figure of 1,214,230,
and has since declined slightly to 1.133.814 in 2002. Foreign earnings from tourism
account for about 22.9% of total exports of goods and services in 1997 (Economic
Survey, January-September 1998). Gross earnings reached a figure of Lm 254.4
million in 1998. Direct employment in hotels and catering establishments is around
9500 employees but it is estimated that the full-time equivalent employment figure is
in the region of 41 ,451. In terms of tourist accommodation provision the current figure
is in the region of 46,884 beds.
Currently, the average annual occupancy, as indicated by the MTA, stands at 56
percent. An acceptable level of occupancy is generally around the 65 percent figure,
annually. At the same time, despite the current level of provision, it is acknowledged
that the demand for new beds is unlikely to decline because of lower occupancy
levels.
The future strategy as set out in the Strategic Plan 2000 - 2002 focuses on product
and market diversification, reducing the seasonality and upgrading of the Maltese
Islands' overall tourism product.
From the main issues addressed in the Topic Study the following key points have
been extracted, 111 I:
Evaluation of Current Structure Plan Policies
Current policies do not reflect the changes and demands of the sector. The emphasis
should be less on tourist accommodation development, although still a major issue,
and more on product development in these zones. Criteria need to be defined to
direct the designation of such zones.
Tourist Accommodation
The current situation indicates that specific categories of tourist accommodation
establishments are moving out of the sector into other businesses. Other
establishments are being redeveloped and extended. New forms of tourism
accommodation might be required (e.g. rural accommodation, accommodation in
historic towns). The MTA's policy in this regard is to decrease the emphasis on
accommodation and on the increase in bed stock but also encourage the
refurbishment of existing accommodation establishments. It is widely recognised that
some areas have reached saturation point in terms of tourist beds and improvements
to improve the cultural tourism offer. On the other hand discussions are underway
with regard to the development of specific projects like golf courses, yacht marinas, a
marine aquarium and other recreationaJ attractions. The further development of the
diving niche and the sinking of diving wrecks is another aspect that needs to be
addressed.
Future Strategy
According to the Tourism Topic Paper, the future strategy should consider a number
of options to meet the demands envisaged by the tourism sector.
Any proposed construction activity in Malta, including the marine waters of Malta, is
subjected to a list of constraints defined by the national legislation and policies as well
as international conventions and legislation, specifically EU legislation. The most
relevant national and international legislation and policies are described in the
following sections, as found in /12/.
The main legal instruments calling for the protection of marine habitats and
biodiversity within the Maltese Islands are the Environment Protection Act (2001)
and its subsidiary legislation, the Development Planning Act (1992) and the
Structure Plan and the Fisheries Conservation and Management Act (2001). Other
legal documents, such as the Malta Maritime Act (1992) make reference to
protection of the marine environment against pollution, /12/.
Environment Protection Act, 2001
According to Part V, Section 9 (2) (k) of the Environment Proteotion Act (2001),
the Minister responsible for the Environrrent may in relation to the protection of
biodiversity:
i. provide for the monitoring and management thereof, (
ii. declare any species to be a protected species and establish rules
for its protection;
iii. declare any species to be an invasive species and establish rules
for its control;
iv. regulate the use of and otherwise protect specimens of fauna or
flora; and in particular prohibit and, or, control possession,
exhibition, artificial propagation or captive breeding of such
specimens of flora and fauna as may be prescribed;
v. provide for the conservation, protection and management of
particular habitats or categories thereof in order to safeguard
biological diversity;
vi. declare any areas or sites on land or in the internal or territorial
waters, or beyond such waters where Malta may have jurisdiction
for the purpose of the protection and control of the environment,
to be protected areas and to provide for their protection and to
regulate their management;
vii. control and regulate any activity that may interfere with the
conservation status of biological diversity,
viii. regulate trade in and the transit, import or export of specimens
of flora and fauna as may be prescribed.
Flora, Fauna and Natural Habitats Protection Regulations, 2003 (LN 257 of
2003)
This legal notice is concerned with the establishment of a National Ecological
Network of special areas of conservation having National or International
Importance. The legal notice aims to transpose the obligations of the Habitats
Directive which call for the establishment of a European network of Special Areas
of Conservation (Natura 2000), composed of sites having the natural habitat types
and species listed in Annexes I and II to the Directive. Additionally, in accordance
with Article 3 of the Habitats Directive, the network is to include Special Protection
Areas classified under the Birds Directive.
Waste Management Regulations (permit and control), 2001 (LN 337 of 2001)
This regulation under the Environment Protection Act transposes the obligations of
the EU waste Framework Directive and the Hazardous Waste Directive into national
legislation.
This regulation controls all operations relating to the production and management of
waste and promote sound waste management practices so as to safeguard human
health and the environment.
Development Planning Act
Under the Development Planning Act (1992) Section 46,
"areas, buildings, structures and remains of geological, palaeontological,
cultural, archaeological,
architectural, historical, antiquarian, or artistic or
landscape importance, as well as areas of natural beauty, ecological or
scientific value (hereinafter referred to as "scheduled property" ) ... are to be
scheduled for conservation ... ".
The Amendments to the Development Planning Act (1997) extend the jurisdiction of
this Act to the marine environment.
The 1990 Structure Plan for the Maltese Islands acknowledges the urgent necessity
of protecting marine areas, due to 'the mounting development pressure all along
the coastal zone'. The Structure Plan observes that the United Nations Convention
on the Law of the Sea provides the legal basis for the management of marine
resources, with Article 192 (5) charging governments with the 'obligation to
protect and preserve the marine environment'.
The Structure Plan acknowledges that various activities require the utilisation of
coastal and marine resources. These needs are to be recognised in the formulation
of a national representative system of marine protected areas that will incorporate
different categories. Fourteen candidate sites are proposed as Marine Conservation
Areas; nevertheless, the need to include additional sites is also recognised.
There are thirteen policies included in the Structure Plan, dealing specifically with
MCAs. They provide general guidelines with respect to the process of development
of MCAs (refer to Appendix A). The Structure Plan marine conservation policies
(MCa 1 to 13) require that:
areas of ecological importance, areas of archaeological importance, and
areas of international importance are given the required protection;
the approach to the designation of protected areas is holistic, and that MCAs
are contiguous with protected land areas where possible;
appropriate data regarding site characteristics and issues linked to the site be
collected, and that such data be managed using Geographic Information
Systems (GIS);
As for international conventions and legislation, the recent entry into the European
Union requires Malta to abide to the existing EU aquis. The EU acquis is primarily
Posidonia beds
Coastal Lagoons
Annex II:
Annex II lists species of plants and animals, whose habitats must be protected for
their survival.
Annex IV:
The Habitats Directive obliges Member States to protect a number of coastal and
marine species found in the Maltese Islands and their territorial waters. Such
species are listed in Annex IV of the Directive.
Article 4.1 of the Habitats Directive requires member states to designate areas for the
protection of Annex I and Annex II types of habitats and species. It is however not
required, that all occurrences of the species are designated for protection /31. This is
especially relevant for the Posidonia Beds, which extends over a substantial part of
the sea bed along the Maltese coastline.
Since the areas are in the process of being designated, and are not presently so,
there is presently no formal or legal restrictions on constrained use of the areas for
other purposes. It may however prove prudent to restrict activities in the candidate
areas for designation, and any proposed activity should be considered with a view to
the ongoing process of designating protected areas.
Pending the designation of marine Special Areas of Conservation, the main
constraints are derived from Article 16 of the EU Habitats Directive, the coastal
Special Protection Areas designated in terms of the EU Wild Birds Directive, as well
as national law, with special reference to provisions of the Development Planning Act
and Environment Protection Act (including their subsidiary regulations). The latter
includes the candidate coastal Special Areas of Conservation listed in Government
Notice 877 of 2003.
Borg & Schembri has in their work been commissioned to propbse Natura 2000 sites
for the Maltese Islands. They have indicated 9 sites along the entire coastline, based
on the findings of their study. The 9 sites are shown in Figure 5.1
The Bern Convention (1979) and the Habitats Directive (1992) have a complete
coincidence of objectives, their main differences relating to the territory they apply to
and the fact that the Habitats Directive is more explicit on the obligations concerning
conservation of natural habitats.
expanding the scope of water protection to all waters, surface waters and
groundwater
achieving "good status" for all waters by a set deadline
water management based on river basins
"combined approach" of emission limit values and quality standards
getting the prices right
getting the citizen involved more closely
streamlining legislation
There are a number of objectives in respect of which the quality of water is
protected. The key ones at European level are general protection of the aquatic
ecology, specific protection of unique and valuable habitats, protection of drinking
water resources, and protection of bathing water. However, the overall objective is to
prevent deterioration of the ecological status of surface waters, and to achieve "good
water quality status" for all waters by 2015.
For coastal waters, the ecological status and chemical status have to be monitored
to allow for the classification of each of the water bodies according to the quality of
the biological quality elements. For protected areas the objectives of the WFD are
supplemented by those requirements arising out of any other Community Legislation
under which the individual protected areas have been designated. For example
Natura 2000 sites that are designated for the protection of species and habitats, may
have more stringent monitoring requirements under the aforecited EU Habitats
Directive.
To achieve the environmental objectives, each Member State must establish a
monitoring programme for the biological and physico-chemical characteristics, and a
programme of measures for each river basin district (in the local context referred to as
the 'water catchment district').
For priority hazardous substances listed, cessation or phasing-out of discharges,
emissions and losses are required. The list contain 33 substances or group of
substances including selected existing chemicals, plant protection products, biocides,
metals and other groups like Polyaromatic Hydrocarbons (PAH).
EU Bird Directive
As with the EU-Habitat Directive, the EU-Bird Protection Directive requires the
designation of specific zones for the protection of birds of national or international
importance. These zones are designated by the national governmental authorities,
based on existing information on the occurrences of bird species, their nesting and
feeding areas, resting areas for migrating birds as well as the threats posed to their
presence on a national and international level.
As with the implementation of the EU- Habitat Directive, these areas are still in the
process of being designated for Malta, for which reason there is presently no formal
EU legislative restrictions on coastal activities with respect to the bird life.
Under the Coastal Zone Management initiative, Joe Sultana and John J. Borg have
prepared a subject plan on ornithology highlighting areas of importance along the
Maltese islands. The area found to be of high ornithological importance is shown in
Appendix B, Figure 2, and includes the main part of the western coast of Malta as
well as parts of the Island of Gozo.
Additional data is informed to be available through a report on Bird Areas important in
terms of the EU Acquis, published by BirdLife Malta in June 2004.
London Dumping Convention
The London Dumping convention, to which Malta has acceded, regulates the disposal
of material at sea. While dumping of a number of specific hazardous substances,
listed in Annex 1 (The black list), is prohibited, dumping of substances which do not in
themselves constitute an environmental hazard (Annex 2, the grey list), are not
considered prohibited by the convention, subject to certain restrictions. The dumping
of such materials is regulated by the national legislation. According to the convention,
the dumping activity is required to be preceded by an assessment of the
environmental consequences, assuring that no significant environmental impact can
be expected from the dumping of the material.
The London Dumping convention is relevant for the present project, if dumping of
inert waste at larger depth is considered as alternative to land reclamation or inland
use of the inert material. Inert material is regarded as Annex 2 substance, being on
the grey list.
In conclusion, the disposal of inert materials at sea can be regarded as a viable
option, from a legal viewpoint, if the impact on the environment is considered
insignificant. Based on the information on marine environmental conditions at larger
depths obtained during the present identification project, it must be considered a
viable option.
of the Mediterranean
Sea against
Pollution
A number of protocols were adopted under this convention, amongst which is the
Protocol concerning Mediterranean Specially Protected Areas. This protocol later
changed to Protocol for specially Protected Areas and Biodiversity in the
Mediterranean (SPABIM).
Parties to this are obliged to establish specially protected areas and shall endeavour
to undertake the action necessary in order to protect these areas and, as appropriate,
to restore them as rapidly as possible, /3/. Both Malta and EU are parties to the
protocol, which also forms part of the EU Acquis (Decision 99/800/EC).
The Integrated Solid Waste Management Strategy from 2001/41 sets out targets to be
achieved over following years. This also includes policies and targets due the
management of inert waste. Some of the key aspects in this relation are described
below.
Quarry activities:
Quarry activities, in particular soft stone quarrying, result in considerable material
wastage and in the generation of limestone residues in the form of waste gravel and
crushed rocks and dusty and powdery wastes. Most of this material is deposited in or
around the quarry from which it is generated.
Construction & Demolition Wastes:
This waste stream, much of which comprises soft stone and is essentially inert, arises
from excavation works and demolition and construction activities. Although some
materials are reused or recycled as part of reclamation or landscaping schemes, the
bulk of these wastes is currently deposited in disused quarries or illegally dumped /
fly-tipped.
Waste Hierarchy:
The SWM-strategy has adopted the waste hierarchy as a concept, providing a
preferred order of priorities for selecting and deciding upon waste management
practices. These are:
1.Waste prevention / reduction
2. Reuse
3. Recycling
4. Recovery
5. Disposal
This principle is to be considered in conjunction with other principles, in particular the
"Best Practicable Environmental Option (BPEO)".
Best Practicable Environmental Option (SPED):
The Best Practicable Environmental Option (BPEO) is the outcome
and consultative decision-making process that emphasises the
conservation of the environment across land, air and water. The
establishes for a given set of objectives and circumstances the option
of options) that provides the greatest benefits or least damage to the
a whole, at an acceptable cost, in the long term as well as i the short
of a systematic
protection and
BPEO process
(or combination
environment as
term.
Year
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
Notes:
1: Assumes waste arisings increase of 3.0% up to 2000, 3.25% at 2000,
3.75% at 2005 and 4.25% at 2010.
2: Growth rates for the Maltese Economy based on constant price rates
established in IMF Reports.
On the Islands, almost all of these wastes have been disposed of to landfill until year
2004. From the beginning of 2004, most of this waste stream has been directed for
disposal at disused stone quarries.
A conversion rate for inert wastes that is widely accepted within the EU assumes that
1.5 tonnes of inert waste equates to 1 cubic metre of landfill capacity. On this basis,
there is a requirement for between 710,000 m3 and just over one million m3 of inert
disposal capacity to be made available each year.
It is the policy of MEPA to seek greater reuse and recycling of inert wastes and
guidance contained in the Public Consultation Draft of the Minerals Subject Plan
deals with standard conditions for recycling of inert materials in quarries and the
disposal of inert wastes in quarries.
MEPA has identified a number of disused quarries to be used as controlled inert
waste disposal sites. This way, disused quarries can be restored and used for
agricultural and recreational purposes. However, at present it is estimated that the
disposal capacity in the disused quarries will expire within the next 5 years.
154,000
383,000
14,000
551,000
tonnes
tonnes
tonnes
tonnes
In addition to this amount, it was estimated that another 700,000 tonnes were
deposited at various quarries.
Waste from quarrying of stone is not included in these figures. Such material does not
enter the waste stream as it is deposited at the quarries or in the nearby vicinity.
If assumed that the composition of the total inert waste amount is similar to that
deposited at Maghtab, then materials from excavations at developments etc.
constitute approximately 70% of the total inert waste amount.
Disposal of wastes at sea can give rise to significant environmental impacts and as
such are controlled by international conventions and protocols. Under certain special
circumstances sea based disposal of inert waste may be considered where it can be
demonstrated that it will not give rise to adverse impacts on the marine environment.
Such proposals would be subject to environmental impact assessment requirements.
MEPA's position on this issue is presented in its Position Paper on Disposal of Waste
at Sea, /21.
Tied with the issue of inert waste management is that of land reclamation. Land
reclamation projects have to be justified as they result in a substantial impact on the
natural processes within coastal areas. The engineering works and financial
resources required to fulfil such projects are high. Structural stability is essential as
the reclaimed areas are continuously exposed to wave action and therefore require
appropriate construction materials and operations to ensure the long-term existence
of the reclaimed areas. The majority of reclamation projects require relative shallow
waters to facilitate construction works, ie within the 50m bathymetric contour of the
coastal waters, which are also considered to be ecologically important. As these
areas are also under intense use from the tourism and recreation sector as well as
maritime activities, the impacts of such projects would therefore be substantial on
both social and economic grounds.
The purpose of any land reclamation is to create high value land, the value of which is
above the construction cost. The value of the land is hence tied to the subsequent
activities to be placed on the land.
The Maltese government has decided not to provide financial support to any land
reclamation projects, but rather promote private developers to initiate any such
reclamation activities, based on economically self-sustainable projects. The activities
foreseen on the reclaimed land are hence required to create revenues that enable
both land reclamation and the cost of establishing the activities on the reclaimed land.
Hence, to justify the economic
conditions need to be fulfilled:
investment
in reclaiming
The types of activities that has so far been generating revenue in Maltese coastal
area based on the location in the coastal zone are:
Tourism:
Hotel industry
Boating/Yachting industry
Marinas
Leisure activities such as
Casinos,
Nightlife
Bathing
Entertainment in general such as cinemas etc.
Shopping centres
Domestic activities:
- Housing/residential areas
During the project identification mission, a number of proposals have been brought
forward on new types of activities, which may be economically sustainable on a
private sector basis on reclaimed land:
- Incineration of hazardous waste
- Cement kilns for production of cement
- Offshore windmill farms
Comparing land reclamation alternatives, shoreline extension would usually entail the
smallest possible construction activity, since the reclaimed land would benefit from
the existing coastal perimeter on the one side, and at the same time be at shallower
depth the than if creating an artificial Island further offshore.
At the same time, however, the impact both to the marine and terrestrial areas may
be significantly higher since:
- The area designated for reclamation is closer to existing uses, and hence could
spur conflicts from the existing users.
- The area would be located in a zone that commonly tends to have a higher
environmental importance in terms of biodiversity, biomass or biological
importance in general.
On the other hand, the economical implications of reclaiming land by shoreline
extension is generally much less than compared to the creation of offshore islands.
The technical issues related to shoreline extension do not differ from that of creating
offshore islands, for which reason this subject is described in more detail under
section 7.3.
phase, an artificial
During the first phase an outer bound would be created around the circumference of
the island
By establishing an outer closed perimeter, the spill of fines during infilling of material
will be confined to the water within the circumference of the island. Hence the release
of fines in the marine environment can be significantly reduced during the subsequent
infilling.
Considering areas within the 30 m depth contour, it is assumed that the underlying
seabed consists of weathered hard limestone allowing only limited penetration of
sheet piles. It would instead allow placement of either a
cofferdam structure
concrete caissons
sheet pilling using double walls
Steel cofferdam
The cofferdam is constructed one cell by one and concurrently filled so only the outer
cell is temporarily not stabilised by fill. In connection with construction of the
cofferdams it is planned to establish a guidance system, which is to be used as
interim support when erecting a new cofferdam.
At some locations it will be necessary to make a protection of the cofferdam top to
avoid erosion from overtopping water. The cofferdam may require a limited scour
protection. The cofferdam structure is constructed and closed before further fitl work
takes place.
After construction of the outer cofferdam structure the filling takes place partly by
back tipping from trucks or through a conveyor belt system. If the island is close to
land, a conveyer belt system from storage and crushing site could transport the infill
to the island. The conveyer belt system should be closed to avoid problems with dust.
Basically the inner area is filled up completely or partly independent of the future use.
Concrete Caissons
As an alternative construction method, concrete caissons can be used to delimit the
outer perimeter of an island.
The use of concrete caissons does however pose requirements to both supplies of
concrete as well as location for construction of the caissons.
Furthermore the use of concrete caissons is more difficult in waters with heavily
sloping sea bottom, which to some extent may be the case outside on some of the
locations, e.g. as indicated outside St. Julians Bay.
Sheet Pilling
Sheet pilling using steel represents an alternative to the caisson or cofferdam. The
sheet pilling will however necessitate the use of a double wall, because of the hard
bottom, for which reason the difference to the cofferdam solution represented
previously is rather small, both in terms of performance and cost.
It is hence considered that under the given Maltese conditions, using steel plated
cofferdam structures is a viable and sensible construction method, and it will
consequently form the basis of the following assessment of construction implications.
Assuming that the indicated interval of material would delimit the construction of an
artificial island, it is seen from Figure 7.6 that an island at more than 100-meter depth
would provide a maximum of 7 Ha land. An island at 30-meter depth on the other
hand would in comparison provide the equivalent of 25 Ha land.
Plane view of circular island with example of one inner canal at reduced
depth. Outer perimeter made of cofferdam, while inner canal can be
made in various less expensive ways.
To relate the construction of an artificial island with a high demand on inert material
for infill to the amount of surplus material presently generated in Malta, Figure 7.6
depicts the quantity of material need for an artificial island at different depths.
The green band in the figure delimits an interval between 5 and 8 million m3 material,
which is the equivalent amount of inert material to be generated within a period of
approximately 5 to 8 years at present rates.
This should be seen with a view to the financial investment involved, requiring the
construction period to remain limited, in order to provide a revenue of the investment
within an acceptable time period.
Figure 7.6
35
Depth
30
ns
.~
Q)
25
-10
meter
-20
meter
...0E
20
-30
meter
15
-50
meter
ns
E
0 10
E
-100
meter
-150
meter
5
0
1
10
15
Ha of land
Note: The green area indicates amounts between 5 and 8 million m3, which is approximately
the equivalent of 5 to 8 years use of annually generated inert material at present day rates.
The marine environment refers to both seabed (benthic) and the water column
(pelagic). Pollutants have no boundaries in the aquatic medium and are transported
by diffusion, by currents and wave motion.
Placing of large quantities of material on the seabed can result in marine pollution
related to spreading of fines, depending on the technique used and caution exerted. If
no precautions are taken, particulate material will result in marine pollution, the
magnitude of which is related to the quantity of the material, particle size,
composition, etc. The condition of the marine environment in the area of deposition,
such as benthic environment, chemical and biological oxygen demand levels (COD,
BOD), bathymetry and currents are also important variables.
The location of the deposited material close to the shore is likely to cause more
damage than further off the coast, since coastal areas sustain ecologically sensitive
benthic habitats some of which are of economic significance (e.g. nursery/fishing
grounds). The importance of the coastal fringe is due to the fact that up to depths of
around 50m, it supports unique habitats that are important in terms of biological
diversity. The damage to such habitats could be irreversible. Coastal areas are also
important for their amenity value and any deposition at sea occurring in these areas
may affect a variety of uses ranging from bathing, water quality for desalination,
aquaculture, etc.
Irrespective of whether the waste is hazardous or not, three likely impacts are
envisaged to arise from dumping-at-sea, namely
- increased turbidity of the water column,
- obliteration of the benthic environment2 immediately beneath the marine
dumpsite and
- smothering of benthic habitats from the settlement of suspended particles.
Turbidity of the water column is caused by the particles in suspension; the smaller the
particles the longer the suspension period. Increased turbidity reduces light
penetration affecting both benthic habitats as well as plankton. There have been
instances where the health of pelagic species has also been affected especially
through the clogging of fish gills leading to increased infertility. The severity of the
impact depends on the release of fines during deposition. The water circulation
pattern of the area will affect the rate of dispersal of suspended material.
Released material will eventually settle on the seabed. As a result of this, the area
immediately below the location of deposition is severely impacted and the local
benthic environment smothered. The longer the process, the wider the affected area.
The severity of impact on the marine environment is particularly dependent on the
bio-chemical nature of the material that is dumped. The impacts associated with
depositing inert waste are limited to those described above, namely smothering of
seabed and increased turbidity. In the case of deposition (or reclamation) in shallow
areas close to the shore, the impacts will also be extended to changes in currents and
the hydrodynamic regime of the area and the promotion of associated impacts related
to sediment transport phenomena such as coastal erosion and sediment
accumulation. Another potential problem that could be associated with 'inert' waste is
that the waste may be contaminated with non-inert substances, potentially of a
polluting or even possibly hazardous nature.
To minimize these environmental impacts, it is proposed, that the perimiter structure
of the reclaimed land is built first, after which, release of fines to the environment can
be almost entirely prevented, dependant on the infill technique used.
Land Reclamation
Study, Malta
Draft Project Identification
Report
The main cost related to the creation of an island, is related to the construction
of the
perimeter. This part approximately
accounts for 50% of the total construction
cost.
This is due to the price of steel, construction
price of the cofferdams
and works
related to construction of the perimeter.
The second most significant contribution to the cost is the handling of the fill material
to the construction.
This accounts for approximately
20% of the total cost.
of constructing
in Figure 7.7.
an
Perimeter structure
Transport, handling etc. of infill
Other structures, scour protection etc.
Contingencies,
administration,
etc
50
20
15
15
0.6 MTL/kg
0.5 MTL/m3
The price
construction
%
%
%
study
on
80
70
...J
....
60
50
ci 40
30
."..
.. .
Circumference/area
of island
.".. "
--1
-
km/8 ha
-
2 km/ 30 ha
- - - 3 km/ 72 ha
20
10
0
5
10
15
20
25
30
35
Depth
The prices indicated in Figure 7.7 apply to circular shaped island, which have the
smallest possible circumference relative to the generated land. If other types of
islands, with more artistic variations of the outer perimeter should be considered, the
price would increase considerably. This is due to the fact that the construction of the
outer perimeter accounts for the bulk of the total cost.
The figure shows, that 30 Ha of land at 30-meter depth results in an approximate cost
of 40 million MTL. This price is construction price of island only, and the subsequent
land development and building construction on the island is additional to this amount.
To enable comparison with the price of land on the existing island of Malta, the price
of reclaimed land indicated in Figure 7.7 is indicated pr m2 in Figure 7.8
Equivalent prices of land in Malta vary highly, for which reason two extreme points of
land value has been sought in Malta. These two points are represented by the low
cost of industrial land in Malta and the high cost of residential areas near the
waterfront around SliemaNaletta. The prices of land in 2004 at these two extremes
are, as provided by MEPA, approximately:
For residential areas, the price is indicative of the price of an apartment, in a multistorey building. Hence the price of the building plot would be lower.
On the other hand, the prices indicated in Figure 7.8 represent the cost of every
square meter of the island, including roads, pedestrian walks, parks etc. Hence the
cost pr. m2 of an apartment on an artificial island would increase relative to the area
used for purposes other than apartment buildings.
It is not envisaged that other major costs would occur as a result of mitigation
measures, egofor wave action etc.
:::J
....
~
....
200
150
...
100
50
0
5
Circumference/area
of island
..
- - - 1 km/ 8 ha
..
--3
2 km/ 30 ha
km/ 72 ha
10
15
20
25
30
35
Depth
Based on the figures obtained, the use of an artificial island for industrial purposes
should be driven by other incentives than economic for it to be realistic. I.e. the
present low value of industrial land compared to that of an artificial island does not
provide adequate incentive for the creation of new land for industrial purposes.
With respect to land value of residential areas, a price interval between 100 and 300
MTL for undeveloped land may not deter an investor. The total price of 20- 60 million
MTL for constructing at 30 m water depth may however prove to pose significant
requirements to the solidity of the developer as well as confidence in the price market
for residential areas. At lower depths, these figures seem more favourable towards
the development of an island.
The creation of Islands for residential or tourism purposes will most likely generate an
increased turnover in the industry in question. It should however be investigated to
which extent the present sector may have a surplus capacity or whether it is in need
of more capacity.
Should surplus capacity exist in the sector, the additional capacity provided by this
type of project may initiate or enhance depreciation in the market value of the existing
commodities in question. Hereby forming a depression in the market.
These aspects are especially relevant if taxation on vacant property is considered, or
the price structure in the market is subject to change by other factors.
Artificial reefs are generally recognised to be effective devices for attracting and
supporting large populations of fish, conditional to the specific environment and type
of reef employed. They can provide complex, hard surface habitat in areas where
only soft bottoms occur. Large artificial reef structures also provide improved feeding
opportunities for many fish by changing water flow patterns. Localised areas of high
flow are created as moving water passes over and around large artificial reef
structures and low flows are established in sheltered areas inside the structure and at
the downstream side. Although it is widely established that high current flows attract
plankton-feeding fish and their predators, the impact Qf such currents in the
oligotrophic Maltese waters are not yet scientifically ascertaihed.
Artificial reefs may provide good opportunities for planktonic fouling organisms to
settle and develop. These fouling organisms, which include polychaetes, barnacles
and mussels, flourish on artificial reefs and attract many predators, such as crabs,
shrimps and fish, to feed and be fed. Artificial reefs are generally recognised to create
new and complex food webs in areas that are habitat limiting.
There are expressed opinions to the opposite view, and preliminary scientific studies
by the research team led by Professor Patrick J Schembri of University of Malta has not
indicated such a big distinction in marine stock and biodiversity, and results are yet
scientifically inconclusive. Potential conflicts with fishing efforts should also be
considered in the context of deploying artificial sub sea structures.
Artificial reefs could be constructed using concrete dolos, tripods or similar structures,
made in part using inert waste material. The concrete structures would be placed on
top of each other on the sea bottom, forming an underwater 'mountain-like' structure.
The height of the structure would depend on the depth at the location, but keeping the
structure below 18-20 m depth would prevent hazard to the ships traffic in the given
area.
The price for the dolos/tripods is based on a low estimate on the price for
prefabricated re-enforced concrete structures at a unit price of 100 MTLlm3
Land Reclamation
Study, Malta
Draft Project Identification
Report
The benefits arising from the creation of artificial reefs would be an increased
fish stock, which in the longer term would benefit the fishing industry in Malta.
Based on the above arguments
with an estimated
turnover
between
MTLlyear,
the fishing industry would not itself be able to sustain the
required to generate artificial reefs at large depths.
marine
1-5 million
investment
It is common practice to use obsolete ships, which are positioned at the seabed. The
shipwrecks
constitute very fine artificial reefs because of the variety of hiding and
refuge places, while at the same time providing a large surface for benthic growth.
The efficiency of windmills is directly related to the wind energy at the location of the
windmill.
Hence the positioning
of windmills at offshore locations usually provides
better conditions
for the windmill, while at the same time removing
any negative
effects, such as noise or aesthetics, in inhabited areas.
To the extent that the locations of offshore windmills are used by sea-birds,
it is
important
to note that these sea-birds
could be negatively
affected
by offshore
windmills.
This is particularly
the case for Wild Birds Directive Annex I species as
Calonectris diomedea, Hydrobates pelagicus and Puffin us yelkouan, which breed in
large numbers in the Maltese Islands.
Windmill efficiency in general is however at present only closing-in on cost-effective
energy production.
When compared to other production forms, such as coal, oil etc.
the production of wind energy is not in itself economically
self-sustainable.
Only state
or governmental
support has until now helped finance the windmill industry.
- gravitational
platforms such as caissons
- mono-pile, tripod structures
- floating substructures
etc
While gravitational
platforms are used at shallow depth until approximately
meter depth, mono-pile and tripod foundations can be used until approximately
At larger depth, these platforms are presently substituted by floating platforms.
10-15
25 m.
At larger depth, the cost of the substructure would quickly become comparable to the
cost of the windmills themselves. So while the construction of offshore islands for
windmills may solve the problem of inert surplus material, the construction of an
artificial island for this purpose is prohibitively expensive
The prices used are based on present day windmill technology and price structure.
The technological development of windmills is however rapid, and the above listed
argument concerning prices may need revision within a 1a-year time period.
Dumping of inert material at sea is a last resort for disposal of inert material.
If no alternative to dumping is available, dumping is a relatively cost effective method
of disposal.
The implications on the marine environment needs to be assessed prior to such
action, and would depend heavily on the presence of fine material in the waste. While
coarser particles would settle to the seabed within a short range of the dumping
location, the fine material would disperse to a large area.
As it appears from the previous chapters, the choice of potential sites for land
reclamation is a task involving many interests. The strategy on how to chose a site
should thus be based on the recognition of these interests followed by a step-wise
approach in which at first unsatisfactory areas are excluded and subsequently more
promising areas are identified. In this way, the search area can be narrowed down
and successively the detail level on subjects to be considered will be increased. The
process can be divided into three major steps:
Only the first step is included in the current identification report. The three steps are
further described in the following.
A map screening has been carried out in order to eliminate unsatisfactory areas. The
entire coastal area surrounding the Maltese Islands has been considered at this
screening exercise (see also Chapter 4).
The areas left after the elimination of unsatisfactory areas as a result of using the
exclusionary criteria are not necessarily all the most potential areas for a land
reclamation project. Some of the areas left will turn out to be better than others and
shall thus be highlighted. The following criteria may be used for highlighting promising
areas:
Limited Conflicts related to protected Nature Territories
Land reclamation close to areas of key interest because of their scenic beauty and
wild life should be avoided.
Distance to Cultural Heritage sites
Areas close to important shipwrecks and/or close to unique archaeological
historical interests on the coastline must be avoided.
or
Water Depth
Areas with water depths less than 30 metres are preferable for both technical and
financial reasons.
Distance to Urban Centres
Assuming that reclaimed land will be used for recreational and/or residential purposes
(e.g. hotels, apartments, marinas), it is considered preferable it the reclaimed land is
located near existing urban centres containing similar developments (synergy
effects). Facilities at the reclaimed land (hotels etc.) need supply of water, electricity,
sewage discharge etc. Furthermore, the land should preferably be easy to access
from the existing road network.
Present Coastal Land use
Due to the impact from reclaimed land on the adjacent coast (visual impact etc.),
locations in front of urban areas are preferred to locations in front of unexploited
coastlines.
Marine Environment
Areas close to or within proposed habitat areas and bird protective zones should be
avoided.
Conflicts with Existing Commercial interests
Sites for land reclamation should preferable be located far from fish farms and other
commercial interests at sea (e.g. bunkering sites; shipping routes).
Attitude of Authorities and the Public
The attitude of local authorities and residents towards a land reclamation project may
be influenced by the execution of a public participation process. Highlighting areas
where the willingness of local authorities and residents to accept such a project
already exists may facilitate the timely realisation of a land reclamation project.
The use of Inert Material as Fill Material
For waste disposal reasons, sites and projects ensuring disposal of large quantities of
inert waste materials are preferable. However, this is assumed to be the case no
matter what site may be used for land reclamation. Therefore, in this respect, all
possible sites may be considered comparable.
Based on the above criteria for excluding or selecting potential areas, six relatively
large coastal areas have been identified as search areas for potential land
reclamation sites:
Area
Area
Area
Area
Area
Area
1: Northeast of Malta
2: Area in front of Sliema
3: Southeast of Malta
4: South of Malta
5: Northwest of Malta
6: North of Gozo
/'
C~
,0
J
I
.
f
,I
I
(
"
-".
Expected Disadvantages:
Expected Advantages:
Expected Disadvantages:
There
are
significant
commercial
activities within the area (fish farms etc.)
Expected Advantages:
The coastline is already being exploited
Expected Disadvantages:
Expected Advantages:
No immediate
conflicts
commercial interests
with
existing
Expected Disadvantages:
Land reclamation
and the use of
reclaimed land will have significant visual
impact on the relatively
unexploited
coastline.
Expected Advantages:
No immediate
conflicts
commercial interests
with
existing
Expected Disadvantages:
Land reclamation
and the use of
reclaimed land will have significant visual
impact on the relatively
unexploited
coastline.
For islands at deep sea, artificial reefs, and dumping of inert material at sea, the
following overall advantages and disadvantages should be mentioned:
Expected Advantages:
Expected Disadvantages:
Following the identification and overall description of potential land reclamation areas,
and the above listing of advantages and disadvantages for each area, the initial
evaluation of these areas may be compared in order to point out whether some areas
seem more promising than other areas. For this purpose, the different areas have
been given scores to illustrate their compliance with the different criteria used at the
evaluation. The following scores have been used:
+ : Probably satisfactory
? : Maybe satisfactory
- : Probably unsatisfactory
n.a.: Not applicable
The initial evaluation of the six coastal areas and possible islands at deep sea,
artificial reefs, and dumping at sea is presented in Table 8-1. It would not be safe to
state firm conclusions on the suitability of the different areas at this preliminary stage.
Obviously, more comprehensive investigations and analyses are needed to create a
proper basis for such conclusions. Nevertheless, it seems as if the areas along the
eastern coastline of Malta are more suitable for land reclamation projects than areas
along the western and northern coastline. Areas at Gozo seem to be less suitable.
Options at deep sea are in general less problematic than options near the coastline.
However, they will probably not be realistic from financial viewpoints.
Criteria
Deep
sea
island
Reef
Dumping
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
n.a.
Marine eflvironment
n.a.
n.a.
n.a.
Conflicts
commercial
Altitudes of
the public
Use of inert
with
existing
interests
authorities and
n.a.
n.a.
n.a.
material
Socio-economical
effects
No conclusions on the feasibility of land reclamation projects have been made at this
stage, since more comprehensive investigations and analyses are needed in order to
form the proper basis for such firm judgements. The issue of land reclamation is
multi-disciplinary and covers a wide range of different interest, many of which are
directly linked to national interests of Malta. It is therefore strongly recommended that
the necessary further preparatory activities are planned and executed by the
Government of Malta. In this connection, the executing party could be the Malta
Environment and Planning Authority.
The private sector may very well be involved in the financing, detailed planning and
implementation of a land reclamation project, once the overall conclusions on the
feasibility of such project has been drawn by the Government on the basis of solid
pre-investigations. At that stage, detailed agreements on land reclamation may be
entered between the Government and the private sector, including clear definitions of
the duties and responsibilities of the parties involved.
The necessary
outlined below.
preparatory
From the initial evaluation of potential areas in Chapter 8 it can be seen that many
uncertainties still remain. It should be the main purpose of additional baseline and
feasibility studies to provide a proper basis for elimination of these and possible other
uncertainties. The additional investigation and studies can be divided into the
following two main components:
Detailed site investigations at the most promising areas for land reclamation
Feasibility study on land reclamation
The marine baseline survey should be performed to enable an assessment of the
present marine environmental conditions along with the carrying capacity of the
marine environment.
The marine survey should provide the basis for a
characterization of the marine environment with respect to environmental value in the
context of designating protective zones under the EU habitat directive, and the basis
for a preliminary impact assessment for large scale marine structures in the area.
At the same time the monitoring should adhere to the obligations for monitoring under
the EU- water framework directive. The final specification of the contents and extent
of the marine survey should thus be prepared taking into consideration the planned
monitoring of the marine environment envisaged to comply with the water framework
directive.
The spatial and temporal resolutions of retrieved data should be assessed with a view
to the subsequent use.
Numeric models for predictive description of hydraulic and marine impacts arising
from the structure should be used to assess the hydraulic and environmental
dynamics of the marine system, especially with respect to projected impact of large
marine structures.
A detailed Feasibility Study shall be carried out in order to describe the Land
Reclamaition Project in sufficient detail to allow the decision makers to conclude on
whether a land reclamation shall be carried out or not.
All relevant issues related to land reclamation shall be covered by the study. The
study shall evaluate and provide recommendations on specific sites for land
reclamation projects. The study is required to assess the construction of an artificial
island in terms of:
-
Draft Terms of Reference for the proposed site investigations and the feasibility study
are attached as Appendix C.
The Government may be able to obtain partly financing of the proposed site
investigations and feasibility study from the EU Structure Fund or from other EU
funds.
A draft overall implementation plan for the proposed further activities is shown in
Figure 9.1. The proposed site investigations and the detailed feasibility study can be
carried out in parallel. Depending on the exact timing and the financing options for
these activities, it can be decided to perform the activities together or to divide them
into two separate projects.
No.
1
2
3
4.1
42
5
6
7
8
9
Activity
04
4
X
X
2005
1
2006
4
X
X
X
Based on the findings from the site investigations and the feasibility study, a political
decision should be made on whether to proceed with the land reclamation project or
not. If yes, a Land Reclamation Request for Proposals (RFP) should be prepared, to
invite private developers to propose land reclamation projects. The RFP should
clearly describe the requirements of the proposers to provide a binding written
proposal based on the covenants, terms and conditions spelled out in the RFP to
provide the complete services, works and facilities for a land reclamation project,
including the financing of the project. The developer will be responsible for providing a
full EIA related to the project development.
12/:
13/:
14/:
A Solid Waste Management Strategy for the Maltese Islands, September 2001,
Carl Bro International.
15/:
16/:
Carl Bro study on land reclamation at Maghtab, For Med Design Consultants,
2001
171
Land reclamation
2004
181
191
1121 Guidelines and Designation Framework for Marine Protected Areas, November
2004, awaiting ministerial approval.
POSITION
Capita Projects Department
Manager
Hydrographer
Project Officer
Minerals Directorate
Director General
Assistant Director
Resources Management
Unit (RMU)
Assistant Director Nature
Protection Unit (NPU)
Assistant Director Pollution
Prevention & Control Unit
(PPCU)
Natural Resources
Planning Team Manager
(RMU)
Minerals Team Manager
(RMU)
Environment Officer Waste
Management Team (RMU)
Waste Management Team
Manager (RMU)
Strategic Planning Team
Manager
Planning Directorate
Senior Environment Officer
(PPCU)
Environment Officer
(NPU)
Environment Officer (NPU)
Senior Environment Officer
Environment Assessment
Team (RMU)
Minister
Ditmar Wechselberger
Vladmir Filipovic
Anthony Gruppetta
NAME
Alfred Xuereb
Joseph Bianco
Louise Refalo
Godwin Cassar
Vincent Gauci
Alfred Baldacchino
Louis Vella
Michelle Borg
Dimitrio Duca
Denise Attard
Kevin Mercieca
Joseph Gauci
Michael Sant
Carmen Mifsud
Christine Tanti
Rachel Xuereb
INSTITUTION
Malta Maritime Authority
Malta Maritime Authority
Malta Resources Authority
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
MEPA
APPENDIX B
Maps on Current Coastal Activities - MEPA
':oastal Strater;y
Topit
P",-p.y
Coas~al Zone
Coastal Zone
(Preliminary)
Inset
,0
S'olt:
1.120,000
D.u :
May:001
INDICATIIIE ONI. Y
NottD1>!".,diJrdinrtirll.apnlwan.
B..
~
c::.,,'CtcJloff
'c -);6Blurvll1h_
"cl1"" 1k."" ilr
Au
rilj
AW"TOl'UTJl.
l.-IPPJANkK
"[1\'
PL.l.NlolJl'[GAlJrHUJ(fN
,l
Sell<:
h120,OOO
May2001
INI:lCilTIIIE ONI. Y
Notto b!us.<11ilr l1lnet~L.
l~n.)talStr"tfr"
'Iopi: P~PQ:I
iCJ
Sclllk :
DIlA!:
~20U
h120,006
lNDIC;'.Tl'IIs: DillY.
Noltot'UStdlix:dinet.~
Funa
JLp~. ~~::~~~-:
e..,~r1LI""
...
.(C
Bcale
1: 17, 500
.. ~.,.
Coula! Sbal.~
Topu:PapU
AwrORlTA
TA' L-IPPJANAR
PLAN":mll7 AllTEORIIY
Underwater Pipelines
and Cables
Stilt :
I,
:no.ooo
DlIl>.
Ma."f 2001
TNDIClI.'I'l'1li:GNlV
Ncl.to~~.dbrditet~.
.1.1I4,.1.19G1lI,...,1tu-
~,.)'W Ko"
~'Vn
'" l. ,
c~
...,.
~D~sites
c::::::::J
CJ
011ll119,1t
Uarll~ A~3 ~xelld!!!I"1l1:J
011 ~bl3lb.
()Je I 1!ft(J bfO P II)
." t>t. __
'l._kIo "
Coastal ltr&tew
Top'" Pape,
AWTORlTil
n' l.IF-PlJ.NAR
YL).NNiNG AtJrnORl1Y
l:lJ!I',OOO
M.o,y%On
::ND:CAIIIIE OllL Y
UC1l:.u
ucwclbd.inctia.JA}J.clA:J.A
...
COa.J~~Zh~ccy
fop>: Paper
D
D
lilanne '
'
al,dldate
(Si~C1uConselVatl(ln Area
to PI<:ln 1QGO}
Lc,cotion of se) b
11shtarm
s..:- .
),20',000
o~aa
Coastu S1rategy
Topic ?ap"r
'<.UTIIOR.1Y
SuLJrnilled Developnel
I'pp icotior
D<tt:
1:120,~00
Ma,y 2.01
DIDICAT:IIE JNLY
lIot t> bt 1S.dMr OrtCl irdsprrIoIi<:a.
Co~hl Sbl'~tca:Y'
Tn['lij'":l~~'t'
Granted Development
,Il,pplicalior
Granted Development
(1994 . 1998)
;co],:
DlIlk:
J:.I2U,~UU
INDI:A'I!IIE
lfQL
'bt
~2'UJ
i)NT..Y
Coastal Strale\'J
TcpicP4per
A'mCRITA TN LIP;>JANilR
P1AllliIHO
AU'llIORr1Y
CJ
While Area
F!(,2/1
CJ
Industrial Zore
CJ
aDZ
Landoulsije C~astal
Bourdal)'
Mo,r :001
Jl;DICAllVEUW. y
lTct.to~e\)f~dford:irectil~l.
10
~
~
50 metre bathymetric
contour
II
for
o(
PIOl~ull~n
!'Ill.!
1:135.0aO
May 2001
lNI>ICJ.m1E 0:lL Y
Noaa h u,.dtir di:tet ~.
11
APPENDIX C
Draft Terms of Reference for Additional Studies
The Malta Environment and Planning Authority (MEPA) is investigating the possibilities for land
reclamation. Especially the formation of one or more artifitial islands may be an attractive solution in
order to create highly valuable land for construction of hotels, apartments, marinas etc. In addition to
the main purpose of reclaiming valuable land, such project would require supply of large amounts of
inert fill material, which again would help to solve the actual nccd for disposal capacity for thcsc
materials.
In 2004, a Project Identification Study was undertaken by an international consulting company on
behalf of MEPA. This study resulted in an overall Project Identification Report. The Project
Tdentification Report provide an overview on current practise within coastal management in Malta
and the legislation and policies concerning land reclamation. Furthermore, the report includcs
examples on technical solutions for land reclamation and an overall identification Qf areas that may be
suitable for land reclamation projects.
The Project Identitication Report should be considered the first step in the procyss of investigating
options for land reclamation. The report highlights the need for further and more detailed site
investigations and pre-feasibility studies to be carried out in order to establish a proper basis for the
decision on whether to proceed with a land reclamation project or not.
The project subject to these TOR will provide detailed survey data on marine areas previously pointed
out as potential sites for land reclamation. It will also include a comprehensive pre-feasibility study.
which will include a multi-criteria analysis of the relevant aspects related to land reclamation and the
use of inert and construction and demolition waste as fill material for the creation of artificial islands.
The global objective of this project is to determine whether land reclamation in the sea is a realistic
option for Malta under consideration of technical, legal, environmental and financial aspects. Both
local and EU Standards should be considered.
of the marine
environment
at the selected
options
marine
for dumping,
The marine baseline survey should be performed to enable an assessment of the present marine
environmental
conditions along with the carrying capacity Of the marine environment. The marine
survey should provide thc basis for:
Characterization
of the marine environment with respect to environmental
of designating protective zones under the EU habitat directive
At the same time the monitoring should adhere to the obligations for monitoring under the EU- water
framework directive. The final specification of the contents and extent of the marine survey should
thus be prepared taking into consideration the planned monitoring of the marine environment
envisaged to comply with the water framework directive.
Water chemistry
Physical characteristics,
nutrients
Benthic vegetation
resolutions
of retrieved
extensive
monitoring
intensive
monitoring
in selected segments,
data on coverage
hereby providing
detailed
information
on
number of species
number of individuals
ship wrecks
issues during
To assess the hydraulic and environmental dynamics of the marine system, especially with respect to
projected impact a large marine structure, the use of numerical models for predictive description of
hydraulic and marine impacts arising from the structure should be performed.
Hydrodynamics
Waves
Sediment dispersal
Eutrophication
Benthic vegetation
Along with the model results, the modclling tool, model set-up, pre-and post processing specification
files, input data, calibration log and all other data rcquired to run the model should be made available
to the client for use in subsequent feedback monitoring during the construction of the large marine
structure.
Realizing, that historic data for model calibration and validation arc scarce, the model calibration
should bc performed to the best possible stage, based on the monitored data from the monitoring
program.
A detailed Feasibility Study shall be carried out in order to describe the Land Reclamaition Project in
sufficient detail to allow the decision makers to conclude on whether a land reclamation shall be
carried out or not.
All relevant issues related to land reclamation shall be covered by the study. The study shall evaluate
and provide rccommendations
on specific sites for land reclamation projects (under consideration of
the findings from the site investigations mentioned under Component I)
etc.
solution
bascd on componcnt
Thc following tcam of expcrts will bc needcd for the projcct, dcpcnding on thc combincd
qualifications and cxperience ofthc membcrs. Each expert should bc flucnt in English.
3. I
Tcam Icadcr/environmentalmanagcment
cxpert
Advanced university degrec in an environmentalmanagemcnt-rclated
f(eld
At Icast fiftccn ycars working experience in managing multi-disciplinary
projccts,
including marine environmcntal, waste management, technical, Icgal and financial issucs
Solid cxperiencc
preparing fcasibility
studies and cnvironmcntal
impact studies
(Environmental Impact Asscssmcnt and Stratcgic Environmcntal Assessment)
Track rccord of facilitating dcvelopment of consensus among stakcholders
3.2
Marinc biologist
Advanced university degree in marinc biology
Solid cxpcriencc in planning and undcrtaking of under watcr survcys at marinc sites
Expcricnce in Mediterrancan benthic and pclagic marinc organisms
projects
3.3
Hydraulic specialist
Advanccd university degrcc in civil/ hydraulic engineering
Solid cxpcriencc in environmcntal hydraulic studies and related numcricalmodelling
Expcricncc with monitoring and survey campaigns
Solid cxpcricncc with scdiment dispcrsal studies
3.5
3.6
Legal expert
Advanced university degree in law
In-depth knowledge of EU environmental
requirements and policies
3.7
law, including
coastal
zone management
Em ironmental economist
Advanced university degree in economics
Solid knowledge of environmental economics, incl. infrastructure costs
Solid experience in carrying out cost estimates and financial analyses
In addition to the above experts, a pool of experts with specific local knowledge in the following areas
must be included in the team:
Marine biology in the Mediterranean and especially the sea surrounding the Maltese islands
Relevant environmental legislation
It is estimated that the duration study will last 6-9 months Depending
the study may commence in spring 2005.
lneeption
Report
The expert(s) \Viii provide an inception report with a project planning activity and resource use
schedule within the first month from the assignment start.
Study)
Report
Report re\'iewing status of project to date, including activities carried out so far. outputs completed
or under way. outcomes status of project resources, any problems encountered or anticipated. etc.,
-+ months a!"ter start.
Report
Final report summarising all activities carried out in the course of the project. all outputs
completed. the results achieved. any gaps between the specifications set forth in the project TOR
and the tinal results achieved, budget used, etc.
All reports should be in English. 2 copies of the reports referred to above must be submitted in hard
copy and electronic format to the Main Beneficiary.
Malta Environment and Planning Authority
Mr. Godwin Cassar. Director General,
St. Francis Ravelin. Floriana.
P.O. Box 200, Marsa GPO a I. Malta
Email address:godwin.eassar@mepa.org.mt
and