Escolar Documentos
Profissional Documentos
Cultura Documentos
JUNE-JULY 2016
For my rising senior summer holiday I interned at a chemical factory in Rayong, Thailand. For the first two weeks of
my internship I received an orientation and I studied how the process works and how the different engineering
departments work together. Throughout this process, I was looking for potential improvements I could make in the
factory, therefore I choose to work on this MEG pump because it was feasible with my time frame. This document
outlines the project from investigating the problem to developing specifications and then the financial analysis and
project outcome.
!
!
BACKGROUND
Mono Ethylene Glycol (MEG) is one of the key raw materials in the production of PET resin.
More than 335 kilograms are used for every ton of PET produced.
MEG is provided by PTT chemicals and
it is delivered to the factory and stored
in a silo 92.26m away from the
production plant. As a liquid it is then
pumped to the production factory. The
MEG has two purposes in the factory:
- Raw material for the main
polymerization processes. (This is a
continuous process )
- Batch preparation (mixed with
catalyst and additives whenever
required). This is a controlled
process, and the second pipeline is
controlled by a valve.
Problem
The pump which is used to transfer the MEG is over 15 years old. It is in a poor condition and has a high power
consumption due to low efficiency. Furthermore, since the factory is looking to expand, a new pump is required to
handle more volume of MEG flow.
Solution
In order to solve this problem we decided to install a new pump. We would still use one of the old pumps as
backup, but we wanted to find a pump which would satisfy the operating specifications and would be energy
efficient. The solution would also need to have a payback period of less than 3 years.
PROJECT SPECIFICATIONS
In order for the new pump to serve a similar purpose in a more efficient manner, we contacted many
different suppliers to see what kind of products were on offer. After sorting through the different
suppliers we choose KSB Pumps. Bellow are the details of the product.
!
Operation Data
Requested Specification
Product Specification
Flow Rate
14.70m
15.12m
Developed Head
80.00m
84.63m
Eciency
Maximum Possible
66.4%
4.65kg/s
Shuto Head
105.12m
Pump Rotation
2951rpm
Discharge Pressure
9.19 bar
!
After all of this data was approved to our specifications and the tests were done on site, the quotation for the
equipment and spare parts was 115,400 baht.
Total
Continuous Process
8.2kW
8030
65846 kWh/year
Continuous+ Batch
Process
9.5kW
730
6935 kWh/year
From the provincial electrical authority, the power cost is 3.25 baht per kilowatt hour. The total usage
electricity usage for both processes is 72781kWh/year, therefore for 1 year the cost is 236,538 baht.
!
!
!
!
Summary of Results:
Fluid Density: 1107kg/m3
Flow Rate: 15.12m3/h
Power Observed: 5.81kW
Net Positive Suction Head: 1.73m
Eective Impeller diameter: 110.00mm
Eciency: 66.4%
!
!
!
!
Diagram of the MEG Silos
Design of
Interior
Design of
Exterior and
Implementation
Module
CONCLUSION
!
!
Old Pump
Continuous
Process
3.1kW
8.2kW
8030
24893 kWh/year
Continuous+
Batch Process
4.5kW
9.5kW
730
3285 kWh/year
!
Total saving in 10 years: $41,411
!
The payback period is 1.51 years, which
successfully meets the projects goal. The new
vertical pump also has a large spare capacity in
order to uphold future factory expansions.