Escolar Documentos
Profissional Documentos
Cultura Documentos
-----
1.
2.
------
Equipment Information
1.1
1.2
1.3
Delivery / Storage
2.1 Site Delivery
2.2
3.
Table of Contents
------------------------------------------------------------------------------------------- 08
Storage ------------------------------------------------------------------------------------------------------ 09
Equipment Installation
3.1
3.2
3.3
4.
5.
Testing
4.1
4.2
Operation
5.1
General ---------------------------------------------------------------------------------------------------- 48
6.
5.2
5.3
Maintenance
6.1 General Maintenance Guidelines -------------------------------------------------------------------- 57
7.
7.3
1. Equipment Information
1.1 General Description
1.1.1 Scope of work
A. The work under this section includes furnishing, and testing a filter system consisting of :
1) Filter underdrain system complete with underdrain blocks, anchor rods.
2) Wash Water Trough
3) Surface Wash System
4) Filter Media(Anthracite)
5) Control Panel
6) Instrument(Turbidity Transmitter, Level Transmitter, Level Sensor, DPI)
B. The following aren't included in our scope ;
Concrete, grout, sealant, anchor adhesive, mechanical equipment anchor bolts, filter system
piping and electrical conduit/wire shall be furnished and installed by the installation contractor.
: 6 Basins
Filter Size
: 45.14
: 380 to 445
: 2,250
( 50 )
( 5 )
225
( 8 to 10.8 )
: 450 mm
Effective Size
: 1.0 mm
Uniformity Coefficient
: 1.50 to 1.70
Acid Solubility
: Less than 5%
Hardness
Effective Size
Uniformity Coefficient
Acid Solubility
: Less than 5%
Manufacturer Specification
No. of unit
Six(6)
two(2)
Type
2250m3/hr
225m3/hr
6 EA
Underdrain Type
Anthracite depth
B.
Under 2.5m
Matrial
Trough
SS 316L
SS 316L
Description
Manufacturer Specification
C.
-1 ~ 45
Filter Media
Anthracite
Minimum thickness
Effective size
Uniformity coefficient
Acid solubility
Sand
300mm
150mm
0.5
1.0
Uniformity coefficient
450mm
1.0
not greater than 1.5
1.50 to 1.70
less than 5%
greater than 2.7
Acid solubility
D.
Less than 5%
Material
HDPE
Description
E.
Manufacturer Specification
Material
HDPE
Thickness of cap
19mm
500 ( 25%)
F.
40 ~ 50 %
tapping screws of type 316SS
Header Pipes(8")
Length
Material
Length
lTwo(2)
12 SET (= 6Basin x 2Cell)
Approx. 6.0m
SS 316L
28 SET
168 EA (=28ea x 6Basin)
Approx. 1.8m
Biilateral pipes : SS316L
Nozzle : Brass
.
Material
2. Delivery / Storage
2.1 Site Delivery
TETRA LP-Blocks are factory inspected and packaged for shipment.
Standard LP-Blocks with or without a Media Retention Plate are recommended to be shipped, palletised,
banded and wrapped with polythene. Other components are packaged separately with proper identification.
It is the receivers responsibility to inspect all components and report any loss or damages to the carrier
before signing the delivery receipt.
Any concealed loss or damage discovered later should be reported to the carrier in writing within 15 days.
The carriers representative should be present during inspection, if required.
Use only correctly designed lifting equipment for lifting and moving pallets. Slings and / or ropes must not
be used as this WILL damage the LP-Blocks.
2.2 Storage
Store the LP Blocks indoors or in a shaded location to protect them from exposure to direct sunlight.
Ensure the blocks are only stored in a clean environment. Do not stack the pallets or LP Blocks on uneven
surfaces as this may cause warping. Store each pallet on a flat surface and protect them from overturning.
Do not stack pallets on top of each other. Do not stand on the blocks.
Stack un-palletised LP Blocks on a flat surface. See Figure 2.1 for instructions for LP Blocks with out Media
Retention Plates and Figure 2.2 for LP Blocks with Media Retention Plates. Do not stack over 10 LP Blocks
high or stack LP Blocks on their sides.
Cover any loose LP Blocks with polythene to keep them clean and to protect from the weather.
Figure 2.1 Stacking of unpalletised LP Blocks NOT fitted with Media Retention Plates
2.3 Storage [ Wash water trough, Surface wash system & Media ]
Wash water trough and surface wash system are stored and packed to the plains while skid.
Do not stack the skid or the steel products on uneven surfaces as this may cause warping.
Store each skid on a flat surface and protect them from overturning.
Do not stack skid on top of each other.
Until installation, do not dismantle the packaging.
Store the Filter Media indoors or in a shaded location to protect them from exposure to direct sunlight.
Ensure the media are only stored in a clean environment.
Store each media bag on a flat surface and protect them from overturning.
Cover any loose media with polythene to keep them clean and to protect from the weather.
10
3. Equipment Installation
3.1 Installation of Underdrain blocks
3.1.1 LP Block Filter Floor Overview
Figure 3.1.1 shows the components and terminology that make up an LP Block filter floor installation.
* NOTE :
For FlumeFlow applications figure 3.1.1 differs ;
A Flum Flow Interface Plate replaces 1 end plate and Hips bridging is not required.
11
* NOTE :
Hyorim Industries Inc. must be informed of any dimensions that are out of tolerance and prior to
attempting any field modifications.
* NOTE :
The filter floor must have a rough surface to provide a key with the grout. Do not paint or any
water-proof works of the surface areas where grout will be installed.
Survey each filter floor to determine the high point and low point using the recommended level.
Check the deviations against the drawing theoretical dimension. If the floor is outside the allowable
tolerance or if the difference between the high point and low point is greater than 30mm, either chip out
or grind out the high level areas to meet tolerances. Re-check the filter floor to determine the new high
point and mark this point as high point datum for use when installing the anchor rods,
* WARINING
Do not fill the low spots as thin screed over the floor may become detached at some point in the future,
which may compromise the operation of the filter.
For dual bay filters, which have two cells either side of a backwash flume, level the floor of each bay so
that the maximum difference between the high points in each bay is less than 12mm.
13
Figure 3.5.1 Typical air pipe and anchor rod layout for a side flume
14
* NOTE :
The assembly of individual LP Blocks into Laterals should be done close to the final location of the Lateral
in order to minimize the amount of lifting.
* WARINING
Care Should be taken when assembling the Lateral as attempting to separate the joint after assembly
may result in damage.
Refer to site specific Lateral Assembly. Ensure that this drawing is available to view at all times whilst
assembling the Laterals.
In order to keep the Media Retention Plates clean during installation, it is necessary to protect the upper
surface immediately after the LP Blocks are unpacked from their delivery pallet. Pre-cut self adhesive
protection sheets are supplied by Hyorim. Peel off the backing and fix to the upper surface of the Media
Retention Plate. Ensure that the protective sheet does not overhang the edges of the Media Retention Plate
as this will make removal difficult following grouting. Apply pressure to the protective sheet if necessary
around the screw heads to ensure that it lays flat on the Media Retention Plate surface.
15
* NOTE :
LP Block installations require only one Endplate, located at the opposite end to the per Lateral.
However, central and side Flume LP Block installations require two Endplates per Lateral, which are located
at opposite ends of the Lateral.
1. The standard Endplate is designed to be fitted to The spigot end or The cut end of an LP Block.
2. Immediately before installing the Endplate, inspect the components to ensure all are thoroughly clean
inside.
3. Stand the LP Block vertically and apply Sikaflex 1A sealant to the mating face of the LP Block
external and internal walls (Figure 3.6.1a) then press the Endplate into place. Ensure that there is a
complete seal between the LP Block and the Endplate (Note: one tube of sealant will be enough to
install approximately 7 Endplates)
4. The Endplate must now be held in place immediately by staples into the end of the LP Block walls.
Use minimum 14 No. Stainless Steel 316 staples (Figure 3.6.1b). View inside the LP Block to ensure all
staples have penetrated the walls and replace / re-staple as necessary.
16
3. Press the FlumeFlow Interface Plate firmly into position, ensure that it fits squarely and tightly up to
the face of the LP Block. Continue to apply pressure and drill a 5mm pilot hole in each side of the
LP Block, 10mm from the end of the LP Block, then retain by 2 Hexagon head self tapping screws
supplied by Hyorim (Figure 3.6.2c).
* NOTE :
Abrade the surfaces of the sealant rebate in FlumeFlow Interface plate with abrasive paper and clean
these surface with Sika Cleaner-205 to remove dust and grease.
17
* WARINING
Lubricate the O-Ring with care to avoid contamination of the sealant.
Place two LP Blocks together with the bottom of the LP Blocks on the floor and the spigot / socket oosely
engaged. Use the assembly tool to join the individual LP Blocks (Figure 3.6.3c). Whilst making the joint,
ensure that the underside of the LP Blocks remain flat on the ground by applying downward pressure to
the free end of mating LP Blocks. Ensure that the End plate are not dragged loose during this operation.
18
* NOTE :
Each joint must be inspected for these conditions and corrected if not properly assembled before
proceeding to the next Block.
19
* IMPORTANT :
Variations in ambient temperature have a significant effect on grout curing successfully.
Failure to follow the specified guidelines relating to ambient temperature will affect the quality of the grout
installation and potentially cause future problems with the filter floor.
* IMPORTANT :
During the Level work using Support Plate, the Error should not be over 3.0mm. When the level
difference between each other basin floor is occur by the civil error, it is Ok with remain but it shall be
20
21
* WARINING
Ensure that the sealant rebate is free from grout and loose debris. Clean the sealant rebate, with Sika
Cleaner 205, to remove grease. The sealant must be introduced with care to ensure that a full and
complete seal is created. Air voids caused by incorrect application of the sealant could cause the seal to
fail in operation.
Figure 3.7.2.3c
Figure 3.7.2.3d
Figure 3.7.2.3e
* NOTE :
Once all the FlumeFlow Interface plates have been sealed to the concrete flume wall; then the floor
installation must be left for 7 days to allow the sealent surface to cure prior to grouting the joints.
Before placing the mortar, it should be protected by using the PE cover sheet, such as the Figure 3.7.3
(a), in order to prevent clogging of the media support plate on the block top.
Figure 3.7.3(a)
23
Figure 3.7.3(b)
After placing the mortar with the period of 1-2 curing days, remove the PE cover, and clean the block
top surface by using a vacuum cleaner. Figure 3.7.3(c)
Figure 3.7.3c
* NOTE :
Ensure that where anchor rods are fitted, the grout fully fills the void between the anchor road and HIPS
bridging.
24
25
* NOTE :
Allow the grout to set for 7 days before adding any water or media to the cell
After 7 days, the filter should be ready for testing and subsequent placement of media.
* NOTE :
If the media is not to be install at this point, the filter floor should now be covered with 6mm plywood a
minimum of 1 meter deep clean chlorinated water. This will eliminate risk of damage from falling objects,
as well as aid in temperature control.
26
27
28
29
30
31
32
33
34
36
37
2014.01
NO.
DATA
0.5~3
ITEM NO.
CODE.
REV.
NO.
SCALE
(MM)
3
38
39
Filter Section
42
43
NOTE.
1. BM 1SET .
2. 12SET .
3.
2
1
2015.04
2015.02
2014.01
NO.
DATA
44
0.5~3
0.2
0.3
0.5
0.8
1.2
2.0
ITEM NO.
CODE.
SCALE
4.0
REV.
NO.
* IMPORTANT :
The LP Blocks may or may not have been supplied with Media Retention Plates fitted. For installations with
Media Retention Plates, a layer of gravel to support the media is NOT required.
4. Testing
4.1 General Testing Guidelines
Prior to media placement, the LP Block Dual Parallel Lateral system must be tested with water and air to
confirm proper installation.
* NOTE :
Allow the grout to set for at least 7 days before testing the filter cell.
Make sure the backwash water / air system is operational. As a minimum the following tasks must be
completed :
1. The filters open / close valves have been tested and are operational.
2. All flow control loops have been tested, calibrated and functional.
3. Backwash Pump and surface wash pump are operational.
4. Ensure an adequate supply of clean potable quality, chlorinated or otherwise disinfected water is
available for testing.
* WARINING
Note that the use of any other water may damage the Media Retention Plates.
* WARINING
Naver allw a pump to deliver its full capacity to the filter upon start up. This will cause shock loading
and may resultin disruption to the LP-Block Dual Parallel Lateral filter floor. Always use soft starting pump
isolation valve and, additionally, ensure tat all water pump are slowly increased up to their full operating
pressure as outlined below.
1. Ensure that the backwash system is free of air and fully pressurized. The contractor and engineer
should review the piping system and ensure that operational air release valves have been installed at
all relevant high points.
2. Slowly fill the filter with clean water at a rate of 5m3/h/m2. Let the water level rise to 150 mm
above the LP-Block Dual Parallel Lateral filter floor. Where Media Retention Plates are fitted, allow the
plates to soak for at least 2 hours before proceeding further.
46
47
5. Operation
5.1 General
The consulting engineer as a part of the complete water treatment plant operation usually provides
operating instructions, specific to a job. Consult with the engineer to determine the required backwash
water flow rates before conducting any backwashes.
49
50
51
52
53
54
55
56
6. Maintenance
6.1 General Maintenance Guidelines
No periodic maintenance is required, however, at any time a filter is taken out of service and media and
gravel are removed, check the following:
1. LP Blocks (Media Retention Plate not fitted) Check for damage. Check top orifices for any blockages.
2. LP Blocks (Media Retention Plate fitted) Check Media Retention Plates for damage check pores for
any blockages.
3. Grout - Check grout between the LP Blocks and at the walls for damage. Repair as necessary.
If any repair work has been undertaken then the complete LP Block Dual Parallel Lateral cell floor must
be re-tested in accordance with Section 6 testing procedures.
57
TETRA LP BlockTM
Dual Parallel Lateral Underdrain
Efficient and Effective Drinking Water Filter Floors
TETRA LP BlockTM
Dual Parallel Lateral Underdrain
650.0046.5 NOV/12
58
TETRA LP BlockTM
Drinking water dual parallel lateral underdrain
In municipal drinking water applications or pre-treatment for desalination plants using
gravity filters, the filter underdrain is one of the most important components contributing
to overall system performance and operation whether a new filter design or retrofitting
an existing filter.
The TETRA LP BlockTM dual parallel lateral underdrain from Severn Trent Services is
a proven design of filter underdrain offering superior distribution of both backwash air
and water, either sequentially or concurrently. The system is NSF61 and UK Secretary of
State approved and also has certification for use with drinking water applications in other
countries.
Effective media cleaning is the key requirement for a filter to function efficiently under all
loading conditions. Backwashing gravity or upflow filters is necessary to remove the solids
collected by the media during the filtration run. In the TETRA LP Block underdrain, air and/
or water is distributed evenly across the entire filter bottom during the backwash cycle to
effectively remove and release solids from the filter. The use of concurrent or sequential air
and water significantly reduces the volume of dirty backwash water produced and drastically
lowers operating costs through the uniform backwash process.
The TETRA LP Block underdrain ensures lower operating costs and effective backwash
distribution that can improve run times.
U BLOCK
CURRENT LP BLOCK
NEW ANCHOR-RITE
LP BLOCK
The TETRA LP Block underdrain features the unique and patented* (US20100314305)
Anchor-Rite and (US Pat. No 6,110,366) GroutGripTM design. The GroutGrip increases
resistance to uplift from the filter floor and the Anchor-Rite fastens the block to the floor.
The LP Block with GroutGrip includes six rows of integrally molded dovetail wedges
that become embedded in the floor grout, offering 1.75 times the pullout strength of a
conventional underdrain block. The LP Block with Anchor-Rite is bolted to the filter floor
to prevent buoyancy. GroutGrip is integral to the block; the Anchor-Rite is optional.
*Patent Pending
59
Benefits
:: Excellent distribution of
backwash air/water - more
efficient bed cleaning and
reduced filter operating
costs
60
Principle of Operation
The TETRA LP Block underdrain provides an improved distribution of backwash water to the filter
media through the use of dual compensating laterals. Backwash water enters the primary laterals
and then passes through the control orifices into the secondary laterals.
Backwash air is properly distributed by the careful design of the upper control orifices between the
primary and secondary laterals, providing even air distribution.
Media retention plates maximize the available filter tank depth. Careful quality control and testing
during the plate manufacturing process is used to ensure that the media retention plates prohibit
media pass through and provide proper flow characteristics. Severn Trent Services should be
consulted on the use of media retention plates when lime softening or alum coagulant are used
upstream as these are known to potentially plug the plates.
Technical Data
Product Specification - TETRA LP Block
Length
Width
Height
Weight
20.3 cm (8)
Approvals
:: UK Secretary of State and NSF61 certification for use with drinking water treatment
:: Local approval
Materials
:: Constructed of HDPE
Secondary
Laterals
Bolt Hole
Distribution
Orifices
Control
Orifices
Primary
Laterals
61
Air Header
:: Engineered for specic backwash requirements
62
Filter Construction
1) A ume or trough is formed in the bottom of the lter cell.
The backwash air header is installed within this trough or, if
required, can also be mounted above the lter TWL. Steel
reinforcing bars are used over the ume area to anchor the
ume blocks down.
2) The TETRA LP Blocks with retention plate tted are preassembled into rows and then installed onto a bed of grout on
the lter oor. Bridging strips prevent the grout falling into the
ume.
63
Benefits
19 mm (3/4)
64
Represented by:
650.0046.5 NOV/12