Escolar Documentos
Profissional Documentos
Cultura Documentos
MASTER OF TECHNOLOGY
IN
POWER SYSTEM AND CONTROL AUTOMATION
Submitted by
A.PRAVEEN
Under the esteemed guidance of
Sri V.MANIKANTA
Project Engineer (SCADA)
CHEMTROLS INDUSTRIES LTD.
A.P.E.P.D.C.L
Visakhapatnam
ACKNOWLEDGEMENT
We express
Sri
our
profound
V.MANIKANTA,
Project
Engineer
(SCADA),A.P.E.P.D.C.L
Visakhapatnam for his valuable guidance rendered by his throughout the project.
We sincerely extend our gratitude to Prof. Dr. K. NARASIMHARAO, to
Head of the Department, Electrical And Electronics Engineering, and Dr. T. Sirish
Associate Professor for their co-operation which helped us to complete this project with in
the time.
We extend our gratitude to A.P.E.P.D.C.L, Visakhapatnam officials for
providing us all the necessary help and guidance at every stage of collecting data.
BY
A.PRAVEEN
M. Tech
Certificate
This is to certify that the project entitled IMPLEMENTATION OF SCADA/DMS
FOR 33/11 KV SUBSTATIONS IN VSP CITY is a bonafide work done by
A.PRAVEEN, Registration no:15131D5303.
InternalGuide
ABSTRACT
SCADA stands for Supervisory Control and Data Acquisition. As the name
indicates, it is not a full control system, but rather focuses on the
supervisory level. It is a computer system for gathering and analyzing real
time data. SCADA systems are used to monitor and control a plant or
equipment in industries such as substations, telecommunications, water
and waste control, energy, oil and gas refining and transportation.
A SCADA system gathers information,
such as substation information, where a leak on a pipeline has occurred,
transfers the information back to a central site, alerting the home station
that the leak has occurred, carrying out necessary analysis and control,
such as determining if the leak is critical, and displaying the information in
a logical and organized fashion. SCADA systems can be relatively simple,
such as one that monitors environmental conditions of a small office
building, or incredibly complex, such as a system that monitors all the
activity in a nuclear power plant or the activity of a municipal water system.
This paper describes the SCADA systems in terms of their architecture,
their interface to the process hardware, the functionality and the application
development facilities they provide.
INDEX
1. Introduction to A.P.E.P.
6-9
2. Introduction
10-12
13-22
23-42
43-56
57
Chapter-1
INTRODUCTION TO A.P.E.P.D.C.L
The Eastern Power Distribution Company of Andhra Pradesh Limited,
with its Head Quarters at Visakhapatnam, comprises five districts
namely Srikakulam, Vizianagaram, Visakhapatnam, East Godavari
and West Godavari.
There are 15 Nos. 220KV Sub-Stations, 55 Nos. 132KV Sub-Stations and
587 Nos. 33KV/11KV Sub-Stations in the APEPDCL area catering to the
needs of different categories of consumers at the end of July 2014.
There are 29 towns in this DISCOM area, and all the towns have line losses
to the tune of 4.87%.
APEPDCL is responsible for undertaking distribution and bulk supply of
power in the operation circles of Srikakulam, Visakhapatnam, Vizianagaram,
East and West Godavari districts and 20 Divisions of Coastal Andhra
Pradesh. APEPDCL supplies power to over 49.7 lakh consumers belonging
to different categories through a network consisting of 587Sub-stations of 33
KV level, 2322 feeders of 11 KV level and more than 1,27,487 distribution
transformers of different levels
APEPDCL, Visakhapatnam is the leading Indian power utility serving a
consumer base of nearly 4 million spread across five districts in the southern
state of Andhra Pradesh. It has always been a pioneer in delivering
technology centric customer care services to its customers. EPDCL has the
lowest AT&C losses and one of the best in terms of operational efficiency
BACKGROUND
Visakhapatnam Circle:
Geographical Information
This circle covers the Visakhapatnam district, which is one of the
North Eastern coastal districts of Andhra Pradesh. It is bounded on
the West and partly on the North by Orissa State. Vizianagaram
district constitutes a part of its northern boundary. On the East is the
Bay of Bengal and the Southern boundary of the district is formed by
East Godavari District. The district can be divided into two distinct
divisions the hilly region of the Eastern Ghats called the agency
division and the plain area (coastal and interior) called the plain
division.
Industry & Tourism
Agriculture is the mainstay of 70% of the households. Visakhapatnam
city has a number of big industrial and Government establishments
including the Vizag Steel plant, HPCL, BHPV and one of the busiest
major ports in the country. Employment in these establishments and
fishing are hence important occupations of a section of the population
as well.
A number of areas of tourist interest in the district are popular. Among
them are Simhachalam Devastanam,Kanaka Mahalakkshmi Temple,
Araku valley, Borra caves, Visakhapatnam city, Rishikonda beach etc.
There are four operation divisions in the circle namely Zone-I, Zone-II,
Anakapalli and Paderu
7
2)
3)
4)
5)
6)
7)
A pilot project of providing 33KV and 11KV UG cable over 6.5 Kms
in Visakhapatnam City was completed at a cost of ` 6.54 Crs to
provide quality power.
8)
Under RGGVY 62,415 Nos. BPL services and 9994 Nos. APL
services were released.
9)
10)
5865 Nos. school services were released out of 8847 Nos. targeted.
11)
12)
Chapter-2
INTRODUCTION
An electrical power system should ensure the availability of electrical
energy without interruption to every load connected to the system. Among all the
systems, electrical energy is quite transferable to the consumers by transmission
and distribution systems. The power supply to the consumer should not disturbed
and the agencies which supplies the power without interruption. As industrial
processes and plants have become more complex and extensive, the demand for
improved reliability of electrical power supplies has also increased. The potential
costs of outage time following a failure of the power supply or plant have
accordingly risen dramatically as well. If at all any fault happens in the system the
fault system has to be isolated so that other system should not be disturbed. This
is a challenge to the engineers to supply the uninterrupted power to the
customers. To attain this, logical and fast acting protective equipment is required.
Chapter-3
INTRODUCTION TO THERMAL POWER PLANT
10
BOILERS
Thermal Power Plant has 5 Boilers each of 330 T/hr. steam capacity at
101 KSCA and 540O C. The boilers are of BHEL make, capable of firing
combination of fuels namely, Coal, Coke Oven Gas, Blast Furnace Gas and Oil.
Normally 4 Boilers are kept in full load operation to produce 247.5 MW of power,
supply steam to 2 Turbo Blowers and process needs. Boilers outlet flue gas is
passed through Electro Static Precipitators to control air pollution.
TURBO GENERATORS
Thermal Power Plant has 4 Turbo Generators, three of 60 MW capacity
each and the fourth 67.5 MW . Special features of the turbo sets are :i)
ii)
iii)
TURBO BLOWERS
11
VSP has 2 Blast Furnaces. To meet the blast air requirement, 3 Turbo
Blowers, each of 6067 NM3 /min capacity, are installed at TPP. These blowers
are of axial type and are the largest blowers installed in India. The blowers are
provided with suction filters, pre-coolers and inter- coolers.
AUXILIARIES OF TPP
These include coal conveyors, cooling towers & pump house No-4 for
cooling water system, pump house for ash water, ash slurry , fire water and fuel
oil & HSD air compressor station, emergency Diesel Generators, electric switch
gear for power distribution, ventilation and air conditioning equipment etc. The
entire power generated at Back Pressure Turbine Station and Gas Expansion
Turbine Station is transmitted over 11 kV cables to power plant, stepped up
through a 220 kV transformer at LBSS5 and transferred to plant grid.
12
Furnace and Sinter Plant for air conditioning purpose at 7 0 C. The return water
temperature is 160 C.
13
TPP ELECTRICS
There are 3 Generators present in the TPP.
generator is 60 MW, Generation of the voltage level 11kV, total generation is 180
MW out of this 30-40 MW are consumed by the Blast furnace, Steel Melting
Shop, Coke oven, Rolling mills and 30-32 MW is consumed by the TPP
auxiliaries. Remaining 110 MW is connected to LBSS5. In addition to this there
is one generator (TG-4) rated at 67.5 MW, 11 Kv, 90 MVA. There are two Gas
Expansion Turbines (GETS) and two Back Pressure Turbines (BPTS) rated 12
MW & 7.5 MW respectively. From this 20 MW is supplied to LBSS5. LBSS1
consumes a load of 40 MW.
consumes a load of 5 MW. There are two APSEB tie lines connected to MRS for
exporting and importing depending upon the conditions.
GSB-1
Generator Switch Board-1 is a 11 kV, 4500 Amps, 3 section board, located
at 0 meters in TPP. Each 60 MW generator is connected to each section of the
board. The bus is provided with a bus coupler and the bus coupler 4500 Amps
reactor between section-1 & 2 as well as between section-2 & 3. To sections-1 &
3 of GSB-1 350 MVA, 220 kV/11 kV are connected. Out of these 3 transformers,
two are always in operation and the other one is standby. The 220 kV side of
14
distributed through the 220 kV network of the plant. All the critical loads of the
steel plant i.e. Water supply, Blast furnace, Steel Melt shop and Coke oven are
connected to GSB through 11 kV cables. In addition all the TPP auxiliaries are
also connected to GSB-1. All outgoing feeders are connected to GSB through
link-reactor and Minimum Oil Circuit Breaker (MOCB) in addition to earthing
switches.
Turbo Generators of TPP normally operate in parallel with state grid. All
three generators of each 60 MW are connected to Generator switch board. This
GSB-1 is a 11 kV 4500 Amps, 3 selection board located at 0 Mt level in AA bay.
All category-1 loads of the steel plant are connected to GSB-1 through 11 kV
cable. Power is evacuated through 50/63 MVA (11kV/220kV) transformer 1, 2 & 3
which are connected to Section-1 and 3 of the GSB-1. Synchronisation facility
exists for any of the incoming generator, 50/63 MVA Transformer-1, 2, 3.
ISLAND OPERATION SCHEME :A scheme has been envisaged at TPP to get isolated form the grid in case
of system disturbance or low frequency condition with ABB make relay type FCX
103b relay with following settings:
df/dt 2 cycles/sec rate of fall below 50 HZ
1st stage 47.5 HZ FOR 0.5 SEC.
over frequency 51.5 HZ with time delay 150 MS
2nd stage 46.9 HZ with 1 sec. delay
POWER REQUIREMENT
15
Annual Energy
(106 kW Hrs.)
Average Demand
(MW)
RMHP
35
4.0
CO & CCP
171
19.5
SINTER PLANT
254
29.0
BLAST FURNACE
210
24.0
126
14.5
LMMM
100
11.5
WRM
118
13.5
MMSM
100
11.5
CRMP
35
4.0
TPP
310
35.0
ASP
258
29.5
131
15.0
AUXILIARY SHOPS
20
2.5
WATER SUPPLY
15
2.0
1.0
TOWNSHIP
28
3.0
LOSSES
14
1.5
TOTAL
1932
221.0
SHOP
SOURCES OF POWER
16
exported to APSEB.
The agreement with APSEB provides for a contract demand of 150 MVA
and permit export of power. Tariff for import, export, demand charges, penalties
etc. are stipulated. For purpose of billing, import and export energy is separately
metered at Main Receiving Station.
17
operate in parallel with state grid. Excess generation over and above plant load is
exported to AP TRANSCO.
The agreement with AP TRANSCO provides for a contract demand of 150
MVA and permit export of power.
paralleled & transformer feeders (T1, T2, T3, T4 & T5) can be either connected to
Bus-1 or Bus-2 or distributed between Bus-1 & Bus-2 depending on
operational/maintenance requirement.
breakers. Synchronising facility exists only for tie lines ML1, ML2, ML3, Bypass
and Bus coupler breakers at Control & Relay panel of LBSS-5 located in ECR.
The loads (lines or transformers) can be transferred form Bus-1 to Bus-2 and vice
versa live through On Load Bus Transfer scheme (OLBT). A typical single line
diagram is enclosed.
SYNCHRONISATION
18
(2)
(3)
closed at (or very near) the instant of the two voltages have correct
phase relationship.
Synchronisation facility exists for any of the incoming generators, 50/63
MVA Transformer 1, 2 & 3, Bus couplers and Bus couplers with reactors at 11
KV. The synchronising operation is to be carried out using synchronising trolley
in ECR.
19
Chapter-4
THEORETICAL REVIEW OF RELAYS
TYPES OF PROTECTIONS: Two types of protection:
1.
Primary protection
2.
Backup protection
Primary protection :Primary protection is the first line of defence and primary relays clear faults
in the protected section as fast as possible. 100% reliability is not guaranteed for
protective scheme and also for associated CTs, PTs and CBs. Therefore some
sort of backup protection must be provided.
Backup protection :Backup relays operate if the primary relays fail and cover not only the local
station but the next one also and have a time delay long enough for the primary
relays to operate if they can.
ELECTROMAGNETIC RELAYS
These are earliest form of relays devices used for power system protection
and till now they are the most widely used variety relays. All these devices
depend upon electromagnetic interaction and have mechanical movement
associated with them which Actually make or break pairs of contacts indicating
relays operations. The electromagnetic interaction is manifested either in form of
20
F = KI2
------------ (1)
INDUCTION RELAYS
Induction type relays are the most widely used for protective relaying
purposed involving A.C. quantities. Torque is produced in these relays when one
alternating flux reacts with the current induced in the rotor by another alternating
flux displaced in time and space but having the same frequency. These relays
are classified depending on the type of rotor. If the rotor is a disc, is known a
induction disc relay. If the rotor is a cup, the relay called as induction cup relay.
The Actuating force is given by F = K 1 2 Sin
---- (2)
21
DESCRIPTION
Reference
Make
Type
27A/27B
EE
VAG 31
27 G
EE
VAG 21
32 G
EE
WCD11
37GA/GB
EE
WCD13
40 G
EE
YCGF11
46 G
EE
CTN31
50T/51G
EE
CTU62
51 V
EE
CDV62
59G1/59G2
EE
CAGM22
64V
EE
VDG14
67RYB
EE
CDD21
67W
EE
CDD21
68A/68E/68PM
EE
VAGM-61
78G
EE
ZTO
87G
EE
CAG34
64G
EE
CAG14
81G
64S/50X
ABB
FTG11
RX1428X
RX12 21
22
When there is no fault in the generator winding for through faults the
current in pilot wires fed from CT connections are equal.
The difference in
current I1 -I2 is zero. When there is a fault inside the protected winding, the
balance is disturbed and difference current (I1- I2) flows through operating coil of
the relays.
Relay settings:
Plug setting
R
0.1
Range
B
0.1 0.1
0.05 to 0.2
CTR- 4500/1A
To
External & Internal circuit connections of generator stator earth fault relay
10%
10%
10%
Range
K3
7.5%
10%
1.78
15%
20%
7.1
30%
16
GENERATOR VOLTAGE
CURRENT RELAY
25
RESTRAINED
OVER
Fault conditions cause a greater drop in busbar voltage than normal over
load, and this fact has been utilised in voltage restrained over current relay. The
relay has two operating characteristics viz. An over load characteristics
determine by the operation of instantaneous under voltage unit monitoring the
generator voltage. Under over load conditions, when the generator voltage is
usually near normal the instantaneous under-voltage unit is energised and the
short across the resistor in the shading coil circuit is removed. Below figure
shows the internal connections diagram.
The relay operates on a long IDMT under fault conditions, when the
generator voltage falls to the setting of the under voltage unit, the resistor is short
circuited and the torque on the disc increased by 2.5 times so that the normal
26
setting currents are 0.4 times those marked on the plug board, and the relay
operates in Accordance with the fault characteristic.
Both characteristic of the relay as shown in figure.
30 20 10 8
1.5
1.5
20
15
10
3.5
2.6
2.2
Plug setting
Time multiplier
CTR -
1.5
1.5
1.5
4500/1A
27
10
10
15
15
20
20
Plug Setting:
R
Range
0.5 -2A
28
CTR - 4500/1A
PSM :
1
1.3
30 20 15 10
2.5
3.5
9 10
12
2.8
14
2.6
16 18 20
2.4
2.2
directional element of the earth fault relay. The relay inverse time characteristic
scale is shown in figure below.
Relay settings:
Plug setting
- 0.1
Range
TMS
- 0.1
0.1 to 0.4
29
CTR-
4500/1A
PSM :
1
1.3
30 20 15 10
2.5
3.5
9 10
12
2.8
14
2.6
16 18 20
2.4
2.2
0.95
0.5 - 2 Amps.
Time setting
10 sec.
Instantaneous setting
6- 60 sec.
relay characteristic, the relay will operate when the generator first starts to slip
poles and will trip the field breaker and will trips the field breaker and disconnect
the generator from the system.
R-X diagram
knowledge of the operating conditions. i.e. the maximum rotor angle at which the
Machine can operate within the stability limit. In general practice is to use an
offset setting equal to half the Machine transient resistance and a circle diameter
equal to synchronous reactance of the Machine X s for rotor angle upto 900. The
external connection diagram of YCGF field failure relay is shown in figure.
31
The relay movement is a high speed induction cup unit with operating,
restraint and bias windings adjusting the ohmic values of the diameter and offset
of the relay characteristic circle is provided by the combination of plug board and
potentiometer settings K1 K2 K3 K4 and K5.
obtained by injecting voltage from the current circuit through transactor. Taps for
this transactor are brought out to plug board K 3 K4 and combinations of two plug
settings provide adjustment of offset settings. K 5 allows course adjustment of the
characteristics circle diameter by selection of taps on an auto-in the resistance
circuit.
0.9
K2
10
32
K3
K4
10
K5
170
25 x 112
100 x 75
18.15 .
4500/1
11000/110
= 200%
112
75
4500/1 = 145.2
1100/110
33
A single earth fault is not in itself dangerous since it does not cause any
fault current, but a second fault effectively short circuits or all parts of the field
system and the unbalancing of the magnetic force caused there by may be
sufficient to spring the shaft and make it eccentric. If the condition were allowed
to persist, however it might lead to reverse mechanical damage.
The figure
shows the method detection using the principle of negative potential biasing,
where by an earth fault any where in the field circuit can be detected. The d.c
supply injection establishes a small bias on the alternator field winding circuit so
that are points are negative with respect to earth.
The rectified output of a transformer fed from the station L.V supply
provides a biasing potential approximately 30v. This is connected with positive
terminal through a current limiting resistor and the secondary winding of
transductor to the positive pole of the field circuit. When a fault occurs current
flows in the bias circuit and the dc winding of the transductor. This results in
saturation of the transductor core which reduces the impedance of the A.C.
winding thus allows the relay A to operate. Thus giving alarm for first rotor earth
34
fault.
Under this
conditions i.e. when auxiliary supply fails the relay B which will be in picked up
condition when the auxiliary supply is available will drops off when auxiliary
supply fails. This then n.c Contacts of the relay B will get through for A.C.
failure alarm circuit.
Technical data
0-450 v d.c
Bias voltage
30v d.c
Sensitivity
1ma DC 10%
Setting of the first rotor earth fault is 1mA. The circuit diagram of first
rotor earth fault is shown in enclosed figure.
This is
because if allowed to run with an E/F on the rotor a subsequent second earth
fault can cause severe damage to the Machine. However a relay which can
detect such a second rotor earth fault and trip out the Machine can make it
possible to run the Machine even with single earth fault with out any such risks
thus helping to preserve the generation Capacity.
The heart of the second rotor earth fault detection scheme is a very
sensitive transductor element. The AC winding of the transductor is connected in
series with a rectified AC voltage relay A. The DC winding of the transductor on
the other hand is connected in series with field earth fault circuit.
35
energised.
When second rotor earth fault occurs a DC current flows through the
transductor DC winding which causes the impedance of the AC winding to reduce
considerably by driving the transductor core into saturation. Hence the applied
voltage is fully available across the relay and the latter operates.
The selector switch SW1 on the generator panel will have 4 (four)
positions as follows.
1.
2.
Balance
3.
Test
4.
Normally the selection of switch will be put in position 1 in which the first
rotor earth fault relay will be in service. If the occurrence of the first rotor earth
fault of any one machine, the selector switch of the machine is put in position-2.
Connecting the coarse control potentiometer across the field winding circuit of
the affected machine.
Simultaneously the milli-ammeter is also inserted in the circuit. As can be
seen from the figure, the portions of the field winding on either side of the first
rotor fault and the coarse control potentiometer forms a DC bridge with millammeter connected across a pair of nodes. By adjusting the coarse/fire control
36
and the range selector switch of the milli-ammeter the bridge is balanced to mull
point. The selector switch is kept in position-3 in which milli-ammeter is replaced
by relay, but the relay trip circuit is isolated. After making sure that the relay does
not pick-up then the SW1 is turned to position-4. Thereby putting the second
rotor earth fault relay complete in service.
Protection against prime mover failure (Need of low forward power
relay and reverse power relay ): The effect of prime mover failure is to cause the
machine to motor by taking power from the system which may result in severe
mechanical damage and, in addition will impose a heavy motoring load on the
generator. The reverse power relay is normally used for two applications as a
reverse power relay to trip the generator when the machine starts motoring and
as a reverse power interlock device to prevent the possibility of a turbo-generator
set overspeeding should a steam valve fail to close completely after the
generator circuit breaker has opened on a fault.
Use a low forward power interlock instead of reverse power interlock. So
that it is not necessary the delay the generator circuit breaker tripping till the set
has actually started motoring. When low interlock with normally closed contact
as soon as the power supplied by the generator falls below O 5 % of rated
power the low power relay resets and completes the tripping circuits to the
generator circuit breaker.
is used. Reason is that other earth fault relay senses earth current of higher
magnitude. But when there is a earth fault near to the neutral it may not be
possible for the machine voltage to drive that much higher current. So one earth
fault relay having very low current operating unit is used for sensitive earth fault
relay. Since it is a low current setting relay it may mal operate. To protect it from
mal operation we have used another relay which will sense earth fault current in
earthing transformer neutral which will ensure that definitely some earth fault is
present. This may operate generator terminal earth fault also. To prevent to do
so we have put over current relay 50 X which will sense over current and prevent
the earth fault relay to operate.
RELAY SETTINGS :
64GS -
2.5 ma
CTR -
4500 / 1A
50 X -
contains two separate relays. One is IDMT/INST over current relay for phase
faults and other one is IDMT earth fault relay for earth faults. The partial
differential relay will act when either of those two relays are acted.
IDMT/INST over current relay:
Plug setting
IDMT
Range
B
38
TMS
0.5-2
Range
TMS
Instantaneous setting - 4
IDMT earth fault relay :
Plug setting
0.1
0.1 - 0.4
0.2
GENERATOR OUT OF STEP RELAY :A CAG 19 relay serves as an over current starter and this is set at
between 50 and 20% of nominal current. Based on 5 A CTs below the current no
operation can occur.
ignore all conditions of load other than those which produce a reversal of power
flow such as would occur with a condition of pole slip or power swing exceeding
90O.
power sourcing and a pole slip condition. A trip condition can only occur if the
timer has timed out before the fault moves into the blinder operate region. If the
fault never reaches the operate region of the blinder or moves between the
directional and blinder characteristics in a time less than the time setting than no
operation will occur. The relay consists of a directional unit and a reverse reach
blinder based on the YTG Mho type static relay measurement technique and
incorporates these components.
39
blinder unit also with a variable lag angle (2) setting between 50 to 75 O which
has reverse resistive reach setting between 0-25 ohms and 32 ohms.
Since it can deal only with a pole slip condition emanating from are
direction.
generator.
R1 = 0.90 to 1
R2 = 0.55 to 1 R3 = 0.5 to 32
Chapter-5
40
and one
generator of 67.5 MW capacity. Our generators are floating neutral type. As our
planet is captive power plant generators are connected to 11 KV Bus (GSB1).
The 11 KV is stepped upto 220 KV through two 220KV/11KV power transformers.
The 220 KV sub station is names as LBSS-5. We earthed our system at GSB-1
through three earthing transformers. Out of three transformers two transformers
are taken to service.
60 MW
MVA rating
75 MVA
0.8
Rated voltage
11000 Volts
Rated current
3936 Amps
Rotor voltage
300 Volts
Rotor current
596 Amps
Connection
Star
41
Speed
3000 rpm
Coolant
Air
Winding type
Double layer
18.8%
19.7%
12.9%
67.5 MW
MVA rating
84.375 MVA
0.8
Rated voltage
11000 Volts
Rated current
4429 Amps
Rotor voltage
307 Volts
Rotor current
624 Amps
Connection
Star
Speed
3000 rpm
Coolant
Air
Winding type
Double layer
21.45%
20.92%
11.57%
ON AN 50000
ON AF 63000
Rated voltage
Rated current
HV
220 kV
LV
11
kV
HV
LV
ON AN
131.2 A
2624.6 A
ON AF
165.3 A
3307.0 A
Frequency
50 Hz
22.67%
42
21.58%
16.79%
9000
Rated voltage
HV
220 kV
LV
11
Rated current
kV
HV 236.2 A
LV 4723.8 A
Frequency
50 Hz
Impedance voltage
11.6%
FAULT CALCULATIONS
Choose a system base of 100 MVA and base voltage as 11 kV at all
Generators. The impedance voltages on 100 MVA base are as below.
= 0.172 pu
Generator TG-4
100
112
Positive sequence impedance or reactance, XG1 (pu) = 0.2145 x --------- x -----84.375
112
= 0.2542 pu
100
112
Negative sequence impedance or reactance, XG2 (pu) = 0.2092 x ------- x -----84.375 112
= 0.2479 pu
100
112
Zero sequence impedance or reactance, XG0 (pu) = 0.1157 x ---------- x -------84.375
112
= 0.13713 pu
REACTORS
Reactance of reactors
= 0.2 (positive)
= 0.2 (negative)
= 1.0 (Zero sequence)
(KV2)b
112
Base reactance, Xb = ------------ = -------- = 1.21
(MV)b
100
0.2
Positive sequence reactance, of reactor = -------- = 0.1653 pu
1.21
0.2
Negative sequence reactance, of reactor = -------- = 0.1653 pu
1.21
1.0
Zero sequence reactance, of reactor = -------- = 0.82645 pu
44
1.21
TRANSFORMERS T1 & T2
100
112
Positive sequence impedance or reactance, XT1 (pu) = 0.2267 x --------- x -----50
112
= 0.4534 pu
100
112
Negative sequence impedance or reactance, XT2 (pu) = 0.2158 x ------- x -----50
112
= 0.4316 pu
100
112
Zero sequence impedance or reactance, XT0 (pu) = 0.1679 x ------- x -------50
112
= 0.3358 pu
TRANSFORMER T3
100
112
Positive sequence impedance or reactance, XT1 (pu) = 0.116 x --------- x -----90
112
= 0.1289 pu
EARTHING TRANSFORMER
Here the 11 kV bus is earthed using zigzag transformer earthing through a
14 resistance.
Actual value
14
Its pu value = --------------------- = ------- = 11.57025 pu
Base value
1.21
45
For Fault at F1 :
The Thevenins equivalent circuit for fault at F 1 is obtained by exciting the
passive Thevenins network at the fault point by negative of pre-fault voltage and
is as shown in figure enclosed.
On reducing the circuit in the enclosed figure we get
The equivalent impedance of circuit at F1 = j 0.12007 pu
1.0
Fault current, If = ----------------- = - j 8.32863 pu
j 0.12007
If (pu) = 8.32863
If = 8.32863 x base value of current
100 x 106
Base value of current = ------------------------ = 5248.6388 Amps
3 x 11 x 103
Fault current, If = 8.32863 x 5248.6388 = 43.71897 kA
If = 43.71897 kA
The contribution of each generator to the fault are given as:
Current contributed by Generator-1, IG1 (pu) = 3.99
IG1 = 3.99 x 5248.6388 = 20.942 kA
IG1 = 20.942 kA
Current contributed by Generator-2, IG2 (pu) = 1.9803
IG2 = 1.9803 x 5248.6388 = 10.394 kA
IG2 = 10.394 kA
Current contributed by Generator-3, IG3 (pu) = 1.27623
46
IG3 = 6.6985 kA
IG4 = 5.6797 kA
TMS
0.45
47
For this fault i.e. for 3- fault on GSB1, differential relay of Generator-1 will
not act since it is a through fault.
If the fault occurs before the generator circuit breaker then the differential
relay will operate to open the generator circuit breaker. The fault current remains
same if the fault occurs either on GSB-1 section or before Generator circuit
breaker or before Power transformer circuit breaker. But the relays operating at
different faults are not same.
If the fault occurs before generator circuit breaker the differential relay will
act instantly and trip the generator circuit breaker. So the remaining system will
not be effected. In the same way if the fault occurs before the power transformer
circuit breaker the transformer differential relay will act and trip the transformer
circuit breaker only, so remaining system will be unaffected.
For Fault at F2 :
The Thevenins equivalent circuit for fault at F 2 is obtained by exciting the
passive Thevenins network at the fault point by negative of pre-fault voltage and
is as shown in figure enclosed.
On reducing the circuit in the enclosed figure we get
The equivalent impedance of circuit at F2 = j 0.10699 pu
1.0
Fault current, If = ----------------- = - j 9.346745 pu
j 0.10699
If (pu) = 9.346745
Fault current, If = 9.346745 x 5248.6388 = 49.0577 kA
If = 49.0577 kA
The contribution of each generator to the fault are given as:
48
IG1 = 11.6632 kA
Current contributed by Generator-2, IG2 (pu) = 3.989
IG2 = 3.989x 5248.6388 = 20.9364 kA
IG2 = 20.9364kA
IG3 = 11.6632 kA
IG4 = 4.7949 kA
TMS
0.45
0.172632 pu
If = 906.083 A
IG1 = 476.7863 A
Current contributed by Generator-2, IG2 (pu) = 0.047182
IG2 = 0.047182 x 5248.6388 = 247.6413 A
IG2 = 247.6413 A
IG3 = 181.6554 A
0.201352
2.0135
Restricted earth fault relay of Generator-1 will operate for Earth faults at
Generator-1 terminals only.
52
EO
1.0
IR1 = IR2 = IRO = ----------------- = -------------------------------Z1+Z2+Z0
17.3553 + J 0.644805
= 0.0575796 -2.128O
Fault current If = 3 x IR1 = 3 x 0.0575796
=
0.172738 pu
If = 906.64 A
The contribution of each generator to the fault are given as:
Current contributed by Generator-1, IG1 (pu) = 0.04720235
IG1 = 0.04720235 x 5248.6388 = 247.748 A
IG1 = 247.748 A
Current contributed by Generator-2, IG2 (pu) = 0.07833
IG2 = 0.07833 x 5248.6388 = 411.1432 A
IG2 = 411.1432 A
IG3 = 247.748 A
53
0.2015
2.015
Restricted earth fault relay of Generator-2 will operate for Earth faults at
Generator-2 terminals only.
Chapter-6
54
CONCLUSION
The very purpose of protection system is to monitor the
unwanted conditions and when such conditions arise, to remove the
fault in the shortest time possible, leaving unaffected are operational.
still
superior
to
microprocessor
based
relays.
Since
55