EichleayFormulaCalculations
19982006,ConstructionExperts,Inc.
Thispaperisintendedtobeafairlystraightforwardexplanationofhowto
performEichleayformulacalculations.Itisnotadefinitivetextoncalculationof
delaydamages.Therearenormallymanycomponentstoconsiderwhen
calculatingdelaydamagesandtheEichleayformuladealswithonlyoneofthese
components.
Checkoutouronline
classes!
TheEichealyFormulaiswidelyusedasamethodofcalculatinghomeoffice
overheaddamagesinconstructiondelaycases.Thiscomponentofdelay
damagesoftenaccountsforaverylargeportionoftheamountsclaimed.
Ifyouarecurrentlydealingwithacaseorclaiminvolvingconstructiondelays
youwillprobablyneedmoreinformationthanispresentedhere.Construction
delayclaimsareamongthemostcomplicatedclaimsandalmostalwaysrequire
theservicesofanexperttobothdeterminedamagesandtodefendagainstthem.
Informationpresentedinthisarticleiscategorizedintothefollowingspecific
sections.
Thebasicformula
Asamplecalculation
ProblemsassociatedwithusingandapplyingEichleay
TheBasicEichleayFormula
ThebasicEichleaycalculationnormallycomesattheendofaprojectwhenall
workhasbeencompleted.Inthatcase,thefollowing3stepcalculationisusedto
determinedamages.
1.AllocableOverhead.Thisisacalculationtodeterminetheportionofthehome
officeoverheadthatshouldbeallocatedtothisproject.Thisprojectisexpected
topayit'sfairshareofhomeofficeoverheadandthisisawayofcalculatingthat
amount.
2.Dailyallocableoverhead.Next,wewanttodetermineadailyrateforthe
allocationofhomeofficeoverhead.
Manymoreonline
classesareavailableat
www.ConstructionClasses.com
3.Homeofficeoverheaddamages.Thisissimplyamatterofmultiplyingthe
numberofcompensabledelaydaysbythedailyallocableoverheadrate.
http://www.constructionguy.com/litigation/eichleay.htm#basic
1/3
11/8/2016
Eichleayformulacalculations
Asamplebasiccalculation
Let'sassumethatwehaveacontractamountof$2,700,00.Thecontractorhas
sufferedcompensabledelaysamountingto45calendardays.Duringthisperiod,
thecontractorhas5projectsunderwaywhoseaggregatevalueis$10,000,000.
Thecontractor'shomeofficeoverheadduringthisperiodtotaled$250,000.The
durationofthisproject,includingdelays,totals265days.Oursamplecalculation
ofhomeofficeoverheaddamagesfollows:
1.Thisproject'sallocableoverhead
2.Dailyallocableoverhead.
3.Homeofficeoverheaddamages.Thisissimplyamatterofmultiplyingthe
numberofcompensabledelaydaysbythedailyallocableoverheadrate.
Thus,inthiscase,ourcontractor'sclaimis$11,462incompensationforhome
officeoverheadthatshouldhavebeenallocatedtothisjobbecauseofthe
increaseddurationoftheproject.
ProblemsAssociatedwithapplyingtheEichleayFormula
1.TheEichleayformulaisconsideredanestimateoranapproximationand
it'saccuracycanbequestioned.Evenso,theEichleayformulaisgenerally
consideredtobeareasonablebasisforestimatingtheamountof
unabsorbedhomeofficeoverheadresultingfromconstructiondelays.
2.ItisreasonablewhenquestioningthevalidityofEichleaycalculationsto
demandthatthecalculationsbebaseduponauditedfinancialstatementsto
determineactualhomeofficeoverheadcosts.Manysmallcontractorsmay
nothaveauditedinformationavailableandevenlargercontractorsmaynot
haveauditedinformationavailableimmediatelyuponthecompletionofa
project.
3.Anobjectiontotheinclusionofcertaincomponentsinthevalueofhome
officeoverheadmayarise.Forexample,onpublicworksprojectswhich
areobtainedthroughhardbidding,thecostofadvertisingand
entertainmentmaybedisallowed.
4.SomestatecourtsmaynotrecognizeEichleayasanacceptablemethodfor
calculatingdelaydamages.
5.ItcanbedifficulttoacceptEichleaycalculationsifthedelayoccurslatein
theproject.Asanextremeexample,ifthedelayoccurswhentheprojectis
99%complete,itcanbearguedthatallallocablehomeofficeoverhead
expensehasalreadybeenpaidtothecontractor.
http://www.constructionguy.com/litigation/eichleay.htm#basic
2/3
11/8/2016
Eichleayformulacalculations
|Home|ConstructionClasses.com|
Lastupdated03/27/2006