Você está na página 1de 27

HAZOP Study of Batch Plants and Operations

Data Requirements
Definition of steps, including process conditions, agitation / mixing, charging,
reacting, discharging etc.
Interlocks in operation during step (e.g. valves held closed)
Necessary conditions to move to next step
Details of alarms, including watchdog timers

Det Norske Veritas AS. All rights reserved.

Preparations
Leader and some members should prepare before study to understand:
Hazards of the process
Control scheme, including sequence control
Cycle of operations and main process steps
Study sections to be used

Det Norske Veritas AS. All rights reserved.

Preparations
Leader must decide how to carry out the study, after preparing the following:
A matrix showing the process steps and the study sections, and showing which
section is active in which step
A chart showing which valves, drives, pumps and instruments are active in each
step of the process

Det Norske Veritas AS. All rights reserved.

Guidewords
The standard guidewords from Process HAZOP are used
Additionally, guidewords related to the following parameters are used:
- Time
- Step
- Action

Det Norske Veritas AS. All rights reserved.

Additional Guidewords: Time


NO TIME

Event or action missed altogether

MORE TIME

Event occurs after it should or takes longer time

LESS TIME

Event occurs before it should or takes shorter time

WRONG TIME

Event or action occurs when it should not

Det Norske Veritas AS. All rights reserved.

Additional Guidewords: Step


STEP TOO LATE

An input fault prevents step on

STEP TOO EARLY

Step on conditions met early

STEP LEFT OUT

Operator forgets a step

STEP BACKWARDS

Fault causes incorrect transfer to another step

Det Norske Veritas AS. All rights reserved.

Additional Guidewords: Step


STEP TOO LATE

An input fault prevents step on (= MORE TIME)

STEP TOO EARLY

Step on conditions met early (= LESS TIME)

STEP LEFT OUT

Operator forgets a step (= NO TIME)

STEP BACKWARDS

Fault causes incorrect transfer to another step


(= WRONG TIME)

Thus, guidewords associated with the parameter STEP can be addressed by TIME

Det Norske Veritas AS. All rights reserved.

Additional Guidewords: Action


PART ACTION

One sub-action in a step is missed

EXTRA ACTION

Operator includes an action from another step

WRONG ACTION

An aberration - needs serious brain storming

Det Norske Veritas AS. All rights reserved.

Procedure: Option 1 Step by Step


Consider 1st step, for all active sections, then all inactive sections
Use all guidewords for active sections, not for inactive sections, where becomes
active is the deviation
Take each step in turn and repeat this process
Identify and study other sections not in normal operation

Det Norske Veritas AS. All rights reserved.

10

Step by Step Method


1st Step

Take 1st Active Section

Complete Logsheet

No
Take next active
section

Last Active Section ?

Yes
Take other inactive sections

Complete Logsheet

Last Step ?
Yes
Finshed

Det Norske Veritas AS. All rights reserved.

11

Next

Step

Procedure: Option 2 Section by Section


Consider 1st section, for all steps:
- First for steps when it is active
- Then for others

Use all guidewords for active steps, not for inactive steps, where becomes active
is the deviation
Take each section in turn, and repeat this process
Identify and study other sections not in normal operation

Det Norske Veritas AS. All rights reserved.

12

Section by Section Method


1st Section

Take 1st Step in which


this section is active

Complete Logsheet

No
Take next step in
which
this section is
active

Last Step in which this


section is active ?

Yes
Take steps in which this
Section is not active

Complete Logsheet

Last Section ?
Yes
Finshed

Det Norske Veritas AS. All rights reserved.

13

Next

Section

Procedure: Which Option?


Consider matrix showing steps and sections:
If there are fewer steps, use step-by-step
If there are fewer sections, use section-by-section
If there are equal numbers of each, it does not matter which option you choose

Det Norske Veritas AS. All rights reserved.

14

Refrigerated Ship Loading: Batch HAZOP Example


XCV4

V281

T1

P1

Q.R.C.
10
150#

T1

V284

V282
1.5

10 Export Line
1.5

XCV3

V78
1

V280

V283
V80

V77

To Sea

e.g. Ammonia or LNG

Det Norske Veritas AS. All rights reserved.

8 Vapour Return Line

15

Analysis Matrix for Refrigerated Ship Loading


Steps

(1)
Cool Line

(2)
Connect
Arm

(3)
Cool Arm

Delivery Line

Recirculation
Line

Loading Arm

Sections

(4)
(5)
(6)
Load Ship Purge and Disconnect
Drain Arm
Arm

Which approach is recommended: section-by-section or step-by-step?


In what order should the steps be considered for each section?

Det Norske Veritas AS. All rights reserved.

16

Open/Closed Valves etc. for Refrigerated Ship Loading


Steps

(1)
Cool Line

(2)
Connect
Arm

(3)
Cool Arm

V77

V80

V78

V284

XCV3

V280

XCV4

V281

QRC

Conn

Conn

Conn

Conn

V282

V283

Valves etc.

(4)
(5)
(6)
Load Ship Purge and Disconnect
Drain Arm
Arm

O = Open; C = Closed; D = Disconnected; Conn = Connected

Det Norske Veritas AS. All rights reserved.

17

Batch Reactor HAZOP Example


Distillation
Column

Nitrogen Purge
Solvent A

Condenser

HV-1

Reactant B

PCV-1

HV-2

Reactant C

HV-5

Coolant in
TCV-2
Catalyst D

HV-3

AV-1
HV-7

Stirrer
AG-1

HV-4

Vacuum
Vent

Receiver
R2

Heating/cooling fluid
TCV-1

Distillate
Transfer

Batch
Reactor R1
P-3

HV-6
Product discharge to storage
P-1

P-2

PCV-2

Det Norske Veritas AS. All rights reserved.

Excess heating/cooling fluid discharge

Slide 18

HAZOP Procedure For Batch Units


VALVE/EQUIPMENT ITEM
PROCESS STEP

HV-1

HV-2

HV-3

HV-4

HV-5

HV-6

HV-7

PCV1

PCV2

AV-1

TCV1

TCV2

AG-1

P-1

P-2

P-3

Before start of batch

Off

Off

Off

Off

1. Nitrogen Purge

Off

Off

Off

Off

2. Charging Solvent A

Off

Off

Off

Off

3. Charging Reactant B

On

Off

Off

Off

4. Charging Reactant C

On

Off

Off

Off

5. Charging Catalyst D

On

Off

Off

Off

6. Heating

On

On

Off

Off

7. Pull Vac on Reactor

On

On

Off

Off

8. Distillation

On

On

Off

Off

9. Break vacuum

On

On

Off

Off

10. Cooling

On

On

Off

Off

11. Discharge Distillate

On

On

Off

On

12. Discharge Product

Off

Off

On

Off

Symbols used:

C = closed
O = open
M = modulating

Det Norske Veritas AS. All rights reserved.

Slide 19

HAZOP Procedure For Batch Units


PROCESS STEPS
STUDY SECTIONS

10

11

12

1. Nitrogen purge

2. Reactor

3. Jacket heating/cooling

4. Heating/cooling supply

5. Heating/cooling discharge

4. Solvent A

5. Reactant B

6. Reactant C

7. Vacuum system

8. Vent system

9. Catalyst D

10. Distillation Column & Condenser

11. Condenser coolant

12. Receiver

13. Distillate transfer system

14. Product Discharge system

circulation system

Det Norske Veritas AS. All rights reserved.

Det
Norske
Veritas
AS. All
rights

22 May
2013

Slide 20

Batch HAZOP Logsheet


Project:

Batch Reactor HAZOP

Node Description:

Step 1
Nitrogen Purge to reactor
Section
Nitrogen purging line to reactor (active for this step)

GUIDEWORD/
DEVIATION

No Flow

More
Pressure

Less Time

CAUSES

Node: 001

Page: 1

CONSEQUENCES

SAFEGUARDS

REC
#

RECOMMENDATION

R1

Provide a flowmeter in
the nitrogen supply line
to indicate nitrogen flow
to the reactor during
purging.

Bursting disc system on R2


reactor set at 3 Barg.
(not shown on
drawing).

Ensure that the nitrogen


supply pressure is below
1 Barg to prevent failure
of the reactor bursting
disc should the reactor
become
pressurised
with nitrogen.
Include in operating
procedures for Step 1
the time the reactor
must be purged with
nitrogen
for
before
proceeding to Step 2.

Manual valve closed No nitrogen supply to reactor.


or line blockage.
There no purging and potential
No nitrogen supply. flammable atmosphere in the
reactor when solvent is charged
(Step 2). Potential fire or
explosion if there is a source of
ignition.
Nitrogen supply
Possible overpressure of reactor,
pressure too high
distillation system and receiver
which could cause failure.

Operator knowledge
and training. Reliable
nitrogen supply.

Operator does not


purge reactor for
long enough.

As for No Flow
(above).

Det Norske Veritas AS. All rights reserved.

As for No Flow (above).

Det
Norske
Veritas
AS. All
rights

22 May
2013

R3

Slide 21

Batch HAZOP Logsheet


Project:

Node Description: Step 1


Section
GUIDEWORD/
DEVIATION

CAUSES

Reverse low Reacor manway


(Reactor)
open

Less Flow
(Vent Line)

Node: 002

Batch Reactor HAZOP

Page: 1

Nitrogen Purge to reactor


Reactor, Distillation line, condenser, receiver and vent line (all active for this step)
CONSEQUENCES

SAFEGUARDS

Discharge of nitrogen around


reactor area. Possible hazard to
operators if they are close to the
reactor

Standard pre-checks
for this process are that
reactor manway should
be bolted closed before
starting the nitrogen
purge.
Standard pre-checks
for this process are that
catalyst charge valve
should be closed
before starting the
nitrogen purge.
As before.
Operating procedures.

Catalyst charge
valve open.

As above.

Vent valve closed


during nitrogen
purging.

Inadequate purging with same


consequences as for No Flow
and More Pressure in Node 1
(i.e. inadequate purging and
increase in pressure in reactor
system).

Det Norske Veritas AS. All rights reserved.

Det
Norske
Veritas
AS. All
rights

22 May
2013

REC
#

RECOMMENDATION

Slide 22

Batch HAZOP Logsheet


Project:

Node: 003

Node Description: Step 1


Section
GUIDEWORD/
DEVIATION

More flow
(vacuum
line)

Nitrogen Purge to reactor


Other non-active sections in this step.

CAUSES

Vacuum valve PCV1 open when


purging reactor with
nitrogen.

Det Norske Veritas AS. All rights reserved.

Page: 1

CONSEQUENCES

SAFEGUARDS

Vacuum created in reactor and


increased purging flow. No
hazard.

Det
Norske
Veritas
AS. All
rights

22 May
2013

REC
#

RECOMMENDATION

Pressure gauge on
reactor.

Slide 23

Batch HAZOP Logsheet


Project:

Node: 001

Node Description: Step 2


Section
GUIDEWORD/
DEVIATION

CAUSES

No flow

Operator forgets to
charge solvent.
Valve blocked.

More time.

Operator error.
Batch meter set
incorrectly.

Wrong
Action

Operator error.
Wrong solvent
supply routed to
reactor.

Det Norske Veritas AS. All rights reserved.

Page: 2

Charging Solvent A to reactor


Solvent A feed line to reactor
CONSEQUENCES

SAFEGUARDS

No solvent transfer to reactor.


Potential exothermic reaction
when other eactants are heated
during the process. This would
cause loss of product (failed
batch).
Too much solvent added to
reactor. Reactor may be
overfilled when reactants are
added. Possible discharge of
reactants and solvent from the
catalyst charging connection
during Step 5.
Wrong solvent transferred to
reactor. Loss of product (failed
batch). Potential hazard of using
incorrect solvents not known.

Det
Norske
Veritas
AS. All
rights

22 May
2013

REC
#

RECOMMENDATION

R4

Provide
software
interlock on batch meter
for Solvent A to ensure
that
batch
quantity
cannot be exceeded.

Operator checks
solvent quantity added
on meter upsteam.
This is entered on the
batch record sheet.
Operating procedures.

Operating procedures.

Check
what
other
solvent
could
be
mistakenly added to the
reactor
and
check
whether these could
create a hazard if they
were used instead of
Solvent A.

Slide 24

Batch HAZOP Logsheet


Project:

Node: 005

Node Description: Step 2


Section
GUIDEWORD/
DEVIATION
Less flow

CAUSES

Reactor drain valve


open

Det Norske Veritas AS. All rights reserved.

Page: 1

Charging Solvent A to reactor


Reactor (active during this step)
CONSEQUENCES

SAFEGUARDS

Solvent discharged from reactor


drain line. Inadequate solvent in
reactor. Possible effect on
reaction/product quality.

Operating procedues
and pre-start checks
that run out valve is
closed before adding
solvent. Solvent loss
would be small since P2 must be used to
remove material from
the reactor

Det
Norske
Veritas
AS. All
rights

22 May
2013

REC
#

RECOMMENDATION

Slide 25

Batch HAZOP Logsheet


Project:

Node: 005

Node Description: Step 2


GUIDEWORD/
DEVIATION

Section
CAUSES

Page: 1

Charging Solvent A to reactor


Other non active sections
CONSEQUENCES

SAFEGUARDS

REC
#

RECOMMENDATION

No hazards identified.

Det Norske Veritas AS. All rights reserved.

Det
Norske
Veritas
AS. All
rights

22 May
2013

Slide 26

Safeguarding life, property


and the environment
www.dnv.com

Det Norske Veritas AS. All rights reserved.

27

Você também pode gostar