ID Task Name

Duration

Start

Finish

PredeceResource Names
13
T

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27

Demand of pneumatic fitting


Pneumatic fitting arrival
M.S fitting arrangement
Modification of Aquamatic Valves 4" (04 Nos.)
New Aquamatic Valves arrival
Arrangement of HCL for Nozzles cleaning
Preparation of Stager Plates ( 10 Nos. )
Preparation of Plastic Valves Bodies ( 10 Nos. )
Preparation of M.S Boxes for Stager ( 02 Nos. )
Fitting of Stager in Box
Checking of New Aquamatic Valves (04 Nos. )
Dismentalling of Old piping + Valves of Plant # 01
Extraction of Filtration Media + Nozzles
Cleaning of Media and Nozzles
Fitting of Nozzles + Filling of Media
Welding of Plant from inside
Modification of Piping Lay out of Plant # 01
Fitting of Stager + Pneumatic Fitting
Start up of Canal Palnt # 01
Dismentalling of Old piping + Valves of Plant # 02
Extraction of Filtration Media + Nozzles
Cleaning of Media and Nozzles
Fitting of Nozzles + Filling of Media
Welding of Plant from inside
Modification of Piping Lay out of Plant # 02
Fitting of Stager + Pneumatic Fitting
Start up of Canal Palnt # 02

Project: Filtration Plants Modification P


Date: Fri 10/14/16

2 days
8.75 days?
12.25 days?
9.63 days?
9.63 days?
6.13 days?
5.25 days?
3.5 days?
4.38 days?
3.5 days?
2.63 days?
1 day?
3.38 days?
5.25 days?
2.63 days?
0.88 days?
5.25 days?
0.88 days?
0.88 days?
0.88 days?
3.5 days?
5.25 days?
2.63 days?
0.88 days?
5.25 days?
0.88 days?
0.88 days?

Sat 10/15/16
Tue 10/18/16
Fri 10/14/16
Fri 10/14/16
Fri 10/14/16
Sat 10/15/16
Mon 10/17/16
Mon 10/17/16
Mon 10/17/16
Sun 10/23/16
Tue 10/25/16
Fri 10/28/16
Sat 10/29/16
Wed 11/2/16
Tue 11/8/16
Fri 11/4/16
Sat 10/29/16
Fri 11/11/16
Sat 11/12/16
Mon 11/14/16
Tue 11/15/16
Fri 11/18/16
Thu 11/24/16
Mon 11/21/16
Tue 11/15/16
Sun 11/27/16
Mon 11/28/16

Mon 10/17/16
Thu 10/27/16
Thu 10/27/16
Mon 10/24/16
Mon 10/24/16
Fri 10/21/16
Sat 10/22/16
Thu 10/20/16
Fri 10/21/16
Wed 10/26/16
Thu 10/27/16
Sat 10/29/16
Tue 11/1/16
Mon 11/7/16
Thu 11/10/16
Fri 11/4/16
Fri 11/4/16
Fri 11/11/16
Sat 11/12/16
Mon 11/14/16
Fri 11/18/16
Wed 11/23/16
Sat 11/26/16
Mon 11/21/16
Sun 11/20/16
Sun 11/27/16
Mon 11/28/16

14
F

Usman
Usman+Nayyer
Usman + Nayyer
Faisal
Rizwan Sb + Usman
Nayyer + Faisal
Kashif
Kashif
Sohail
7,8,9 Soahil + Faisal
5
Babar + Faisal
10 Workshop + utility Team
12 Utility Team + 05 Sweepers
13 Utility Team + 05 Sweeper
14 Utility Team + 05 Sweepers
13 Workshop Team
12 Workshop Team
17,15 Utility Team
18 Faisal
19 Workshop + utility Team
20 Utility Team + 05 Sweepers
Utility Team + 05 Sweeper
22 Utility Team + 05 Sweepers
21 Workshop Team
19 Workshop Team
23,25 Utility Team
26 Faisal

21
F

22
S

23
S

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 1

October 2016
15 16 17 18 19 20
S
S M
T W T
Usman

Nayyer +
Kas
Kashif
Sohail

24
M

25
T

26
W

27
T

28
F

29
S

30
S

31
M

1
T

2
W

3
T

4
F

5
S

6
S

7
M

8
T

9
W

10
T

11
F

12
S

13
S

November 2016
14 15 16 17
M
T W T

18
F

19
S

20
S

21
M

22
T

23
W

24
T

25
F

26
S

27
S

28
M

29
T

30
W

1
T

2
F

Usman+Nayyer
Usman + Nayyer
Faisal
Rizwan Sb + Usman
+ Faisal
shif

Soahil + Faisal
Babar + Faisal
Workshop + utility Team
Utility Team + 05 Sweepers
Utility Team + 05 Sweeper
Utility Team + 05 Sweepers
Workshop Team
Workshop Team
Utility Team
Faisal
Workshop + utility Team
Utility Team + 05 Sweepers
Utility Team + 05 Sweeper
Utility Team + 05 Sweepers
Workshop Team
Workshop Team
Utility Team
Faisal

Project: Filtration Plants Modification P


Date: Fri 10/14/16

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline

Page 2