1 General
The function of the oil pressure supply units is to supply pressure to all kinds of
hydraulic equipment. Now it was widely utilized in the hydraulic turbine governor
equipment system, the turbine unit control system, the large-scale pumping station,
inlet valve, emptying valve and globe valve etc, it can also be used in the place which
use the oil pressure as the power resource.
The oil pressure supply units is composed of pressure tank and sump tank, the
units is compacted, and is with smaller footprints, and easy to install. its connecting
pipe is short.
The operational medium of the oil pressure supply units is compressed air and
the No.46 turbine oil.
2 Working principle
The oil pressure supply units and other equipments, which use the pressure oil
as the power resources, compose a close oil loop. The clean oil in the sump tank are
pressured and piped into the pressure tank by the oil suction pipe of the screw oil
pump. The screw oil pump is driven by the motor through the coupling. The oil was
piped into the check valve. With the increase of the oil, the pressure in the inner of
the retaining valve is increase too. Until the pressure exceed the pressure of the
check valve upper limit, the oil was piped into the pressure tank through the check
valve.
The oil pressure supply units are equipped with two screw pumps to guarantee
the operational reliability of units, one is in service, the other is in standby. There
should be switched, and can operate simultaneous in short period at special
occasion.
In general, the upper of pressure tank is filled with 2/3 compressed air, the lower
is filled with 1/3 turbine oil. The supplement and discharge of compressed air was
completed by the air check valve.
In order to indicate the oil level in the pressure tank, a level indicator is applied.
From the indicator plate, the indicator can monitor the oil level in the pressure tank
from the plate directly, and give an alarm when the oil level exceed to the
upper/lower limit.
standby for the other needs of the customs. There is a flange which is used to
support the check valve for release oil
At the bottom of the pressure tank, there is a checking hole or enter hole for
exam an repair
motor. With the rotating of the screw, the oil of inner was pipe into the meshing space,
the raised tooth of initiative screw meshed closely with the concave tooth of driven
screw. Insuring the definite working length of the initiative screw, the meshing space
form the sealed cavum, the liquid which enter the sealed cavum can not rotate as the
liquid screw, and moved along the screw equabley, at last are evacuate from the
vent orifical.
Except the moment of the startup, the driven screw always driven by the
pressure oil, so the driven screw do not endured the main torque. it worked as the
pressurized set which prevent the oil circumfluence, for this reason, the contact
stress between the screws is smaller then the contact stress between the gear of
gear pump. At the same time, because the support area of the screw structure is very
big, the friction is very small.
This structure feature ensure the pump with longer life.
In the hydraulic system figure, the two main component(one main valve and one
check valve) and three pilot valve was figure as following symbol:
CV1- main valve
CV2- check valve
YV1- unloading pilot valve
YV2- relief pilot valve
YV3- unloading pilot valve
(1) Unloading valve
Because of the big motor inertia of the high power screw pump, it need some
time from startup to stable state. It is a great disadvantage for screw pump and
hydraulic pressure, if the loading was loaded before the screw pump arrived the rated
flux. Using the unloading valve, the screw pump was in the unloading state when it
was started, until the motor arrived the rotated speed, the screw pump output the
rated operated pressure and flux.
The unloading valve is composed of unloading pilot valve and main valve.
When oil pump is startup, because of the action of P, the check valve is at the
closed state. At the action of spring, the leakage valve is at the opening state. There
are no pressure oil in the control cavity of the main valve, the pressure oil was piped
to the sump tank through the main orificeWith the increase of the rotate speed of
the motor, the pressure of P is increase, the control oil are piped to the upper cavity
of leakage valveovercome the force of spring and move the piston, close the
leakage valveAt the moments, pressure oil enter into the control cavity and close
the cavity. For this reason, the pressure of P reach the rating value, the check valve
is opened and piped the oil to the pressure tank. After the pump was stopped, the
leakage valve go back to the initial state. The operational pressure of leakage valve
can be adjusted by the preset force of spring
Note there is no that valve when the motor power is very low.
(2) Relief valve
The relief vale is the discharge setting for the safety of the pressure tank. It
prevent the screw pump and the pressure tank to over loading.
The relief valve is composed of relief pilot valve and main valve.
When there are some failure, the screw pump is still running, the oil pressure is
higher. When the force is acted on the pilot valve, the push force is bigger then the
adjusting force of spring, YV2
drainaged. Under the action of pressure of P, the main valve was opened ,the check
valve was closed, the oil pump is running under the self-circulation state, the
pressure tank and screw are both operated under the rating pressure.
(3)Unloading valve
The unloading valve (by-pass valve) is composed of unloading pilot valve and
main valveIt is used for the continuously running of the screw pump.
when the screw pump running continuously, the pressure of the pressure tank is
variety with the flux, when input flux is bigger then output flux, the pressure is
increase. When the pressure arrived at the upper limit, the control cavity pressure of
unloading pilot valve overcome the spring force, and cut off the control oil resource
from the oil pump, because the CV1 control the antrum to release the oil, the piston
was pushed through, the pressure oil in the main oil path was released, and the
screw pump worked in the self-cycle state. With the deplete of the system, the
pressure in the pressure tank is reduce, when the pressure arrived at the lower limit,
the unloading pilot valve was closed by the spring. The control antrum was closed
with the main valve, the screw pump restart to supply the oil to pressure tank. The
action pressure of the relief valve and the unloading can be adjusted through the
spring force of
a. After the screw oil pump was connected with the motor by coupling
manual rotating it softly, it require that the screw oil pump running neatly, and no
block instance appeared.
b. The screw oil pump was close connected with inlet pipe, assure the seal,
dont allow any cavity
c. Before the first installation or the first operation after the screw oil pump
was checked, the oil should be filled into the pump through the flange at the back of
pump.
(2) The first time startup after installation
a. all the valve from the screw pump to pressure tank should be opened.
b. Start up the screw pump by press, check the rotate direction of the motor,
the rotate direction should be consistent with the arrowhead direction on the screw oil
pump, then start up the screw oil pump, piped the oil to the pressure tank until the oil
level arrived at the normal value. In this period, check that whether the oil pump
operated smoothly, no quiver and unwonted noise, at last open the automation refill
setting, fill the pressure tank with compressed air manually or automatically(if there is
no automatically refill setting, we can use the air inverted valve to refill the
compressed air manually). When the pressure arrived at 0.5Mpa. check the seal of
the oil pipe and all components at the joint. Ensure no leaking air and oil.
c. Piped the air to pressure tank until the pressure arrived at 2 Mpa, lasting 30
minutes, the oil level should be in the normal level, check the seal at the joint, ensure
no leaking.
Note: the compressed air to pressure tank must be dry air that be
separated from water and air.
(3) Setting the electric-point pressure meter
for example the rating pressure is 6.3Mpa.
a. When the lower limit switch point pressure value arrive at 5.8Mpa, the
working oil pump was operated automatically; when the upper limit switch point
pressure value arrive at 6.3Mpa, the working oil pump stop running.
b. When the lower limit switch point pressure value arrive at 5.6Mpa, the
standby oil pump was operated automatically; when the upper limit switch point
pressure value arrive at 6.3Mpa, the standby oil pump stop running.
c. The tripping pressure value is decided by the engineer. (the engineer can
calculate the value according to the power station design.)
7
quickly and strictly against the counter flowing of the oil to pressure tank. If the valve
must check whether the valve plug is blocked, and whether the
control orifice is jammed, after eliminating the abnormity, restart the test.
Note: Before dismantling the pilot valve and valve cover, we must cut off the
check valve of the combined valve which is on the line to the pressure tank, the
control oil of the pilot valve is come from the back of the one way valve. Cutting off
the stop valve can void the pressure oil ejected from the control orifice.
5 Installation in site
Installation of the equipment is a very important working procedure in the
process of equipment operation, because it connects with the security, reliability and
normal capability of the equipment. So before the installation, the whole technique
files must be acquainted. Based on spot situations, the installation can be carried on.
6 Operation
(1) After installation of the pressure oil supply unit, the piping must be checked
whether it is right, and can be supply the oil and air;
(2) According to blueprint, the whole connection controlling the loop must be
checked whether it is right;
(3) After all the check, turn on the power supply and pressure oil source. When
the testing based on national standard GB/T9652.1 Technical qualifications of
10
governors
Testing check and accept guide of governors and pressure oil supply units for hydroturbines is eligible, the equipment can be launched into operation formally.
11