Você está na página 1de 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC

A. SUB STRUCTURE
1. EXCAVATION AND EARTH WORK
1.01

Clear the site to remove the top soil to an average


m2
depth of 200mm starting from natural ground level.

1.02

Bulk Excavation of ordinary soil to a depth not


m3
exceeding 1500mm below strip ground level.

2,514.65

135.00

339,477.68

2,467.50

135.00

333,112.50

(6,365.18)
-

Ditto the above but for soft rock excavation and from a
m3
depth of 1500mm from strip ground level.

1,645.00

145.00

238,525.00

1,676.43

145.00

243,082.35

4,557.35

1,676.43

17.00

28,499.36

1,676.43

17.00

28,499.36

1.03

1.04

Trench Excavation under basement peripheral beam


with an average depth of 1200mm from stripped
m3
ground floor level.

128.96

620.00

79,955.20

79,955.20
-

1.04

Excavation of isolating footing in hard rock to a depth


m3
of 1500mm below reduced ground level.

1,662.23

620.00

1,030,582.60

1,195.61

620.00

741,278.20

(289,304.40)
-

1.05

1.06

Excavation of isolating footing in hard rock to a depth


of 1500mm to 3000mm below reduced ground level.
m3

1,079.00

640.00

690,560.00

Fill under hard core to depth of 450mm with quarry


waste selected material brought from outside and
ram in layer not exceed 200mm thick.
m3

4,957.48

250.00

306.00

250.00

1.08

Ditto as item No.1.05 but around isolated footing pad.

1.09

Ditto as item No.1.05 but around RC retaining wall.

m3

916.63

640.00

586,643.20

(103,916.80)
-

1,239,370.00

2,632.00

250.00

658,000.00

(581,370.00)
-

76,500.00

1,660.34

250.00

415,085.00

338,585.00
-

m3

218.44

250.00

54,610.00

218.44

250.00

54,610.00

1.10

Cart away surplus excavated soil to a distance not


m3
exceeding 5km from site.

5,123.07

200.00

1,024,613.20

5,091.13

200.00

1,018,226.00

(6,387.20)
-

1.11

250mm thick basaltic or equivalent stone hared core


well rolled, consolidated and blinded with crushed
m2
stone.

1,147.15

120.00

137,658.00

1,242.35

120.00

149,082.00

11,424.00
-

Phase II Executed Work to Date

1 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Allow lump sum amount of dewatering from


excavation pit.

Ls

Qty

(B) Main Contract Data


Rate
Amount

Qty
1.00

TOTAL CARRIED TO SUMMARY

(B) Computations
Rate
Amount
10,000.00

4,860,395.84

10,000.00
4,307,573.81

Net Difference BC
10,000.00
(552,822.03)
-

2, CONCRETE WORKS
2.01

b)

5cms.thich lean concrete in class C-5 with


minimum cement content of 150kg /m3.
under Isolated footing pad
m2
under basement floor beams
m2

c)

under masonry foundation wall

d)

under Septic tanker bottom slab

m2

125.00

63.00

125.00

7,875.00

7,875.00

e)

under 10cm thick R. concrete for basement floor slab


m2

125.00

1,242.35

125.00

155,293.75

155,293.75

a)

2.02

658.00

125.00

82,250.00

588.07

125.00

73,508.75

(8,741.25)

166.40

125.00

20,800.00

240.44

125.00

30,055.00

9,255.00

94.00

125.00

11,750.00

169.12

125.00

21,140.00

9,390.00

Reinforced Concrete quality C-25, with minimum


cement content of 360Kg/m3 filled into formwork
and vibrated around steel reinforcements. The
formwork and reinforcements shall be measured
separately.

a)

In isolating footing pad

m3

358.60

2,800.00

1,004,080.00

358.59

2,800.00

1,004,052.00

(28.00)

b)

In foundation column

m3

25.20

2,800.00

70,560.00

22.22

2,800.00

62,216.00

(8,344.00)

c)

In basement column

m3

34.50

2,800.00

96,600.00

34.52

2,800.00

96,656.00

56.00

66.60

2,800.00

186,480.00

68.70

2,800.00

192,360.00

5,880.00

83.00

2,800.00

232,400.00

79.10

2,800.00

221,480.00

(10,920.00)

1,321.90

300.00

396,570.00

1,242.35

300.00

372,705.00

(23,865.00)

m2

89.00

480.00

42,720.00

89.25

480.00

42,840.00

120.00

m3

3.40

2,800.00

9,520.00

7.04

2,800.00

19,712.00

10,192.00

7.40

2,800.00

20,720.00

17.94

2,800.00

50,232.00

29,512.00

28.00

2,800.00

78,397.20

28.00

2,800.00

78,397.20

d)

In basement floor beam

e)

In Ground floor beam

f)

In 10cm thick R. concrete for basement floor slab

g)

In 16cm thick R. concrete suspended ground floor slab

h)

In Stair case extended from basement to ground floor

i)

In Lift shaft extended from basement to ground floor

j)

In retaining shear wall extended from BFB to GFG

2.02

Suspended floor ribbed slab made of 60mm thick


slab 80 x 240mm one way concrete ribbed beam
spacing c/c 400mm, hollow concrete block all
according to the detail structural drawing.

Suspended ground floor ribbed slab.

Phase II Executed Work to Date

1,016.00

320.00

325,120.00

1,015.97

320.00

325,110.40

(9.60)

2 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC
-

2.04

Provide cut & fix in position formwork for concrete


work. Work shall includes all nailing, fixing, over
buttressing and associated works

m2

530.00

230.00

121,900.00

530.04

230.00

121,909.20

249.80

230.00

57,454.00

224.03

230.00

51,526.90

For basement-Ground column

m2

342.20

230.00

78,706.00

342.23

230.00

78,712.90

6.90

d)

For basement floor beam

m2

532.50

230.00

122,475.00

549.58

230.00

126,403.40

3,928.40

e)

For Ground floor beam

m2

331.50

230.00

76,245.00

336.44

230.00

77,381.20

1,136.20

f)

For R. concrete suspended ribbed & solid ground floor

m2

1,105.00

230.00

254,150.00

1,105.22

230.00

254,200.60

50.60

g)

For Stair case extended from basement to ground floor

m2

21.00

250.00

5,250.00

51.78

250.00

12,945.00

7,695.00

h)

For Lift shaft extended from basement to ground floor

m2

75.00

250.00

18,750.00

173.90

250.00

43,475.00

24,725.00

i)

For retaining shear wall

279.99

250.00

69,997.50

279.99

250.00

69,997.50

a)

For isolating footing pad

b)

For foundation column

c)

9.20
(5,927.10)

2.05

Steel reinforcements according to the structural


drawing. Price shall include cutting, bending,
placing in position and tying wires.

In footing pad

a)

Dia. 12 deformed bars

Kg

460.00

37.00

17,020.00

422.00

37.00

15,614.00

(1,406.00)

b)

Dia. 14 deformed bars

Kg

4,734.10

37.00

175,161.70

4,583.00

37.00

169,571.00

(5,590.70)

428,918.80

11,340.00

37.00

419,580.00

(9,338.80)

146.00

37.00

5,402.00

5,402.00
8,857.80

c)

Dia. 16 deformed bars

Kg

11,592.40

37.00

d)

Dia. 20 deformed bars

Kg

0.00

37.00

a)

494.60

37.00

18,300.20

734.00

37.00

27,158.00

b)

In foundation column extended from footing pad to


BFB 8 deformed bars
Dia.
Kg
Dia. 14 deformed bars
Kg

87.20

37.00

3,226.40

87.00

37.00

3,219.00

(7.40)

c)

Dia. 16 deformed bars

Kg

1,992.10

37.00

73,707.70

1,993.00

37.00

73,741.00

33.30

d)

Dia. 20 deformed bars

Kg

4,316.01

37.00

159,692.37

4,316.00

37.00

159,692.00

(0.37)

b)

In basement column extended from basement to


GFB
Dia. 8 deformed bars
Kg
Dia. 14 deformed bars
Kg

c)

Dia. 16 deformed bars

a)

Phase II Executed Work to Date

Kg

932.75

37.00

34,511.75

1,187.00

37.00

43,919.00

9,407.25

291.33

37.00

10,779.21

181.00

37.00

6,697.00

(4,082.21)

2,000.65

37.00

74,024.05

1,812.00

37.00

67,044.00

(6,980.05)

3 of 15

Comparision b/n Contract Data and Assessment

Item
d)

Description
Dia. 20 deformed bars

(B) Main Contract Data


Rate
Amount

Unit

Qty

Kg

3,902.99

37.00

144,410.63

Qty
3,910.00

(B) Computations
Rate
Amount
37.00

144,670.00

Net Difference BC
259.37
-

In basement floor beam


a)
b)

Dia. 8 deformed bars

Kg

Dia. 12 deformed bars

Kg
Kg

Dia. 14 deformed bars

1,606.23

37.00

59,430.44

1,648.00

37.00

60,976.00

1,545.56

3,440.82

37.00
37.00

127,310.30

124.00
3,609.00

37.00
37.00

4,588.00
133,533.00

4,588.00
6,222.70

In ground floor beam

a)

Dia. 8 deformed bars

Kg

2,066.34

37.00

76,454.57

2,013.00

37.00

74,481.00

(1,973.57)

b)

Dia. 10 deformed bars

Kg

823.62

37.00

30,473.98

895.00

37.00

33,115.00

2,641.02

c)

Dia. 12 deformed bars

Kg

1,043.44

37.00

38,607.11

1,071.00

37.00

39,627.00

1,019.89

d)

Dia. 14 deformed bars

Kg

2,053.60

37.00

75,983.20

1,699.00

37.00

62,863.00

(13,120.20)

e)

Dia. 16 deformed bars

Kg

1,031.98

37.00

38,183.26

1,019.00

37.00

37,703.00

(480.26)

f)

Dia. 20 deformed bars

Kg

9,087.26

37.00

336,228.59

8,898.00

37.00

329,226.00

(7,002.59)
-

In ground ribbed beam

a)

Dia. 6 deformed bars

Kg

3,166.56

37.00

117,162.72

2,821.00

37.00

104,377.00

b)

Dia. 8 deformed bars

Kg

357.88

37.00

13,241.56

358.00

37.00

13,246.00

c)

Dia. 10 deformed bars

Kg

2,020.60

37.00

74,762.20

2,034.00

37.00

75,258.00

495.80

d)

Dia. 12 deformed bars

Kg

3,313.10

37.00

122,584.70

3,306.00

37.00

122,322.00

(262.70)

e)

Dia. 14 deformed bars

Kg

2,898.05

37.00

107,227.85

2,900.00

37.00

107,300.00

72.15

(12,785.72)
4.44

In basement and ground floor slab


a)

Dia. 8 deformed bars

Kg

2,503.67

37.00

92,635.79

4,051.00

37.00

149,887.00

57,251.21
-

In ground ribbed beam

a)

Dia. 6 deformed bars

Kg

2,671.99

37.00

98,863.63

1,984.00

37.00

73,408.00

(25,455.63)

b)

Dia. 8 deformed bars

Kg

360.62

37.00

13,342.94

92.00

37.00

3,404.00

(9,938.94)

c)

Dia. 10 deformed bars

Kg

2,901.57

37.00

107,358.09

963.00

37.00

35,631.00

(71,727.09)

d)

Dia. 12 deformed bars

Kg

6,788.12

37.00

251,160.44

3,201.00

37.00

118,437.00

(132,723.44)
-

b)

In Stair case extended from basement to ground


floor
Dia. 8 deformed bars
Kg
Dia. 12 deformed bars
Kg

e)

Dia. 16 deformed bars

Kg

60.12

37.00

2,224.44

60.00

37.00

2,220.00

(4.44)

f)

Dia. 20 deformed bars

Kg

85.04

37.00

3,146.48

85.00

37.00

3,145.00

(1.48)
-

a)

Phase II Executed Work to Date

175.70

37.00

6,500.90

224.00

37.00

8,288.00

1,787.10

582.88

37.00

21,566.56

705.00

37.00

26,085.00

4,518.44

4 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC

In Lift shaft shear wall

a)

Dia. 8 deformed bars

Kg

34.76

37.00

1,286.12

b)

Dia. 10 deformed bars

Kg

282.83

37.00

10,464.71

c)

Dia. 12 deformed bars

Kg

282.83

37.00

10,464.71

2,083.00

37.00

77,071.00

66,606.29

d)

Dia. 14 deformed bars

Kg

154.62

37.00

5,720.94

250.00

37.00

9,250.00

3,529.06

18.00

37.00

666.00

37.00

(620.12)
(10,464.71)

In Retaining shear wall extended from BFB to GFB

a)

Dia. 10 deformed bars

Kg

985.96

37.00

36,480.52

985.96

37.00

36,480.52

b)

Dia. 12 deformed bars

Kg

1,487.58

37.00

55,040.35

1,487.58

37.00

55,040.35

TOTAL CARRIED TO SUMMARY

6,456,554.61

6,524,119.67

3. MASONRY WORK
3.01 500mm thick stone masonry under grade beam and
bedded in cement sand mortar 1:4 to retain fill under
hard core.

67,565.06

m3

141.52

1,450.00

205,206.90

141.42

1,450.00

205,059.00

(147.90)
-

TOTAL CARRIED TO SUMMARY

205,206.90

205,059.00

(147.90)
-

11,522,157.35

11,036,752.48

B. SUPER STRUCTURE
1. CONCRETE WORKS

(485,404.87)
-

In Typical Floor
1.01

Concrete quality C-25, with minimum cement


content of 360Kg/m3 filled into formwork and
vibrated around reinforcements. The formwork
and reinforcements shall be measured separately.

m3
m3

a)

In Elevation Column extended from GFB-FRFB

b)

In Typical Floor beams

c)

In 160mm thick solid slab in typical floor

d)

In Stair case and landing extended from GFB-FRFB

m3

e)

In Lift shaft shear wall extended from GFB-FRFB


15cm thick concrete gutter

m3

Phase II Executed Work to Date

m2

155.10

2,800.00

434,280.00

156.08

2,800.00

437,024.00

2,744.00

415.50

2,800.00

1,163,400.00

437.08

2,800.00

1,223,824.00

60,424.00

212.50

480.00

377.68

480.00

181,286.40

79,286.40

37.00

2,800.00

103,600.00

49.27

2,800.00

137,956.00

34,356.00

68.20

2,800.00

190,960.00

70.88

2,800.00

198,464.00

7,504.00

216.10

480.00

103,728.00

103,728.00

480.00

102,000.00

5 of 15

Comparision b/n Contract Data and Assessment

Item

Description
Concrete pergola

1.02

1.03

Suspended typical floor Ribbed slab made of 60


mm thick concrete slab, 80 x 240 mm one way
concrete ribbed beam with c/c spacing of 400 mm ,
200 x 400 mm hollow concrete ribbed block all
according to the detail structural drawing.

Unit

Qty

(B) Main Contract Data


Rate
Amount

m3

m2

2,800.00

5,005.43

450.00

Qty
-

2,252,443.50

0.67

5,079.85

(B) Computations
Rate
Amount

Net Difference BC

2,800.00

1,876.00

1,876.00
-

500.00

2,539,925.00

287,481.50
-

Provide cut & fix in position formwork for concrete


work. Work shall includes all nailing, fixing, over
buttressing and associated works

a)

To Elevation Column extended from GFB-FRFB

m2

1,900.30

200.00

380,060.00

1,798.16

200.00

359,632.00

(20,428.00)

b)

To Typical Floor beams

m2

1,888.30

190.00

358,777.00

2,262.58

190.00

429,890.20

71,113.20

8,172.70

190.00

1,552,813.00

5,478.53

190.00

1,040,920.70

261.30

200.00

52,260.00

362.43

200.00

72,486.00

20,226.00

491.80

200.00

98,360.00

723.12

200.00

144,624.00

46,264.00

c)
d)
e)

To typical floor solid and ribbed slab


To Stair case and landing extended from GFB-FRFB
To Lift shaft shear wall extended from GFB-FRFB

(511,892.30)

15cm thick concrete gutter

200.00

368.63

200.00

73,726.00

73,726.00

Concrete pergola

200.00

8.64

200.00

1,728.00

1,728.00
-

1.04

Steel reinforcements according to the structural


drawings. Price shall include cutting, bending,
placing in position and tying wires.

In Elevation Column extended from GFB-FRFB

a)

Dia. 8mm deformed bars

Kg

5,049.50

35.00

176,732.50

5,001.00

36.00

180,036.00

3,303.50

d)

Dia. 14mm deformed bars

Kg

695.80

35.00

24,353.00

4,565.00

36.00

164,340.00

139,987.00

e)

Dia. 16mm deformed bars

Kg

11,367.70

35.00

397,869.50

11,944.00

36.00

429,984.00

32,114.50

Dia. 20mm deformed bars

Kg

23,417.90

35.00

819,626.50

6,554.00

36.00

235,944.00

(583,682.50)
-

In Typical Floor beams

a)

Dia. 8mm deformed bars

Kg

10,331.70

35.00

361,609.50

11,876.00

36.00

427,536.00

65,926.50

b)

Dia. 10mm deformed bars

Kg

4,118.10

35.00

144,133.50

4,735.00

36.00

170,460.00

26,326.50

c)

Dia. 12mm deformed bars

Kg

5,217.20

35.00

182,602.00

5,340.00

36.00

192,240.00

9,638.00

d)

Dia. 14mm deformed bars

Kg

10,268.00

35.00

359,380.00

10,757.00

36.00

387,252.00

27,872.00

e)

Dia. 16mm deformed bars

Kg

5,159.90

35.00

180,596.50

6,819.00

36.00

245,484.00

64,887.50

f)

Dia. 20mm deformed bars

Kg

45,436.30

35.00

1,590,270.50

51,289.00

36.00

1,846,404.00

256,133.50

Phase II Executed Work to Date

6 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

In Typical Floor Solid and Ribbed slab

Net Difference BC
-

a)

Dia. 6mm deformed bars

Kg

12,518.40

35.00

438,144.00

9,921.00

36.00

357,156.00

(80,988.00)

b)

Dia. 8mm deformed bars

Kg

1,803.10

35.00

63,108.50

1,020.00

36.00

36,720.00

(26,388.50)

c)

Dia. 10mm deformed bars

Kg

1,068.80

35.00

37,408.00

4,659.00

36.00

167,724.00

130,316.00

d)

Dia. 12mm deformed bars

Kg

6,787.90

35.00

237,576.50

2,785.00

36.00

100,260.00

(137,316.50)
-

In Typical floor ribbed beam

a)

Dia. 6 deformed bars

Kg

13,360.00

35.00

467,600.00

14,107.00

36.00

507,852.00

40,252.00

b)

Dia. 8 deformed bars

Kg

1,803.10

35.00

63,108.50

1,792.00

36.00

64,512.00

1,403.50

c)

Dia. 10 deformed bars

Kg

9,662.90

35.00

338,201.50

10,169.00

36.00

366,084.00

27,882.50

d)

Dia. 12 deformed bars

Kg

16,141.60

35.00

564,956.00

16,534.00

36.00

595,224.00

30,268.00

e)

Dia. 14 deformed bars

Kg

13,944.20

35.00

488,047.00

14,500.00

36.00

522,000.00

33,953.00
-

In Stair case and landing extended from GFB-FRFB

a)

Dia. 8mm deformed bars

Kg

1,054.20

35.00

36,897.00

1,346.00

36.00

48,456.00

11,559.00

b)

Dia. 12mm deformed bars

Kg

3,497.30

35.00

122,405.50

4,230.00

36.00

152,280.00

29,874.50

c)

Dia. 16mm deformed bars

Kg

360.70

35.00

12,624.50

361.00

36.00

12,996.00

371.50

d)

Dia. 20mm deformed bars

Kg

510.30

35.00

17,860.50

511.00

36.00

18,396.00

535.50

In Lift shaft shear wall extended from GFB-FRFB

a)

Dia. 8 deformed bars

Kg

1,697.00

35.00

59,395.00

125.00

36.00

4,500.00

(54,895.00)

b)

Dia. 10 deformed bars

Kg

2,834.50

35.00

99,207.50

1,548.00

36.00

55,728.00

(43,479.50)

c)

Dia. 12 deformed bars

Kg

927.70

35.00

32,469.50

3,717.00

36.00

133,812.00

101,342.50

d)

Dia. 14 deformed bars

Kg

340.10

35.00

11,903.50

959.00

36.00

34,524.00

22,620.50
-

In concrete gutter & pergola


a) Dia. 8 deformed bars
b) Dia. 8 deformed bars
c) Dia. 16 deformed bars

Kg

2,840.00

36.00

Kg
Kg

102,240.00

102,240.00

55.00

36.00

1,980.00

1,980.00

417.00

36.00

15,012.00

15,012.00
-

In Terrace and roof Floor


1.01

Concrete quality C-25, with minimum cement


content of 360Kg/m3 filled into formwork and
vibrated around reinforcements. The formwork
and reinforcements shall be measured separately.

Phase II Executed Work to Date

7 of 15

Comparision b/n Contract Data and Assessment

Item

Description

26.20

3,000.00

78,600.00

3,200.00

(78,600.00)

44.70

3,000.00

134,100.00

3,200.00

(134,100.00)

1,146.40

500.00

573,200.00

500.00

(573,200.00)

b)

In Terrace Floor beams

m3
m3

c)

In 150mm thick solid slab in terrace floor

m2

e)

In Stair case and landing extended from FRFB-TRFB


In Lift shaft shear wall extended from FRFB-TRFB

Net Difference BC

Qty

In Elevation Column extended from FRFB-TRFB

Qty

(B) Computations
Rate
Amount

Unit

a)

d)

(B) Main Contract Data


Rate
Amount

3.40

3,000.00

10,200.00

3,200.00

(10,200.00)

10.80

3,000.00

32,400.00

3,200.00

(32,400.00)
-

1.02

b)

Provide cut & fix in position formwork for concrete


work. Work shall includes all nailing, fixing, over
buttressing and associated works
To Elevation Column extended from FRFB-TRFB
m2
To terrace floor beams
m2

c)

To terrace floor solid slab

m2

d)

To Stair case and landing extended from FRFB-TRFB

m2

a)

e)

To Lift shaft shear wall extended from FRFB-TRFB

319.50

250.00

79,875.00

250.00

(79,875.00)

383.50

250.00

95,875.00

250.00

(95,875.00)

1,146.40

250.00

286,600.00

250.00

(286,600.00)

21.40

250.00

5,350.00

280.00

(5,350.00)

108.10

250.00

27,025.00

280.00

(27,025.00)
-

1.04

Steel reinforcements according to the structural


drawings. Price shall include cutting, bending,
placing in position and tying wires.

In Elevation Column extended from FRFB-TRFB

a)

Dia. 8mm deformed bars

Kg

716.20

35.00

25,067.00

37.00

(25,067.00)

b)

Dia. 14mm deformed bars

Kg

1,544.40

35.00

54,054.00

37.00

(54,054.00)

c)

Dia. 16mm deformed bars

Kg

1,537.10

35.00

53,798.50

37.00

(53,798.50)
-

In Terrace and roof floor beams

a)

Dia. 8mm deformed bars

Kg

307.60

35.00

10,766.00

37.00

(10,766.00)

c)

Dia. 14mm deformed bars

Kg

44.90

35.00

1,571.50

37.00

(1,571.50)

d)

Dia. 16mm deformed bars

Kg

843.40

35.00

29,519.00

37.00

(29,519.00)
-

In Terrace floor Solid slab

a)

Dia. 8mm deformed bars

b)

Dia. 10mm deformed bars

Kg
Kg

3,545.70
12,707.40

35.00
35.00

124,099.50
444,759.00

37.00
37.00

(124,099.50)
(444,759.00)

c)

Dia. 12mm deformed bars

Kg

6,262.50

35.00

219,187.50

37.00

(219,187.50)
-

a)
b)

In Stair case and landing extended from FRFBTRFB


Dia. 8mm deformed bars
Kg
Dia. 12mm deformed bars
Kg
TOTAL CARRIED TO SUMMARY

Phase II Executed Work to Date

18.30

35.00

640.50

37.00

(640.50)

874.00

35.00

30,590.00

37.00

(30,590.00)

16,334,317.50

14,524,226.30

(1,810,091.20)

8 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC
-

2. MASONRY WORKS

2.01

20 cm thick Hollow Concrete block wall laid in cement


sand mortar 1:4, both faces left for plastering

m2

4,783.32

250.00

1,195,830.92

3,712.65

250.00

928,162.50

(267,668.42)
-

2.02

Ditto as above but 15cms thick

4,791.46

250.00

1,197,864.48

7,042.52

250.00

1,760,630.00

562,765.52
-

TOTAL CARRIED TO SUMMARY

2,393,695.40

2,688,792.50

295,097.10
-

3, ROOFING

3.01

Apply Light weight concrete attaining 2% slope with


an average thickness of 50mm. As per the supplier
specification.

m2

1,379.00

115.00

158,585.00

312.67

115.00

35,957.05

(122,627.95)
-

3.02

Apply APP Bituminous membrane Water proof on the


top of roof slab according to the manufacturer
m2
specification.

1,454.00

750.00

1,090,500.00

312.67

750.00

234,502.50

(855,997.50)
-

3.04

Apply APP Bituminous membrane Water proof on


m2
concrete gutter.

279.65

750.00

209,737.50

209,737.50

3.03

Supply and fix approved standard Metro roof cover


made of polyurethane core, based on 0.5mm thick
(nominal) metal skin with modified polyester paint
fixed to "Zigba" purlin with 5.5mm diameter carbon
steel self drilling fasteners. Price shall include all
necessary fixing accessories like ridge hip, ridge
cup,valley gutter, self drilling fasteners, drip trim,
corner trim, eave trim, girt trim, girt clip, wooden
truss member, zigba purlin spaced c/c 360mm and all
others necessary fixing accessories. (The roof
measured in inclined projection.). All detail and
installation shall be in accordance with the
m2
manufacturer's drawing.

1,240.00

849.35

1,053,192.30

1,053,192.30
-

TOTAL CARRIED TO SUMMARY

1,249,085.00

1,533,389.35

284,304.35
-

Phase II Executed Work to Date

9 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

(B) Computations
Rate
Amount

Qty

Net Difference BC

6. FINISHING
6.01

Apply two coats of plaster in cement-sand mortar mix


1:3
and smooth finish to internal HCB wall & vertical
concrete surface. All wall-concrete structure joints
m2
shall be recessed to avoid hairline cracks.

17,283.24

120.00

2,073,989.38

16,983.28

120.00

2,037,993.60

(35,995.78)
-

6.02

Ditto plaster but for concrete ceiling, stair case side


m2
belly and soffits surface.

6.03

Apply gypsum plastering to plastered internal HCB


m2
and Vertical wall surface.

6.04

Apply three coats of plaster in cement-sand mortar


mix 1:3 to the external HCB wall & vertical concrete
m2
surface as located in the drawings.

8,206.94

105.00

861,728.70

8,299.63

105.00

871,461.15

9,732.45
-

45.00

45.00

5,016.80

115.00

576,932.55

3,335.99

115.00

383,638.85

(193,293.70)
-

6.05

Apply two coats of plaster in cement-sand mortar mix


1:3
m2
to receive ceramic wall tile in toilet and kitchen.

1,676.60

100.00

167,659.80

3,381.79

100.00

338,179.00

170,519.20
-

TOTAL CARRIED TO SUMMARY

3,680,310.43

3,631,272.60

(49,037.83)
-

SANITARY INSTALLATION FOR G+5


1
1.1

WATER SUPPLY SYSTEM

Water Supply Pipes


Supply, lay and connect Polypropylene pipe (PPR)
pressure pipes with metallic insert, class E (PN 16), for
cold and hot water supply system to sanitary fixture.
Complete with all the necessary connecting pieces
such as bends, Ys, Ts, reducers, nipples, unions,
galvanized clips, the interval shall be as per
manufacturer's recommendation & supports (if any)
etc Unit price shall include, disinfection of the pipes
with chlorine and all the necessary assistance to the
works. The pipes and fittings shall conform to
BS3505/DIN8062 or equivalent institution.

1.1.1

` Diameter 20mm

ml

935.34

59.00

55,185.06

59.00

(55,185.06)

1.1.2

Outer diameter 25mm

ml

1,969.44

72.00

141,799.68

72.00

(141,799.68)

Phase II Executed Work to Date

10 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

(B) Computations
Rate
Amount

Qty

Net Difference BC

1.1.3

Outer diameter 32mm

ml

108.00

85.00

9,180.00

108.00

85.00

9,180.00

1.1.4

Outer diameter 40mm

ml

144.00

91.00

13,104.00

144.00

91.00

13,104.00

1.1.5

Outer diameter 50mm

ml

47.92

98.00

4,696.16

98.00

1.1.6

Outer diameter 75mm

ml

60.00

104.00

6,240.00

60.00

104.00

6,240.00

1.1.7

Outer diameter 90mm

ml

48.00

110.00

5,280.00

48.00

110.00

5,280.00

(4,696.16)

1.2

Angle valve
Supply and fix chrome plated service (angle) valves,
adjucent to Hand wash basin, water closets complete
with unions, elastic water proofing, hand wheels of
normal quality and with all other necessary
accessories.
dimension of 20mm

pcs

1,162.00

104.00

120,848.00

104.00

(120,848.00)
-

1.3

Gate Valve
Supply and fix 20mm diameter gate valve made of
bronze, complete with all accessories (working
pressure 16 bar). The quality of material should satisfy
the requirements of British Standard Specification BS
5154
pcs

52.00

98.00

5,096.00

52.00

98.00

5,096.00

1.3.1

Ditto item No 1.3 above but dia.25mm

pcs

144.00

104.00

14,976.00

144.00

104.00

14,976.00

1.3.2

Ditto item No 1.3 above but dia.32mm

pcs

48.00

110.00

5,280.00

48.00

110.00

5,280.00

1.3.3

Ditto item No 1.3 above but dia.40mm

pcs

48.00

117.00

5,616.00

48.00

117.00

5,616.00

1.3.4

Ditto item No 1.3 above but dia.63mm

pcs

4.00

124.00

496.00

4.00

124.00

496.00

1.3.5

Ditto item No 1.3 above but dia.75mm

pcs

8.00

130.00

1,040.00

8.00

130.00

1,040.00

1.3.6

Ditto item No 1.3 above but dia.90mm

pcs

4.00

143.00

572.00

4.00

143.00

572.00

2.1
2.1.1

Waste Drainage System


Supply lay and connect PVC pipes for foul drainage.
The quality of material should satisfy the
requirements of British Standard Specification BS
5481 or equivalent institution complete with all
accessories.
external dia.50mm

Phase II Executed Work to Date

ml

240.00

65.00

15,600.00

240.00

65.00

15,600.00

11 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC

2.1.1

external dia.80mm

ml

180.00

91.00

16,380.00

180.00

91.00

16,380.00

2.1.2

external dia. 110mm

ml

800.00

104.00

83,200.00

800.00

104.00

83,200.00

10

Down Pipe

SUB SOIL DRAINAGE SYSTEM


a-Supply and lay purpose made uPVC slotted plastic

pipe to BS 1194:1969 for subsoil drainage system

around the building according to where shown on

the basement floor plan and detail drawing.

Unit price shall include:

- filling and spreading of coarse gravel to an average

depth of 4.5 meters & average width of 1.0 meter.

- covering of geosynthetics around the gravel pack.

- 1.0meter thick fine gravel above the coarse gravel.

- min.5mm thick damp proofing membrane in

accordance to the manufacturer's instruction.

-100-120mm solid block to protect damp proofing

membrane

- well compacted clay soil on the top

- All other necessary connecting pieces and

civil assistance works.


Dia. 160 mm

ml

90.00

3,880.00

349,200.00

90.00

3,880.00

349,200.00

Septic Tank

Excavation Work
Excavation in gard rock

m3

312.50

620.00

193,750.00

193,750.00

Back fill

m3

125.00

250.00

31,250.00

31,250.00

Caraway

m3

312.50

200.00

62,500.00

62,500.00

25cm Concrete bottom slab

m2

63.00

700.00

44,100.00

44,100.00

Concrete shear wall

m2

130.00

700.00

91,000.00

91,000.00

Concrete top slab

m2

63.00

700.00

44,100.00

44,100.00

Concrete

Form work

Phase II Executed Work to Date

12 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

Net Difference BC

Concrete shear wall

m2

260.00

230.00

59,800.00

59,800.00

Concrete top slab

m2

63.00

230.00

14,490.00

14,490.00

Steel Reinforcement

Kg

5,096.00

37.00

188,552.00

188,552.00
-

TOTAL CARRIED TO SUMMARY

853,788.90

1,260,802.00

407,013.10
-

ELECTRICAL INSTALLATION

Supply and install :-

1 Power & Tele Intakes


Quantity)
1.2

(Provisional

Manhole
Manhole in bricks and with concrete base internally of
600x600x700mm including concrete cover with lifting
hole.

12.00
No

12.00
1,250.00

15,000.00

1,250.00

15,000.00

PVC pipes.

1.1

110 mm diameter.

ml

35.00

125.00

4,375.00

35.00

125.00

4,375.00

1.2

32 mm diameter.

ml

210.00

35.00

7,350.00

210.00

35.00

7,350.00

1.3

70 mm diameter.

ml

42.00

80.00

3,360.00

42.00

80.00

3,360.00

1.4

50 mm diameter.

ml

105.00

55.00

5,775.00

105.00

55.00

5,775.00

No

2.00

14,500.00

29,000.00

2.00

14,500.00

29,000.00

Tele Terminal Box


1.4

Tele Terminal Box ( By Telephone Utility).

2 Low Voltage System Earth

2.1

20x1000mm earth rod.

2.2

1x70 sq mm bare copper earth conductor from kWhmt


board earth terminal to earth rods in PVC pipe 50mm
diameter.

No

2.00

1,200.00

2,400.00

2.00

1,200.00

2,400.00

24.00
ml

24.00
210.00

5,040.00

210.00

5,040.00

4.1

4 Distribution Boards
Flush mounted distribution Board, MDB with lockable
door and including bus bars of 630 Amp3Phase, all
necessary fixing and connecting accessories, complete
and consisting:7 pcs 10A, MCB, 1Phase

Phase II Executed Work to Date

13 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

2 pc 16A, MCB, 1Phase


2 pc 20A, MCB, 1Phase

Net Difference BC
-

No

2.00

54,200.00

108,400.00

2.00

54,200.00

108,400.00

20 pc 32A, MCB, 3Phase

1 pc 50A, MCB, 3Phase

1 pc 25A, MCB, 3Phase

1 pc 630A, MCB, 3Phase

6.2

Ditto, but SDB-gf/5f with a bus bar of 32Amp/3Phase


and consisting:8 pc 16A, MCB, 1Phase
3 pc 10A, MCB, 1Phase

No

40.00

5,700.00

228,000.00

48.00

5,700.00

273,600.00

45,600.00
-

1pc 32A, MCB, 3Phase

3 pc 25A, MCB, 1Phase

1 pc 6A, MCB, 1Phase

6.3

Ditto, but SDB-CO with a bus bar of 20Amp/1Phase


and consisting:1 pc 16A, MCB, 1Phase
3 pc 10A, MCB, 1Phase

No

8.00

2,100.00

16,800.00

8.00

2,100.00

16,800.00

6 pc 25A, MCB, 1Phase

5 Feeder Power Cables


Multi-core power cable copper conductor, PVC/PVC,
color coded, in PVC conduits, connected and tested, all
as specified and as shown on drawings
CABLES

5.1

(5x10) Sqmm

ml

65.00

135.00

8,775.00

65.00

135.00

8,775.00

5.2

(3x300/150) Sqmm

ml

88.00

2,750.00

242,000.00

88.00

2,750.00

242,000.00

5.3

(5x6) Sqmm

ml

625.00

85.00

53,125.00

890.00

85.00

75,650.00

5.4

(5x4) Sqmm

ml

145.00

45.00

6,525.00

145.00

45.00

6,525.00

22,525.00
-

6 Light Points

6.1

Flush mounted light points fed through PVC insulated


conductors of 2x2.5mm2 inside PVC conduits of 16mm
diameter, including junction boxes with covers and
insulating screw cap connectors, complete

Phase II Executed Work to Date

No

1,491.00

245.00

365,295.00

2,407.00

245.00

589,715.00

224,420.00

14 of 15

Comparision b/n Contract Data and Assessment

Item

Description

Unit

Qty

(B) Main Contract Data


Rate
Amount

Qty

(B) Computations
Rate
Amount

8 Flush Mounted Socket Outlet Points

Net Difference BC
-

8.1

10-16A/1P socket outlet points fed through PVC


insulated conductors of 3x2.5mm2 inside PVC conduit
of 16mm diameter including junction boxes with
covers and insulating screw cap connectors.

No

1,184.00

245.00

290,080.00

1,076.00

245.00

263,620.00

(26,460.00)
-

11 Telephone System

11.1

Telephone system only conduits of 50/32/20 mm


diameter, pulling wire, boxes, terminals all as shown
on the drawings.

No

355.00

65.00

23,075.00

236.00

65.00

15,340.00

(7,735.00)
-

13 TV System

13.1

TV point fed through co-axial cable of RG/59 BU


inside PVC conduit of 25mm diameter including
junction boxes with covers, insulating screw cap
connectors, and flush mounted terminal TV socket .

NO

288.00

200.00

57,600.00

184.00

200.00

36,800.00

(20,800.00)
-

15 Lightning Protection

15.1

Fix Lightning Vertical Air Terminal 15x1200 mm

No.

1.00

500.00

500.00

1.00

500.00

500.00

15.2

Fix Copper roof conductor 1x50 sq mm fixed at


intervals of not more than 1000mm.

ml

42.00

25.00

1,050.00

42.00

25.00

1,050.00

15.3

Fix 1x50 sq mm bare copper down and earth


conductor in PVC pipe diameter 32mm.

ml

100.00

35.00

3,500.00

100.00

35.00

3,500.00

15.4

Fix Test junction box with connection clamps.

No

2.00

250.00

500.00

2.00

250.00

500.00

15.5

Fix 16x2400sqmm Earthling Rod Copper Bond with


Clamp for Earth Conductor including Coupling and
Driving Stud.

No

2.00

500.00

1,000.00

2.00

500.00

1,000.00

15.6

Fix Manhole in bricks with concrete base internally of


500x500x500mm including concrete cover with lifting
No
hole.
Total Carried to Summary

Phase II Executed Work to Date

3.00

300.00

900.00
1,479,425.00

3.00

300.00

900.00

1,716,975.00

15 of 15

Você também pode gostar