i.
SITE
ii.
iii.
SOIL TEST
iv.
Set line and grade benchmarks.
Trial pit excavation and measured points for design and
construction methods.
MIX DESIGN
CLEARING , HOARDING
Site is cleared and prepared for excavation to tank base pit and
& EXCAVATION
TIMBERING/SHORING
SURFACE TREATMENT
1ST FORMWORK
weak concrete.
Faces of base slab and wall kicker up-stand are shuttered as edge
timber at about 1000mm high.
REINFORCEMENT
i. Starters for pad foundation and columns are fixed and cast to
CONCRETING
bars.
[Pre-mixed concrete is preferred]
i. About 100m of concrete is poured for the base slab including
1st Pour
thickening at the wall base and the up-stand for the water bar.
Concrete will be cast and vibrated continues at a goal.
ii. After the base slab is poured and dressed the internal
nd
Form
CURING
i.
ii.
PROFCON LTD
profcon_ltd@yahoo.com
METHOD STATEMENT
the slab and made wet as it dries to avoid rapid drying rate.
COLUMNS
3rd Fixing
3rd Form
2nd Pour
WALLS
th
4 Form
4th Fixing
3rd Pour
5 Fixing
4th Pour
Formwork is removed 21 days after casting of concrete
STRIKING OF FORM
All necessary Pipeworks and installation of pipe fittings are fixed.
PLUMBING
INSTALLATION
Pumps, control panels and all other electrical installation will be
ELECTRICAL
INSTALLATION
TESTING
executed.
The system will be disinfected and tested to rectify any defects
before it starts full operation.
The site is cleaned of debris and made good of any damage caused
FINAL CLEAN UP
FINAL INSPECTION &
HANDING OVER
during construction.
The client and the contractor take the last inspection and the facility
is handed over.