PA - Oracle Applications Project Billing Training Document

How the Manual Is Organized


This manual is divided into 9 major sections:
1. Introduction
2. Basic Concepts
3. Setups
4. Project Initiation
5. Expenditure Entry
6. Revenue and Invoice generation
7. Revenue and Invoice Interfaces
8. Accounting Entries
9. Reports

Raju Chinthapatla

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Introduction
Module Overview
Oracle Project Costing and Billing provides an integrated cost management solution for all projects and activities
within an enterprise. With Project Costing you can manage costs across currency and organizational boundaries
Where as using Oracle Project Billing provides you with the ability to simplify your client invoicing, improve
your cash flow, and measure the performance and profitability of your contract projects.
Oracle Project Billing, together with Oracle Project Costing, provides a complete, integrated project billing
solution.
Overview

Create Contract Project type, project template


Create Agreement against the customer
Define Bill rate schedule
Enter time and expenses against the project
Generate Revenue and Invoices
Transfer to Receivables.

Integration of Oracle Projects with other Oracle Modules:


Projects Module is integrated with other Oracle Modules like Oracle Sales, Inventory, Payables, Assets and
General Ledger. Oracle Projects suite works together with other modules to provide a complete enterprise
project management solution.

Oracle Projects Integration with Other Oracle Modules

Inventory

Receivables

Purchasing

Projects

General Ledger

Payables

Fixed Assets

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Basic Concepts
Project
A unit of work that requires resources to produce measurable results. A project can be broken down into one or
more tasks.
Project/Task organization
The Organization that owns the project or task. This can be any organization in the list of values for the project
setup. The Project/Task Organization LOV contains organizations of the Project/Task Organization Type in the
Organization Hierarchy and Version below the Start Organization. You specify your Start Organization and
Version in the Implementation Options window.
Task
A subdivision of project work. Each project can have a set of top tasks and a hierarchy of subtasks below each
top task.
Agreement
A contract with a customer that serves as the basis for work authorization. An agreement may represent a
legally binding contract, such as a purchase order, or a verbal authorization. An agreement sets the terms of
payment for invoices generated against the agreement, and affects whether there are limits to the amount of
revenue you can accrue or bill against the agreement. An agreement can fund the work of one or more projects.
Project Template
A standard template you create for use in creating other projects. You set up project templates that have features
common in the projects you want to create.
Invoice format
The columns, text, and layout of invoice lines on an invoice.
Expenditure type
An implementation-defined classification of cost that you assign to each expenditure item. Expenditure types are
grouped into cost groups (expenditure categories) and revenue groups (revenue categories).
Expenditure category
An implementation- defined grouping of expenditure types by type of cost. For example, an expenditure
category with a name such as Labor refers to the cost of labor.
Auto Accounting
In Oracle Projects, a feature that automatically determines the account coding for an accounting transaction
based on the project, task, employee, and expenditure information.
Auto Accounting Lookup Set
An implementation-defined list of intermediate values and corresponding Accounting Flexfield segment values.
AutoAccounting lookup sets are used to translate intermediate values such as organization names into account
codes.
AutoAccounting parameter

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

A variable that is passed into AutoAccounting. AutoAccounting parameters are used by AutoAccounting to
determine account codings. Example AutoAccounting parameters available for an expenditure item are the
expenditure type and project organization. AutoAccounting parameters are predefined by Oracle Projects.
AutoAccounting Rule
An implementation-defined formula for deriving Accounting Flexfield segment values. AutoAccounting rules
may use a combination of AutoAccounting parameters, AutoAccounting lookup sets, SQL statements, and
constants to determine segment values.
Bill rate schedule
A set of standard bill rates that maintains the rates and percentage markups over cost that you charge clients for
your labor and non-labor expenditures.
Revenue category
A revenue category describes a source of your organization's revenue. For example, a revenue category with a
name such as Labor refers to labor revenue.
First bill offset days
The number of days that elapse between a project start date and the date that the projects first invoice is issued.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Setups Overview
Setting up is the process where the Oracle Applications Modules will be configured to meet the requirements of
an organization based on their requirements.
Following are the steps involved in the setting up Oracle Projects Billing Module. However before configuring
the Project Billing ensure whether the following Prerequisites are complied with:
General Pre-requisites:

Ensure that required organizations are setup

Create an Project Super User responsibility for the Operating Unit (OU)

Attach relevant Profile options (e.g. Set of Books) to the responsibility

Perform the setups in the same order as suggested below


Project Billing Setups:
Step
Required /
No.
Optional
1
Required
2
Required
3
Required
4
Required
5
Required
6
Required
7
Required
8
Required
9
Required
10
Required
11
Required
12
Required
12
Required
13
Optional
14
Optional
15
Optional
16
Optional
17

Optional

Particulars
Set the profile option PA: Licensed to Use Project Billing to Yes
Define Receivables System Options
Define and assign output tax codes
Define Payment terms
Define Rate schedules
Define Invoice formats
Define Event types
Define Agreement types
Define Customers
Setup to AutoAccounting
Define Project Types with project class Contract
Define Project Template
Enable Billing Implementation Options
Define Invoice print method
Define Credit types
Define and assign billing assignments
Define percent complete revenue accrual and invoicing options
Set the profile option PA: Maintain Unbilled Receivables and
Unearned Revenue Balances

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Setups
Billing Implementation Options
Navigate to the Implementation Options Screen.
N Setup System Implementation Options

1. Operating Unit: Its a new feature in R12. You can define your Implementation options based on
your Operating Units. It means that from a single responsibility you can Define/Query Multiple
Operating Unit based Implementation Options Set Ups. The same feature was not available in
previous releases.
2. Ledger: In R10.5.10 the same information was defined under Set of Books Tab. In R12 the name has
been changed to Ledger. If you are implementing Oracle Projects for a single organization, then
you must specify a set of books to tell Oracle Projects which set of general ledger books to use. If
your implementation of Oracle Projects is for multiple organizations, Set of Books is a display-only
field. Its value defaults from the Legal Entity for the operating unit.
3. Summarization Period Type: summarization period type is used when updating project summary
amounts.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

4. Calendar Name: When you implement Oracle Projects, you can select the calendar used to
maintain PA periods.
5. PA Period Type: Specify a Period Type, which is used to copy Project Accounting Periods from the
calendar associated with the GL Set of Books.
6. Maintain Common PA and GL Periods: When this option is enabled, the system automatically
maintains PA period statuses as you maintain the GL period statuses.
7. Default Asset Book: Optionally, select a default asset book from the list of values. The value that
you select for this field will be the default value for all project assets that you create. You can
override the default value at the asset level.
8. Default Reporting Organization Hierarchy: You specify an organization hierarchy and version to
indicate which organization hierarchy you want Oracle Projects to use as the default reporting
organization hierarchy.

1. Functional Currency: This display-only field shows the functional currency of your companys
set of books.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

2. Exchange Rate Date Type: Specify a default exchange rate date type for converting foreign
currency transactions from the transaction currency to the functional and project currencies.
3. Exchange Rate Type: Select the GL Rate Type to determine the rate. The system-defined rate
types, such as Corporate, User, or Spot, are defined in Oracle General Ledger.

1. Project Numbering: Specify whether you want Oracle Projects to number projects automatically,
or whether you plan to enter project numbers manually.
2. Project/Task Owning Organization Hierarchy: You assign a project/task owning organization
hierarchy to the operating unit to control which organizations can own projects and tasks.
3. Version: Enter the version number.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Interface Revenue to GL: If you want to interface revenue with Oracle General Ledger, you
need to enable the system option for revenue interface.
2. Invoice Numbering Method: You specify whether you want Oracle Projects to number
invoices automatically, or whether you plan to enter invoice numbers manually.
3. Next Number: If you want Oracle Projects to automatically number each invoice, you
specify a starting invoice number.
4. Centralized Invoice Processing: If you want all of the project invoices for the operating unit
to be processed using the Oracle Projects seeded transaction types, leave the check box
enabled. With decentralized invoicing, you allow organizations to process their own invoice
collections.
5. Invoice Batch Source: Oracle Projects provides a predefined batch source name PROJECTS
INVOICES. You must select this batch.
6. Enable Multi-Currency Billing: Check this box if you want to enter transactions in multiple
currencies.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

7. Require Rate and Discount Reason: Oracle Projects allows you to enter a reason for the rate
or discount override to the standard bill rate schedules. Check this box if you want to require
users to enter the rate and discount override reason.
8.

Allow Bill Rate Override: Check this box if you want to be able to override bill rates for all
the projects in the operating unit.

9. Allow Bill Rate Discount Override: Check this box if you want to be able to override the bill
rate discount for all the projects in the operating unit.
10. Share Bill Rate Schedules Across Operating Units: Check this box if you want to fund
projects across operating units. If you enable this functionality, the list of values for project
number includes active projects that are associated with the agreement of the customer.
11. Require Credit Memo Reason: Enable this option if you require a user to select a credit
memo reason when releasing canceled invoices, write-offs, and credit memos.
12. Save your work

Define Work Type


Work types are an implementation-defined classification of work performed. Work types are used to classify
both actual and forecast amounts. Examples are Billable, Non-Billable, Training, and Personal. Work types are
grouped together by Utilization Categories.
N Setup UtilizationWork Types

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Enter Work Type name in the Name field.


2. Enable the Billable Check Box if you want the work type to be billable
3. Enter Description if required
4. Enter the Effective start and end dates for the work type.
5. Click on Utilization Tab and select the utilization category from list of values
6. Enter the Weighting Percentage as 100.
7. Select the utilization category from list of values under the Organization Region.
8. Enter the Weighting Percentage as 100

Define Expenditure Types


An expenditure type is a classification of cost that you assign to each expenditure item you enter in Oracle
Projects.
N Setup ExpendituresExpenditure Types

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Name: Enter a unique name for the expenditure type.


2. Expenditure Category and Revenue Category: Enter the expenditure category and revenue
category you want to associate with this expenditure type.
3. Unit of Measure: Enter the unit of Measure you want Oracle Projects to use when calculating the
cost for this expenditure type. You must enter Hours for labor expenditure types.
4. Tax Classification Code: This is a new feature in R12. You need to click Tax Classification Code
and select the tax classification code for customer invoice lines for this expenditure type and
operating unit. Oracle Projects uses this code as the default tax classification code based on the
Application Tax Options hierarchy that you define in Oracle E-Business Tax for Oracle Projects and
the specified operating unit.
5. Rate Required: If this expenditure type requires a cost rate, check the Rate required check box,
then choose Cost Rate to navigate to the Expenditure Cost Rates window and enter a cost rate and
its effective date(s).
6. Description and Dates: In the Description, Dates region, enter a description for the expenditure
type. You can optionally enter effective dates for the expenditure type.
7. Expenditure Type Classes: In the Expenditure Type Classes region, enter the
Expenditure Type Class or classes you want Oracle Projects to associate with
This expenditure type, to determine how to process the expenditure item.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Define Rate Schedules.


Oracle Projects determines rates from a combination of rate schedules or rate overrides and uses these rates to
calculate cost, revenue, and bill amounts. We can define four types of rate schedules:
Employee
Job
Non-Labor
Resource Class
Define Billing and Non Billing rate schedules
N Setup ExpendituresRate Schedules
First Define Employee Bill Rate Schedule

To define a rate schedule:


1. Specify the Operating Unit. This is a new feature in Release 12. Specify the operating unit to which your
organization and rate schedule belong. When you have access to only one operating unit, that operating unit
appears as a default value in this field.
2. Specify the organization that maintains the schedule.
The organization you enter can be any organization from your organization hierarchy, regardless of whether the
organization has the Expenditure Organization classification, and regardless of the start and end dates for the
organization.
3. Enter a schedule name and a description of the schedule.
4. Specify a currency for the schedule.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Note: You can specify a different currency for your Bill Rate Schedule if the Enable Multi Currency Billing
option is enabled for the operating unit. See: Enable Multi Currency Billing, Billing Implementation Options, and
Oracle Projects Implementation Guide.
4. Check the Share across Operating Units check box to allow other operating units to use this schedule.
Note: To share bill rate schedules, you must also enable the Share Bill Rate Schedules across Operating Units
options in the Billing tab of the Implementation Options window. See: Share Bill Rate Schedule Across
Operating Units, Billing Implementation Options, and Oracle Projects Implementation Guide.
5. Select a schedule type.
6. Rates can be defined employee wise or Job wise. Incase of job wise rate Click on the Job Tab and Select Job
group.
7. Select Employee name against whom the rate need to be defined.
8. Employee Number and UOM defaults.
9. Enter the Rate or Markup percent.
10. Enter the effective start and end date for the rate.
Now, define Job Bill Rate Schedule

Just update the Organization, Schedule Name and Currency and save your work.
Now, define Non Labor Bill Rate Schedule

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Just update the Organization, Schedule Name and Currency and save your work.

Define Invoice Formats


An invoice format determines how Oracle Projects creates an invoice line. You can define different formats for
labor, non-labor, the columns, text, and layout of invoice lines on an invoice.
N Setup Billing Invoice Formats

1. Name: Enter a unique, descriptive name for this invoice format.


2. Format Type. Select a format type. The format type controls the invoice formats you see
for labor, non-labor, retention, and retention billing when you enter invoice formats
using the Projects window.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

3. Start and End. Specifies where you want this field to appear on the invoice line. Enter
numbers between 1 and 240.
4. Grouping: Enter a grouping option for this invoice format. You can choose any grouping
option available for this type of invoice. A grouping option specifies what fields are the
primary groupings of items into invoice lines, and is based on the funding level of the
project. A project budgeted at the top task will have a top task grouping rule.
5. Use For: Select an option to indicate if you want to use this invoice format for customer
invoices, intercompany invoices, or both.
6. Field Name: Enter the name of the field that you want to appear on the invoice line. You
can choose any invoice line field available for grouping option or the invoice format.
7. Right Justify Select if you want this field value to appear right justified between the
specified start and end positions.

Define Billing Cycle


In Oracle Projects, user-defined cycles are used to specify when certain actions and processes take place. Billing
cycles determine how often and on what dates a project is billed.
N Setup System Cycles

1. Enter the name of the billing cycle in the Name field.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

2. Select the type from list of values based on the requirement and enter days in the cycle days
value field.
3. Enter the effective start and end dates

Define Event Types


An implementation-defined classification of events that determines the revenue and invoice effect of an event.
Typical event types include Milestones, Scheduled Payments, and Write-Offs.
N Setup Billing Event Types

1. Enter a unique, descriptive name for this event type.


2. Revenue Category: Enter the revenue category that you want to associate with this event type.
3. Class: Enter a classification for this event type
Automatic. An Automatic classification generates an automatic event for
revenue or
invoice amounts that may be positive or negative, depending on your implementation of
billing extensions.
Manual. A Manual classification allows you to enter both a revenue amount and a bill
amount. These two amounts can be different. Classify an event type as manual when
you need to indicate different revenue and bill amounts.
4. Enter the effective start and end dates.
5. Tax Classification Code. This is a new feature in R12 .Optionally; click Tax Classification
Code to select the tax classification code for customer invoice lines created for this event type
and operating unit. Oracle Projects uses this as the default tax classification code based on
the Application Tax Options hierarchy that you define in Oracle E-Business Tax for the

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Oracle Projects application and the project's operating unit. For more information on setting
up tax classification codes and the hierarchy of application tax options, see the Oracle EBusiness Tax User Guide.

Define Resource List


Define the resource list as a hierarchy of resources up to two levels. The top level is restricted to resource types,
such as organization, expenditure category, and revenue category. Use the resource types Event Type,
Expenditure Type, Revenue Category, and Expenditure Category to define the second level of the hierarchy:
N Setup Budgets Resource Lists

1. Enter the Resource List name and Description.


2. Group Resources By: Choose how you want to group the resource list. If you choose to group the
resource list, and then you enter resource groups. Select the resource group, and override the alias and
order if necessary.
3. If the resource list is job-based, then you must enter a job group to be used for summarization. The
Resources region then displays jobs that belong to the job group you entered.
4. In the Resources region, enter the resources for each resource group. If you do not use grouping for the
resource list, then use the Resources region to enter resources for the resource list.
5. Select the resource type and resource .Resource type could be Expenditure type, Event etc
6. Alias and the Order number defaults automatically .Override the values if required.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Define Agreement Types


Agreement types categorize the various kinds of agreements you negotiate with clients. For example, you can
define one agreement type for all verbal agreements and another for all agreements using purchase orders.
N Setup Billing Agreement Types

1. Enter a unique, name and description for this Agreement type.


2. If you want payment terms to default when you enter an agreement with this agreement
type, enter the Default Terms.
3. Enable the Default Revenue/Invoice Limit option if you want the Hard Limit option of the
Agreements widow to be enabled by default when you enter an agreement with this
agreement type.
4. Enter Effective Start and End Dates.

Define Budget Entry Method


Budget entry methods specify and control how you enter a budget or forecast. You use budget entry
methods when you create budgets and forecasts that use budgetary controls and budget integration features.
N Setup Budgets Entry Methods
Oracle Projects predefines three budget entry methods:
By lowest tasks and date range, Categorized by Resources
By lowest tasks and GL period, Categorized by Resources
By lowest tasks and PA period, Categorized by Resources
You can define additional budget entry methods during implementation.
Defining Budget Entry Methods
1. Navigate to the Budget Entry Methods window.
2. Enter a name and description for the budget entry method.
3. Select an entry level. The entry level can be Project, Top Tasks, Lowest Tasks, or Top and Lowest Tasks.
4. Select Categorized by Resources if you want to categorize amounts by resources.
5. Select a time phased type. The choices are Date Range, GL Period, PA Period, or None.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

6. Select the enterable fields for cost and revenue using the displayed check boxes.
7. Save your work.

Define Project Type


The project type controls how Oracle Projects creates and processes projects, and is a primary classification for
the projects your business manages. You must set up at least one project type to create projects in Oracle
Projects. There are three project classes:Contract: Collect and track costs, labor hours, revenue, and billing for services performed for and reimbursed
by a client.
Indirect: Collect and track expenditure item costs and labor hours for overhead activities, such as administrative
and overhead work, marketing, and bid & proposal preparation.
Capital: Collect and track costs and labor hours for asset development activities that you plan to capitalize as
one or more assets.
N Setup Projects Project Types

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Operating Unit: This is a new Feature R12. You can now define your Project
Operating Unit basis.
2. Enter a name & Description for the Project type.

Types on an

3. Class: Select Contract to create a contract project type


4. Enter effective start date of the project type
5. Service Type: Select the required service type from the list of values.
6. Work Type: Select the work type created above in the setup.
Click on the Billing Information Tab (Tab gets enables only when the class is Contract)

1. Operating Unit: Its a new feature in R12. You can define your Project Types based on
Operating Units. It means that from a single responsibility you can Define/Query
Multiple Operating Unit based Implementation Options Set Ups. The same feature was
not available in previous releases.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

2. Funding Level: The level at which you allow funding for contract projects of this project
type. You can choose from the values of Project, Top Task, or Both.
3. Billing Job Group: Enter a default job group for billing purposes. The job group you
enter serves as the default Billing Job Group when you define a contract project with this
project Type.
4. Labor: Select Bill Rate Schedule or Burden Schedule for labor billing.
5. Non-Labor: Select Bill Rate Schedule or Burden Schedule for non-labor billing.

Organization: Select the default organization that owns the labor and non-labor
bill rate schedules.

Schedule: The default burden schedule for non-labor revenue and invoicing.
6. Invoice Formats: Select the default labor and Non labor invoice format created above
7. Select the default billing cycle for projects of this type.
8. Baseline Funding without Budget: Check this box if you want to automatically create a
revenue budget when you baseline your funding.
9. Revaluate Funding: Check this box if you want to revaluate funding for the project type.
This option cannot be unchecked if the Revaluate Funding option is enabled at the
Project level.
10. Funding Revaluation includes Gains and Losses: This option can be enabled only if the
Funding Revaluation includes Gains and Losses option is enabled in the Implementation
Options window and Revaluate Funding is enabled for the project type. Check this box if
you want funding revaluation to include gains and losses. If you enable this functionality
you should define the project revenue realized gains and losses event types for account
reclassifications. If this functionality is not enabled, the revaluation process only
considers the funding backlog amount.
11. Realized Gains and Losses Event Types: If the Funding Revaluation Includes Gains and
Losses functionality is enabled at the Project Types level, define new gains and losses
event types. These event types record the realized gains and losses events while
processing funding revaluation.
Click on the Distribution Rules Tab

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Name: You select the distribution rules that can be allowed for any project of this project type. You can
choose any predefined distribution rule:
Cost/Cost: Accrue revenue and bill using the ratio of actual cost to budgeted cost (percent
spent)
Cost/Event: Accrue revenue using the ratio of actual cost to budgeted cost (percent spent), bill
based on events
Cost/Work: Accrue revenue using the ratio of actual cost to budgeted cost (percent spent), bill
as work occurs.
Event/Event: Accrue revenue and bill based on events.
Event/Work: Accrue revenue based on events, bill as work occurs.
Work/Event: Accrue revenue as work occurs, bill based on events.
Work/Work: Accrue revenue and bill as work occurs.
Click on the Project Status, Workflow Tab

PA - Oracle Applications Project Billing Training Document

Starting status for new projects and workflows to be used for status changes
Define Project Template
NSetup Projects Project Templates

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Operating Unit: Its a new feature in R12. You can define your Project Types based on Operating
Units. It means that from a single responsibility you can Define/Query Multiple Operating Unit
based Project Template Set Ups. The same feature was not available in previous releases.
2. Enter a name and number for Project Template.
3. Type: Select the project type to be used with this template.
4. Organization: Select the organization, to which the template belongs .This organization defaults
when a project is created, can be overridden as per requirement.
5. Long Name can be same as your Template Name.
6. Optionally enter the Trans duration start and end dates.
7. Description can be same as your Long Name.
8. Show Checkbox: You can check the check box if you wish the Options to get copied over to the
projects that you create using the same Template.
9. Oracle by defaults enables standard project options. You can update a project template at any time.
All changes to a project template affect projects that are created from the template after the changes
are made.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

10. Click on the Setup Quick Entry: Quick Entry fields which specify fields to enter for the new project
when creating it from a template.
11. Save your work.

Auto Accounting
Oracle Projects creates many different accounting transactions throughout its business cycle (when posting labor
cost debits and labor revenue credits, for example). You can use AutoAccounting to specify how to determine
the correct general ledger account for each transaction.
When you implement AutoAccounting, you define the rules and circumstances that determine which general
ledger accounts Oracle Projects uses. Oracle Projects then uses the rules when performing accounting
transactions.
Define AutoAccounting rules to generate account combinations, and then assign a set of rules to each
AutoAccounting transaction you want to use for your company.
De ning a Lookup Set
In lookup sets you specify pairs of values. For each intermediate value, you specify a corresponding account
segment value. One or more related pairs of intermediate values and segment values form a lookup set. Use the
Segment Value Lookup Region zone to specify an intermediate value, and then map that intermediate value to a
specific segment value of your Accounting Flexfield.
De ning AutoAccounting Rules
AutoAccounting rule you define supplies one Accounting Flexfield segment value at a time. Thus, you need to
specify one AutoAccounting rule for each segment in your Accounting Flexfield for each AutoAccounting
transaction you want to use. Some of the AutoAccounting rules you define can be quite simple, such as always
supplying a constant company code or natural account. Others can draw upon context information (parameters),
such as the revenue category for a particular posting or the organization that owns a particular asset. You can
even use multiple parameters to provide a segment value. You can reuse the same AutoAccounting rules for
many different functions and their transactions.
Assigning Rules to Transactions
AutoAccounting function consists of several distinct transactions; you assign rules to each transaction you want
to use. These rule assignments then determine which general ledger account AutoAccounting uses to process
that transaction. After you enable a transaction, you match each segment in your Accounting Flexfield with the
appropriate AutoAccounting rule. For example, if you have a two-segment Accounting Flexfield containing a
Company segment and an Account segment, you assign one rule to the Company segment and one rule to the
Account segment.

PA - Oracle Applications Project Billing Training Document

Profile Options
Profile

Value

GL Set of Books Name

Vision Operations (USA)

MO: Operating Unit

Vision Operations

Rouser Type

HR User

PA: Licensed to use Project Billing

Yes

PA: Licensed to use Project Collaboration


PA: Licensed to use Project Costing

Yes

PA: Licensed to use Project Management

Yes

PA: Licensed to use Project Resource Management


PA Time: Allow Entry of Negative Hours

Yes

PA Time: Enable Business Message

Yes

PA: Allow Project Time and Expense Entry

Yes

PA: Auto Approve Timesheets

No

PA: Debug Log Directory

/usr/tmp

PA: Debug Mode

Yes

PA: Default Burden Schedule Type

Firm

PA: Default Calendar

Vision Operations

PA: Default Public Sector

No

PA: Display Find Tasks Window


PA: Enable Budget Integration and Budgetary Control
Feature

Yes

PA: Enable Enhanced Period Processing

Yes

PA: Expenditure Items Per Set

100

PA: Global Week Start Day

Monday

PA: Highlight Starting Tasks: Number of Days

PA: Require Work Type Entry for Expenditures

Yes

Yes

PA: Starting Assignment Status


PA: Tasks to Display for Expenditure Entry

Chargeable tasks

PA: Transaction Billability derived from Work Type

No

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Initiation
Project Creation
N Double click on the projects menu in the Navigator
1. The Projects screen will be displayed.

2. Select the project template using which you need to create project and click on find button

3. Select Copy To Button

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

4. Enter the project details in the quick entry fields, fields marked as Required are to be
mandatory entered
5. Click OK to complete project creation process.
Approve the Project
Project need to be approved before any transactions are raised against it. Click on the Change Status
button and select the status approve.

Project Options
You specify project and task options to control how Oracle Projects processes your projects. Project and Task
options are available at various levels of your financial and/or work plan structure. Use the Projects and Tasks
windows to specify project and task options.
Customers and Contacts: Enter the customer and contact information of the project. You can define
multiple customers for one project.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Name/Number: Choose a project customer. You can choose any active customer in the Oracle
Receivables customer database.
2. Relationship: The relationship between this customer and your project, such as Primary, or Non-Paying.
3. Contribution: The percentage of this projects revenue and billing you expect this customer to contribute.
If you enter more than one customer for this project, the total customer contributions towards revenue
and billing must sum to 100% before you can accrue revenue or bill invoices against this project.
4. Bill to Name: Enter the name of the customer who will receive the project invoices. Depending on the
Customer Relationships setting in the Implementation Options window, you can choose the project
customer, a related customer, or any customer defined in Oracle Receivables
5. Billing Address: The address where you want to send this customers invoices. You can choose any
active billing address defined for the Bill To customer in Oracle Receivables.
6. Shipping Address: The address where work will be performed for this project. You can choose any
active Ship to address defined for the Ship To customer in the Oracle Receivables database.
7. Bill another Project: Select if you want to identify a project as a provider project for purposes of interproject billing.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

8. Receiver Project / Receiver Task: Enter the numbers of the projects and tasks that will receive the work
performed on this project. Valid receiver projects and tasks belong to receiver operating units that have
identified the current operating unit as a provider
9. Invoice Currency: If you want to invoice the project customer in a currency different from the project
currency.
10. Allow Rate Type "User": Enable this option if you want to allow the rate type "User" for invoicing this
project customer.
11. Code: The default invoice currency code for the customer.
12. Rate Date: The default exchange rate date. If this field is left blank, the system will use the Bill Through
date for the exchange rate date.
13. Rate Type: The default rate type.
14. Contacts Type: A contact type, such as Billing or Shipping, to identify a contact. The billing contacts are
limited to the contacts defined for the Bill To customer and billing address. The shipping contacts are
limited to the contacts defined for the Ship To customer and shipping address.
15. Name: Choose any active contact name defined for the Bill To customer
Billing Information:
Billing Setup

1. Revenue Accrual Method and Invoice Method: The project type determines which distribution rule
appears as the default value for these fields. The revenue accrual method and invoice method you enter
determines how revenue is calculated and how invoices are generated for this project.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Work/Work: Revenue and the Bill or Invoicing is based on as the work occurs.
Work/Event: Accrue revenue as work occurs, and Bill based on events.
Event/Event: Accrue revenue and Bill based on events.
2. By Default Distribution Rule set for the Project Type gets defaulted on to the project. The Other attributes
which get defaulted in the billing section from the Project Type are Billing Cycle, Next Billing Date.
Invoice Formats
3. Invoice Method at Top Task: Check this box if you want the ability to override the project level invoice
method at the top task. If you enable this option you can use multiple invoice methods for a project.
4. Baseline Funding without Budget: Check this box if you want to automatically create an approved
revenue budget and baseline youre funding for this project.
Bill Rates and Discount Overrides: Select and expand Bill Rates and Discount Overrides Options in Project
Window
Standard Billing Schedules

1. Enter a Labor or Non-Labor billing schedule (see the rate schedule setup Topic), you must choose
whether to use a Bill Rate Schedule or a Burden Schedule
2. Enter a Non-Labor Bill Rate Schedule; enter the Organization, Schedule Name, Fixed Date, Discount %,
and Discount Reason.
3. Rate can be defined Employee wise, Job wise, Non labor wise. This rate can be overridden for
each of these levels.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

4. Employee Bill Rates and Discount Overrides: You can override an employees standard bill rate by rate
or discount when there is an override the new bill rate or discount rate of the employee takes precedence
over the job bill rate and discount override you define at the project level and task level.
5. Job Bill Rate and Discount Overrides: You can override a jobs standard bill rate for a project or lowest
task by rate or discount. When you override a jobs standard bill rate by rate override, the new job bill
rate becomes the jobs bill rate for this project or lowest task.
6. Non-Labor Bill Rate and Discount Overrides You can override a non-labor standard bill rate for nonlabor expenditure types and non-labor resources. When you override a usage expenditure type, the
override applies to all non-labor resources within that usage expenditure type.
Agreement Creation
An agreement provides the funding for projects and tasks. Oracle Projects allows you to define agreements,
projects, and tasks to organize your project work.
N Billing Agreement

1. Select the customer name


2. Operating Unit: Its a new feature in R12. You can define your Implementation options based on
your Operating Units. It means that from a single responsibility you can Define/Query Multiple
Operating Unit. The same feature was not available in previous releases.
3. Enter a Number to identify this agreement, such as the customers purchase order number.
4. Select agreement Type.
5. Enter the Amount of this agreement.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

6. Enter the payment terms (defined in Oracle Receivables) for any invoices funded by this
agreement.
7. Choose the Revenue Hard Limit or/and Invoice Hard Limit check box to impose a hard limit on
revenue accrual and invoice generation for projects funded by this agreement. Otherwise, Oracle
Projects imposes a soft limit.
8. Optionally enter the date this agreement expires.
9. Enter the name of the organization that owns the agreement.
10. Note: You can choose any project owning organization (in the project owning organization
hierarchy assigned to the operating unit) as the organization that owns the agreement.
11. Save your work.
Project Funding
You must fund a project before the project can accrue revenue and be billed. Funding is the step that allocates an
amount associated with a customer agreement to a specific project. The total amount of allocated project funding
must equal the current approved project revenue budget amount in order to successfully baseline the project.

1. Project Number: Enter the number of the project you want to fund with this agreement.
2. Task Number: Enter the number of the top-level task you want to fund with this agreement. If
you do not want to restrict funding for a particular task, leave this field blank.
3. Date Allocated: Enter a Date to record when you allocated agreement funds to this project or
task. The Date Allocated is used as the rate date to determine the exchange rate when the Rate
Date Type for the project's funding currency attribute is PA/Invoice Date.
4. Amount: Enter the Amount you want to allocate to this project or task.
Funding Classification: Enter the Funding Classification to indicate the nature of the allocations. Funding lines
can be aggregated by funding classification and reported accordingly using Project Intelligence

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Budgets
A budget is the estimated cost or revenue for a project or task. You track project status and performance by
comparing budgeted amounts to actuals using reports and Project Status Inquiry.
Budget can be tracked at various levels like Top Task or Lowest Task level, Project level. Each budget can have
detailed or summary information in the following areas, as appropriate for each project.
We can enter a budget for the duration of the project or tasks (also known as budget at completion), or you can
enter timephased budgets which contain budget amounts by time period. We can enter timephased budgets
at the project, top task, or lowest task levels by organization and then by expenditure category within that
organization. The Budget Entry Method selected for each budget determines the duration of the budget.
We can have multiple Budget versions created for a project. Each budget has a draft, which is a working area for
an inprocess budget. The draft will not appear in any project status tracking inquiries or reports. (Note that
draft is not a budget type, since any type of budget can have a draft.) For each budget, you can create and save
many budget versions. Each time you baseline a draft, you create a new version. To help identify budget
versions, you can give each version a unique name and specify a change reason. You can view summary and
detail information for all budget versions.
Each budget version has one of the following classifications:
Original Budget: The first time you baseline a draft, the version is marked as the Original Budget.
Revised Original Budget: You may need to revise your Original Budget due to budget entry errors or changes
in the project scope. When you baseline a draft, you can identify the new baselined version as a Revised
Original. In calculations and displays that use the Original Budget, the most recent Revised Original is used (or
the Original Budget, if there is no Revised Original).
Current Budget: The most recent baselined version of the budget is the Current Budget. You can have only one
Current Budget for each budget type. Current Budget amounts are shown in the Project Status Inquiry window.
Historical Baselined Versions: Any baselined budget that is not the Current Budget is considered an historical
version of the
budget.
Budget types identify the different kinds of budgets that you enter for your projects. For cost budget types, you
can enter quantities, raw cost, and burdened costs. For budget using revenue budget types, you can enter
quantities and revenue amounts.
Oracle Projects predefines four budget types:
Approved Cost Budget
Approved Revenue Budget
Forecast Cost Budget
Forecast Revenue Budget

PA - Oracle Applications Project Billing Training Document


Budget Creation-Cost Budget

Navigate: Budgets

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1.

Choose the project for which you want to enter or revise budget amounts.

2.

Choose the budget type. The budget type field enables you to have more than one series of budgets
for a project. The budget type determines whether the budget is a revenue budget or cost budget.

3.

Version Name: Enter the version name.

4.

Budget Status :The budget status will be displayed, indicating where the budget is
in the working/submission/baselining process.

5.

Change Reason: Enter a change reason. The change reason identifies the reason for changing a
budget version from a previous version.

6.

Budget Entry Method You can accept or override the default budget entry method (BEM), which
determines the level of detail for the budget. If you are entering the first draft for the budget type,
the default BEM is determined by the project type of the project. If a prior version of the budget
type exists, the default BEM is the budget entry method of the projects current budget for the
budget type.

7.

Resource List: The resource list is the set of resources that can be used as budget categories for a
categorized (detail) budget. These resources will be displayed on the list of values for resource
when you are entering budget lines.

8.

Choose the Details button to open the Budget Lines window.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Select the Resource against which you want to budget


2. Select the Amount Type, amount types are dependant upon the Resource selection.
If you are entering a project level budget, the Budget Lines window will open. If you are entering a task level
budget, the Task Budgets window will open. Select a task, and then choose Budget Lines to open the Budget
Lines window.
If you are entering a budget that is periodphased (timephased by PA period or GL period), the matrix entry
Budget Lines window will be displayed for budget lines entry. The matrix entry window opens automatically
when you navigate to the Budget Lines window for a periodphased budget. The type of timephasing of the
budget is determined by the Budget
Entry Method selected for the budget.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

When you complete budget entry, you need to submit your draft budget to indicate that it is ready for review
and baselining.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Baselining is the process of approving a budget for use in reporting and accounting. When the baselining
function is called, the system copies the draft amounts into a new baselined budget
Version. The most recent baselined version is named the Current Budget, which is used for reporting. All
previously baselined budgets are historical baselined versions. The Current Budget, and all other baselined
budget versions, has a status of Baselined.
Budget Creation- Revenue Budget

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

For contract projects in Oracle Project Billing, the baseline function verifies that the budget amounts for the
budget type Approved Revenue Budget equals the total funding for the project within the project. If this check is
successful, a new budget version is created. If the amounts are not equal, Oracle Projects displays an error and
does not create a new budget version.
You must enter and submit an approved revenue budget and allocate funds to the project or task before you can
baseline it or automatically create a baseline budget when you baseline funding

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Expenditure Entry
You charge expenditures to a project to record actual work performed or cost incurred. Actual expenditure
could be timecards, expense reports, usage logs, and supplier invoices.
Expenditure on the project can be through various methods
1. Preapproved Batches
Preapproved Batches can be entered for
Timecards
Expense reports
Usage logs
Miscellaneous transactions
Burden transactions
Inventory transactions
Work in process transactions
2. Events
3. Import from other modules:
Purchasing and Payables :- Oracle Projects fully integrates with Oracle Purchasing and Oracle Payables and
allows you to enter projectrelated Requisitions, purchase orders, and supplier invoices using those Products
Receivables :- Oracle Projects generates draft invoices and uses Oracle Receivables features to create invoices
and interface the Accounting transactions to Oracle General Ledger.
Assets : - Oracle Projects integrates with Oracle Assets, allowing you to Manage capital projects in Oracle
Projects and update your fixed assets records when assets are ready to be placed in service
Project Manufacturing : Oracle Project Manufacturing is a solution for companies that manufacture products
using projects or contracts. When used as a part of the Project Manufacturing functionality, Oracle Projects acts
as a cost repository for manufacturing-related activities

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Expenditure- Preapproved Batch-Time Cards


N ExpendituresPre-Approved Batches Enter

1. Operating Unit: This is a new feature in R12. It gets defaulted from Profile Options.
Its a new feature in R12. You can define your Implementation options based on your Operating Units.
It means that from a single responsibility you can Define/Query Multiple Operating Unit based
Implementation Options Set Ups. The same feature was not available in previous releases.
2. Batch. Enter a unique Batch name to identify this set of expenditures.
3. Ending Date. Enter the expenditure Ending Date for the batch. If you enter a date that is not the last day
of an expenditure week, the system automatically updates the date to the next valid week ending date.
4. Description. Optionally enter a Description of the batch, or leave the field blank to use the name of the
expenditure type class.
5. Class. Choose the expenditure type class for this batch.
6. Amounts. Optionally enter Control Totals and Control Count in the Amounts region. Use the Running
Totals and Counts and the Difference column to verify actual versus entered totals.
7. Employee and Organization. In the Expenditures window, enter the employee or organization that
incurred the cost.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

For each expenditure item, enter the following information:


1. Expenditure Item Date. The date of the expenditure item.
2.

Project Number. The Project Number to charge for this expenditure item.

3.

Task Number. The lowest level Task Number to charge for this expenditure item.

4.

Assignment Name. When Oracle Project Resource Management is installed, you can associate labor and
expense report expenditures to scheduled work assignments.

5. Work Type. You can choose any active work type.


6. Expenditure Type. You can choose any expenditure type within the current expenditure type class.
7. Non-Labor Resource and Non-Labor Organization. If the expenditure type class for the batch is Usages,
enter the non-labor resource and its owning organization. This enables you to track usage of companyowned assets.
8. Currency Fields. You can optionally display and enter the currency fields.
9. Quantity. The quantity of units (the unit of measure is determined by the expenditure type). For
example, on a timecard, you enter the quantity for professional labor in hours. You can enter a mixture
of units, such as currency and miles, for an expense report.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Expenditure Preapproved Batch- Miscellaneous Transactions


Miscellaneous Transactions are similar to a journal entry in the GL. They are used to make entries that may or
may not have an employee or non-labor resource attached to them.
Miscellaneous Transactions are used to track miscellaneous project costs. This expenditure type class is similar
to usages. The difference is that, for miscellaneous transactions expenditure items, you are not required to
specify a nonlabor resource or a nonlabor resource organization, as you
are for usage expenditure items. Miscellaneous transactions may be used for the following costs:
Fixed assets depreciation
Allocations
Interest charges
Navigate to Expenditure Preapproved Batches Enter

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

1. Batch: Enter a unique Batch name to identify this set of expenditures.


2. Ending Date: Enter the expenditure Ending Date for the batch. If you enter a date that is not
the last day of an expenditure week, the system automatically updates the date to the next
valid week ending date.
3. Class: Choose the Miscellaneous type class
4. In Expenditure entry screen window, enter the employee or organization that incurred the cost.
5. Organization: It is the organization that is ordering or has ordered the goods or services,
which may be different from the project owning organization.
Enter the Project, Task, Expenditure and quantity Information
Submit and Release the Batch.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Generate Cost
In order to compute various expenditures that are booked for a project Oracle Projects uses Distribution
Processes.

Distribute Labor Costs: The process computes the labor costs for timecard hours and determines the GL account
to which to post the cost.
Distribute Usage and Miscellaneous Costs: The process computes the costs and determines the GL account to
which to post the cost for expenditure items with the following expenditure type classes:
Usages, Miscellaneous Transactions, Inventory and WIP transactions not already costed or accounted
Distribute Expense Report Costs: The process computes the costs of expense report expenditure items,
including adjustments, and determines the account to which to post the cost.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Expenditure- Supplier Invoices


We can record project information on supplier invoices for the purchases made for a specific project
For each transaction, Payables records the project name, task, and expenditure information. The Account
Generator creates a charge account for each invoice distribution that has project information. Project-related
transactions are interfaced back to Projects where the transactions are recorded and associated with particular
projects.
Project information can also be captured at the purchased order level .When you match an invoice to a purchase
order in Oracle Payables, the project information from the purchase order is copied to the invoice. When you
enter new projectrelated invoices in Oracle Payables, you only need to enter project information on the source
i.e. the invoice. If you use distribution sets with project information, Oracle Payables automatically supplies
project information for your supplier invoice distribution lines.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Create Project Related Supplier Invoice

When we specify project-related information in the Project fields region of the Invoice distribution lines. The
account information will automatically be created by the Account Generator, based on the project-related
information you enter. Make sure the Account Generator is enabled.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Enter Project , Task and Expenditure Type information.


Expenditure Type is an expenditure type classified with an expenditure type class of Supplier Invoices.
Expenditure Organization is the organization that is ordering or has ordered the goods or services, which may
be different from the project owning organization.
The Expenditure Item Date is the date that you expect to incur the expense for the goods or services that you are
requesting for a requisition or purchase order, or the date that you incur the charge for an invoice. This date is
used during online validation against project transaction controls, and becomes the expenditure item date on the
expenditure item in Oracle Projects. This date defaults to the current date each time you create a new
Accounting Flexfield combination.

PA - Oracle Applications Project Billing Training Document

Validate and Account the Invoice


Interface Costs

To load invoices and receipt accruals from Oracle Payables to Oracle Projects, use the

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

PRC: Interface Supplier Costs process in Oracle Projects.


The process selects transactions based on the parameter values entered. It first retrieves all eligible accounted,
project-related receipt accrual information, supplier invoice distributions (including non-recoverable tax lines)
and all payment discounts that are distributed to project-related distributions. The process then interfaces the
amounts
To Oracle Projects.
Note : All invoice distributions, excluding non-recoverable tax lines, are included in one batch.
Non-recoverable tax lines are grouped into a second batch,
Payment discounts are included in a third batch,
Receipt accruals for project related items with a destination type of Expenses are grouped
In the fourth .
Within each batch, expenditure is created for each invoice and an expenditure item is created for each invoice or
discount distribution.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Expenditure Inquiry
Use the Expenditure Items window to review a project's expenditure items. Use the Find Expenditure Items
window to enter search criteria for expenditures and expenditure items . You can search expenditures based on
Various Attributes like Project ,Expenditure Type, Task ,Employee , Billability etc.
Navigate to the Find Project Expenditure Items or Find Expenditure Items window and enter project number

Click on the Item Details to select a window for reviewing the details of this expenditure item. The Inquiry
Options window will be displayed, from which you can choose one of the following options:
Choose Cost Distribution Lines to view individual transactions and the debit and credit GL
accounts charged for raw and burdened costs for each expenditure item. You can also view other
information about the cost lines, such as PA and GL period and interface status and the rejection
reason if transactions could not be interfaced.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Choose Revenue Distribution Lines to view the revenue transactions generated for a specific
expenditure item. The GL account credited for the revenue is displayed. You can also see the GL and
PA posting period for the revenue and the interface status. The rejection reason will be displayed for
any transactions that are rejected during the interface to GL.
Choose AP Invoice to drill down to the Invoice Overview form in Oracle Payables. (This option is
only enabled for expenditure items whose expenditure type class is either Supplier Invoices or
Expense Reports.)

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Project Status Inquiry


Oracle Projects provides a default configuration for the displayed columns in Project Status Inquiry (also known
as PSI). With Project Status Inquiry (PSI), you can review the current status of your projects and then drill down
to commitments, actuals, and events detail for tasks and resources for more detailed review of a project and its
tasks.
Run the Update Project Summary Amounts process for your projects. The Project Status window uses the data
that is summarized by this process.

Project and Task PSI Columns


Column
Column Description
Prompt
Project or
Project Number or Task Number
Task
Over Bgt

Over Budget: Displays an asterisk (*) if the ITD actual burdened cost is greater than 110% of
the ITD burdened cost budget amount; if not over budget, column is blank.

ITD - Rev Bgt

ITD (Inception-to date) revenue budget amount

ITD - Act Rev ITD actual revenue


ITD - Cost
Bgt

ITD current burdened cost budget amount

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

ITD - Act
Cost

ITD actual burdened cost

PTD - Cost
Bgt

PTD current burdened cost budget amount

PTD - Act
Cost

PTD actual burdened cost

ITD - Bgt Hrs

ITD current labor hours budget amount

ITD - Act Hrs

ITD actual labor hours

PTD - Bgt
Hrs

PTD current labor hours budget amount

Fin %
Complete

Financial percentage complete: ITD actual burdened cost / total current


burdened cost budget amount * 100

Hrs %
Complete

Hours percentage complete: ITD actual labor hours / (Total current budget
labor hours * 100)

Est. to
Complete

Estimate to Complete: Total current burdened cost budget amount - (ITD actual burdened cost
+ PTD commitment burdened cost)

1. Navigate to the Project Status window.


2. Enter the search criteria to find the project(s) you want to review.
3. Choose the Find button.
4. To view totals for the project rows returned based on your search criteria,
Choose Totals.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Oracle Projects displays only the projects with a current budget that is summarized or with summarized actuals
and commitments. This window displays the Current Period as the current reporting period by which Oracle
Projects calculates the values for projects. Amounts for all summarization brackets (periodtodate, prior period,
yeartodate, and inceptiontodate) are calculated as of the current reporting period.

To review actuals details for a task or resource:


1. Navigate to the Project Status window.
2. Find the project(s) you want in the Find Project Status window.
3. Choose the Actuals button from either the Task Status or Resource Status window.
By default, Project Status Inquiry displays expenditure items incurred in the last period that was summarized
for the project. To view expenditure items from prior periods in the Expenditure Items window, change the
default date range using the Find Expenditure Items window. You can set the start date to the earliest possible
date by choosing the Clear button.
To drill down to the Oracle Payables Invoice Overview window:
1. Navigate to the Project Status window.
2. Find the project(s) you want in the Find Project Status window.
3. Choose the Actuals button from the Task Status window. Use the Find Expenditure Items window
to reduce the number of expenditure items that appear in the Expenditure Item Details window.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

4. Choose the AP Invoice button to view the related invoice in the Oracle Payables Invoice Overview
form.
The AP Invoice button is only enabled (1) for expenditure items whose expenditure type class is either Supplier
Invoices or
Expense Reports and (2 if function security is implemented in such a way that the user is able to see the button.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Adjusting Expenditures
Oracle Projects provides powerful features that allow you to:
adjust expenditure items on your projects
interface the adjustments to other Oracle applications
report the audit trail of the adjustments
We can make adjustments to expenditure items after the items have been costed, revenue distributed, and
invoiced. Oracle Projects automatically processes the adjusted items and interfaces the adjusting accounting
transactions to other Oracle Applications.
You can correct the following attributes of an approved expenditure item using the Pre-Approved Expenditure
Entry windows:
Date
Expenditure type
Project
Task
Amount
Other attributes which can be adjusted
Billable Status
Recalculate Raw Cost
Recalculate Cost and Revenue
Change Work Type
Split Item
Transfer Item
You make the corrections by reversing the original item and then creating a new item using the correct
information. You cannot correct these items using the Expenditure Items window.
You cannot correct the amount, date, expenditure type, or supplier of supplier invoice items in Oracle Projects.
You must correct these attributes of supplier invoice item in Oracle Payables.
Preapproved Batch -Adjustment
After you submit a batch, you can add, delete, and revise expenditures and expenditure items. You also must
correct a batch if your supervisor rejects and returns a submitted batch to you. If the batch has a status of
Submitted, locate the batch, return its status to Working, and change the expenditure or expenditure item before
resubmitting the batch.
If the batch has a status of Released, correct the individual expenditure items by reversing the full amount of the
original item and then entering the correct information. For example, if you entered six hours on a timecard
expenditure item when the correct number of hours is four, create a reversing item equal to a negative six hours,
then add a new expenditure item of four hours. To enter the corrected items, create a new batch and then follow
the normal steps for submitting and releasing expenditures.
Preapproved Batch Adjustment can be done at two levels:

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Batch Level
Line Level

Adjusting at Batch Level


To correct a released expenditure item:
Create a new batch for the correction items. The Expenditure Ending date must identify the week that includes
the expenditure item you are reversing.
Actual Expenditure Batch

To reverse the entire batch click on the Reverse Button of the Actual Batch. This reverses the Entire batch

PA - Oracle Applications Project Billing Training Document

This creates a new batch reversing all the expenditure lines

Submit and Release the Reversed Batch.


Adjusting at Batch Line Level
To reverse specific lines in the Batch.
Create a new batch and Click on Expenditures Button

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Click on the Reverse Original Button to search for the expenditure batch lines relating to that resource

Select the required lines to be reversed and Click on Reverse Button.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Submit and Release the Expenditure Batch


Use the adjustment actions Billable to NonBillable and NonBillable to Billable to change the billable status of
an expenditure item.
A billable item accrues workbased revenue and can be invoiced.
A nonbillable item does not accrue workbased revenue and is not invoiced. You may want to
check the setup of the billable status of your project to reduce the number of items you need to adjust
for billable classification.
Navigate to the Expenditure Inquiry Screen.
Query for the project on which the expenditure adjustment need to be made
Select the expenditure line and navigate to Tools > Non Billable

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Billing Hold
You can place an expenditure item on billing hold. An item on billing hold is not included on an invoice until
you release the billing hold on the item.
OneTime Hold
You can place an expenditure item on onetime billing hold. An item on onetime billing hold is not billed on
the current invoice but is eligible for billing on the next invoice. The onetime billing hold is released when you
release the current invoice.
Split
You can split an item into two items so that you can process the two resulting split items differently.
For example, you may have an item for 10 hours, of which you want 6 hours to be billable and 4 hours to be
nonbillable. You would split the item of 10 hours into two items of 6 hours and 4 hours, marking the 6 hours as
billable and 4 hours as nonbillable. The resulting split items are charged to the same project and task as the
Original item.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

N Expenditures Expenditures Inquiry Enter Project number

Transfer
You can transfer an item from one project and task to another project and task. Oracle Projects provides security
as to which employees can transfer items between projects.

PA - Oracle Applications Project Billing Training Document

Expenditure is transferred to new project

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Adjusting the Supplier Invoices


Invoice before adjustment

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Making an adjustment on the project by Transferring the Cost from one project to other

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Process the adjustment by running the PRC: Distribute Supplier Invoice Adjustment Costs process
Cost is transferred to new project

Please Note: The Adjusted Entries will only be visible in Expenditure Inquiry Screen in Projects. However, in
Payables in the Invoice Batches it will still show the original Entry being charged to Original Project Only.
If there is any adjustments that needs to be done to the Payables Invoice in Payables, then a new line item will
need to be created with the negative amount which is being charged to the original Project and a new Line Item
will need to be created with the Positive Amount which is being charged to the New Project in Payables.
Then, the adjusted Line items need to be interfaced to Projects in order for the same to reflect in Projects.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Revenue and Invoice Generation


Oracle Projects generates revenue based on the transactions that you charge to your projects. When you generate
revenue, Oracle Projects calculates revenue and expenditure item revenue, determines GL account codings, and
maintains funding balances. You can generate revenue for a range of projects or for a single project.
Distribution Rules defined on the project determine how and when you can generate revenue
For projects that use as-work-occurs revenue accrual, the total potential revenue is simply the sum of the
revenue of all expenditure items plus events. For Milestone based projects where the revenue needs to be
accrued on a fixed date the potential revenue would be the amount raised using a Project Event.
Project Events
Event in Projects are a summary level transaction assigned to a project or top task that records work completed
and generates revenue and/or billing activity, but is not directly related to any expenditure items. For example,
unlike labor costs or other billable expenses, a bonus your business receives for completing a project ahead of
schedule is not attributable to any expenditure item, and would be entered as an event. We Use the Event
Details window to enter and review events for a project or top task. Examples of events include an invoice
reduction, a performance bonus, revenue write-off, or adjusting revenue.
N Billing Events Projects

Using Event Details window we can enter, or review all of the information for a single event on one screen.
1. Enter the details of the project, task, and event.
2. Enter number of the event.
3. Select the event type.
4. Enter the organization of the event. Default value would Project Organization.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

5. Enter a description for the event. In the currency field. Click on the Currency button
To review or override the currency conversion attributes defined for the project
6. Revenue amount in project functional currency or the project currency that is calculated during
the revenue generation process
7. Bill amount in project functional currency and the project currency that is calculated during the
invoice generation process
Generate Revenue
To generate revenue for a single project Submit the PRC: Generate Draft Revenue for a Single Project process
from the Submit Request window
Navigate to Submit Request window.
N Others Requests Run

A Parameters window automatically appears if you select a request that requires


parameter values.
Select the project number for which the revenue need to be generated
Accrue Through Date: Enter the period for which you need the revenue to be accrued.
Select the Submit button

Review and Release Revenue


Using the Revenue Review window to review detailed information about project revenue.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

N Billing Revenue Review


Enter the project name or the project number and click on find

Click on the Lines to view the expenditure item wise revenue lines.
The Revenue Lines window displays the task, revenue source, revenue category, and amount for the revenue
lines that comprise a draft revenue item.
Select Release Button.
Submit PRC: One-Step Interface Streamline Processes to GL to transfer the Revenue lines to General Ledger
module.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

The Revenue Status will change to Accepted.


Generate Invoice
When you generate invoices, Oracle Projects calculates bill amounts, creates formatted invoices for printing and
posting, and maintains funding balances.
Submit PRC: Generate Draft Invoice process to generate project Invoice. When you generate an
Invoice, Oracle Projects first selects projects, tasks, and their associated events and
Expenditure items those are eligible for billing. You need to specify an Invoice Date as well as a Bill through
Date as process parameters. The Bill through Date is the date through which you want system to process all
eligible expenditure items and events.
The Invoice Date parameter is used as the AR Invoice Date for all the invoices generated. You can override the
AR Invoice Date when you manually release an invoice.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Approve and Release Invoice


After you review invoices and make any necessary adjustments, you need to approve them before you can
release them for interfacing to Oracle Receivables.
N Billing Invoice Review
Enter the project number or project name

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Select Approve Button

Select the Release Button .Optionally you can change the Invoice Date in the release invoice window.

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Submit PRC: Interface Invoices to Receivables to transfer the invoice lines to receivables module.
When you interface invoices to Oracle Receivables, system collects all eligible released draft invoices in Oracle
Projects and interfaces them to Oracle Receivables interface tables. This process also maintains project balances
of unbilled receivables and unearned revenue and creates accounting transactions for these amounts.
After you run the Auto Invoice program to create invoices in Oracle Receivables, you tieback successfully
interfaced invoices as well as rejected invoices using PRC: Tieback Invoices from Receivables.

PA - Oracle Applications Project Billing Training Document

Review the Invoice in the Receivables Module.


Source of these invoices would be PROJECTS INVOICES

Raju Chinthapatla

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Accounting Entries
Oracle Projects runs AutoAccounting to determine the appropriate general ledger accounts. AutoAccounting
selects all of the AutoAccounting parameters for each item or event, determines the account coding, validates
the account coding against the general ledger, and updates each revenue and invoice distribution line with
The appropriate account.
Accrue prior to billing
Revenue transaction entry prior to billing: Unbilled Receivables To Revenue
Invoice transaction entry prior to billing: Receivables To Unbilled Receivables
Invoice prior to accrual
Invoice transaction entry prior to accrual: Receivables To Unearned Revenue
Revenue transaction entry prior to accrual: Unearned Revenue To Revenue
Expenditure Entry
Labor Cost Transaction : Labor Expense To Payroll Clearing
Supplier Expense Transaction : Expense To Payables Liability

PA - Oracle Applications Project Billing Training Document

Raju Chinthapatla

Reports
Oracle Projects gives various standard reports to provide a detailed view of the cost, revenue, and invoice
activities of your projects. Use them to review your project expenditures, revenues, invoices, and expenditure
item adjustments.
MGT: Revenue, Cost, Budgets by Resources (Project Level): report to review project revenue and costs broken
down by resources for a particular PA Period and for the project-to-date. This report also displays budgeted
revenue and cost amounts broken down into the same resources, but only under the project-to-date column
since budgets are independent of PA Periods.
MGT: Transfer Activity report to review the expenditure item transfers into and out of a particular project. You
can use this report as an audit tool to control project costs by identifying incorrect or unauthorized transfers for a
project. You can also use this report to verify any expenditure item transfers that you perform.
AUD: Cost Audit Report to review labor and usage cost distribution lines interfaced from Oracle Projects to
Oracle General Ledger. This report displays items by the expense account number. Information about the item
and the liability account are also displayed.
AUD: Revenue Audit Report to review a listing of the revenue distribution lines interfaced from Oracle Projects
to Oracle General Ledger.
PRC: Distribute Labor Costs The process computes the labor costs for timecard hours and determines the
default GL account to which to post the cost. The process also identifies if a transaction is cross-charged and
determines the processing it may need. This process is a required prerequisite for the generation of revenue and
invoices for timecard items.
PRC: Distribute Expense Report This process computes the burden costs associated with expense report
expenditure items and determines the account to which to post the raw costs. The process also identifies if a
transaction is cross-charged and determines the processing it needs. This process is a prerequisite for the
generation of revenue and invoices for expense report expenditure items
PRC: Distribute Usage and Miscellaneous Costs the process computes the costs and determines the default GL
account to which to post the cost for expenditure items with the following expenditure type classes: Usages,
Burden Transactions, Miscellaneous Transactions & Inventory and WIP transactions not already costed or
accounted
The process also identifies if a transaction is cross-charged and determines the processing it may need. The
Distribute Usage and Miscellaneous Costs process is a prerequisite for the generation of revenue and invoices
for assets usage expenditure items and miscellaneous transactions.