Você está na página 1de 221

ABOUT ESTIMATE

Name of the wor Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi
Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in
Kakinada Town limits at Railway Km 14.05 of Kakinada Town Kakinada Port
Section in E.G.Dist.
Section
Asst. Executive Engineer (R&B),
(R&B) East Section : Kakinada

Sub - Division

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Division

Executive Engineer (R&B),


(R&B) Division : Kakinada

Circle

Superintending Engineer (R&B),


(R&B) Circle : Kakinada

ROADS & BUILDINGS DEPARTMENT


Name of work : Construction of Road Over Bridge at
Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214
Junction at Manasarovar Hotel to
Dairy Form Centre in Kakinada Town
limits at Railway Km 14.05 of
Kakinada Town Kakinada Port
Section in E.G.Dist.

Technical sanction

Rs. 2,150.00 Lakhs

(T.S. Memo No.E-in-C (NH&A) 28 / 2008-09, dt.15.11.2008)

Sub-estimate : Service Roads, Drains.


Original Estimate Amount : Rs.233.00 Lakhs
Deviation proposals : Rs.330.00 Lakhs

(R&B) East Section : Kakinada


(R&B) East Sub-divn., : Kakinada
(R&B) Division : Kakinada
(R&B) Circle : Kakinada
EAST GODAVARI DISTRICT

Specification report accompany the deviations for the work of


Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy Form
Centre in Kakinada Town limits at Railway Km 14.05 of Kakinada Town
Kakinada Port Section in E.G.Dist.
Sub-estimate : Service Roads, Drains.
Original Estimate Amount : Rs.233.00 Lakhs
Deviation proposals : Rs.330.00 Lakhs
The the work Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada
Town limits at Railway Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist was
sanctioned for Rs.2,150.00 Lakhs vide Engineer-in-Chief (R&B), N.H. & Admn., A.P., Hyderabad
T.S. memo No. 28 / 2008-2009, dt.15.11.2008. The work was entrusted to M/S I.V.R.C.L.
Infrastructures & Projects Ltd., Hyderabad, vide Agrt. C.R. No.97 / 2008-09, dt.02.03.2009 at a
tender premium of 2.27% excess over Estimate Contract Value.

The Foundation, Sub-structure and Abutment work work completed on Port side
approaches. The Super structure work is in progress and completed for 17 Nos. out of 18 Nos.
On Kakinada side all the foundations are completed and Sub-structure is in progress. The Super
structure work is in progress and completed 1 No. out of 15 Nos. Casting of Segmental blocks is
completed to take up the work on RE Wall portion. Part of the CC Drains work completed.

Rigid pavement with GSB 200mm + VCC (1:4:8) 100mm + VCC M.35 gr. 200mm is
proposed to restrict excavations near by ROB, in place of flexible pavement for service roads.
Dowel bars are proposed at Transverse joint with PVC caps on one side and Tie bars are proposed
on longitudinal joint. Provision for 300mm dia RCC Pipes is now made for crossing the utilities in
the C.C. Pavement area in the vented portion. A width of 0.50m left between Footpaths &
Service roads is proposed for providing interlocking tiles by providing sand bed. Certain items of
CC Drains are increased due to providing required sections at road crossings and other places
where the height of the drain wall is more. Chequrred Terrazo tiles are now proposed to provide
on top of footpath.

The deviation proposals are prepared by incorporating the above deviatioins for an
amount of Rs.330.00 Lakhs

RATES:
The estimate is prepared with 2008-2009 commom SSR for all Engineering
Department and datas as per MoRT&H standard data book duly adopting over head charges @
6% and contractors profit at 10% as per G.O.Ms No 141, T(R&B) Dept, dated 27.07.2006.
Provision for VAT is shown separately as PART "B" in the estimate as per G.O.Ms No 141, T(R&B)
Dept., Dt 27.07.2006 The work will carriedout as per relevant clauses of IRC & MORTH
specifications.

Asst. Executive Engineer (R&B), Dy. Executive Engineer (R&B),

Executive Engineer (R&B),

(R&B) East Section : Kakinada. (R&B) East Sub-divn., : Kakinada (R&B) Division : Kakinada

GENERAL ABSTRACT
Name of work :
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy
Form Centre in Kakinada Town limits at Railway Km 14.05 of Kakinada
Town Kakinada Port Section in E.G.Dist.
Sl.
No.
1

Sub-Estimate Description
2

Viaduct portion

II

Retainingwall portion

III

Approach Roads

IV

Service Roads, Drains.

Improvements to the existing road

VI
1)

L.S. Provisions
Land Acquisition & Acquisition of Structures

2)

Provision towards shifting of Utility lines such as


Electrical, Telephone, Water lines, etc.,

3)

Dismantling and clearing of debris

4)

Electrification of R.O.B.

5)

Provision for 2 Nos. of Staircases

6)

Improvements of Junctions

7)

Conversion of Viaduct in to Godowns & Landscaping

8)

Provision of Quality Control

9)

Provision for Road Safety Interventions

10)

P.S. and Contingencies

11)

Provision for Price escalation

12)

Provision for approximate cost of R.O.B. proper

say
(Rupees Twenty One Crores and Fifty Lakhs only)
The estimate is technically sanctioned for Rs.2150 lakhs (Rupees Twenty One
hundred and fifty lakhs only) against Administraive sanction for Rs.2150 lakhs
(Rupees Twenty One hundred and fifty lakhs only) accorded vide G.O. Ms.
No.354, T,R&B (R-II) Dept., dt.19.12.2007 and assigned T.S. Memo No.E-in-C (NH
& A) 28 / 2008-09. dt.15.11.2008.

The estimate is technically sanctioned for Rs.2150 lakhs (Rupees Twenty One
hundred and fifty lakhs only) against Administraive sanction for Rs.2150 lakhs
(Rupees Twenty One hundred and fifty lakhs only) accorded vide G.O. Ms.
No.354, T,R&B (R-II) Dept., dt.19.12.2007 and assigned T.S. Memo No.E-in-C (NH
& A) 28 / 2008-09. dt.15.11.2008.

ACT

kinada in lieu of L.C.No.11 on


at Manasarovar Hotel to Dairy
Railway Km 14.05 of Kakinada
.
Estimate Amount
3
Rs. 665.00 Lakhs
Rs. 138.00 Lakhs
Rs. 40.00 Lakhs
Rs. 330.00 Lakhs
Rs. 10.00 Lakhs
-----------------------------Rs. 1,183.00 Lakhs

Rs. 725.00 Lakhs


Rs. 40.00 Lakhs
Rs. 2.00 Lakhs
Rs. 15.00 Lakhs
Rs. 10.00 Lakhs
Rs. 5.00 Lakhs
Rs. 10.00 Lakhs
Rs. 15.00 Lakhs
Rs. 5.00 Lakhs
Rs. 5.00 Lakhs
Rs. 32.00 Lakhs
Rs. 200.00 Lakhs
-----------------------------Rs. 2,247.00 Lakhs
Rs. 22.470 Crores
------------------------------

2150 lakhs (Rupees Twenty One


traive sanction for Rs.2150 lakhs
only) accorded vide G.O. Ms.
d assigned T.S. Memo No.E-in-C (NH

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Viaduct portion
ABSTRACT ESTIMATE
Sl.
No.
1

Description

Quantity

Rate / per

Amount

1 Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per MoRT&H specification
304(4th Revision) and as directed by the Engineer-in-Charge
a) Excluding Dewatering charges

1,600.00
Cum.

52.00
/ 1 Cum.

83,200

b) Including Dewatering charges

1,760.00
Cum.

54.00
/ 1 Cum.

95,040

2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (4th Revision) and as directed by the Engineer-inCharge as Levelling course under Footings.
160.00
Cum.

3,900.00
/ 1 Cum.

6,24,000

3 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(4th Revision) for Abutment footings.
93.00
Cum.

4,540.00
/ 1 Cum.

4,22,220

4 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of
all
materials to site and all labour charges for machine mixing, laying in
position,Compacting, Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification
1500,1700, 2200 (4th Revision) for Abutment Sub structure .
118.00
Cum.

4,810.00
/ 1 Cum.

5,67,580

5 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for Pier foundation.

971.00
Cum.

5,520.00
/ 1 Cum.

53,59,920

6 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for Pier Sub-structure, Pier Cap,
Bedblocks and Backing walls.

For Pier Substructure

580.00
Cum.

5,850.00
/ 1 Cum.

33,93,000

For Pier Cap

191.00
Cum.

5,850.00
/ 1 Cum.

11,17,350

Bedblocks & Backing walls over Abutments

16.00
Cum.

5,850.00
/ 1 Cum.

93,600

7 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per drawing BD/1-69 (A) but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for Bearing Pedestals.

For Bearing Pedestals

16.00
Cum.

5,440.00
/ 1 Cum.

87,040

8 Supplying, fitting and fixing in position true to line and level elestomeric bearing /
neopran bearing conforming to IRC 83 (Part-II) Section IX and clause 2005 of
MORT&H Specifications complete including all accessaries as per drawing and
technical specification.
For Bearings

192.00
Nos.

,5,870.00
/ 1 Cum.

11,27,040

9 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P etc., complete as per
approved drawings and as directed during execution but excluding cost of steel and its
fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 &
2200 (4th revision ) and as directed by the Engineer-in-Charge for T-beam slab
Superstructure.
T Beam girder slab
Kerbs under footpaths and approaches,
Footpath slabs, Kerb base, etc.,

1,710.00
Cum.

6,880.00
/ 1 Cum.

1,17,64,800

230.00
Cum.

5,850.00
/ 1 Cum.

13,45,500

10 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per drawing BD/1-69 (A) but excluding cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for wearing coat over Deck slab.

240.00
Cum.

5,380.00
/ 1 Cum.

12,91,200

11 Construction of precast VRCC railing of M30 grade using HBG crushed stone
aggregate of size not exceeding 12 mm and fine aggregate conforming to table 1000-2
true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to
centre spacing between vertical posts not to exceed 2000mm, leaving adequate space
between vertical posts for expansion including cost, seigniorage conveyance of all
materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P as per
approved drawings and as directed during execution but excluding cost of steel and its
fabrication charges as per approved drawings and technical specifications for finished
item of work as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)

1,440.00
RM

1,010.00
/ 1 RM

14,54,400

12 Vibrated reinforced cement concrete M.30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per Approved drawing but including cost of steel and its
fabrication charges as per MoRT&H specification 1500, 1600,1700, & 2704 (4th
Revision) and as directed by the Engineer-in-Charge for Approach slab.
18.00
Cum.

8,760.00
/ 1 Cum.

1,57,680

13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for foundations
of R.C.C items.
49.00
M.T.

65,410.00
/ 1 MT

32,05,090

14 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub
structure of R.C.C items.
For Sub-structure :

79.00
M.T.

65,510.00
/ 1 MT

51,75,290

15 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Super
structure of R.C.C items.
For Super-structure

301.00
M.T.

66,320.00
/ 1 MT

1,99,62,320

16 Providing anti corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy
Coating (FBEC) not less than 175 microns thickness and upto 300 microns to
reinforcement of all diameters as per IS 13620-1993 including testing of coating at
plant. The rate is inclusive of cost on account of careful handling, PVC coated binding
wire instead of GI binding wire, touch up material supplied by coating agency, repair
work, transportation from the source of supply of steel to the plant and transportation
of coated steel from the plant to site of work, loading, unloading and traightening of
bent rods etc., complete as per MoRT&H specification No.1600 and as directed by the
Engineer-in-charge.
For Super-structure

429.00
MT

11,080.00
/ 1 MT

47,53,320

17 Providing weep holes in VCC Abutments, Return walls and wing walls with 100mm
Diameter AC pipe extending through the full width of the structure at 1.00m C/C in both
horizontal and vertical direction so that the weep holes in each horizontal direction is
staggered from the weep holes laying above and below lines as shown in drawing
including cost and conveyance of the A.C pipes and labour charges for cutting to
required length, placing the pipe with a slope of about 1V : 20H towards stream side
face etc., complete for finished item of work for weep holes as per MoRT&H
specification 2706 & 2200 (4th Revision)
50.00
RM

78.00
/ 1 RM

3,900

18 Supplying & fixing drainage spouts at site made of 210mm x 210mm water sput at top
with 100mm dia GI Drain spout and MS Plate of 12mm x 40mm x 6mm thick plates
including cost & conveyance of all materials to site and all labour charges for cutting
bending & welding, placing in position, etc., complete for deck slab as per Drawing
No.BD / 1-69 & as directed by the Engineer-in-charge.
132.00
Nos.

779.00
/ 1 No

102,828

19 Providing and laying of a strip seal type expansion joint catering to maximum horizontal
movement upto 70 mm, complete as per approved drawings and standard
specifications to be installed by the manufacturer / supplier or their authorised
representative ensuring compliance to the manufacturer's instructions for installation.
263.00
RM

4,500.00
/ 1 RM

11,83,500

20 Providing and laying of filter media with granular materials / stone crushed aggregate
satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to
athickness of not less than 600mm with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface behind the abutment, wing wall
and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal seignorage charges ,and all labour charges as directed by
the departmental officers as per drawing and Technical specifications as per clause
710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4th Revision) for finished item of work.

50.00
Cum.

1,480.00
/ 1 Cum.

74,000
---------------6,34,43,818

21 Providing G.I. Pipes for drainage.

L.S.

3,00,000

22 Providing paints to viaduct portion

L.S.

2,00,000

23 Provision for Soil Testing & Bores, etc.,

L.S.

3,00,000

24 Provision for VAT @ 2.8%

17,76,427

25 Provision for variation in G.L.s, unforseen items & rounding off.

L.S.

4,79,755
---------------6,65,00,000

(Rupees Six Crores and Sixty Five Lakhs only)

Asst. Executive Engineer (R&B),

Dy. Executive Engineer (R&B),

Executive Engineer (R&B),

2
(R&B) East Section : Kakinada

3
(R&B) East Sub-divn., : Kakinada

4
5
(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Reinforced earth walls
ABSTRACT ESTIMATE
Sl.
No.
1

Description

Quantity

Rate / per

Amount
5

1 Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per MoRT&H specification
304(4th Revision) and as directed by the Engineer-in-Charge

500.00
Cum.

46.00
/ 1 Cum.

23,000

2 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(4th Revision) for foundation leveling pad below the facing panel

100.00
Cum.

3,830.00
/ 1 Cum.

3,83,000

3 Construction of Reinforced Soil Wall which includes designing, providing constructin


drawing, supply and erection of segmental blocks of minimum Grade M35, minimum
thickness 300mm including approved soil reinformecment consisting of punched and
oriented HDPE Geogrid or High adherence metallic strips galvanized to 1000 g/m of
minimum dimension 40mm x 5mm with all accessories complete, as per the design and
drawings and technical specifications of the approved specialist firms technical experts
doing the work and as per the instruction of the Engineer-in-Charge.

1,840.00
Sqm.

4,200.00
/ 1 Sqm.

77,28,000

4 Supply and placement of approved quanlity fill material, compaction 95% Procter
Density of fill material as per Specification in requisite layers including cost ,conveyance
and seigniorage of all materials to site etc., complete as per Drawing and technical
specifications for finished item of work and as directed by the Engineer-in-charge of the
work.
6,120.00
Cum.

633.00
/ 1 Cum.

38,73,960

5 Providing well graded drainage fill, drain pipes wrapped with geotextile, cost of hire and
labour for plant / machineries, dressing, leveling of slope etc., including engineering
supervision all complete as per specification and approved drawing as directed by
Engineer-in-Charge.
770.00
Cum.

1,620.00
/ 1 Cum.

12,47,400
---------------1,32,55,360

6 Providing drainage collection pipes wrapped with Geotextile.

L.S.

2,00,000

7 Providing paints to Retaining wall & Dividers, etc.,

L.S.

1,00,000

8 Provision for VAT @ 1.4%

1,85,575

9 Provision for unforseen items & rounding off.

L.S.

59,065
---------------1,38,00,000

(Rupees One Crore and Thirty Eight Lakhs only)

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Approach Roads
ABSTRACT ESTIMATE
Sl.
No.
1

Description

Quantity

Rate / per

Amount

1 Construction of Granular sub-base by providing HBG material confirming to Grading III of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
means, on prepared surface mixing by mix in place method with Rotavator / approved
means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4th revision)
and as directed by the Engineer-in-charge. ( Payment will be made based on levels for
finished item of work ).
640.00
Cum.

1,450.00
/ 1 Cum.

9,28,000

2 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to
Wet Mix macadem specification including cost,seignorage of all materials and including
premixing the material with water at OMC in Mechanical mix plant carriage of mixed
material by tipper to site , laying in uniform layers with paver in base courses on well
prepared surface and compacting with Vibratory roller to acheive the desired density
etc., as directed by the Engineer-in-Charge and as per MoRT&H specification.406 (4th
revision) for finished item of work. (Payment based on levels for finished item of work)

480.00
Cum.

1,880.00
/ 1 Cum.

9,02,400

3 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG
machine crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of
80/100 grade @ 0.75 kg / sqm including cost, seigniorage and conveyance of all
materials to work site and laid on prepared surface and rolling with 8-10 T Power Road
Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4th
Revision) and as directed by the Engineer-in-charge.

2,280.00
Sqm.

46.70
/ 1 Sqm.

106,476

4 Providing and applying tack coat with bitumen Emulsion (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification
503 (4th revision) and as directed by the Engineer-in-Charge.

6,770.00
Sqm.

10.10
/ 1 Sqm.

68,377

5 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing
an average output of 37.5 tonnes per hour using hard blasted granite crushed
aggregates of Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th
Revision) premixed with bituminous binder of 60/70 grade @ 3.3% by weight of total
mixture, transported to site, laid over a previously prepared surface with mechanical
paver finisher to the required grade, level and alignment and rolled as per Clauses
501.6 and 501.7 to achieve the desired compaction for finished item of work as directed
by the Engineer-in-Charge including hire and opeational charges all T&P and all
other contingent charges necessary including cost of seigniorage charges on all
materials etc., complete and as per MoRTH specification No. 504(4th Revision) .

170.00
Cum.

6,830.00
/ 1 Sqm.

11,61,100

6 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant


using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
grade @ 5% of mix and filler, transporting the hot mix to work site, laying with
mechanical paver finisher to the required grade, level and alignment, rolling with
smooth wheeled,vibratory and tandem rollers to achieve the desired compaction as per
MoRT&H Specification 508 (4th Revision) complete for finished item of work in all
respects as directed by Engineer-in-charge.(Payment will be made based on levels for
finished item of work)

85.00
Cum.

8,550.00
/ 1 Cum.

7,26,750

---------------38,93,103
7 Provision for VAT @ 1.4%

54,503

8 Provision for unforseen items & rounding off.

L.S.

52,394
---------------40,00,000

(Rupees Forty Lakhs only)

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Service Roads, Drains
ABSTRACT ESTIMATE
Sl.
No.
1

Description

Quantity

Rate / per

Amount

1 Earthwork excavation and removal of unserviceable soils upto SDR by mechanical


means including trimming bottom and side slopes in accordance with requirements of
lines, grades and cross sections etc., and loading and disposal upto 1000 mts etc.,
complete including seignioarge charges for finished item of work as per MoRT&H
specification 301(4th Revision) and as directed by the Engineer-in-Charge
3,670.00
Cum.

70.20
/ 1 Cum.

257,634

2 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and


disposal of scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th
Revision) Specn. No.305.4.3
1,580.00
Sqm.

5.50
/ 1 Sqm.

8,690

3 Construction of Granular sub-base by providing HBG material confirming to Grading III of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
means, on prepared surface mixing by mix in place method with Rotavator / approved
means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4th revision)
and as directed by the Engineer-in-charge. ( Payment will be made based on levels for
finished item of work ).
2,331.00
Cum.

1,450.00
/ 1 Cum.

3,379,950

4 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (4th Revision) and as directed by the Engineer-inCharge for base coarse below CC Pavement.
1,290.00
Cum.

3,060.00
/ 1 Cum.

5 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for
finished item of work as per MoRT&H specification 1500, 1700, 2100 & 2702 (4th
Revision) and as directed by the Engineer-in-Charge for C.C Pavement.

3,947,400

3
2,524.00
Cum.

4
4,920.00
/ 1 Cum.

5
12,418,080

6 Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put
up bars of all diameters including cost and conveyance of steel to site and all labour
charges for fabrication of reinforcement including cutting, bending, binding rods, tying
grills, placing them in position etc., complete including cost and conveyance of binding
wire and all handling charges and operational charges etc., and including over lapping
welding if required etc., complete for all R.C.C items for finished item of work as per
standard drawings, as per the directions of the Engineer-in-Charge and as per
MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985.
23.00
M.T.

56,780.00
/ 1 MT

1,305,940

7 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub
structure of R.C.C items.
2.00
MT

57,390.00
/ 1 MT

114,780

8 Providing, laying Reinforced cement concrete Hume pipes of 300mm Dia., NP-3 class
for pipe culverts including cost and conveyance of Pipes etc., complete and Labour
charges for laying, jointing of 300mm dia. R.C.C Hume pipes in position including
lifting, aligning, lowering and hoisting etc., as per drawing and as per MoRT&H
Specification 2900, 2905 and 2906 (4th Revision) and IRC Special Publication No: 13
and as directed by the Engineer-in-Charge for finished item of work.

250.00
RM

940.00
/ 1 RM

235,000

9 Sand filling in foundation including cost, seignoirage and conveyence of all materials to
site and watering, tamping etc., complete for finshed item of work as per MoRT&H
specification 304 (4th Revision) and as directed by the Engineer - in - Charge.
116.00
Cum.

660.00
/ 1 Cum.

76,560

10 Cost and supply of Mastic pads 25.40mm thick including cost and conveyance of
mastic pads to the required soze amd fixing in position etc., complete as directed by the
Engineer-in-charge.
46.00
Sqm.

805.00
/ 1 Sqm.

37,030

11 Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical
specifications and as directed by the Engineer-in-charge.
2,362.00
RM

30.70
/ 1 RM

72,513

12 Providing Vaccum Dewatered Flooring Services including leveling the concrete to be


followed by placement of the bottom and top mats, operation of the Vaccum Machine to
release the excess free water in the Concrete, removal of the mat after completion of
dewatering process, conduction of the initial floating using power floater followed by
finishing using power trowel of adquate capacity. The rate is not inclusive of pin
vibration of the concrete, placement of the concrete and / or provision of the special
toppings, but including hire and operational charges of Generator of adequate capacity
and other T&P and labour charges for all operations etc. complete

12,395.00
Sqm.

40.00
/ 1 Sqm.

495,800

13 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric


powered saw of suitable capacity to give a finished groove of 4mm width and 1/4 to 1/3
depth in the cured concrete in the longitudinal and transverse directions along
predetermined lines. The rate is inclusive of the cost of consumables such as diamond
blade. Masons engaged for the marking is also deemed to be included in the rate and
pouring of Polysulphide Sealent to the full depth of groove. The rate is inclusive of the
cleaning of the groove after the sawing to remove cementatious particles adn cement
washings to give a clean dry surface and surface preparation of the sides of the groove
to accommodate the sealent material etc., to give a neat finished look including cost of
sealent, hire and operational charges of Generator of Adequate capacity and other T&P
and labour charges for all operations etc. complete.

4,565.00
RM

60.00
/ 1 RM

273,900

14 Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction
of shoring and bracing, removal of stumps and other deleterious matter, dressing sides
of bottom, back filling the excavation earth to the extent required etc., complete
including seignioarge charges for finished item of work as per MoRT&H specification
304(4th Revision) and as directed by the Engineer-in-Charge

1,660.00
Cum.

46.00
/ 1 Cum.

76,360

15 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2100 (4th Revision) and as directed by the Engineer-inCharge for Base course (Bed) of C.C. Drains
410.00
Cum.

3,410.00
/ 1 Cum.

1,398,100

16 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including all other incidental and operational
charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500,1700, 2200 (4th Revision) and as directed by the Engineer-inCharge for side walls of Drains.
860.00
Cum.

3,760.00
/ 1 Cum.

3,233,600

17 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials,


seigniorage charges, labour charges, curing etc complete for finished item of work as
directed by the Engineer -in-Charge
5,085.00
Sqm.

61.00
/ 1 Sqm.

310,185

18 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including other incidental hire and operational charges of all T&P as per approved
drawings and as directed during execution but excluding cost of steel and its
fabrication charges for finished item as per MoRT&H specification 1500,1600,1700 &
2200 (4th revision ) and as directed by the Engineer-in-Charge for Cover slabs over
side drains
424.00
Cum.

4,510.00
/ 1 Cum.

1,912,240

19 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position,
Compacting , Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100
(4th Revision) for Kerbs.
167.00
Cum.

3,980.00
/ 1 Cum.

664,660

20 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub
structure of R.C.C items.
27.50
MT

57,390.00
/ 1 MT

1,578,225

21 Providing Chequrred Terrazo tiles of 30 mm thick (medium shade) 0.305 M x 0.305 M


of approved brand and colour laid over drain slab covers set over CM(1:8) 12mm thick
base and neat grey cement slurry at the rate of 3.30 Kgs of cement per sqm and jointed
with heat white cement paste mixed with pigments of matching shade and including
cost,seigniorage charges and conveyance of all materials etc. from approved sources
to work site and all operational,incidental labour charges such as mixing mortar,laying
lift charges ,water curing etc;complete for finished item of work.

Rate as approved for deviation of Hand Rail

2,320.00
Sqm.

2,640.00
/ 10 Sqm

612,480
---------------32,409,127

22 Provision for VAT @ 1.4%

453,728

23 Provision for providing M.S. Grating over drains.

L.S.

100,000

24 Provision for unforseen items & rounding off.

L.S.

37,145
---------------33,000,000

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from NH
214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway Km
14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Viaduct portion
DETAILED ESTIMATE
Sl.
No.
1

Description

No.

L
4

Measurements
B
5

D
6

1 Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing sides of
bottom, back filling the excavation earth to the extent required etc., complete including
seignioarge charges for finished item of work as per MoRT&H specification 304(4th
Revision) and as directed by the Engineer-in-Charge
a) Above Sill level
For Abutments
For Piers foundation
(Kakinada side 15 spans) 14 Piers
(Port side 18 spans) 17 Piers
b) Below Sill level
For Abutments
For Piers foundation

1x2
1x31

11.25
9.20

4.90
5.20

1.00
1.00
or say

1x2
1x31

11.25
9.20

4.90
5.20

1.10
1.10
or say

2 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge as Levelling
course under Footings.
Levelling course under Footings
For Abutments
For Pier foundation

1x2
1x31

11.25
9.20

4.90
5.20

0.10
0.10
or say

3 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position, Compacting ,
Vibrating and curing including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4th Revision) for
Abutment footings.
Abutment Footing : 1st Footing
2nd Footing

1x2
1x2

11.05
11.05

4.70
3.70

0.50
0.50

6
or say

4 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing, laying in position,Compacting,
Vibrating and curing including all other incidental and all other operational charges of T&P
required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4th Revision) for
Abutment Sub structure .
Abutment Trapezoidal footing
Abutment Sub-structure
Kakinada side
Port side

1x2

11.05

(1.70+2.70)/2

1.00

1x1
1x1

11.05
11.05

(1.00+1.70)/2
(1.00+1.70)/2

2.342
2.307
or say

5 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished item of work
as per Approved drawing but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the
Engineer-in-Charge for Pier foundation.
For Pier Footing slab
Bottom beam

1x31
1x31

9.00
9.00

5.00
1.20

0.60
0.40
or say

6 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished item of work
as per Approved drawing but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the
Engineer-in-Charge for Pier Sub-structure, Pier Cap, Bedblocks and Backing walls.
Average height of Pier above Average G.L.
Kakinada side (15 Vents)
(6.453 + 2.424) M
Port side (18 Vents)
(6.585 + 2.367) M
Average height Pier above Footings
Kakinada side (15 Vents)
(7.453 to 3.424)
Port side (18 Vents)
(7.585 to 3.367)
Kakinada side (14 Colomns)
3x14
TT / 4 x (1.20)2
Port side (17 Colomns)
3x17
TT / 4 x (1.20)2

5.644 M
5.401 M
5.644
5.401
or say

Pier Top beam


(Trapezoidal)

1x31
2x31

7.20
0.90

1.20
1.20

0.60
(0.60+0.30)/2
or say

2
Bed blocks over Abutments
Backing walls
Deduct for approach slab

1x2
1x2
1x2

11.05
11.05
7.50

1.05
0.30
0.30

0.30
1.511
0.300
or say

7 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished item of work
as per drawing BD/1-69 (A) but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the
Engineer-in-Charge for Bearing Pedestals.
Kakinada side Over Piers
Over Abutments
Port side Over Piers
Over Abutments

6x1x14
3x1x1
6x1x17
3x1x1

0.93
0.93
0.93
0.93

0.52
0.52
0.52
0.52

0.185
0.15
0.157
0.15
or say

8 Supplying, fitting and fixing in position true to line and level elestomeric bearing / neopran
bearing conforming to IRC 83 (Part-II) Section IX and clause 2005 of MORT&H
Specifications complete including all accessaries as per drawing and technical
specification.
Kakinada side Over Piers
Over Abutments
Port side Over Piers
Over Abutments

6x1x14
3x1x1
6x1x17
3x1x1

-----

-----

-----

9 Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including
other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication
charges for finished item as per MoRT&H specification 1500,1600,1700 & 2200 (4th
revision ) and as directed by the Engineer-in-Charge for T-beam slab Superstructure.
Concrete / span
Concrete / RM
Kakinada side average length
Port side average length

1x1
1x1

@ 53.55
@ 53.55
180.274
235.800

Cum. / span
/ 13.07 =
x
x

Table 1 of MOST drg BD / 5-74A

4.10
4.10
4.10
or say

Kerbs under footpaths over approaches


(139.276+164.20) = 303.476=304 1x2
Road side
1x2
Deductions
1x4
Precast slabs
1x2
Kerb base
1x2

304.00
304.00
304.00
304.00
304.00

0.275
(0.275+0.20)/2
0.075
1.375
0.450

0.325
0.275
0.070
0.070
0.300
say

10 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished item of work
as per drawing BD/1-69 (A) but excluding cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the
Engineer-in-Charge for wearing coat over Deck slab.
180.274+235.800+4.0 x 2
= 424.074 M

1x1

424.074

7.500

0.075
say

11 Construction of precast VRCC railing of M30 grade using HBG crushed stone aggregate of
size not exceeding 12 mm and fine aggregate conforming to table 1000-2 true to line and
grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing
between vertical posts not to exceed 2000mm, leaving adequate space between vertical
posts for expansion including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other
incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges as per
approved drawings and technical specifications for finished item of work as per MoRT&H
Specification 2703, 1500, 1600, 1700(4th Revision)
(320 + 400) = 720 M

1x2

720.000

--

-say

12 Vibrated reinforced cement concrete M.30 grade using 20mm & 10mm HBG crushed
stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost, seigniorage conveyance of all materials to site
and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all
other incidental and operational charges of all T&P etc., complete for finished item of work
as per Approved drawing but including cost of steel and its fabrication charges as per
MoRT&H specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the
Engineer-in-Charge for Approach slab.
1x2

4.00

7.50

0.30

13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for foundations of
R.C.C items.
For Piers Footing

971.00
cum

50.00
kgs/cum

14 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub structure
of R.C.C items.
Substructure

( 580

+ 191.00 +
cum

16.000 )
cum

100.00
kgs/cum

15 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing
them in position etc., complete including cost and conveyance of binding wire and all
handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard
drawings, as per the directions of the Engineer-in-Charge and as per MoRT&H
specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Super structure
of R.C.C items.
Superstructure
Kgs / RM
Kakinada side average length
Port side average length

1x1
1x1

Wearing coat, kerbs, precast slabs, etc.


(240+54.34+58.52) = 352.86 Cum.

9042.00
9,042
180.274
235.800

kgs/span
/ 13.07 =
x
x

353.000
Cum.

35.00
Kgs. / Cum.

691.81
691.81
691.81

16 Providing anti corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy
Coating (FBEC) not less than 175 microns thickness and upto 300 microns to
reinforcement of all diameters as per IS 13620-1993 including testing of coating at plant.
The rate is inclusive of cost on account of careful handling, PVC coated binding wire
instead of GI binding wire, touch up material supplied by coating agency, repair work,
transportation from the source of supply of steel to the plant and transportation of coated
steel from the plant to site of work, loading, unloading and traightening of bent rods etc.,
complete as per MoRT&H specification No.1600 and as directed by the Engineer-incharge.
For Foundation
For Sub-structure
For Superstructure

17 Providing weep holes in VCC Abutments, Return walls and wing walls with 100mm
Diameter AC pipe extending through the full width of the structure at 1.00m C/C in both
horizontal and vertical direction so that the weep holes in each horizontal direction is
staggered from the weep holes laying above and below lines as shown in drawing including
cost and conveyance of the A.C pipes and labour charges for cutting to required length,
placing the pipe with a slope of about 1V : 20H towards stream side face etc., complete for
finished item of work for weep holes as per MoRT&H specification 2706 & 2200 (4th
Revision)
Kakinada side
Port side

2x10
2x10

1.00
1.00

---

---

18 Supplying & fixing drainage spouts at site made of 210mm x 210mm water sput at top with
100mm dia GI Drain spout and MS Plate of 12mm x 40mm x 6mm thick plates including
cost & conveyance of all materials to site and all labour charges for cutting bending &
welding, placing in position, etc., complete for deck slab as per Drawing No.BD / 1-69 & as
directed by the Engineer-in-charge.
Kakinada side (15 x 4)
Port side (18 x 4)

1x2
1x2

30
36

---

---

19 Providing and laying of a strip seal type expansion joint catering to maximum horizontal
movement upto 70 mm, complete as per approved drawings and standard specifications to
be installed by the manufacturer / supplier or their authorised representative ensuring
compliance to the manufacturer's instructions for installation.
Kakinada side (15 Spans)
Port side (18 Spans)

1x16
1x19

7.50
7.50

---

--or say

20 Providing and laying of filter media with granular materials / stone crushed aggregate
satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to
athickness of not less than 600mm with smaller size towards the soil and bigger size
towards the wall and provided over the entire surface behind the abutment, wing wall and
return wall to the full height compacted to a firm condition including cost and conveyance of
all metal seignorage charges ,and all labour charges as directed by the departmental
officers as per drawing and Technical specifications as per clause 710.1.1 of IRC:78 and
Clause 2200 of MoRT&H (4th Revision) for finished item of work.
Behind abutment

1x2

10.00

0.60

4.00
or say

21 Providing G.I. Pipes for drainage.


22 Providing paints to viaduct portion
23 Provision for Soil Testing & Bores, etc.,
24 Provision for unforseen items & rounding off.

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

e at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from NH


el to Dairy Form Centre in Kakinada Town limits at Railway Km
da Port Section in E.G.Dist.
DETAILED ESTIMATE
Quantity
7

110.25
1,483.04
1,593.29
1,600.00
Cum.
121.28
1,631.34
1,752.62
1,760.00
Cum.

11.03
148.30
159.33
160.00
Cum.

51.94
40.89
92.83

7
93.00
Cum.

48.62
34.94
34.41
117.97
118.00
Cum.

837.00
133.92
970.92
971.00
Cum.

268.20
311.65
579.85
580.00
Cum.
160.70
30.13
190.83
191.00
Cum.

7
6.96
10.02
-1.35
15.63
16.00
Cum.

7.52
0.22
7.74
0.22
15.70
16.00
Cum.

84
3
102
3
192
Nos.

739.12
966.78
1,705.90
1,710.00
Cum.

54.34
39.71
-6.38
58.52
82.08
228.27
230.00
Cum.

238.54
240.00
Cum.

1,440.000
1,440.00
RM

18.00
Cum.

48,550.00
49.000
MT

78,700.00
79.000
MT

124,715.36
163,128.80
12,355.00
300,199.16
301.000
MT

49.00
79.00
301.00
429.00
MT

20.00
20.00
40.00
50.00
RM

60
72
132
Nos.

120.00
142.50
262.50
263.000
RM

48.00
50.00
Cum.
L.S.
L.S.
L.S.
L.S.

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Reinforced earth walls
DETAILED ESTIMATE
Sl.
No.
1

Description

No.

L
4

Measurements
B
5

D
6

Quantity
7

1 Earthwork excavation in soils upto SDR by mechanical means for foundations of


structures as per drawing and technical specification including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing sides of
bottom, back filling the excavation earth to the extent required etc., complete including
seignioarge charges for finished item of work as per MoRT&H specification 304(4th
Revision) and as directed by the Engineer-in-Charge
Kakinada side
Port side

1x2
1x2

139.28
164.20

0.80
0.80

1.00
1.00
or say

222.85
262.72
485.57
500.00
Cum.

2 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size
HBG crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine
aggregate conforming to table 1000-2) including cost,seignorage and conveyance of all
materials to site and all labour charges for machine mixing,laying in position, Compacting
, Vibrating and curing including all other incidental and all other operational charges of
T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4th
Revision) for foundation leveling pad below the facing panel
Kakinada side
Port side

1x2
1x2

139.28
164.20

0.80
0.80

0.20
0.20
or say

44.57
52.54
97.11
100.00
Cum.

3 Construction of Reinforced Soil Wall which includes designing, providing constructin


drawing, supply and erection of segmental blocks of minimum Grade M35, minimum
thickness 300mm including approved soil reinformecment consisting of punched and
oriented HDPE Geogrid or High adherence metallic strips galvanized to 1000 g/m of
minimum dimension 40mm x 5mm with all accessories complete, as per the design and
drawings and technical specifications of the approved specialist firms technical experts
doing the work and as per the instruction of the Engineer-in-Charge.
Kakinada side
Port side

1x2
1x2

139.28
164.20

-----

1/2 x (5.044+1.217)
1/2 x (5.004+0.858)
or say

872.03
962.54
1,834.57
1,840.00
Sqm.

4 Supply and placement of approved quanlity fill material, compaction 95% Procter Density
of fill material as per Specification in requisite layers including cost ,conveyance and
seigniorage of all materials to site etc., complete as per Drawing and technical
specifications for finished item of work and as directed by the Engineer-in-charge of the
work.
Kakinada side
Port side
Delete for drainage fill

1x1
1x1
1x1

139.28
164.20
303.48

(11.05 - 0.30)
(11.05 - 0.30)
0.60 x 2

1/2x(4.244+0)
1/2x(4.204+0)
1/2x(4.244+0)
or say

3,177.19
3,710.35
-772.78
6,114.76
6,120.00
Cum.

5 Providing well graded drainage fill, drain pipes wrapped with geotextile, cost of hire and
labour for plant / machineries, dressing, leveling of slope etc., including engineering
supervision all complete as per specification and approved drawing as directed by
Engineer-in-Charge.
Kakinada side
Port side

1x2
1x2

139.28
164.20

0.60
0.60

1/2x(4.244+0)
1/2x(4.204+0)
say

354.66
414.18
768.84
770.00
Cum.

6 Providing drainage collection pipes wrapped with Geotextile.

L.S.

7 Providing paints to Retaining wall

L.S.

8 Provision for unforseen items & rounding off.

L.S.

Asst. Executive Engineer (R&B),


Dy. Executive Engineer (R&B),
(R&B) East Section : Kakinada (R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from
NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway
Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Approach Roads
DETAILED ESTIMATE
Sl.
No.
1

Description

No.

L
4

Measurements
B
5

D
6

Quantity
7

1 Construction of Granular sub-base by providing HBG material confirming to Grading - III


of MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all
materials to work site and spreading in uniform layers with motor grader or by approved
means, on prepared surface mixing by mix in place method with Rotavator / approved
means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4th revision) and
as directed by the Engineer-in-charge. ( Payment will be made based on levels for
finished item of work ).
Kakinada side
Port side
Under Footpath Kakinada side
Port Side

1x1
1x1
1x1
1x1

139.28
164.20
139.28
164.20

(11.05-0.30-0.6x2)
(11.05-0.30-0.6x2)
(1.525 - 0.60)
(1.525 - 0.60)

0.20
0.20
0.20
0.20
or say

266.02
313.62
25.77
30.38
635.79
640.00
Cum.

2 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to
Wet Mix macadem specification including cost,seignorage of all materials and including
premixing the material with water at OMC in Mechanical mix plant carriage of mixed
material by tipper to site , laying in uniform layers with paver in base courses on well
prepared surface and compacting with Vibratory roller to acheive the desired density etc.,
as directed by the Engineer-in-Charge and as per MoRT&H specification.406 (4th
revision) for finished item of work. (Payment based on levels for finished item of work)

Kakinada side
Port side

1x1
1x1

139.28
164.20

7.80
7.80

0.20
0.20
or say

217.28
256.15
473.43
480.00
Cum.

3 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG
machine crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of
80/100 grade @ 0.75 kg / sqm including cost, seigniorage and conveyance of all
materials to work site and laid on prepared surface and rolling with 8-10 T Power Road
Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4th
Revision) and as directed by the Engineer-in-charge.
Kakinada side
Port side

1x1
1x1

139.28
164.20

7.50
7.50

--or say

1,044.60
1,231.50
2,276.10
2,280.00
Sqm.

4 Providing and applying tack coat with bitumen Emulsion (Bulk) using Emulsion pressure
distributor at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface
cleaned with mechanical broom for finished item of work as per MoRT&H Specification
503 (4th revision) and as directed by the Engineer-in-Charge.
Before laying BM & SDBC
Kakinada side
Port side
For approach road
Kakinada side (370-320)
Port side (450-400)

1x2
1x2

139.28
164.20

7.50
7.50

---

2,089.20
2,463.00

1x2
1x2

50.00
50.00

11.05
11.05

---

1,105.00
1,105.00
6,762.20
6,770.00
Sqm.

or say
5 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an
average output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of
Grading - II as per table 500-4 of MoRT&H specificaion 504 (4th Revision) premixed
with bituminous binder of 60/70 grade @ 3.3% by weight of total mixture, transported to
site, laid over a previously prepared surface with mechanical paver finisher to the required
grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the
desired compaction for finished item of work as directed by the Engineer-in-Charge
including hire and opeational charges all T&P and all other contingent charges
necessary including cost of seigniorage charges on all materials etc., complete and as
per MoRTH specification No. 504(4th Revision) .

Kakinada side
Port side
For approach road
Kakinada side (370-320)
Port side (450-400)

1x1
1x1

139.28
164.20

7.50
7.50

0.050
0.050

52.23
61.58

1x1
1x1

50.00
50.00

11.05
11.05

0.050
0.050

27.63
27.63
169.07
170.00
Cum.

or say
6 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant
using hard blasted granite crushed aggregates of Grading -2 as per table 500-15 of
specification 508 of MoRT&H (4th Revision), premixed with bituminous binder 60/70
grade @ 5% of mix and filler, transporting the hot mix to work site, laying with mechanical
paver finisher to the required grade, level and alignment, rolling with smooth
wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoRT&H
Specification 508 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.(Payment will be made based on levels for finished item of
work)
Kakinada side
Port side
For approach road
Kakinada side (370-320)
Port side (450-400)

1x1
1x1

139.28
164.20

7.50
7.50

0.025
0.025

26.12
30.79

1x1
1x1

50.00
50.00

11.05
11.05

0.025
0.025

13.81
13.81
84.53
85.00
Cum.

or say
7 Provision for unforseen items & rounding off.

L.S.

2
Asst. Executive Engineer (R&B),
(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre
in Kakinada Town limits at Railway Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Service Roads, Drains
COMPARATIVE STATEMENT
Sl.
No.
1

Description
2

As per the Original Estimate


Quantity
Rate / per
Amount
3
4
5

As per the Deviation proposals


Quantity
Rate / per
Amount
6
7
8

More

Less

Remark

10

11

---

322,260

4,914

---

1 Forming embankment with borrowed useful earth from outside road boundary by mechanical
means upto SDR with all leads and lifts including pre-watering of soil at borrow area, removal of top
soil, excavation of soils at borrowed area, conveyance of soil, depositing the soil on the
embankment, spreading soil, breaking clods, sectioning, grading and consolidation with 8 to 10
Tonnes Vibratory Road Roller @ OMC to meet requirement of table 300-2 of MoRT&H, including
all hire and operational charges of T&P and seigniorage charges, complete for finished item of
work as per MoRT&H specification 305 (4th revision) (Payment will be made based on level for
finished item of work).
2,460.00
Cum.

131.00
/ 1 Cum.

322,260

0.00
Cum.

131.00
/ 1 Cum.

No formation is being
taken hence deleted.

2 Earthwork excavation and removal of unserviceable soils upto SDR by mechanical means including
trimming bottom and side slopes in accordance with requirements of lines, grades and cross
sections etc., and loading and disposal upto 1000 mts etc., complete including seignioarge
charges for finished item of work as per MoRT&H specification 301(4th Revision) and as directed
by the Engineer-in-Charge
3,600.00
Cum.

70.20
/ 1 Cum.

252,720

3,670.00
Cum.

70.20
/ 1 Cum.

257,634

3 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th Revision) Specn.
No.305.4.3
--

--

1,580.00
Sqm.

5.50
/ 1 Sqm.

8,690

8,690

---

As per actual
requirement.

Existing road upto the


Junction beyond the
landing point is now
proposed for
improvements.

10

4 Construction of Granular sub-base by providing


HBG material confirming to Grading - III of
MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all materials to work
site and spreading in uniform layers with motor grader or by approved means, on prepared surface
mixing by mix in place method with Rotavator / approved means at OMC and compacting with
vibratory roller to achieve the desired density etc., complete for finished item of work as per
MoRT&H Specification 401 (4th revision) and as directed by the Engineer-in-charge. ( Payment
will be made based on levels for finished item of work ).
2,400.00
Cum.

1,450.00
/ 1 Cum.

3,480,000

2,331.00
Cum.

1,450.00
/ 1 Cum.

11

In thie original estimate


provision was made for
a width of 7.30m. As
per actual site condition
the width is varying
from 4.70m to 7.20m
near RE Wall and from
6.20m to 7.20m near
Via-duct portion.

3,379,950

---

100,050

---

4,418,000

Savings due deletion of


flexible pavement.

---

536,116

-- do --

---

231,896

-- do --

5 Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix
macadem specification including cost,seignorage of all materials and including premixing the
material with water at OMC in Mechanical mix plant carriage of mixed material by tipper to site ,
laying in uniform layers with paver in base courses on well prepared surface and compacting with
Vibratory roller to acheive the desired density etc., as directed by the Engineer-in-Charge and as
per MoRT&H specification.406 (4th revision) for finished item of work. (Payment based on levels for
finished item of work)
2,350.00
Cum.

1,880.00
/ 1 Cum.

4,418,000

0.00
Cum.

1,880.00
/ 1 Cum.

6 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine
crushed stone aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @
0.75 kg / sqm including cost, seigniorage and conveyance of all materials to work site and laid on
prepared surface and rolling with 8-10 T Power Road Roller etc., complete for finished item of work
as per MoRT&H Specification 510 (4th Revision) and as directed by the Engineer-in-charge.

11,480.00
Sqm.

46.70
/ 1 Sqm.

536,116

0.00
Sqm.

46.70
/ 1 Sqm.

7 Providing and applying tack coat with bitumen Emulsion (Bulk) using Emulsion pressure distributor
at the rate of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with
mechanical broom for finished item of work as per MoRT&H Specification 503 (4th revision) and as
directed by the Engineer-in-Charge.
22,960.00
Sqm.

10.10
/ 1 Sqm.

231,896

0.00
Sqm.

10.10
/ 1 Sqm.

10

11

---

3,920,420

Savings due deletion of


flexible pavement.

---

2,453,850

-- do --

3,947,400

---

8 Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average
output of 37.5 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per
table 500-4 of MoRT&H specificaion 504 (4th Revision) premixed with bituminous binder of
60/70 grade @ 3.3% by weight of total mixture, transported to site, laid over a previously prepared
surface with mechanical paver finisher to the required grade, level and alignment and rolled as per
Clauses 501.6 and 501.7 to achieve the desired compaction for finished item of work as directed by
the Engineer-in-Charge including hire and opeational charges all T&P and all other contingent
charges necessary including cost of seigniorage charges on all materials etc., complete and as per
MoRTH specification No. 504(4th Revision) .
574.00
Cum.

6,830.00
/ 1 Sqm.

3,920,420

0.00
Cum.

6,830.00
/ 1 Sqm.

9 Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using hard
blasted granite crushed aggregates of Grading -2 as per table 500-15 of specification 508 of
MoRT&H (4th Revision), premixed with bituminous binder 60/70 grade @ 5% of mix and filler,
transporting the hot mix to work site, laying with mechanical paver finisher to the required grade,
level and alignment, rolling with smooth wheeled,vibratory and tandem rollers to achieve the
desired compaction as per MoRT&H Specification 508 (4th Revision) complete for finished item of
work in all respects as directed by Engineer-in-charge.(Payment will be made based on levels for
finished item of work)

287.00
Cum.

8,550.00
/ 1 Cum.

2,453,850

0.00
Cum.

8,550.00
/ 1 Cum.

10 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance
of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by the
Engineer-in-Charge for base coarse below CC Pavement.

--

--

1,290.00
Cum.

3,060.00
/ 1 Cum.

3,947,400

Proposed as Base
coarse below CC
Pavement.

10

11

11 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost, seigniorage conveyance of all materials to site and labour charges, centering,
machine mixing, laying, vibrating, curing etc., including all other incidental and operational charges
of all T&P etc., complete for finished item of work as per MoRT&H specification 1500, 1700,
2100 & 2702 (4th Revision) and as directed by the Engineer-in-Charge for C.C Pavement.

--

--

2,524.00
Cum.

4,920.00
/ 1 Cum.

12,418,080 12,418,080

---

Due to change of
provision to CC
Pavement in place of
Flexible pavement.

12 Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985.

--

--

23.00
M.T.

56,780.00
/ 1 MT

1,305,940

1,305,940

---

-- do --

114,780

---

-- do --

13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub
structure of R.C.C items.
--

--

2.00
MT

57,390.00
/ 1 MT

114,780

10

14 Providing, laying Reinforced cement concrete Hume pipes of 300mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for laying,
jointing of 300mm dia. R.C.C Hume pipes in position including lifting, aligning, lowering and
hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and 2906 (4th
Revision) and IRC Special Publication No: 13 and as directed by the Engineer-in-Charge for
finished item of work.
--

--

250.00
RM

940.00
/ 1 RM

235,000

235,000

---

15 Sand filling in foundation including cost, seignoirage and conveyence of all materials to site and
watering, tamping etc., complete for finshed item of work as per MoRT&H specification 304 (4th
Revision) and as directed by the Engineer - in - Charge.
--

--

116.00
Cum.

660.00
/ 1 Cum.

76,560

76,560

11

Provision is now made


for crossing the utilities
in the C.C. Pavement
area in the vented
portion.

---

The 0.50M width left


between Footpaths &
Service roads is
proposed for providing
interlocking tiles by
providing sand bed.

Due to change of
provision to CC
Pavement in place of
Flexible pavement.

16 Cost and supply of Mastic pads 25.40mm thick including cost and conveyance of mastic pads to
the required soze amd fixing in position etc., complete as directed by the Engineer-in-charge.
--

--

46.00
Sqm.

805.00
/ 1 Sqm.

37,030

37,030

---

72,513

72,513

---

-- do --

495,800

495,800

---

-- do --

17 Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical
specifications and as directed by the Engineer-in-charge.
--

--

2,362.00
RM

30.70
/ 1 RM

18 Providing Vaccum Dewatered Flooring Services including leveling the concrete to be followed by
placement of the bottom and top mats, operation of the Vaccum Machine to release the excess free
water in the Concrete, removal of the mat after completion of dewatering process, conduction of the
initial floating using power floater followed by finishing using power trowel of adquate capacity. The
rate is not inclusive of pin vibration of the concrete, placement of the concrete and / or provision of
the special toppings, but including hire and operational charges of Generator of adequate capacity
and other T&P and labour charges for all operations etc. complete

--

--

0 12,395.00
Sqm.

40.00
/ 1 Sqm.

10

11

19 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric powered saw of
suitable capacity to give a finished groove of 4mm width and 1/4 to 1/3 depth in the cured concrete
in the longitudinal and transverse directions along predetermined lines. The rate is inclusive of the
cost of consumables such as diamond blade. Masons engaged for the marking is also deemed to
be included in the rate and pouring of Polysulphide Sealent to the full depth of groove. The rate is
inclusive of the cleaning of the groove after the sawing to remove cementatious particles adn
cement washings to give a clean dry surface and surface preparation of the sides of the groove to
accommodate the sealent material etc., to give a neat finished look including cost of sealent, hire
and operational charges of Generator of Adequate capacity and other T&P and labour charges for
all operations etc. complete.

--

--

4,565.00
RM

60.00
/ 1 RM

Due to change of
provision to CC
Pavement in place of
Flexible pavement.

273,900

273,900

---

76,360

---

23,460

As per actual execution


and due to decrease in
width of drain.

1,398,100

---

170,500

As per actual execution


and due to decrease in
width of drain.

C.C. Drains
20 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per
drawing and technical specification including setting out, construction of shoring and bracing,
removal of stumps and other deleterious matter, dressing sides of bottom, back filling the
excavation earth to the extent required etc., complete including seignioarge charges for finished
item of work as per MoRT&H specification 304(4th Revision) and as directed by the Engineer-inCharge

2,170.00
Cum.

46.00
/ 1 Cum.

99,820

1,660.00
Cum.

46.00
/ 1 Cum.

21 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate
and fine aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance
of all materials to site and labour charges, centering, machine mixing, laying, Vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per MoRT&H specification 1500,1700, 2100 (4th Revision) and as directed by the
Engineer-in-Charge for Base course (Bed) of C.C. Drains

460.00
Cum.

3,410.00
/ 1 Cum.

1,568,600

410.00
Cum.

3,410.00
/ 1 Cum.

10

22 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone aggregate and
fine aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of
all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per MoRT&H specification 1500,1700, 2200 (4th Revision) and as directed by the
Engineer-in-Charge for side walls of Drains.
620.00
Cum.

3,760.00
/ 1 Cum.

2,331,200

860.00
Cum.

3,760.00
/ 1 Cum.

3,233,600

902,400

---

310,185

60,085

---

11

Due to providing
required sections at
road crossings and
other places where the
height of the drain wall
is more.

23 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials, seigniorage
charges, labour charges, curing etc complete for finished item of work as directed by the Engineer
-in-Charge
4,100.00
Sqm.

61.00
/ 1 Sqm.

250,100

5,085.00
Sqm.

61.00
/ 1 Sqm.

24 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table
1000-2) including cost, seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as directed during execution but
excluding cost of steel and its fabrication charges for finished item as per MoRT&H specification
1500,1600,1700 & 2200 (4th revision ) and as directed by the Engineer-in-Charge for Cover slabs
over side drains
360.00
Cum.

4,510.00
/ 1 Cum.

1,623,600

424.00
Cum.

4,510.00
/ 1 Cum.

1,912,240

288,640

---

-- do --

Due to providing
required thickness of
cover slabs for road
crossings and also due
to increase in width of
the cover slab.

25 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all materials to site and
all labour charges for machine mixing,laying in position, Compacting , Vibrating and curing including
all other incidental and all other operational charges of T&P required etc., complete as per
MoRT&H Specification 1500,1700, 2100 (4th Revision) for Kerbs.
140.00
Cum.

3,980.00
/ 1 Cum.

557,200

167.00
Cum.

3,980.00
/ 1 Cum.

664,660

107,460

---

Due to providing Kerbs


on both sides of the
Passage road in viaduct portion.

10

11

---

Due to providing
required thickness of
cover slabs for road
crossings and also
additional crank bars
provided in the cover
slabs of drains for extra
strength, since the ROB
is located near New
Port Railway Station
and Municipal
corporation Office, etc.,

---

Chequrred Terrazo tiles


are now proposed to
provide on top of
footpath.

26 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of
reinforcement including cutting, bending, binding rods, tying grills, placing them in position etc.,
complete including cost and conveyance of binding wire and all handling charges and operational
charges etc., and including over lapping welding if required etc., complete for all R.C.C items for
finished item of work as per standard drawings, as per the directions of the Engineer-in-Charge and
as per MoRT&H specification 1600 &2200 (4th revision) and as per I.S.1786 of 1985 for Sub
structure of R.C.C items.
15.00
MT

57,390.00
/ 1 MT

860,850

27.50
MT

57,390.00
/ 1 MT

1,578,225

717,375

27 Providing Chequrred Terrazo tiles of 30 mm thick (medium shade) 0.305 M x 0.305 M of approved
brand and colour laid over drain slab covers set over CM(1:8) 12mm thick base and neat grey
cement slurry at the rate of 3.30 Kgs of cement per sqm and jointed with heat white cement paste
mixed with pigments of matching shade and including cost,seigniorage charges and conveyance of
all materials etc. from approved sources to work site and all operational,incidental labour charges
such as mixing mortar,laying lift charges ,water curing etc;complete for finished item of work.

--

--

0
---------------22,906,632

28 Provision for VAT @ 1.4%

2,640.00
/ 10 Sqm.

612,480
---------------32,409,127

612,480
---------------21,679,047

---------------12,176,552

320,693

453,728

133,035

---

100,000

100,000

---

29 Provision for providing M.S. Grating over drains.

L.S.

30 Provision for unforseen items & rounding off.

L.S.

72,675
---------------23,300,000

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

2,320.00
Sqm.

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

L.S.

37,145
---------------33,000,000

Executive Engineer (R&B),


(R&B) Division : Kakinada

-----------------21,912,082

35,530
---------------12,212,082

10

11

NAME OF WORK
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from NH
214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits at Railway Km
14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sub-Estimate : Service Roads, Drains
DETAILED ESTIMATE
Sl.
No.
1

Description

No.

L
4

Measurements
B
5

D
6

Quantity
7

1 Earthwork excavation and removal of unserviceable soils upto SDR by mechanical means
including trimming bottom and side slopes in accordance with requirements of lines, grades
and cross sections etc., and loading and disposal upto 1000 mts etc., complete including
seignioarge charges for finished item of work as per MoRT&H specification 301(4th Revision)
and as directed by the Engineer-in-Charge
Kakinada Side
Service Roads
Viaduct portion (MKRP to KP14)
Between KA and KP14
RE Wall Portion
Passages under Viaduct portion
Bellmouth for passages
Existing road upto Junction
"
"
Port Side
Service Roads (North Side)
Viaduct portion (MPRP to PP13)
(PP13 to PP17)
Between PP17 and PA
RE Wall Portion
"
"
Service Roads (South Side)
Viaduct portion (MPRP to PP17)
Between PA and PP17
RE Wall Portion
"
"
"
"
Sub-way portion
Passages under Viaduct portion
Bellmouth for passages
"
"
near MPRP

2x1
2x1
2x1
3x1
3x2x2
1x1
1x2

171.40
13.10
140.00
9.00
1/2 x 2.00
38.00
16.00

6.20
(6.20+4.70)/2
(4.70+5.20)/2
7.40
2.00
(21.00-10.00)
(5.50+0.00)/2

(Avg. Depth)
0.40
0.40
0.40
0.40
0.40
0.20
0.20

850.14
57.12
554.40
79.92
9.60
83.60
17.60

1x1
1x1
1x1
1x1
1x1

168.30
52.40
13.10
46.20
118.00

7.20
6.20
(6.20+4.70)/2
(4.70+7.20)/2
7.20

0.50
0.30
0.20
0.20
0.20

605.88
97.46
14.28
54.98
169.92

1x1
1x1
1x1
1x1
1x1

220.70
13.10
84.20
10.00
70.00

6.20
(6.20+4.70)/2
(4.70+4.90)/2
(4.90+6.20)/2
6.20

0.40
0.50
0.20
0.20
0.20

547.34
35.70
80.83
11.10
86.80

1x1
4x1
3x2x2
1x1x2

11.65
9.00
1/2 x 2.00
1/2 x 2.00

6.00
7.40
2.00
2.00

0.20
0.40
0.40
0.40

13.98
106.56
9.60
1.60

0.50
0.50
0.50

0.300
0.300
0.300

97.35
59.70
16.65

or say

3,662.11
3,670.00
Cum.

For providing Interlocking tiles along Service road


2x1
324.50
Kakinada Side
1x1
398.00
Port Side (South Side)
"
" (North Side) (PP12 to
1x1
111.00
Sub-way)

2 Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of
scarified material with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th Revision) Specn.
No.305.4.3
Kakinada Side
Existing road upto Junction

Port Side
Existing road upto Junction

1x1
1x1
1x1

38.00
16.00
16.00

10.00
(10.00+21.00)/2
22.00

----

380.00
248.00
352.00

1x1

80.00

7.50

--

600.00
1,580.00
1,580.00
Sqm.

or say

3 Construction of Granular sub-base by providing HBG material confirming to Grading - III of


MoRT&H Table 400-2 including cost, seigniorage charges and conveyance of all materials to
work site and spreading in uniform layers with motor grader or by approved means, on
prepared surface mixing by mix in place method with Rotavator / approved means at OMC
and compacting with vibratory roller to achieve the desired density etc., complete for finished
item of work as per MoRT&H Specification
401 (4th revision) and as directed by the
Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).

Kakinada Side
Service Roads
Viaduct portion (MKRP to KP14)
Between KA and KP14
RE Wall Portion
Passages under Viaduct portion
Bellmouth for passages
Existing road upto Junction
"
"
Port Side
Service Roads (North Side)
Viaduct portion (MPRP to PP13)
(PP13 to PP17)
Between PP17 and PA
RE Wall Portion
"
"
Service Roads (South Side)
Viaduct portion (MPRP to PP17)
Between PA and PP17
RE Wall Portion
"
"
"
"
Sub-way portion
Passages under Viaduct portion
Bellmouth for passages
"
"
near MPRP
Existing road upto Junction

2x1
2x1
2x1
3x1
3x2x2
1x1
1x2

171.40
13.10
140.00
9.00
1/2 x 2.00
38.00
16.00

6.20
(6.20+4.70)/2
(4.70+5.20)/2
7.40
2.00
(21.00-10.00)
(5.50+0.00)/2

0.20
0.20
0.20
0.20
0.20
0.20
0.20

425.07
28.56
277.20
39.96
4.80
83.60
17.60

1x1
1x1
1x1
1x1
1x1

168.30
52.40
13.10
46.20
118.00

7.20
6.20
(6.20+4.70)/2
(4.70+7.20)/2
7.20

0.20
0.20
0.20
0.20
0.20

242.35
64.98
14.28
54.98
169.92

1x1
1x1
1x1
1x1
1x1

220.70
13.10
84.20
10.00
70.00

6.20
(6.20+4.70)/2
(4.70+4.90)/2
(4.90+6.20)/2
6.20

0.20
0.20
0.20
0.20
0.20

273.67
14.28
80.83
11.10
86.80

1x1
4x1
3x2x2
1x1x2
1x1

11.65
9.00
1/2 x 2.00
1/2 x 2.00
80.00

6.00
7.40
2.00
2.00
(24.00+22.00)/2

0.20
0.20
0.20
0.20
0.20

13.98
53.28
4.80
0.80
368.00
2,330.84
2,331.00
Cum.

or say

4 Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Kakinada Side
Service Roads
Viaduct portion (MKRP to KP14)
Between KA and KP14
RE Wall Portion
Passages under Viaduct portion
Bellmouth for passages
Existing road upto Junction
Side Road Approaches
Port Side
Service Roads (North Side)
Viaduct portion (MPRP to PP13)
(PP13 to PP17)
Between PP17 and PA
RE Wall Portion
"
"
Service Roads (South Side)
Viaduct portion (MPRP to PP17)
Between PA and PP17
RE Wall Portion
"
"
"
"
Sub-way portion
Passages under Viaduct portion
Bellmouth for passages
"
"
near MPRP
Existing road upto Junction
Side Road Approaches

2x1
2x1
2x1
3x1
3x2x2
1x1
1x4

171.40
13.10
140.00
9.00
1/2 x 2.00
70.00
5.00

6.20
(6.20+4.70)/2
(4.70+5.20)/2
7.40
2.00
21.00
(12.00+5.00)/2

0.10
0.10
0.10
0.10
0.10
0.10
0.05 (Avg.)

212.54
14.28
138.60
19.98
2.40
147.00
8.50

1x1
1x1
1x1
1x1
1x1

168.30
52.40
13.10
46.20
118.00

7.20
6.20
(6.20+4.70)/2
(4.70+7.20)/2
7.20

0.10
0.10
0.10
0.10
0.10

121.18
32.49
7.14
27.49
84.96

1x1
1x1
1x1
1x1
1x1

220.70
13.10
84.20
10.00
70.00

6.20
(6.20+4.70)/2
(4.70+4.90)/2
(4.90+6.20)/2
6.20

0.10
0.10
0.10
0.10
0.10

136.83
7.14
40.42
5.55
43.40

1x1
4x1
3x2x2
1x1x2
1x1
1x4
1x6

11.65
9.00
1/2 x 2.00
1/2 x 2.00
80.00
6.00
6.00

6.00
7.40
2.00
2.00
(24.00+22.00)/2
(6.00+3.50)/2
(10.00+5.00)/2

0.10
0.10
0.10
0.10
0.10
0.05 (Avg.)
0.05 (Avg.)

6.99
26.64
2.40
0.40
184.00
5.70
13.50
1,289.53
1,290.00
Cum.

or say
5 Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate
(Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 10002) including cost, seigniorage conveyance of all materials to site and labour charges,
centering, machine mixing, laying, vibrating, curing etc., including all other incidental and
operational charges of all T&P etc., complete for finished item of work as per MoRT&H
specification 1500, 1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-inCharge for C.C Pavement.
Kakinada Side
Service Roads
Viaduct portion (MKRP to KP14)
Between KA and KP14
RE Wall Portion

2x1
2x1
2x1

Passages under Viaduct portion


Bellmouth for passages

3x1
3x2x2

171.40
13.10
140.00
324.50
9.00
1/2 x 2.00

6.00
(6.00+4.50)/2
(4.50+5.00)/2

0.20
0.20
0.20

411.36
27.51
266.00

7.00
2.00

0.20
0.20

37.80
4.80

2
Existing road upto Junction
Side Road Approaches

3
1x1
1x4

4
70.00
5.00

5
21.50
(12.00+5.00)/2

6
0.20
0.10 (Avg.)

7
301.00
17.00

Port Side
Service Roads (North Side)
Viaduct portion (MPRP to PP13)
(PP13 to PP17)
Between PP17 and PA
RE Wall Portion
"
"

1x1
1x1
1x1
1x1
1x1

168.30
52.40
13.10
46.20
118.00
398.00

7.00
6.00
(6.00+4.50)/2
(4.50+7.00)/2
7.00

0.20
0.20
0.20
0.20
0.20

235.62
62.88
13.76
53.13
165.20

Service Roads (South Side)


Viaduct portion (MPRP to PP17)
Between PA and PP17
RE Wall Portion
"
"
"
"

1x1
1x1
1x1
1x1
1x1

220.70
13.10
84.20
10.00
70.00
398.00
11.65
9.00
1/2 x 2.00
1/2 x 2.00
80.00
6.00
6.00

6.00
(6.00+4.50)/2
(4.50+4.70)/2
(4.70+6.00)/2
6.00

0.20
0.20
0.20
0.20
0.20

264.84
13.76
77.46
10.70
84.00

6.00
7.00
2.00
2.00
(24.00+22.00)/2
(6.00+3.50)/2
(10.00+5.00)/2

0.20
0.20
0.20
0.20
0.20
0.10 (Avg.)
0.10 (Avg.)

13.98
50.40
4.80
0.80
368.00
11.40
27.00
2,523.20
2,524.00
Cum.

Sub-way portion
Passages under Viaduct portion
Bellmouth for passages
"
"
near MPRP
Existing road upto Junction
Side Road Approaches

1x1
4x1
3x2x2
1x1x2
1x1
1x4
1x6

or say

6 Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars
of all diameters including cost and conveyance of steel to site and all labour charges for
fabrication of reinforcement including cutting, bending, binding rods, tying grills, placing them
in position etc., complete including cost and conveyance of binding wire and all handling
charges and operational charges etc., and including over lapping welding if required etc.,
complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th
revision) and as per I.S.1786 of 1985.
Contraction joints
Dowel rods 25mm Dia.,
(Length 500mm, spacing 250mm)

Total length of Service Roads


Kakinada side : 324.50 x 2
Port side
: 398.00 x 2
Total
: 1445 M
Average width = 6.50 M
Total length of Existing roads
Kakinada side : 70.00
Port side
: 80.00
Total
: 150.00 M
Width = 22.00 M

Total joints = 1445/4.50= 321-1= 320


Length of dowel bars in each joint =
0.50 x(6500/250) =13.00 mts
Weight of dowel bars = 3.85 Kg/RM
Total weight = 3.85x320x13.00 = 16,016.00 Kg,

16.016

Total joints = 150/4.50= 33-1= 32


Length of dowel bars in each joint =
0.50 x(22000/250) = 44.00 mts
Total weight = 3.85x32x44.00 = 5,420 Kg,

5.420

Passages - 7Nos. & Sub-way


Total weight = 3.85 x 24 x 14.00 = 1,293.60 Kg.
3 joints per each = 3 x 8 = 24 Nos.
or say

1.294
22.730
23.000
M.T.

7 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.

Longitudinal joint
Tie Rods 12mm Dia.,
(Length 500mm, spacing 500mm)

For Service roads


No. of Rods = 1445 / 0.50
For Existing Roads
No. of Rods = 150/0.50 x 3 lines
Passages - 7Nos. & Sub-way
7 x 9.00M + 11.65 = 74.65 M

Total Length of bars =


0.50 x ( 1445 / 0.50) = 1445.00 mts
Weight of bars = 0.89 Kg/RM
Total weight = 0.89x1445 = 1,286.05 Kgs

1.286

Total Length of bars =


0.50 x ( 150 / 0.50) x 3 = 450.00 mts
Total weight = 0.89x450 = 400.50 Kgs

0.400

0.50 x (74.65 / 0.50) = 74.65 Mts


Total weight = 0.89 x 74.65 = 66.44 kgs.

0.066

or say

1.752
2.00
MT

8 Providing, laying Reinforced cement concrete Hume pipes of 300mm Dia., NP-3 class for pipe
culverts including cost and conveyance of Pipes etc., complete and Labour charges for
laying, jointing of 300mm dia. R.C.C Hume pipes in position including lifting, aligning,
lowering and hoisting etc., as per drawing and as per MoRT&H Specification 2900, 2905 and
2906 (4th Revision) and IRC Special Publication No: 13 and as directed by the Engineer-inCharge for finished item of work.
At Road Crossings & other places

10

25.00

--

--

250.00
RM

9 Sand filling in foundation including cost, seignoirage and conveyence of all materials to site
and watering, tamping etc., complete for finshed item of work as per MoRT&H specification
304 (4th Revision) and as directed by the Engineer - in - Charge.
Below Interlocking tiles along Service road
Kakinada Side
2x1
1x1
Port Side (South Side)
"
" (North Side) (PP12 to
1x1
Sub-way)

324.50
398.00
111.00

0.50
0.50
0.50

0.200
0.200
0.200
or say

64.90
39.80
11.10
115.80
116.00
Cum.

10 Cost and supply of Mastic pads 25.40mm thick including cost and conveyance of mastic pads
to the required soze amd fixing in position etc., complete as directed by the Engineer-incharge.
Expansion joint
Total length of Service Roads
Kakinada side : 324.50 x 2
Port side
: 398.00 x 2
Total
: 1445 M / 50 =
29 - 1 = 28 Nos.
Average width = 6.50 M

1x28

6.50

--

0.20

36.40

2
Total length of Existing roads
Kakinada side : 70.00
Port side
: 80.00
Total
: 150.00 M
Width = 22.00 M

1x2

22.00

--

0.20

8.80

or say

45.200
46.000
Sqm.

11 Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical
specifications and as directed by the Engineer-in-charge.
For Dowel rods
Total number of rods
320 x (6500/250) = 8320
32 x (22000/250) = 2816
24 x (7000/250) = 672
8320 + 2816 + 672 = 11808

1x11808

0.20

--

-or say

2,361.60
2,362.00
RM

12 Providing Vaccum Dewatered Flooring Services including leveling the concrete to be followed
by placement of the bottom and top mats, operation of the Vaccum Machine to release the
excess free water in the Concrete, removal of the mat after completion of dewatering process,
conduction of the initial floating using power floater followed by finishing using power trowel of
adquate capacity. The rate is not inclusive of pin vibration of the concrete, placement of the
concrete and / or provision of the special toppings, but including hire and operational charges
of Generator of adequate capacity and other T&P and labour charges for all operations etc.
complete
Kakinada Side
Service Roads
Viaduct portion (MKRP to KP14)
Between KA and KP14
RE Wall Portion

2x1
2x1
2x1

Passages under Viaduct portion


Bellmouth for passages
Existing road upto Junction

3x1
3x2x2
1x1

Port Side
Service Roads (North Side)
Viaduct portion (MPRP to PP13)
(PP13 to PP17)
Between PP17 and PA
RE Wall Portion
"
"

171.40
13.10
140.00
324.50
9.00
1/2 x 2.00
70.00

6.00
(6.00+4.70)/2
(4.70+5.00)/2

----

2,056.80
140.17
1,358.00

7.00
2.00
21.50

----

189.00
24.00
1,505.00

1x1
1x1
1x1
1x1
1x1

168.30
52.40
13.10
46.20
118.00
398.00

7.00
6.00
(6.00+4.70)/2
(4.70+7.00)/2
7.00

------

1,178.10
314.40
70.09
270.27
826.00

Service Roads (South Side)


Viaduct portion (MPRP to PP17)
Between PA and PP17
RE Wall Portion
"
"
"
"

1x1
1x1
1x1
1x1
1x1

6.00
(6.00+4.70)/2
(4.70+4.90)/2
(4.90+6.00)/2
6.00

------

1,324.20
70.09
404.16
54.50
420.00

Sub-way portion
Passages under Viaduct portion
Bellmouth for passages
"
"
near MPRP
Existing road upto Junction

1x1
4x1
3x2x2
1x1x2
1x1

220.70
13.10
84.20
10.00
70.00
398.00
11.65
9.00
1/2 x 2.00
1/2 x 2.00
80.00

6.00
7.00
2.00
2.00
(24.00+22.00)/2

------

69.90
252.00
24.00
4.00
1,840.00
12,394.68

6
or say

7
12,395.00
Sqm.

13 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric powered saw
of suitable capacity to give a finished groove of 4mm width and 1/4 to 1/3 depth in the cured
concrete in the longitudinal and transverse directions along predetermined lines. The rate is
inclusive of the cost of consumables such as diamond blade. Masons engaged for the
marking is also deemed to be included in the rate and pouring of Polysulphide Sealent to the
full depth of groove. The rate is inclusive of the cleaning of the groove after the sawing to
remove cementatious particles adn cement washings to give a clean dry surface and surface
preparation of the sides of the groove to accommodate the sealent material etc., to give a
neat finished look including cost of sealent, hire and operational charges of Generator of
Adequate capacity and other T&P and labour charges for all operations etc. complete.

Total length of Service Roads


Kakinada side : 324.50 x 2 + Port side : 398.00 x 2
Total
: 1445 M =
1x1
1,445.00
1445 / 4.50 = 320 Nos. 1x320
6.50
Average width = 6.50 M
Existing Roads Kakinada side : 70.00 + Port side : 80.00
Total
: 150.00 M
1x1
142.00
150 / 4.50 = 32 Nos. 1x32
22.00
Width = 22.00 M
Passages - 7Nos. & Sub-way
7 x 9.00M + 11.65 = 74.65 M
1x1
74.65
Avg. Width = 7.00 M
1x17
7.00

---

---

1,445.00
2,080.00

---

---

142.00
704.00

---

---

74.65
119.00
4,564.65
4,565.00
RM

or say

SIDE DRAINS
14 Earthwork excavation in soils upto SDR by mechanical means for foundations of structures
as per drawing and technical specification including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing sides of bottom, back
filling the excavation earth to the extent required etc., complete including seignioarge
charges for finished item of work as per MoRT&H specification 304(4th Revision) and as
directed by the Engineer-in-Charge
Kakinada Side : North Side
from Rly. Boundaty Ch.0 to 48.0
Ch.48.00 to 60.00 (Crossing)
Ch.60.00 to 244.00
Ch.244.00 to 255.00 (Crossing)
Ch.255.00 to 270.00
Kakinada Side : South Side
from Rly. Boundaty Ch.0 to 50.0
Ch.50.00 to 65.00 (Crossing)
Ch.65.00 to 142.00
Ch.142.00 to 154.00 (Crossing)
Ch.154.00 to 360.00
Port Side : North Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
Ch.320.00 to 335.00 (Crossing)

1x1
1x1
1x1
1x1
1x1

48.00
12.00
184.00
11.00
15.00

1.50
1.70
1.50
1.70
1.50

1.10
1.10
1.10
1.10
1.00

79.20
22.44
303.60
20.57
22.50

1x1
1x1
1x1
1x1
1x1

50.00
15.00
77.00
12.00
206.00

1.10
1.70
0.90
1.30
0.90

1.10
1.10
1.00
0.90
0.90

60.50
28.05
69.30
14.04
166.86

1x1
1x1
1x1
1x1

280.00
12.00
28.00
15.00

0.90
1.70
1.50
1.70

0.812
1.28
1.28
1.28

204.62
26.11
53.76
32.64

2
Ch.335.00 to 360.00
Ch.360.00 to 372.00 (Crossing)

3
1x1
1x1

4
25.00
12.00

5
1.50
1.70

6
1.28
1.28

7
48.00
26.11

2
Ch.372.00 to 420.00
Ch.420.00 to 432.00 (Crossing)
Ch.432.00 to 465.00
Ch.465.00 to 480.00 (Crossing)
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00

1x1
1x1
1x1
1x1

48.00
12.00
33.00
15.00

1.50
1.70
1.50
1.70

1.28
1.28
1.28
1.28

92.16
26.11
63.36
32.64

1x1
1x1
1x1

280.00
12.00
28.00

0.90
1.70
1.50

0.810
1.25
0.81

204.12
25.50
34.02
1,656.21
1,660.00
Cum.

or say

15 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, Vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2100 (4th Revision) and as directed by the Engineer-in-Charge for Base course (Bed) of
C.C. Drains
Kakinada Side : North Side
from Rly. Boundaty Ch.0 to 48.0
Ch.48.00 to 60.00 (Crossing)
Ch.60.00 to 244.00
Ch.244.00 to 255.00 (Crossing)
Ch.255.00 to 270.00

1x1
1x1
1x1
1x1
1x1

48.00
12.00
184.00
11.00
15.00

1.50
1.70
1.50
1.70
1.50

0.30
0.30
0.30
0.30
0.30

21.60
6.12
82.80
5.61
6.75

Kakinada Side : South Side


from Rly. Boundaty Ch.0 to 50.0
Ch.50.00 to 65.00 (Crossing)
Ch.65.00 to 142.00
Ch.142.00 to 154.00 (Crossing)
Ch.154.00 to 360.00

1x1
1x1
1x1
1x1
1x1

50.00
15.00
77.00
12.00
206.00

1.10
1.70
0.90
1.30
0.90

0.25
0.30
0.20
0.30
0.20

13.75
7.65
13.86
4.68
37.08

1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1

280.00
12.00
28.00
15.00
25.00
12.00
48.00
12.00
33.00
15.00

0.90
1.70
1.50
1.70
1.50
1.70
1.50
1.70
1.50
1.70

0.20
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30
0.30

50.40
6.12
12.60
7.65
11.25
6.12
21.60
6.12
14.85
7.65

1x1
1x1
1x1

280.00
12.00
28.00

0.90
1.70
1.50

0.20
0.30
0.20

50.40
6.12
8.40

or say

409.18
410.00
Cum.

Port Side : North Side


from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
Ch.320.00 to 335.00 (Crossing)
Ch.335.00 to 360.00
Ch.360.00 to 372.00 (Crossing)
Ch.372.00 to 420.00
Ch.420.00 to 432.00 (Crossing)
Ch.432.00 to 465.00
Ch.465.00 to 480.00 (Crossing)
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00

16 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone
aggregate and fine aggregate conforming to table 1000-2 of MoRT&H including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine
mixing, laying, vibrating, curing etc., including all other incidental and operational charges of
all T&P etc., complete for finished item of work as per MoRT&H specification 1500,1700,
2200 (4th Revision) and as directed by the Engineer-in-Charge for side walls of Drains.

Kakinada Side : North Side


from Rly. Boundaty Ch.0 to 48.0
Ch.48.00 to 60.00 (Crossing)
Ch.60.00 to 244.00
Ch.244.00 to 255.00 (Crossing)
Ch.255.00 to 270.00
On the top of the existing drain
Ch.270.00 to 360.00
Kakinada Side : South Side
from Rly. Boundaty Ch.0 to 50.0
Ch.50.00 to 65.00 (Crossing)
Ch.65.00 to 142.00
Ch.142.00 to 154.00 (Crossing)
Ch.154.00 to 360.00
Port Side : North Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
Ch.320.00 to 335.00 (Crossing)
Ch.335.00 to 360.00
Ch.360.00 to 372.00 (Crossing)
Ch.372.00 to 420.00
Ch.420.00 to 432.00 (Crossing)
Ch.432.00 to 465.00
Ch.465.00 to 480.00 (Crossing)
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
On the top of the existing drain
Ch.320.00 to 470.00

2x1
2x1
2x1
2x1
2x1

48.00
12.00
184.00
11.00
15.00

(0.50+0.25)/2
(0.60+0.35)/2
(0.50+0.25)/2
(0.60+0.35)/2
(0.50+0.25)/2

1.20
0.975
1.20
0.850
1.20

43.20
11.12
165.60
8.88
13.50

2x1

90.00

(0.30+0.25)/2

0.30

14.85

2x1
2x1
2x1
2x1
2x1

50.00
15.00
77.00
12.00
206.00

(0.40+0.25)/2
(0.60+0.35)/2
(0.30+0.20)/2
(0.60+0.35)/2
(0.30+0.20)/2

1.00
0.570
0.75
0.500
0.75

32.50
8.12
28.88
5.70
77.25

2x1
2x1
2x1
2x1
2x1
2x1
2x1
2x1
2x1
2x1

280.00
12.00
28.00
15.00
25.00
12.00
48.00
12.00
33.00
15.00

(0.30+0.20)/2
(0.60+0.35)/2
(0.50+0.25)/2
(0.60+0.35)/2
(0.50+0.25)/2
(0.60+0.35)/2
(0.50+0.25)/2
(0.60+0.35)/2
(0.50+0.25)/2
(0.60+0.35)/2

0.75
0.75
1.10
0.75
1.10
0.75
1.10
0.75
1.10
0.75

105.00
8.55
23.10
10.69
20.63
8.55
39.60
8.55
27.23
10.69

2x1
2x1
2x1

280.00
12.00
28.00

(0.30+0.20)/2
(0.60+0.35)/2
(0.50+0.25)/2

0.75
1.25
1.25

105.00
14.25
26.25

2x1

150.00

(0.30+0.25)/2

0.50

41.25

or say

858.94
860.00
Cum.

17 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials,


seigniorage charges, labour charges, curing etc complete for finished item of work as
directed by the Engineer -in-Charge
Kakinada Side : North Side
from Rly. Boundaty Ch.0 to 48.0
Ch.48.00 to 60.00 (Crossing)
Ch.60.00 to 244.00
Ch.244.00 to 255.00 (Crossing)
Ch.255.00 to 270.00
On the top of the existing drain
Ch.270.00 to 360.00

1x1
1x1
1x1
1x1
1x1

48.00
12.00
184.00
11.00
15.00

------

4.02
3.56
4.02
3.32
4.02

192.96
42.72
739.68
36.52
60.30

2x1

90.00

--

0.85

153.00

2
Kakinada Side : South Side
from Rly. Boundaty Ch.0 to 50.0
Ch.50.00 to 65.00 (Crossing)
Ch.65.00 to 142.00
Ch.142.00 to 154.00 (Crossing)
Ch.154.00 to 360.00
Port Side : North Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
Ch.320.00 to 335.00 (Crossing)
Ch.335.00 to 360.00
Ch.360.00 to 372.00 (Crossing)
Ch.372.00 to 420.00
Ch.420.00 to 432.00 (Crossing)
Ch.432.00 to 450.00
Ch.450.00 to 462.00 (Crossing)
Ch.462.00 to 480.00
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
Ch.280.00 to 292.00 (Crossing)
Ch.292.00 to 320.00
On the top of the existing drain
Ch.320.00 to 400.00
Ch.400.00 to 470.00

1x1
1x1
1x1
1x1
1x1

50.00
15.00
77.00
12.00
206.00

------

3.42
2.96
2.82
2.82
2.82

171.00
44.40
217.14
33.84
580.92

1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1
1x1

280.00
12.00
28.00
15.00
25.00
12.00
48.00
12.00
18.00
12.00
18.00

------------

2.82
3.32
3.82
3.32
3.82
3.32
3.82
3.32
3.82
3.32
3.82

789.60
39.84
106.96
49.80
95.50
39.84
183.36
39.84
68.76
39.84
68.76

1x1
1x1
1x1

280.00
12.00
28.00

----

2.82
4.32
4.12

789.60
51.84
115.36

2x1
2x1

80.00
70.00

---

0.90
1.35

144.00
189.00
5,084.38
5,085.00
Sqm.

18 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to
table 1000-2) including cost, seigniorage conveyance of all materials to site and labour
charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental
hire and operational charges of all T&P as per approved drawings and as directed during
execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed by the
Engineer-in-Charge for Cover slabs over side drains
Cover slabs over Drains
Kakinada Side : North Side
from Rly. Boundaty Ch.0 to 48.0
Ch.60.00 to 244.00
Ch.255.00 to 270.00
Ch.270.00 to 360.00(Existing
Drain)
Kakinada Side : South Side
from Rly. Boundaty Ch.0 to 50.0
Ch.65.00 to 142.00
Ch.154.00 to 360.00
Port Side : North Side
from Rly. Boundaty Ch.0 to 280.0
Ch.292.00 to 320.00
Ch.335.00 to 360.00
Ch.372.00 to 420.00
Ch.432.00 to 465.00

1x1
1x1
1x1

48.00
184.00
15.00

1.50
1.50
1.50

0.15
0.15
0.15

10.80
41.40
3.38

1x1

90.00

1.50

0.15

20.25

1x1
1x1
1x1

50.00
77.00
206.00

1.50
1.50
1.50

0.15
0.15
0.15

11.25
17.33
46.35

1x1
1x1
1x1
1x1
1x1

280.00
28.00
25.00
48.00
33.00

1.50
1.50
1.50
1.50
1.50

0.15
0.15
0.15
0.15
0.15

63.00
6.30
5.63
10.80
7.43

2
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
Ch.292.00 to 320.00
Ch.400.00 to 470.00
Cover slabs over Crossings
Kakinada Side : North Side
Ch.48.00 to 60.00 (Crossing)
Ch.244.00 to 255.00 (Crossing)
Kakinada Side : South Side
Ch.50.00 to 65.00 (Crossing)
Ch.142.00 to 154.00 (Crossing)
Port Side : North Side
Ch.280.00 to 292.00 (Crossing)
Ch.320.00 to 335.00 (Crossing)
Ch.360.00 to 372.00 (Crossing)
Ch.420.00 to 432.00 (Crossing)
Ch.465.00 to 480.00 (Crossing)
Port Side : South Side
Ch.280.00 to 292.00 (Crossing)
Ch.320.00 to 400.00

1x1
1x1
1x1

280.00
28.00
70.00

1.50
1.50
1.50

0.15
0.15
0.15

63.00
6.30
15.75
328.97

1x1
1x1

12.00
11.00

1.70
1.70

0.30
0.30

6.12
5.61

1x1
1x1

15.00
12.00

1.70
1.70

0.30
0.30

7.65
6.12

1x1
1x1
1x1
1x1
1x1

12.00
15.00
12.00
12.00
15.00

1.70
1.70
1.70
1.70
1.70

0.30
0.30
0.30
0.30
0.30

6.12
7.65
6.12
6.12
7.65

1x1
1x1

12.00
80.00

1.70
1.20

0.30
0.30

6.12
28.80
94.08

Total Qty.
or say

423.05
424.00
Cum.

19 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG
crushed stone aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate
conforming to table 1000-2) including cost,seignorage and conveyance of all materials to site
and all labour charges for machine mixing,laying in position, Compacting , Vibrating and
curing including all other incidental and all other operational charges of T&P required etc.,
complete as per MoRT&H Specification 1500,1700, 2100 (4th Revision) for Kerbs.

Kerbs
Kakinada Side along Service road

2x1
2x1

324.50
324.50

0.225
(0.225+0.20)/2

0.200
0.225

29.21
31.03

along passage roads

3x2
3x2

9.00
9.00

0.225
(0.225+0.20)/2

0.200
0.225

2.43
2.58

Port Side along Service road

2x1
2x1

398.00
398.00

0.225
(0.225+0.20)/2

0.200
0.225

35.82
38.06

along passage roads

4x2
4x2

9.00
9.00

0.225
(0.225+0.20)/2

0.200
0.225

3.24
3.44

Port Side : South Side


Footpath and Raised Kerb adjecent to the existing drain
Ch.320.00 to 400.00
1x1
80.00
Ch.320.00 to 400.00
1x1
80.00

(0.225+0.20)/2
1.50

0.500
0.100

8.50
12.00

or say

166.31
167.00
Cum.

20 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all
diameters including cost and conveyance of steel to site and all labour charges for fabrication
of reinforcement including cutting, bending, binding rods, tying grills, placing them in position
etc., complete including cost and conveyance of binding wire and all handling charges and
operational charges etc., and including over lapping welding if required etc., complete for all
R.C.C items for finished item of work as per standard drawings, as per the directions of the
Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.

For Cover Slabs over Drains


For Cover Slabs over Crossings

328.97 Cum. x
94.08 Cum. x

60.00 Kgs. / Cum


80.00 Kgs. / Cum

19,738.20
7,526.40
27,264.60
27.50
MT

21 Providing Chequrred Terrazo tiles of 30 mm thick (medium shade) 0.305 M x 0.305 M of


approved brand and colour laid over drain slab covers set over CM(1:8) 12mm thick base and
neat grey cement slurry at the rate of 3.30 Kgs of cement per sqm and jointed with heat white
cement paste mixed with pigments of matching shade and including cost,seigniorage charges
and conveyance of all materials etc. from approved sources to work site and all
operational,incidental labour charges such as mixing mortar,laying lift charges ,water curing
etc;complete for finished item of work.
Footpath over Drains
Kakinada Side : North Side
from Rly. Boundaty Ch.0 to 48.0
1x1
Ch.60.00 to 244.00
1x1
Ch.255.00 to 270.00
1x1
Ch.270.00 to 360.00
1x1
Kakinada Side : South Side
from Rly. Boundaty Ch.0 to 50.0
1x1
Ch.65.00 to 142.00
1x1
Ch.154.00 to 360.00
1x1
Port Side : North Side
from Rly. Boundaty Ch.0 to 280.0
1x1
Ch.292.00 to 320.00
1x1
Ch.335.00 to 360.00
1x1
Ch.372.00 to 420.00
1x1
Ch.432.00 to 480.00
1x1
Port Side : South Side
from Rly. Boundaty Ch.0 to 280.0
1x1
Ch.292.00 to 320.00
1x1
Footpath adjecent to the existing drain
Ch.320.00 to 470.00
1x1

48.00
184.00
15.00
90.00

1.50
1.50
1.50
1.50

-----

72.00
276.00
22.50
135.00

50.00
77.00
206.00

1.50
1.50
1.50

----

75.00
115.50
309.00

280.00
28.00
25.00
48.00
33.00

1.50
1.50
1.50
1.50
1.50

------

420.00
42.00
37.50
72.00
49.50

280.00
28.00

1.50
1.50

---

420.00
42.00

150.00

1.50

--

225.00
2,313.00
2,320.00
Sqm.

or say
22 Provision for providing M.S. Grating over drains.

L.S.

23 Provision for unforseen items & rounding off.

L.S.

Asst. Executive Engineer (R&B),

Dy. Executive Engineer (R&B),

Executive Engineer (R&B),

1
2
(R&B) East Section : Kakinada

3
4
5
(R&B) East Sub-divn., : Kakinada

6
7
(R&B) Division : Kakinada

DATA FOR ROAD ITEMS


Name of Work ::-

Quantity
1

Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi


Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in
Kakinada Town limits at Railway Km 14.05 of Kakinada Town Kakinada Port
Section in E.G.Dist.
Description of Item

Rate

Scarifying the existing B.T surface to a depth of 50 mm by Mechanical means and disposal of scarified material
with all leads and lifts upto 1000 Mtrs as per MoRT&H (4th Revision) Specn. No.305.4.3
Unit = sqm
Page 67,68 of MoRT&H SDB
Taking output = 100 sqm
(A) Labour
0.01
day
Mate
188.00
0.25
day
Mazdoor
146.00
20.00 %
Extra for Municipal Area Allowance on Rs.
38.38
Total
(B) Machinery
0.08
hr
Tractor with ripper attachment @ 60 cu
345.00
Front
end
loader
1
cum
capacity
1320.00
0.20
hr
Tipper 5.50 cum capacity, 4 trips/Hour
575.00
0.23
hr
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00
%
Add Contractors Profit at 10% on (A)+(B)+
Cost per 100 sqm
Rate per 1 sqm
Rate to be adopted

per

day
day

hr
hr
hr

Providing Vibrated Cement Concrete (1:4:8) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.
Unit = cum
(A) Labour
0.64 nos
1.00 nos
15.00 nos
25.00 %
(B)
13.50
6.75
2.43

Taking output = 15 cum


Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Material
cum
Cost of 40mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site
Total
Machinery
6.00
hr
Concrete mixer 0.4/0.28 cum
6.00
hr
Generator set 35 KVA
2.00
hr
Water tanker 6 KL

188.00
193.40
146.00
2503.72

day
day
day

1121.93
540.80
4500.00

cum
cum
MT

345.00
620.00
345.00

hr
hr
hr

Quantity
(D)
6.00
(E)
(F)

Description of Item
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted

per

Vibrated cement concrete M 35 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse aggregate
conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost, seigniorage
conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating, curing etc.,
including all other incidental and operational charges of all T&P etc., complete for finished item of work as per
MoRT&H specification 1500, 1700, 2100 & 2702 (4th Revision) and as directed by the Engineer-in-Charge
for C.C Pavement.
Unit = cum
(A) Labour
0.86 nos
1.50 nos
20.00 nos
25.00 %

(B)
8.10
5.40
6.75
6.33

Material
cum
cum
cum
MT

Taking output = 15 cum

Page 345,346 of MoRT&H SDB

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Cost of 20mm SS-5 HBG M/C metal


Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
3.50
(E)
6.00
(F)
(G)

Rate

188.00
193.40
146.00
3371.78

day
day
day

1553.18
1196.93
540.80
4500.00

cum
cum
cum
MT

345.00
620.00

hr
hr

Form work
%
Form work @ 3.50% on (A)+(B)+( C)
61184.31
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

Providing Uncoated Mild Steel bars ( Fe-250 ) of different diameters, wrought and put up bars of all diameters
including cost and conveyance of steel to site and all labour charges for fabrication of reinforcement including
cutting, bending, binding rods, tying grills, placing them in position etc., complete including cost and
conveyance of binding wire and all handling charges and operational charges etc., and including over lapping
welding if required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per
the directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as
per I.S.1786 of 1985.

Quantity
Unit = MT

Description of Item
Rate
Taking output = 1 MT
Page 460 of MoRT&H SDB

per

Quantity
(A) Labour
0.28 nos
1.50 nos
5.50 nos
25.00 %

Description of Item
Mate
Black smith
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
1.05 MT
Mild steel bars including overlaps
6.00 Kg
Binding wire
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT
Rate to be adopted
5

per

188.00
188.00
146.00
1137.64

day
day
day

44800.00
38500.00

MT
MT

Providing, laying Reinforced cement concrete Hume pipes of 300mm Dia., NP-3 class for pipe culverts
including cost and conveyance of Pipes etc., complete and Labour charges for laying, jointing of 300mm dia.
R.C.C Hume pipes in position including lifting, aligning, lowering and hoisting etc., as per drawing and as per
MoRT&H Specification 2900, 2905 and 2906 (4th Revision) and IRC Special Publication No: 13 and as
directed by the Engineer-in-Charge for finished item of work.
Unit = metre
(A)
0.14
0.50
3.00
25.00

Labour
nos
nos
nos
%

Taking output = 12.5 metre


300 mm Dia.,

Page 272,273 of MoRT&H SDB

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
12.50 RM
Cost of 300mm Dia., pipes
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 12.5 metre (D)+(E)
Rate for 1 RM
Rate to be adopted
6

Rate

188.00
193.40
146.00
561.02

day
day
day

747.00

RM

Sand filling in foundation including cost, seignoirage and conveyence of all materials to site and watering,
tamping etc., complete for finshed item of work as per MoRT&H specification 304 (4 th Revision) and as
directed by the Engineer - in - Charge.
Unit = cum
Page 422 of MoRT&H SDB
Taking output = 1 cum
(A) Labour
0.01 day
Mate
0.30 day
Mazdoor
25.00 %
Extra for Corporation Area Allowance on Rs.

188.00
146.00
45.68

day
day

Quantity

Description of Item

Rate

per

Quantity
Description of Item
(B) Material
1.20 Cum
Sand for filling
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)
Or say

Rate

per

425.80

cum

Cost and supply of Mastic pads 25.40mm thick including cost and conveyance of mastic pads to the required
soze amd fixing in position etc., complete as directed by the Engineer-in-charge.

Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical specifications and as
directed by the Engineer-in-charge.
1.00 RM

PVC Pipe 25.40mm dia

30.70

1 RM

Providing Vaccum Dewatered Flooring Services including leveling the concrete to be followed by placement of
the bottom and top mats, operation of the Vaccum Machine to release the excess free water in the Concrete,
removal of the mat after completion of dewatering process, conduction of the initial floating using power floater
followed by finishing using power trowel of adquate capacity. The rate is not inclusive of pin vibration of the
concrete, placement of the concrete and / or provision of the special toppings, but including hire and operational
charges of Generator of adequate capacity and other T&P and labour charges for all operations etc. complete

Rate as per lowest quotation

10 Sawing of Concrete Pavement using a self propelled walk behind, petro/electric powered saw of suitable
capacity to give a finished groove of 4mm width and 1/4 to 1/3 depth in the cured concrete in the longitudinal
and transverse directions along predetermined lines. The rate is inclusive of the cost of consumables such as
diamond blade. Masons engaged for the marking is also deemed to be included in the rate and pouring of
Polysulphide Sealent to the full depth of groove. The rate is inclusive of the cleaning of the groove after the
sawing to remove cementatious particles adn cement washings to give a clean dry surface and surface
preparation of the sides of the groove to accommodate the sealent material etc., to give a neat finished look
including cost of sealent, hire and operational charges of Generator of Adequate capacity and other T&P and
labour charges for all operations etc. complete.

Rate as per lowest quotation

Asst. Executive Engineer (R&B),

Dy. Executive Engineer (R&B),

Executive Engineer (R&B),

Quantity
(R&B) East Section : Kakinada

Description of Item
(R&B) East Sub-divn., : Kakinada

Rate
per
(R&B) Division : Kakinada

Forming embankment with Side earth by mechanical means upto SDR including pre-watering of soil , removal
of top soil, excavation of soils , depositing the soils on the embankment, spreading soil, breaking clods,
sectioning , grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement
of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges,
complete for finished item of work as per MoRT&H specification 305 (4 th revision) (Payment will be made
based on level for finished item of work).

Forming embankment with Side earth by mechanical means upto SDR including pre-watering of soil , removal
of top soil, excavation of soils , depositing the soils on the embankment, spreading soil, breaking clods,
sectioning
, grading and consolidationDescription
with 8 to 10ofTonnes
to meet requirement
Quantity
Item Vibratory Road Roller
Rate@ OMCper
of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges,
complete for finished item of work as per MoRT&H specification 305 (4 th revision) (Payment will be made
based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.02 day
0.50 day
20.00 %

Page 70 of MoRT&H SDB

Mate

188.00

day

Mazdoor unskilled
Extra for Municipal Area Allowance on Rs.

146.00
76.76

day

13.00

cum

Motor Grador for Grading @ 100 cum per hour

2600.00

hr

Water tanker 6 KL
Vibratory roller 8T

345.00
1550.00

hr
hr

20.00

cum

(B) Machinery
100.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005
1.00 hr
4.00 hr
1.00 hr

(C) Seigniorage charges


100.00 Cum
Seigniorage charges
(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum
1

Forming embankment with borrowed useful earth from outside road boundary by mechanical means upto SDR
with all leads and lifts including pre-watering of soil at borrow area, removal of top soil, excavation of soils at
borrowed area, conveyance of soil, depositing the soil on the embankment, spreading soil, breaking clods,
sectioning, grading and consolidation with 8 to 10 Tonnes Vibratory Road Roller @ OMC to meet requirement
of table 300-2 of MoRT&H, including all hire and operational charges of T&P and seigniorage charges,
complete for finished item of work as per MoRT&H specification 305 (4 th revision) (Payment will be made
based on level for finished item of work).
Unit : Cum
Taking out put = 100 Cum
(A) Labour
0.04 day
1.00 day
25.00 %

Page 68,69 of MoRT&H SDB

Mate

188.00

day

Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

146.00
153.52

day

13.00

cum

4.50

t.km

2760.00
2600.00
345.00
1550.00

hr
hr
hr
hr

(B) Machinery
100.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005
160.00 t.km
Tipper (for 1 Km = 160x1 = 160)
Add 10% of cost of carriage to cover cost of
loading and unloading
0.50
1.00
4.00
1.00

hr
hr
hr
hr

Dozer 80 HP for spreading @ 200 cum per hour


Motor Grador for Grading @ 100 cum per hour
Water tanker 6 KL
Vibratory roller 8T

Quantity

Description of Item

(C) Seigniorage charges


100.00 Cum
Seigniorage charges
(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 100 cum (E) + (F)
Rate per Cum
Rate per 1 cum
3

Rate

per

20.00

cum

Earthwork excavation in soils upto SDR by mechanical means including trimming bottom and side slopes in
accordance with requirements of lines , grades and cross sections etc., complete including seignioarge charges
for finished item of work for trench cutting as per MoRT&H specification 301(4 th Revision) and as directed by
the Engineer-in-Charge
Unit : Cum
Taking out put = 180 Cum
(A) Labour
0.08
day
2.00
day
25.00 %

Page 50 of MoRT&H SDB


Mate

188.00

day

146.00
307.04

day

(B) Machinery
180.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005

13.00

cum

(C) Seigniorage charges


180.00 Cum
Seigniorage charges

20.00

cum

Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 180 cum (E) + (F)
Rate per Cum
Rate per 1 cum
2

Earthwork excavation and removal of unserviceable soils upto SDR by mechanical means including trimming
bottom and side slopes in accordance with requirements of lines, grades and cross sections etc., and loading and
disposal upto 1000 mts etc., complete including seignioarge charges for finished item of work as per
MoRT&H specification 301(4th Revision) and as directed by the Engineer-in-Charge

Unit : Cum
Taking out put = 360 Cum
(A) Labour
0.08
day
2.00
day
25.00 %

Page 58 of MoRT&H SDB


188.00

day

146.00
307.04

day

(B) Machinery
360.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005

13.00

cum

16.36

575.00

Hr

Hrs

Mate
Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

Tippers 5.50 cum capacity

Quantity
Description of Item
(C) Seigniorage charges
360.00 Cum
Seigniorage charges

Rate

per

20.00

cum

(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 360 cum (E) + (F)
Rate per Cum
Rate per 1 cum

Construction of Granular sub-base by providing HBG material confirming to Grading - III of MoRT&H Table
400-2 including cost, seigniorage charges and conveyance of all materials to work site and spreading in uniform
layers with motor grader or by approved means, on prepared surface mixing by mix in place method with
Rotavator / approved means at OMC and compacting with vibratory roller to achieve the desired density etc.,
complete for finished item of work as per MoRT&H Specification 401 (4 th revision) and as directed by the
Engineer-in-charge. ( Payment will be made based on levels for finished item of work ).

Unit = cum
Taking output = 300 cum
Page 95 of MoRT&H SDB
(A) Labour
0.40 day
Mate
2.00 day
Mazdoor skilled
8.00 day
Mazdoor unskilled
25.00 %
Extra for Corporation Area Allowance on Rs.
Total
(B) Machinery
6.00 hr
Motor grader 3.35M Blade @50 cum/Hr
12.00 hr
Tractor with Rotavator
6.00 hr
Vibratory roller 8T
3.00 hr
Water tanker 6 KL
Total
(C) Material
Coarse graded Granular sub-base material as per
Table 400-2 of MORT&H
9.5mm to 4.75mm @ 66%
255.00 cum
(Av. rate of 9.5-11.2mm , 5-7mm & 2.36 - 5mm
HBG M/C metal)
2.36mm and below @34%
129.00 cum
(Rate of 2.36mm & below HBG metal)
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted
6

188.00
193.40
146.00
1630.00

day
day
day

2600.00
345.00
1550.00
345.00

hr
hr
hr
hr

1006.93

Cum

654.10

Cum

Scarifying the existing granular surface to a depth of 50 mm by Manual means including all labour charges
etc., complete as per MoRT&H (4th Revision) Specn. No.305.4.3 for finished item of work.

Quantity
Description of Item
Unit = sqm
Page 67 of MoRT&H SDB
Taking output = 100 sqm
(A) Labour
0.20 day
Mate
5.00 day
Mazdoor including loading & unloading
5.00 Cum
Deduct for loading & unloading
20.00 %
Extra for Municipal Area Allowance on Rs.
Total
(B) Over head charges @ 6% (10%-VAT)
6.00 %
Add for Over head charges @ 6% on (A)
(C) Total of (A) + (B)
(D) Add Contractors Profit at 10% on (A)+(B)
Cost per 100 sqm
Rate per 1 sqm
Rate to be adopted
8

Rate

per

188.00
146.00
17.00
682.60

day
day
Cum

Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - II - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7&9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Power Road Roller 810 Tonnes in stages to proper grade and camber applying and brooming requisite type ' A ' screenings as per
table 400-8&9 and binding materials as to fill up the interstices of coarse aggregates,watering and compacting to
the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed
by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)

Unit = cum
Page 104,105,106 of MoRT&H SDB
Taking output = 360 cum
(A) Labour
10.08 nos.
Mate
188.00
2.00 nos.
Mazdoor skilled
193.40
250.00 nos.
Mazdoor
146.00
20.00 %
Extra for Municipal Area Allowance on Rs.
38781.84
Total
(B) Machinery
smooth wheeled roller 8 Ton
12.00 hr
540.00
24.00 hr
water tanker 6 KL
345.00
Total
(C) Material
217.80 cum
63mm IRC&MoRT&H HBG metal
859.10
200.38 cum
45mm IRC&MoRT&H HBG metal
999.10
17.42 cum
22.40 mm IRC&MoRT&H HBG M/C metal
1553.18
57.60 cum
Screenings 13.2mm@ 0.12cum/10sqm
1115.68
(Ave of 9.5-11.2 mm & 5-7 mm M/C )
28.80

(D)
6.00
(E)
(F)

cum

Binding material @ 0.06 cum / 10sqm (Rate of


2.36mm & Below)

Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)

654.10

day
day
day

hr
hr

cum
cum
cum
cum
cum

Quantity

Description of Item
Cost per 360 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum

Rate

per

Providing, Laying, Spreading for a compacted thickness of 75 mm, using stone aggregates of Grade - III - IRC
& MoRT&H - H.B.G Metal (Machine crushed metal for 22.40mm and below) as per Table 400-7& 9 of
MoRT&H Specification 404 of 4th revision for Water Bound Macadam specification including cost, conveyance
and seignorage charges and spreading in uniform thickness, hand packing, rolling with Power Road Roller 810 Tonnes in stages to proper grade and camber applying and brooming requisite type ' B ' screenings as per
table 400-8&9 and binding materials to fill up the interstices of coarse aggregates,watering and compacting to
the required density for finished item of work as per MoRT&H specification 404 (4 th revision) and as directed
by the Engineer-in-Charge (Payment will be made based on levels for finished item of work)

Unit = cum
Page 104,105,106 of MoRT&H SDB
Taking output = 360 cum
(A) Labour
10.08 nos.
Mate
188.00
2.00 nos.
Mazdoor skilled
193.40
250.00 nos.
Mazdoor
146.00
20.00 %
Extra for Municipal Area Allowance on Rs.
38781.84
Total
(B) Machinery
smooth wheeled roller 8 Ton
12.00 hr
540.00
24.00 hr
water tanker 6 KL
345.00
Total
(C) Material
357.19 cum
45mm IRC&MoRT&H HBG metal
999.10
78.41 cum
22.40mm IRC&MoRT&H HBG M/C metal
1553.18
Screenings 11.2mm @0.18cum/10sqm
86.40 cum
721.77
(Av. Rate of 2.36 - 5mm & 2.36mm&Below)
28.80 cum

(D)
6.00
(E)
(F)

Binding material @ 0.06 cum / 10sqm


(Rate of 2.36mm & Below)

Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 360 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum

654.10

day
day
day

hr
hr

cum
cum
cum
cum

Quantity
4

Description of Item

Rate

per

Providing, Laying, Spreading and compacting graded HBG crushed stone aggregate to Wet Mix macadem
specification including cost,seignorage of all materials and including premixing the material with water at OMC
in Mechanical mix plant carriage of mixed material by tipper to site , laying in uniform layers with paver in
base courses on well prepared surface and compacting with Vibratory roller to acheive the desired density etc.,
as directed by the Engineer-in-Charge and as per MoRT&H specification.406 (4 th revision) for finished item of
work. (Payment based on levels for finished item of work)
Unit = cum
Page 110,111 of MoRT&H SDB
Taking output = 225 cum
(A) Labour
0.48 nos.
Mate
188.00
2.00 nos.
Mazdoor skilled
193.40
10.00 nos.
Mazdoor
146.00
25.00 %
Extra for Corporation Area Allowance on Rs.
1937.04
Total
(B) Machinery
6.60 hr
Wet mix plant of 60 tonne hr. capacity
1320.00
6.00 hr
Electric generating set 125 KVA
1090.00
6.00 hr
front end loader 1 cum capacity
1320.00
6.00 hr
Mechanical Paver finisher 100 TPH
1090.00
3.90 hr
Vibratory roller 8-10 T
1550.00
3.00 hr
Water tanker
345.00
Total
(C) Material
89.10 cum
45 to 22.40mm IRC&MoRT&H HBG M/C
1403.18
metal@ 30% (Av. Of 40-45, 25-27, 19-22mm )
118.80 cum
22.4 to 2.36mm IRC&MoRT&H HBG M/C
1186.68
metal@40% (Av. Of 19-22mm, 12-14mm, 9.511.2mm, 5-7mm, 2.36 - 5mm )
89.10 cum
2.36mm to 75 micron @ 30% (2.36mm & below)
654.10
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 225 cum (E) + (F)
Rate per 1 cum
Rate to be adopted per 1 cum

day
day
day

hr
hr
hr
hr
hr
hr

cum
cum

cum

17 Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine crushed stone
aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @ 0.75 kg / sqm including cost,
seigniorage and conveyance of all materials to work site and laid on prepared surface and rolling with 8-10 T
Power Road Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4 th Revision)
and as directed by the Engineer-in-charge.
Unit = sqm
Page 141,142 of MoRT&H SDB
Taking output = 9000 sqm
(A) Labour
Mate
0.44 nos.
188.00
Mazdoor
9.00 nos.
146.00
Mazdoor skilled
2.00 nos.
193.40
20.00 %
Extra for Municipal Area Allowance on Rs.
1783.52

day
day
day

Quantity
(B)
7.20
7.20
6.00
6.00

Description of Item
Total
Machinery
Mechanical broom @ 1250 sqm/hr.
hr
Air compressor 250 cfm
hr
hr
Hydraulic self propelled chip spreader @ 1500
sqm/hr.
hr
Tipper 10Tonne capacity for carriage of stone
chips from stock pile on road side to chip spreader
(Rate of Tipper 5 cum

6.00 hr
6.00 hr
6.00 hr

Front end loader 1 cum bucket capacity


Bitumen pressure distributor @1750 sqm/hr
smooth wheeled roller 8 Ton
Total

(C) Material
Bitumen 80/100 @ 0.75 Kg / sqm
6.75 MT
36.00 cum
Crushed stone chippings 6 mm nominal size
@0.004 cum/sqm
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 9000 sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted.
5

Rate

per

290.00
370.00
2070.00

hr
hr
hr

497.00

hr

1320.00
940.00
540.00

hr
hr
h

41971.18
1034.43

MT
cum

Providing and laying surface dressing in single coat using 6 mm nominal size IRC HBG machine crushed stone
aggregates @ 0.004 cum / sqm on a layer of bitumen binder of 80/100 grade @ 0.75 kg / sqm including cost,
seigniorage and conveyance of all materials to work site and laid on prepared surface and rolling with 8-10 T
Power Road Roller etc., complete for finished item of work as per MoRT&H Specification 510 (4 th Revision)
and as directed by the Engineer-in-charge.
Unit = sqm
Page 141,142 of MoRT&H SDB
Taking output = 9000 sqm
(A) Labour
Mate
0.44 nos.
188.00
Mazdoor
9.00 nos.
146.00
Mazdoor
skilled
2.00 nos.
193.40
25.00 %
Extra for Corporation Area Allowance on Rs.
1783.52
Total
(B) Machinery
Mechanical broom @ 1250 sqm/hr.
7.20 hr
290.00
Air compressor 250 cfm
7.20 hr
370.00
6.00 hr
Hydraulic self propelled chip spreader @ 1500
2070.00
sqm/hr.
Tipper 10Tonne capacity for carriage of stone
6.00 hr
575.00
chips from stock pile on road side to chip spreader
(Rate of Tipper 5 cum

6.00 hr
6.00 hr
6.00 hr
(C) Material

Front end loader 1 cum bucket capacity


Bitumen pressure distributor @1750 sqm/hr
smooth wheeled roller 8 Ton
Total

1320.00
940.00
540.00

day
day
day

hr
hr
hr
hr

hr
hr
h

Quantity
6.75 MT
36.00 cum

(D)
6.00
(E)
(F)

Description of Item
Bitumen 80/100 @ 0.75 Kg / sqm
Crushed stone chippings 6 mm nominal size
@0.004 cum/sqm
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 9000 sqm (E) + (F)
Rate per 1 sqm
419988.94
Rate to be adopted.

Rate
41971.18
1034.43

per
MT
cum

/ 9000

Providing and applying tack coat with bitumen Emulsion (Bulk) using Emulsion pressure distributor at the rate
of 0.20 kgs per sqm on the prepared bituminous/granular surface cleaned with mechanical broom for finished
item of work as per MoRT&H Specification 503 (4th revision) and as directed by the Engineer-in-Charge.
unit = sqm
Page 124 of MoRT&H SDB
Taking output = 3500 sqm
(A) Labour
0.08 nos
Mate
2.00 nos
Mazdoor
25.00 %
Extra for Corporation Area Allowance on Rs.
Total
(B) Machinery
2.80 hr
Mechanical broom Hydraulic @ 1250 sqm/hr.
2.80 hr
Air compressor 250 cfm
2.00 hr
Emulsion pressure distributor @1750 sqm/hr
Total
(C) Material
Bitumen Emulsion @ 0.20 Kgs/sqm
0.70 MT
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 3500 sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted

188.00
146.00
307.04

day
day

290.00
370.00
690.00

hr
hr
hr

38188.83

MT

Quantity
Description of Item
Rate
per
20 Providing , laying of close graded premix surfacing material ( Mixed seal surfacing) of 20 mm thickness by hot
mix plant using hard blasted granite crushed aggregates of 13.2mm to 0.09mm (Type 'B') as per table 500-26
of specification 512 of MoRT&H (4th Revision), premixed with bituminous binder 60/70 grade @ 19 Kg per 10
Sqm area, including cost and seigniorage of all materials and transporting the hot mix to work site, laying with
mechanical paver finisher to the required grade, level and alignment, rolling with smooth wheeled roller 8 to 10
Tonnes as per MoRT&H Specification 512 (4th Revision) complete for finished item of work in all respects as
directed by Engineer-in-charge.

Unit = sqm
Page 146,147 of MoRT&H SDB
Taking output = 10250 sqm (205 cum) (450 tonnes.)
(A) Labour
0.84 nos.
Mate
188.00
Mazdoor working with HMP, Mechanical broom,
14.00 nos.
146.00
paver, roller, asphalt cutter and assistance for
setting outlines, levels and layout of construction.
5.00 nos.
20.00 %

193.40
3168.92

day

(B)
12.00
6.00
6.00
6.00
6.00

15525.00
1550.00
1320.00
1090.00
540.00

hr
hr
hr
hr
hr

42923.15

MT

1006.86

cum

(C)
19.48

Skilled Mazdoor for checking line and levels.


Extra for Municipal Area Allowance on Rs.
Total
Machinary
hr
Hot mix plant 40 to 60 TPH
hr
Generator 250 KVA
hr
Front end loader 1 cum capacity
hr
Mechanical Paver finisher @ 100 TPH
hr
Smooth wheeled roller 8-10 Tonnes
Total
Material
M.T
(i) Bitumen 60/70 Grade @19 kg per 10 sqm
(ii) Aggregate
For Type 'B'
HBG M/C aggregates 13.2mm to 0.09mm @ 0.27
cum per 10 sqm

day
day

276.75 cum

(D)
6.00
(E)
(F)

Average rate of IRC&MoRT&H HBG M/C metal


of sizes 12-14, 9.5-11.2, 5-7mm, 2.36 - 5mm and
HBG 2.36mm&below

Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 10250 Sqm (E) + (F)
Rate per 1 sqm
Rate to be adopted

Quantity
Description of Item
Rate
per
Providing and laying of 50mm thick Bituminous Macadam with hot mix plant producing an average output
of 37.5 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per table 500-4 of
MoRT&H specificaion 504 (4th Revision) premixed with bituminous binder of 60/70 grade @ 3.3% by
weight of total mixture, transported to site, laid over a previously prepared surface with mechanical paver
finisher to the required grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the
desired compaction for finished item of work as directed by the Engineer-in-Charge including hire and
opeational charges all T&P and all other contingent charges necessary including cost of seigniorage
charges on all materials etc., complete and as per MoRTH specification No. 504(4th Revision) .

Unit = cum
Taking out put = 205 cum (450 tonne)
Page 125,126,127 of MoRT&H SDB
(A)
Labour
0.84
nos.
Mate
188.00
Mazdoor working with HMP, mechanical broom,
14.00 nos.
146.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction.
Mazdoor skilled
Extra for Corporation Area Allowance on Rs.
Total
Machinery
hr
Hot Mix Plant 40 to 60 TPH
hr
Air Compressor 250 cfm
hr
Mechanical Paver finisher 100 TPH
hr
Generator 250 KVA
hr
Front end loader 1 cum bucket capacity
hr
Smooth wheeled roller 8-10 tonnes for initial break
down rolling

nos.
nos.

5.00
nos.
25.00 %

193.40
3168.92

nos.

(B)
12.00
2.20
6.00
6.00
6.00
3.90

15525.00
370.00
1090.00
1550.00
1320.00
540.00

hr
hr
hr
hr
hr
hr

3.90

hr

Vibratory roller 8 tonnes for intermediate rolling

1550.00

hr

3.90

hr

Finish rolling with 6-8 tonnes smooth wheeled


tandem roller.

1320.00

hr

Total
(C)
14.85

116.04

Material
MT
Bitumen 60/70 @ 3.3 % of weight of mix
ii)
Aggregate
Total weight of mix = 450 tonnes
weight of bitumen - 14.85 tonnes
Weight of aggregate = 450-14.85 = 435.15 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate = 290.1 cum
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
cum
IRC &MORT&H HBG M/C chips 25 to 10mm @
40%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 25-27mm, 19-22mm, 12-14mm, 9.511.2mm

42923.15

1410.99

MT

cum

Quantity
116.04 cum

Description of Item
IRC &MORT&H HBG M/C chips 10 to 5mm @
30%

Rate
1115.68

per
cum

721.77

cum

Average rate of IRC&MoRT&H HBG M/C metal


of sizes 9.5-11.2mm, 5 to 7mm
58.02

cum

IRC &MORT&H HBG M/C chips 5mm and


below @ 40%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 2.36 to 5mm and 2.36mm& below

(D)
6.00
(E)
(F)

Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 205 cum (E) + (F)
Rate per 1 cum
Rate to be adopted

Providing and laying of Dense Graded Bituminous Macadam with hot mix plant producing an average output
of 37.5 tonnes per hour using hard blasted granite crushed aggregates of Grading - II as per table 500-4 of
MoRT&H specificaion 504 (4th Revision) premixed with bituminous binder of 60/70 grade @ 4.50% by weight
of total mixture, transported to site, laid over a previously prepared surface with mechanical paver finisher to the
required grade, level and alignment and rolled as per Clauses 501.6 and 501.7 to achieve the desired compaction
for finished item of work as directed by the Engineer-in-Charge including hire and opeational charges all T&P
and all other contingent charges necessary including cost of seigniorage charges on all materials etc., complete
and as per MoRTH specification No. 507 (4th Revision) .

Unit = cum
Taking out put = 195 cum (450 tonne)
Page 125,126,127 of MoRT&H SDB
(A)
Labour
0.84
nos.
Mate
188.00
14.00 nos.
Mazdoor working with HMP, mechanical broom,
146.00
paver, roller, asphalt cutter and assistance for
setting out lines, levels and layout of construction.
5.00
nos.
25.00 %

193.40
3168.92

nos.

(B)
12.00
2.20
6.00
6.00
6.00
3.90

15525.00
0.00
1090.00
1550.00
1320.00
540.00

hr
hr
hr
hr
hr
hr

1550.00

hr

3.90

Mazdoor skilled
Extra for Corporation Area Allowance on Rs.
Total
Machinery
hr
Hot Mix Plant 40 to 60 TPH
hr
Air Compressor 250 cfm
hr
Mechanical Paver finisher 100 TPH
hr
Generator 250 KVA
hr
Front end loader 1 cum bucket capacity
hr
Smooth wheeled roller 8-10 tonnes for initial break
down rolling

nos.
nos.

hr

Vibratory roller 8 tonnes for intermediate rolling

Quantity
3.90
hr

(C)
19.13

86.16

80.43

Description of Item
Finish rolling with 6-8 tonnes smooth wheeled
tandem roller.

Total
Material
MT
Bitumen 60/70 @ 4.25 % of weight of mix
ii)
Aggregate
Total weight of mix = 450 tonnes
weight of bitumen - 19.13 tonnes
Weight of aggregate = 450-19.13 = 430.87 tonnes
Taking density of aggregate = 1.5 tonne/cum
Volume of aggregate = 287.25 cum
Grading - II (19 mm nominal size)
116.04 Cum of 25-10mm @ 40%
cum
IRC &MORT&H HBG M/C chips 25 to 10mm @
30%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 25-27mm, 19-22mm, 12-14mm, 9.511.2mm
cum

IRC &MORT&H HBG M/C chips 10 to 5mm @


28%

Rate
1320.00

42923.15

per
hr

MT

1410.99

cum

1115.68

cum

721.77

cum

654.10

cum

Average rate of IRC&MoRT&H HBG M/C metal


of sizes 9.5-11.2mm, 5 to 7mm
114.90

cum

IRC &MORT&H HBG M/C chips 5mm and


below @ 40%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 2.36 to 5mm and 2.36mm& below

8.62

Filler @ 2% of weight of aggregates.


Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00
%
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 195 cum (E) + (F)
Rate per 1 cum
Rate to be adopted

cum

Providing 25 mm thick compacted Semi-Dense Bituminous Concrete by hot mix plant using hard blasted
granite crushed aggregates of Grading -2 as per table 500-15 of specification 508 of MoRT&H (4 th Revision),
premixed with bituminous binder 60/70 grade @ 5% of mix and filler, transporting the hot mix to work site,
laying with mechanical paver finisher to the required grade, level and alignment, rolling with smooth
wheeled,vibratory and tandem rollers to achieve the desired compaction as per MoRT&H Specification 508 (4 th
Revision) complete for finished item of work in all respects as directed by Engineer-in-charge.(Payment will be
made based on levels for finished item of work)

Unit = cum
Taking output = 195 cum (450 tonnes.)
(A) Labour
0.84
nos.
Mate

Page 135,136,137 of MoRT&H SDB

188.00

day

Quantity
14.00 nos.

5.00
nos.
25.00 %

Description of Item
Mazdoor working with HMP, Mechanical broom,
paver, roller, asphalt cutter and assistance for
setting outlines, levels and layout of construction.

Skilled Mazdoor for checking line and levels.


Extra for Corporation Area Allowance on Rs.
Total
(B) Machinary
Hot mix plant 40 to 60 TPH
11.00 hr
6.00
hr
Mechanical Paver finisher @ 100 TPH
Generator 250 KVA
6.00
hr
Front end loader 1 cum capacity
6.00
hr
Power road roller 8 tonne for initial break down
3.90
hr
rolling
3.90
hr
Vibratory roler 8 tonne for intermediate rolling
Finish rolling with 6-8 tonne smooth wheeled
3.90
hr
tandem roller.
Total

Rate
146.00

per
day

193.40
3168.92

day

15525.00
1090.00
1550.00
1320.00
540.00
1550.00
1320.00

hr
hr
hr
hr
hr
hr
hr

Quantity
Description of Item
(C) Material
22.50 M.T
(I) Bitumen 60/70 @ 5% by weight of mix
(ii) Aggregate
For Grading II
IRC &MORT&H HBG M/C chips 9.5 to 4.75mm
162.450 cum
@ 57%

Rate

per

42923.15

MT

1006.93

cum

721.77

cum

654.10

cum

Average rate of IRC&MoRT&H HBG M/C metal


of sizes 9.5-11.2, 5-7mm,2.36 - 5mm
116.850 cum

IRC &MORT&H HBG M/C chips 4.75 mm and


below @ 41%
Average rate of IRC&MoRT&H HBG M/C metal
of sizes 2.36 - 5mm and 2.36mm& below

5.70

cum

Filler @ 2% of weight of aggregates.


Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00
%
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 195 cum (E) + (F)
Rate per 1 cum
Rate to be adopted

23 Construction of Gravel shoulders including cost, seigniorage charges and conveyance of all materials to work
site and spreading in uniform layers by approved means, on prepared surface and compacting with vibratory
roller to achieve the desired density at OMC etc., complete for finished item of work as per MoRT&H
Specification 401& 407 (4th revision) and as directed by the Engineer-in-charge.
( Payment will be made based on levels for finished item of work ).

Unit = cum
Taking output = 300 cum
(A) Labour
0.40 day
Mate
2.00 day
Mazdoor skilled
8.00 day
Mazdoor unskilled
20.00 %
Extra for Municipal Area Allowance on Rs.
Total
(B) Machinery
6.00 hr
Vibratory roller 8T
3.00 hr
Water tanker 6 KL
Total
(C) Material
384.00 cum
Gravel
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 300 cum (E) + (F)
Rate per 1 cum
Rate to be adopted

188.00
193.40
146.00
1630.00

day
day
day

1550.00
345.00

hr
hr

284.00

Quantity

Description of Item

Rate

per

25 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for base coarse below CC
Pavement.

(A)
0.64
1.00
15.00
20.00
(B)
13.50
6.75
3.45

6.00
6.00
2.00
(D)
6.00
(E)
(F)

Unit = cum
Taking output = 15 cum
Page331of MoRT&H SDB
Labour
nos
Mate
nos
Mason
nos
Mazdoor
%
Extra for Municipal Area Allowance on Rs.
Total
Material
cum
Cost of 40mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
hr
Generator set 35 KVA
hr
Water tanker 6 KL
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E) + (F)
Rate for 1 cum
Rate to be adopted

188.00
193.40
146.00
2503.72

day
day
day

1121.93
540.80
4500.00

cum
cum
MT

345.00
620.00
345.00

hr
hr
hr

Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc.,
complete including seignioarge charges for finished item of work as per MoRT&H specification 304(4 th
Revision) and as directed by the Engineer-in-Charge
Unit : Cum
Taking out put = 240 Cum
(A) Labour
0.32 day
8.00 day
25.00 %

Page 323 of MoRT&H SDB

Mate

188.00

day

Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

146.00
1228.16

day

(B) Machinery
240.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005

13.00

cum

(C) Seigniorage charges


240.00 Cum
Seigniorage charges

20.00

cum

Quantity
Description of Item
(D) Over head charges @6% (10%-VAT) on (A) + (B)+( C)
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 240 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

Rate

per

30 Providing first class bedding with Granular material below the pipes of Hume pipe culverts suitably compacted
/ rammed including cost, seigniorage and conveyance of materials to site etc., complete as per drawing and
MoRT&H Specification 2900 ( 4th Revision) and as directed by the Engineer-in-Charge.
Unit = cum
Page 462 of MoRT&H SDB
Taking output = 10 cum
(A)
0.28
7.00
20.00

Labour
nos
nos
%

Mate
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
12.00 cum
Cost of Granular material
Total
Machinery
2.50 hr
Plate compactor/Power rammer
0.05 hr
Water tanker 6 KL capacity
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

188.00
146.00
1074.64

day
day

284.00

cum

40.00
345.00

hr
hr

10 Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge for Base course (Bed) of C.C.
Drains
Unit = cum
Page 331 of MoRT&H SDB
Taking output = 15 cum
(A)
0.64
1.00
15.00
25.00

Labour
nos
nos
nos
%

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
13.50 cum
Cost of 40mm SS-5 HBG M/C metal
6.75 cum
Sand at site

188.00
193.40
146.00
2503.72

day
day
day

1121.93
540.80

cum
cum

Quantity
3.45 MT

Rate
4500.00

per
MT

6.00
6.00
2.00

345.00
620.00
345.00

hr
hr
hr

(D)
6.00
(E)
(F)

Description of Item
Cement at site
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
hr
Generator set 35 KVA
hr
Water tanker 6 KL capacity
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

11 Providing Vibrated Cement Concrete ( 1:3:6 ) using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2200 (4th Revision) and as directed by the Engineer-in-Charge for side walls of Drains.
Unit = cum
Page331,455 of MoRT&H SDB
Taking output = 15 cum
(A)
0.64
1.00
15.00
25.00

Labour
nos
nos
nos
%

(B)
13.50
6.75
3.45

Material
cum
Cost of 40mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site
Total

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
2503.72

day
day
day

1121.93
540.80
4500.00

cum
cum
MT

Quantity
Description of Item
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
2.00 hr
Water tanker 6 KL capacity
(D)
10.00
(E)
6.00
(F)
(G)

Rate

per

345.00
620.00
345.00

hr
hr
hr

Form work
%
Form work @ 10% on (A)+(B)+( C)
43931.11
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

34 Filling in between body walls with gravel including cost ,conveyance and seigniorage of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200&2907 (4 th
Revision) and as per Drawing and technical specifications for finished item of work
Unit = cum
Page 462 of MoRT&H SDB
Taking output = 10 cum
(A)
0.28
7.00
20.00

Labour
nos
nos
%

Mate
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
12.00 cum
Cost of Gravel
Total
Machinery
2.50 hr
Plate compactor/Power rammer/road roller
0.05 hr
Water tanker 6 KL capacity
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

188.00
146.00
1074.64

day
day

284.00

cum

40.00
345.00

hr
hr

35 Providing SS Revetment 300 mm thick including cost, seigniorage charges and conveyance of materials to site
and including labour charges for packing the stones for revetment etc., complete for finished item of work as per
MoRT&H specification 2504 ( 4th revision ) and as directed by the Engineer-in-Charge for Pitching of slopes
(A)
0.04
0.35
0.75
20.00

Labour
nos
nos
nos
%

Page 522 of MoRT&H SDB


Mate
Mason
Mazdoor for laying stones, filling quarry spalls
Extra for Municipal Area Allowance on Rs.
Total

188.00
193.40
146.00
184.71

day
day
day

Quantity
Description of Item
(B) Material
1.00 cum
Cost of SS Revetment 300 mm
0.20 cum
Cost of stone spalls
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)
Rate to be adopted

Rate

per

189.60
468.85

cum
cum

36 Providing and laying filter material with Gravel underneath pitching in slopes including cost, seigniorage
charges and conveyance of materials to site including labour charges etc., complete for finished item of work as
per MoRT&H Specification 2504 (4th Revision) and as directed by the Engineer-in-Charge

0.05
0.25
1.00
20.00

1.20
(C)
6.00
(D)
(E)

Unit = cum
Page 523 of MoRT&H SDB
Taking output = 1 Cum
(A) Labour
nos
Mate
nos
Mazdoor skilled
nos
Mazdoor for laying stones, filling quarry spalls
%
Extra for Municipal Area Allowance on Rs.
Total
(B) Material
cum
Cost of gravel
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)
Rate to be adopted

188.00
193.40
146.00
203.75

day
day
day

284.00

cum

12 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4 th
Revision) for Kerbs.
Unit = cum
Page 335 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75

Material
cum
cum
cum
cum

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site

1121.93
1553.18
1196.93
540.80

cum
cum
cum
cum

Quantity
4.13 MT

Description of Item
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
4.00
(E)
6.00
(F)
(G)

Rate
4500.00

per
MT

345.00
620.00

hr
hr

Form work
%
Form work @ 4% on (A)+(B)+( C)
49234.00
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

38 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine mixing,
laying in position,Compacting, Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision) for Sub
structure .
Unit = cum
Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75
4.13

Material
cum
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
10.00
(E)
6.00
(F)
(G)

188.00
193.40
146.00
3371.78

day
day
day

1121.93
1553.18
1196.93
540.80
4500.00

cum
cum
cum
cum
MT

345.00
620.00

hr
hr

Form work
%
Form work @ 10% on (A)+(B)+( C)
49065.41
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

Quantity
Description of Item
Rate
per
39 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed by the Engineer-in-Charge for
Bed blocks & Backing walls
Unit = cum
Page 472,457 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
5.12

Material
cum
cum
cum
MT

6.00
6.00
(D)
10.00
(E)
6.00
(F)
(G)

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 10% on (A)+(B)+( C)
55570.72
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

cum
cum
MT

hr
hr

Cum

40 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished
item as per MoRT&H specification 1500,1600,1700 & 2200 (4 th revision ) and as directed by the Engineer-inCharge for Deck slab
Unit = cum
Page 472 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B) Material

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

Quantity
8.10 cum
5.40 cum
6.75 cum
5.12 MT

6.00
6.00
(D)
20.00
(E)
6.00
(F)
(G)

Description of Item
Rate
1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 20% on (A)+(B)+( C)
55570.72
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

per
cum
cum
MT

hr
hr

Cum

41 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per drawing BD/1-69( A) but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-Charge for wearing
coat over Deck slab.
Unit = cum
Page 477,492 of MoRT&H SDB
Taking output = 15 cum
(A)
0.90
1.50
21.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.10

Material
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

188.00
193.40
146.00
3525.30

day
day
day

Cost of 20mm SS-5 HBG M/C metal


Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA

1553.18
1196.93
540.80
4500.00

cum
cum
cum
MT

345.00
620.00

hr
hr

2.25
(D)
6.00
(E)
(F)

146.00

day

nos
Labour for cleaning deck slab concrete
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)

Quantity

Description of Item
Rate for 1 cum M 30 Concrete
Rate to be adopted

Rate

per

42 Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the Engineer-in-Charge for
Approach slab.
Unit = cum
Page 340,501 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.05

Material
cum
cum
cum
MT

6.00
6.00
(D)
2.00
(E)
6.00
(F)
(G)

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 2% on (A)+(B)+( C)
59755.72
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum M 25 Concrete
Rate to be adopted

cum
cum
cum
MT

hr
hr

Cum

43 Construction of precast VRCC railing of M20 grade using HBG crushed stone aggregate of size not exceeding
12 mm and fine aggregate conforming to table 1000-2 true to line and grade, tolerance of vertical RCC post not
to exceed 1 in 500, centre to centre spacing between vertical posts not to exceed 2000mm, leaving adequate
space between vertical posts for expansion including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as directed during execution but excluding cost
of steel and its fabrication charges as per approved drawings and technical specifications for finished item of
work as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)

Unit = 1 RM
Page 472,497 of MoRT&H SDB
Hand rails without foot paths
Material

Quantity

(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
5.12

Material
cum
cum
cum
MT

6.00
6.00
(D)
12.00
(E)
6.00
(F)
(G)

0.3881

Description of Item
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.77 =
Internal vertical posts = 3x0.18x0.20x0.77 =
hand rail in2 tier =6.74-(2x0.3+3x0.18)=5.60 RM
quantity of RCC = 2x5.60x0.115x0.165 =
Total Concrete =
VRCC M 20 Grade

per
0.0924
0.0832
0.2125
0.3881

188.00
193.40
146.00
3371.78

day
day
day

1359.43
Cost of 12mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 12% on (A)+(B)+( C)
54001.34
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Cost of Railing for one side
Cum
Cost per
6.74 RM =
4701.43
Cost per 1 RM =
Rate to be adopted

cum

0.6776 Cum

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Rate

Hand rails without foot paths (Output =12.719 RM)


Material
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.77 =
Internal vertical posts = 6x0.18x0.20x0.77 =
hand rail in2 tier =12.719-(2x0.3+6x0.18)=11.04 RM
quantity of RCC = 2x11.04x0.115x0.165 =
Total Concrete =
Cost of Railing for one side
Cost per
12.719 RM =
4701.43
Cost per 1 RM =
Rate to be adopted

cum
MT

hr
hr

Cum

cum

0.0924
0.1663
0.4189
0.6776
cum

Quantity
Description of Item
Rate
per
44 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100,2700 (4 th
Revision) for levelling course
Unit = cum
Page 335,500 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
20.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75
4.13

Material
cum
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 33 KVA
(D)
6.00
(E)
(F)

188.00
193.40
146.00
3371.78

day
day
day

1121.93
1553.18
1196.93
540.80
4500.00

cum
cum
cum
cum
MT

345.00
620.00

hr
hr

Over head charges @ 6% (10%-VAT)


Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

45 Providing Grouted Revetment with rough stone (HBG) of not less than 300 mm size grouted with 0.20 cum of
CC (1:4:8) including cost, seigniorage charges and conveyance of materials to site and including labour charges
for packing the stones for revetment etc., complete for finished item of work as per MoRT&H specification
2504 ( 4th revision ) and as directed by the Engineer-in-Charge for quadrential revetment.
Cost of CC(1:4:8)
Page 331,522 of MoRT&H SDB
Taking output = 15 cum
(A)
0.64
1.00
15.00
20.00
(B)
13.50
6.75
2.43

Labour
nos
nos
nos
%

Mate
Mason
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

Material
cum
Cost of 40mm SS-5 HBG M/C metal
cum
Sand at site
MT
Cement at site
Total

188.00
193.40
146.00
2503.72

day
day
day

1121.93
540.80
4500.00

cum
cum
MT

Quantity
Description of Item
Machinery
6.00
hr
Concrete mixer 0.4/0.28 cum
6.00
hr
Generator set 33 KVA
2.00
hr
Water tanker 6 KL capacity
Total
Cost per 15 cum
Rate for 1 cum
Cost of Grouted Revetment
Unit = Cum
Taking output = 1 cum
(A) Labour
0.04 nos
Mate
0.35 nos
Mason
0.75 nos
Mazdoor for laying stones, filling quarry spalls
20.00 %
Extra for Municipal Area Allowance on Rs.
Total
(B) Material
0.20 cum
Cost of CC(1:4:8)
1.00 cum
Cost of Rough stone HBG 300mm thick
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Cost per 1 cum (D)+(E)
Rate to be adopted

Rate

per

345.00
620.00
345.00

hr
hr
hr

188.00
193.40
146.00
184.71

day
day
day

2614.39
189.60

cum
cum

46 Back filling behind Abutments with gravel including cost ,conveyance and seigniorage of all materials to site
etc., complete as per Clause 710.1.4 of IRC : 78and as per MoRT&H Specification No. 2200 (4 th Revision)
and as per Drawing and technical specifications for finished item of work
Unit = cum
Page 462 of MoRT&H SDB
Taking output = 10 cum
(A)
0.28
7.00
20.00

Labour
nos
nos
%

Mate
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
12.00 cum
Cost of Granular material
Total
Machinery
2.50 hr
Plate compactor/Power rammer/road roller
0.05 hr
Water tanker 6 KL capacity
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum

188.00
146.00
1074.64

day
day

284.00

cum

40.00
345.00

hr
hr

Quantity

Description of Item
Rate to be adopted

Rate

per

47 Providing and laying of filter media using 50% of 150 mm IRC soling stone and 50 % of 40 mm HBG metal
satisfying the requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness of not less
than 600mm with smaller size towards the soil and bigger size towards the wall and provided over the entire
surface behind the abutment, wing wall and return wall to the full height compacted to a firm condition
including cost and conveyance of all metal seignorage charges ,and all labour charges as directed by the
departmental officers as per drawing and Technical specifications as per clause 710.1.1 of IRC:78 and Clause
2200 of MoRT&H (4th Revision) for finished item of work.

Unit = cum
Page 463 of MoRT&H SDB
Taking output = 10 cum
(A)
0.32
7.00
1.00
20.00

Labour
nos
nos
nos
%

Mate
Mazdoor for filling watering, ramming etc
Mazdoor skilled
Extra for Municipal Area Allowance on Rs.
Total

188.00
146.00
193.40
1275.56

day
day
day

581.10
999.10

cum
cum

345.00

hr

(B) Material

6.00
6.00

0.06
(D)
6.00
(E)
(F)

Filter media of stone aggregate conforming


to clause 2504.2.2 of MoRT&H
cum
Cost of 150mm size IRC soling stone (HBG)
cum
Cost of 40mm size IRC HBG metal
Total
Machinery
hr
Water tanker 6 KL capacity
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

48 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.

Unit = MT
Page 489,490 of MoRT&H SDB
Taking output = 1 MT
(A)
0.44
3.00
8.00
20.00

Labour
nos
nos
nos
%

Mate
Black smith
Mazdoor
Extra for Municipal Area Allowance on Rs.

188.00
188.00
146.00
1814.72

day
day
day

Quantity

Description of Item

Rate

per

45000.00
38500.00

MT
MT

Total
(B) Material
1.05 MT
HYSD bars including overlaps
8.00 Kg
Binding wire
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.

Unit = MT
Page 459,460 of MoRT&H SDB
Taking output = 1 MT
(A)
0.34
2.00
6.50
25.00

Labour
nos
nos
nos
%

Mate
Black smith
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
1.05 MT
HYSD bars including overlaps
6.00 Kg
Binding wire
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

188.00
188.00
146.00
1388.92

day
day
day

45000.00
38500.00

MT
MT

50 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for foundations of R.C.C items.

Unit = MT
Page 448 of MoRT&H SDB
Taking output = 1 MT
(A) Labour

Quantity
0.40 nos
2.00 nos
6.00 nos
20.00 %

Description of Item
Mate
Black smith
Mazdoor
Extra for Municipal Area Allowance on Rs.
Total

(B) Material
1.05 MT
HYSD bars including overlaps
6.00 Kg
Binding wire
Total
(C) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
6.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

Rate
188.00
188.00
146.00
1327.20

per
day
day
day

45000.00
38500.00

MT
MT

15 Vibrated reinforced cement concrete M 20 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P as per approved drawings and as
directed during execution but excluding cost of steel and its fabrication charges for finished item as per
MoRT&H specification 1500,1600,1700 & 2200 (4th revision ) and as directed by the Engineer-in-Charge for
Cover slabs over side drains

(A)
0.86
1.50
20.00
25.00
(B)
8.10
5.40
6.75
5.12

6.00
6.00
(D)
4.00
(E)
6.00
(F)
(G)

Unit = cum
Taking output = 15 cum
Page 472,457 of MoRT&H SDB
Labour
nos
Mate
188.00
nos
Mason
193.40
nos
Mazdoor
146.00
%
Extra for Corporation Area Allowance on Rs.
3371.78
Total
Material
cum
1553.18
Cost of 20mm SS-5 HBG M/C metal
cum
1196.93
Cost of 10mm SS-5 HBG M/C metal
cum
Sand at site
540.80
MT
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 4% on (A)+(B)+( C)
55739.31
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

day
day
day

cum
cum
cum
MT

hr
hr

Quantity
Description of Item
Rate
per
16 Plastering in CM (1:5) 12 mm thick including cost and conveyance of all materials, seigniorage charges, labour
charges, curing etc complete for finished item of work as directed by the Engineer -in-Charge
Unit = 10 sqm
Taking output = 10 sqm
Page 452 & 333 of MoRT&H SDB
(A) Labour
0.04
day
Mate
0.50
day
Mason
0.50
day
Mazdoor
25.00 %
Extra for Corporation Area Allowance on Rs.
(B)
0.144
(C)
6.00
(D)

Material
Cum
Cement Mortar (1:5)
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)

188.00
193.40
146.00
177.22

day
day
day

2104.99

Cum

524.65

Quantity
Description of Item
(E) Add Contractors Profit at 10% on (D)
Cost per 10 sqm (D)+(E)
Cost per 1 sqm
Or say

0.303
1.05

MT
cum

0.04
day
0.90
day
25.00 %

Sub-Analysis
Cement Mortar (1:5)
(a) Material
Cement
Sand for Mortar

4500.00
540.80

(b) Labour
Mate
Mazdoor
Extra for MAA on

188.00
146.00
138.92

Rate
556.13

MT
cum

per

1363.50
567.84
1931.34

7.52
131.40
34.73
173.65
Rate per cum
2104.99
56 Painting two coats after filling the surface with synthetic enamel paint in all shades on new plastered concrete
surfaces
Unit = 1 sqm
Taking output = 40 sqm

Page 220 of MoRT&H SDB

(A)
0.12
2.00
1.00
20.00

Labour
day
day
day
%

(B)
6.00
(C)
6.00
(D)
(E)

Material
Litres
Paint Confirming to requirement of clause 803.3
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost per 40 sqm (D)+(E)
Rate for 1 Sqm
Or say

Mate
Painter
Mazdoor
Extra for Municipal Area Allowance on Rs.

188.00
193.40
146.00
555.36

day
day
day

146.50

Lit

1545.43

X Cost and supply of Mastic pads 20mm thick ilncluding cost and conveyance of mastic pads to the required soze
amd fixing in position etc., complete as directed by the Engineer-in-charge.
Cost as per SSR for 25.40 mm thick Mastic pad

609.80 1 Sqm

Cost as per SSR for 12.70 mm thick Mastic pad

349.00 1 Sqm

Difference in cost of 12.70mm & 25.40mm thick

260.80 1 Sqm

Now required 20mm thick Mastic Pad


Cost of 12.70mm thick difference

260.80 1 Sqm

Difference between 25.40 mm - 20 mm thick :


5.40mm thick : 226.80 / 12.70 x 5.40 =

110.89 / Sqm.

Quantity
Description of Item
Proportional cost of 20mm thick Mastic Pad :

Rate

per

(Cost of 25.40mm thick - difference 5.40mm thick)


= Rs.530.30 - 96.43 =
Rate to be adopted

498.91 1 Sqm.

X Supply and fixing cap to reinforcement with PVC Pipe of 25.40mm dia as per technical specifications and as
directed by the Engineer-in-charge.
1.00 RM

30.70

PVC Pipe 25.40mm dia


Rate to be adopted

1 RM

X Dismantling of existing structure comprising of Cement Concrete including T&P and scaffolding wherever
necessary, sorting the dismantled material, disposal of unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by the Engineerin-Charge.
Unit = cum
(A)
Labour
0.04
day
1.00
day
20.00 %
(B)
0.27
(C)
6.00
(D)
(E)

Taking output = 1.25 cum

MoRT&H SDB Spec. No.202 : 2.4 (i) A (Pg.24)

Mate
Mazdoor for dismantling and loading
Extra for Municipal Area Allowance on Rs.
Total
Machinery
hr
Tractor-trolley
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Or say

188.00
146.00
153.52

day
day

345.00

hr

277.37

X Dismantling of existing structure comprising of Reinforced Cement Concrete including T&P and scaffolding
wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by the
Engineer-in-Charge.
Unit = cum
(A)
Labour
0.15
day
0.25
day
3.50
day
20.00 %
(B)
0.27
(C)
6.00
(D)

Taking output = 1.25 cum

MoRT&H SDB Spec. No.202 : 2.4 (i) C (Pg.25)

Mate
Blacksmith
Mazdoor for dismantling, loading and unloading
Extra for Municipal Area Allowance on Rs.
Total
Machinery
hr
Tractor-trolley
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)

188.00
188.00
146.00
586.20

day
day
day

345.00

hr

796.59

Quantity
Description of Item
(E)
Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Or say

Rate

per

X Dismantling of existing structure comprising of Brick masonry in Cement Mortar including T&P and
scaffolding wherever necessary, sorting the dismantled material, disposal of unserviceable material and stacking
the serviceable material with all lifts and lead of 1000 metres as per MoRT&H Spec. No.202 and as directed by
the Engineer-in-Charge.
Unit = cum
(A)
Labour
0.03
day
0.75
day
20.00 %
(B)
0.27
(C)
6.00
(D)
(E)

Taking output = 1.25 cum

MoRT&H SDB Spec. No.202 : 2.4 (ii) B (Pg.27)

Mate
Mazdoor for dismantling, loading and unloading
Extra for Municipal Area Allowance on Rs.
Total
Machinery
hr
Tractor-trolley
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost for 1.25 cum
Rate per 1 cum
Or say

188.00
146.00
115.14

day
day

345.00

hr

231.32

No.11 on Brahmarshi
orm Centre in
n Kakinada Port
Amount

osal of scarified material

1.88
36.50
7.68
46.06
27.60
264.00
132.25
423.85
28.19
49.81
547.91
5.48
5.50
1 Sqm

one aggregate and fine


ance of all materials to
ding all other incidental
MoRT&H specification
base coarse below CC

120.32
193.40
2190.00
625.93
3129.65
15146.06
3650.40
10935.00
29731.46
2070.00
3720.00
690.00

Amount
6480.00
2360.47
41701.58
4170.16
45871.74
3058.12
3060.00
1 Cum

egate (Coarse aggregate


uding cost, seigniorage
g, vibrating, curing etc.,
hed item of work as per
the Engineer-in-Charge

161.68
290.10
2920.00
842.95
4214.73

12580.76
6463.42
3650.4
28485
51179.58
2070.00
3720.00
5790.00
2141.45
3799.55
67125.31
6712.53
73837.84
4922.52
4920.00
1 Cum

up bars of all diameters


reinforcement including
ete including cost and
including over lapping
andard drawings, as per
0 (4 th revision) and as

Amount

Amount
52.64
282.00
803.00
284.41
1422.05
47040.00
231.00
47271.00
2921.58
51614.63
5161.46
56776.09
56780.00
1 MT

lass for pipe culverts


jointing of 300mm dia.
per drawing and as per
lication No: 13 and as

26.32
96.70
438.00
140.26
701.28
9337.50
9337.50
602.33
10641.11
1064.11
11705.22
936.42
940.00
1 RM

s to site and watering,


(4 th Revision) and as

1.88
43.80
11.42

Amount
57.10

Amount
510.96
34.08
602.14
60.21
662.35
660.00
1 cum

tic pads to the required


805.00
1 Sqm

al specifications and as
30.70
1 RM

llowed by placement of
water in the Concrete,
ting using power floater
of pin vibration of the
ing hire and operational
ations etc. complete

40.00
1 Sqm

owered saw of suitable


crete in the longitudinal
of consumables such as
he rate and pouring of
of the groove after the
ry surface and surface
ve a neat finished look
city and other T&P and

60.00
1 RM

Engineer (R&B),

Amount
vision : Kakinada

atering of soil , removal


g soil, breaking clods,
MC to meet requirement
nd seigniorage charges,
(Payment will be made

Amount

3.76
73.00
15.35
92.11
1300.00
2600.00
1380.00
1550.00
6830.00
2000.00

535.33
9457.44
945.74
10403.18
104.03
104.00
1 Cum
anical means upto SDR
l, excavation of soils at
ng soil, breaking clods,
MC to meet requirement
nd seigniorage charges,
(Payment will be made

7.52
146.00
38.38
191.90
1300.00
720.00
72.00
1380.00
2600.00
1380.00
1550.00

Amount
9002.00

2000.00
671.63
11865.53
1186.55
13052.09
130.52
131.00
1 Cum
ttom and side slopes in
ing seignioarge charges
ion) and as directed by

15.04
292.00
76.76
383.80
2340.00
3600.00

379.43
6703.23
670.32
7373.55
40.96
41.00
1 Cum
ans including trimming
ns etc., and loading and
item of work as per

15.04
292.00
76.76
383.80
4680.00
9407.00
14087.00

Amount
7200.00
1300.25
22971.05
2297.11
25268.16
70.19
70.20
1 Cum

- III of MoRT&H Table


nd spreading in uniform
x in place method with
the desired density etc.,
) and as directed by the

75.20
386.80
1168.00
407.50
2037.50
15600.00
4140.00
9300.00
1035.00
30075.00

256767.15
84378.90
341146.05

22395.51
395654.06
39565.41
435219.47
1450.73
1450.00
1 Cum
uding all labour charges
rk.

Amount

37.60
730.00
-85.00
136.52
819.12

49.15
868.27
86.83
955.10
9.55
9.60
1 Sqm
ates of Grade - II - IRC
per Table 400-7&9 of
luding cost, conveyance
h Power Road Roller 8' A ' screenings as per
ering and compacting to
evision) and as directed
ork)

1895.04
386.80
36500.00
7756.37
46538.21
6480.00
8280.00
14760.00
187111.98
200199.66
27056.40
64263.17
18838.08
497469.29
33526.05
592293.55
59229.36

Amount
651522.91
1809.79
1810.00
Cum
ates of Grade - III - IRC
per Table 400-7& 9 of
luding cost, conveyance
h Power Road Roller 8' B ' screenings as per
ring and compacting to
evision) and as directed
ork)

1895.04
386.80
36500.00
7756.37
46538.21
6480.00
8280.00
14760.00
356868.53
121784.84
62360.50

18838.08
559851.95
37269.01
658419.17
65841.92
724261.09
2011.84
2012.00
Cum

Amount

to Wet Mix macadem


erial with water at OMC
m layers with paver in
the desired density etc.,
on) for finished item of

90.24
386.80
1460.00
484.26
2421.30
8712.00
6540.00
7920.00
6540.00
6045.00
1035.00
36792.00
125023.34
140977.58

58280.31
324281.23

21809.67
385304.20
38530.42
423834.62
1883.71
1880.00
Cum
G machine crushed stone
kg / sqm including cost,
nd rolling with 8-10 T
ation 510 (4 th Revision)

82.72
1314.00
386.80
356.70

Amount
2140.22
2088.00
2664.00
12420.00
2982.00

7920.00
5640.00
3240.00
36954.00
283305.47
37239.48
320544.95
21578.35
381217.52
38121.75
419339.27
46.59
46.60
1 Sqm

G machine crushed stone


kg / sqm including cost,
nd rolling with 8-10 T
ation 510 (4 th Revision)

82.72
1314.00
386.80
445.88
2229.40
2088.00
2664.00
12420.00
3450.00

7920.00
5640.00
3240.00
37422.00

Amount
283305.47
37239.48
320544.95

21611.78
381808.13
38180.81
419988.94
46.67
46.70
1 Sqm
re distributor at the rate
ical broom for finished
ineer-in-Charge.

15.04
292.00
76.76
383.80
812.00
1036.00
1380.00
3228.00
26732.18
26732.18
1820.64
32164.62
3216.46
35381.08
10.11
10.10
1 Sqm

Amount
20 mm thickness by hot
B') as per table 500-26
0 grade @ 19 Kg per 10
o work site, laying with
h wheeled roller 8 to 10
work in all respects as

157.92
2044.00

967.00
633.78
3802.70
186300.00
9300.00
7920.00
6540.00
3240.00
213300.00
836142.96

278649.61

1114792.57
79913.72
1411808.99
141180.90
1552989.89
151.51
152.00
1 sqm

Amount
ucing an average output
I as per table 500-4 of
0/70 grade @ 3.3% by
with mechanical paver
nd 501.7 to achieve the
rge including hire and
ng cost of seigniorage
ision) .

157.92
2044.00

967.00
792.23
3961.15
186300.00
814.00
6540.00
9300.00
7920.00
2106.00
6045.00
5148.00
224173.00
637408.78

163731.28

Amount
129463.51

41877.10

972480.67
72036.89
1272651.71
127265.17
1399916.88
6828.86
6830.00
1 Cum

ucing an average output


I as per table 500-4 of
ade @ 4.50% by weight
cal paver finisher to the
the desired compaction
ational charges all T&P
materials etc., complete

157.92
2044.00

967.00
792.23
3961.15
186300.00
6540.00
9300.00
7920.00
2106.00
6045.00

Amount
5148.00
223359.00
821119.86

121570.90

89734.14

82931.37

5638.34
1120994.61
80898.89
1429213.65
142921.37
1572135.02
8062.23
8060.00
1 Cum

ant using hard blasted


MoRT&H (4 th Revision),
e hot mix to work site,
t, rolling with smooth
H Specification 508 (4 th
charge.(Payment will be

157.92

Amount
2044.00

967.00
792.23
3961.15
170775.00
6540.00
9300.00
7920.00
2106.00
6045.00
5148.00
207834.00

Amount
965770.88

163575.78

84338.82

3728.37
1217413.85
85752.54
1514961.54
151496.15
1666457.69
8545.94
8550.00
1 Cum

of all materials to work


mpacting with vibratory
work as per MoRT&H

75.20
386.80
1168.00
326.00
1956.00
9300.00
1035.00
10335.00
109056.00
7280.82
128627.82
12862.78
141490.60
471.64
472.00

Amount
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
base coarse below CC

120.32
193.40
2190.00
500.74
3004.46
15146.06
3650.40
15525.00
34321.46
2070.00
3720.00
690.00
6480.00

2628.36
46434.28
4643.43
51077.71
3405.18
3405.00
1 Cum
ures as per drawing and
val of stumps and other
e extent required etc.,
H specification 304(4 th

60.16
1168.00
307.04
1535.20
3120.00
4800.00

Amount
567.31
10022.51
1002.25
11024.76
45.94
46.00
1 Cum
erts suitably compacted
ete as per drawing and

52.64
1022.00
214.93
1289.57

3408.00
3408.00
100.00
17.25
117.25

288.89
5103.71
510.37
5614.08
561.41
561.00
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
e course (Bed) of C.C.

120.32
193.40
2190.00
625.93
3129.65
15146.06
3650.40

Amount
15525.00
34321.46
2070.00
3720.00
690.00
6480.00

2635.87
46566.98
4656.70
51223.68
3414.91
3410.00
1 Cum
one aggregate and fine
ance of all materials to
ding all other incidental
MoRT&H specification
s of Drains.

120.32
193.40
2190.00
625.93
3129.65
15146.06
3650.40
15525.00
34321.46

Amount
2070.00
3720.00
690.00
6480.00
4393.11

2899.45
51223.67
5122.37
56346.04
3756.40
3760.00
1 Cum
e of all materials to site
on No. 2200&2907 (4 th

52.64
1022.00
214.93
1289.57
3408.00
3408.00
100.00
17.25
117.25

288.89
5103.71
510.37
5614.08
561.41
561.00
1 Cum
ance of materials to site
hed item of work as per
or Pitching of slopes

7.52
67.69
109.50
36.94
221.65

Amount
189.60
93.77
283.37

30.30
535.32
53.53
588.85
589.00
1 Cum
uding cost, seigniorage
inished item of work as
ge

9.40
48.35
146.00
40.75
244.50
340.80

35.12
620.42
62.04
682.46
682.00
1 Cum
ze HBG crushed stone
ming to table 1000-2)
r charges for machine
ncidental and all other
n 1500,1700, 2100 (4 th

161.68
290.10
2920.00
842.95
4214.73
9087.63
6290.38
1615.86
3650.40

Amount
18585.00
39229.27
2070.00
3720.00
5790.00
1969.36

3072.20
54275.56
5427.56
59703.12
3980.21
3980.00
1 Cum
ze HBG crushed stone
ming to table 1000-2)
es for machine mixing,
nd all other operational
0 (4 th Revision) for Sub

161.68
290.10
2920.00
674.36
4046.14
9087.63
6290.38
1615.86
3650.40
18585.00
39229.27
2070.00
3720.00
5790.00
4906.54
3238.32
57210.27
5721.03
62931.30
4195.42
4195.00
1 Cum

Amount
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
proved drawings and as
or finished item as per
Engineer-in-Charge for

161.68
290.10
2920.00
674.36
4046.14
12580.76
6463.42
3650.40
23040.00
45734.58
2070.00
3720.00
5790.00
5557.07

3667.67
64795.46
6479.55
71275.01
4751.67
4752.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
mplete as per approved
on charges for finished
cted by the Engineer-in-

161.68
290.10
2920.00
674.36
4046.14

Amount
12580.76
6463.42
3650.40
23040.00
45734.58
2070.00
3720.00
5790.00
11114.14

4001.09
70685.95
7068.60
77754.55
5183.64
5184.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
r-in-Charge for wearing

169.20
290.10
3066.00
705.06
4230.36

12580.76
6463.42
3650.40
27450.00
50144.58
2070.00
3720.00
5790.00
328.50
3629.61
64123.05
6412.31
70535.36

Amount
4702.36
4702.00
1 Cum
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
Engineer-in-Charge for

161.68
290.10
2920.00
674.36
4046.14

12580.76
6463.42
3650.40
27225.00
49919.58
2070.00
3720.00
5790.00
1195.11

3657.05
64607.88
6460.79
71068.67
4737.91
4738.00
1 Cum
te of size not exceeding
of vertical RCC post not
0mm, leaving adequate
all materials to site and
ther incidental hire and
ution but excluding cost
ons for finished item of

Amount
cum
cum
cum
cum

161.68
290.10
2920.00
674.36
4046.14
11011.38
6463.42
3650.40
23040.00
44165.20
2070.00
3720.00
5790.00
6480.16
3628.89
64110.39
6411.04
70521.43
4701.43
1824.62
270.72
271.00
1 RM

cum
cum
cum
cum
3185.69
250.47
250.00
1 RM

Amount
ze HBG crushed stone
rming to table 1000-2)
r charges for machine
ncidental and all other
00,1700, 2100,2700 (4 th

161.68
290.10
2920.00
674.36
4046.14
9087.63
6290.38
1615.86
3650.40
18585.00
39229.27
2070.00
3720.00
5790.00

2943.92
52009.33
5200.93
57210.26
3814.02
3814.00
1 Cum
outed with 0.20 cum of
ncluding labour charges
MoRT&H specification
t.

120.32
193.40
2190.00
500.74
3004.46
15146.06
3650.40
10935.00
29731.46

Amount
2070.00
3720.00
690.00
6480.00
39215.92
2614.39

7.52
67.69
109.50
36.94
221.65
522.88
189.60
712.48

56.05
990.18
99.02
1089.20
1089.00
1 Cum
e of all materials to site
No. 2200 (4 th Revision)

52.64
1022.00
214.93
1289.57

3408.00
3408.00
100.00
17.25
117.25
288.89
5103.71
510.37
5614.08
561.41

Amount
561.00
1 Cum
% of 40 mm HBG metal
o athickness of not less
provided over the entire
ed to a firm condition
s as directed by the
1 of IRC:78 and Clause

60.16
1022.00
193.40
255.11
1530.67

3486.60
5994.60
9481.20
20.70
20.70

661.95
11694.52
1169.45
12863.97
1286.40
1286.00
1 Cum
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

82.72
564.00
1168.00
362.94

Amount
2177.66
47250.00
308.00
47558.00

2984.14
52719.80
5271.98
57991.78
57992.00
1 MT
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

63.92
376.00
949.00
347.23
1736.15
47250.00
231.00
47481.00

2953.03
52170.18
5217.02
57387.20
57390.00
1 MT
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

Amount
75.20
376.00
876.00
265.44
1592.64
47250.00
231.00
47481.00

2944.42
52018.06
5201.81
57219.87
57220.00
1 MT
stone aggregate (Coarse
000-2) including cost,
ixing, laying, vibrating,
proved drawings and as
or finished item as per
Engineer-in-Charge for

161.68
290.10
2920.00
842.95
4214.73
12580.76
6463.42
3650.40
23040.00
45734.58
2070.00
3720.00
5790.00
2229.57
3478.13
61447.01
6144.70
67591.71
4506.11
4510.00
1 Cum

Amount
niorage charges, labour
harge

7.52
96.70
73.00
44.31
221.53
303.12
31.48
556.13

Amount
55.61
611.74
61.17
61.00
1 Sqm

new plastered concrete

22.56
386.80
146.00
111.07
666.43
879.00
92.73
1638.16
163.82
1801.98
45.05
45.00
1 Sqm

ads to the required soze

Amount

498.91
499.00
1 Sqm

al specifications and as

30.70
31.00
1 RM

d scaffolding wherever
tacking the serviceable
rected by the Engineer: 2.4 (i) A (Pg.24)
7.52
146.00
30.70
184.22
93.15
16.64
294.01
29.40
323.41
258.73
259.00
1 Cum

ng T&P and scaffolding


terial and stacking the
2 and as directed by the
: 2.4 (i) C (Pg.25)
28.20
47.00
511.00
117.24
703.44
93.15
47.80
844.39

Amount
84.44
928.83
743.06
743.00
1 Cum

ar including T&P and


le material and stacking
o.202 and as directed by
: 2.4 (ii) B (Pg.27)
5.64
109.50
23.03
138.17
93.15
13.88
245.20
24.52
269.72
215.78
216.00
1 Cum

ROAD METAL RATES


Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in Kakinada Town
limits at Railway Km 14.05 of Kakinada Town Kakinada Port Section in E.G.Dist.
Sl.
No
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26

Description of Metal
60 to 63 mm IRC and MoRTH HBG metal
50 to 55 mm IRC and MoRTH HBG metal
40 to 45 mm IRC and MoRTH HBG metal
150 mm soling stone HBG metal
40 to 45 mm IRC and MoRTH HBG M/C metal
25 to 27 mm IRC and MoRTH HBG M/C metal
19 to 22 mm IRC and MoRTH HBG M/C metal
12 to 14 mm IRC and MoRTH HBG M/C metal
9.5 to 11.20 mm IRC and MoRTH HBG M/C metal
5 to 7 mm IRC and MoRTH HBG M/C metal
2.36 to 5 mm IRC and MoRTH HBG M/C metal
HBG Stone chips 2.36mm and below
Gravel
40 mm SS-5 HBG M/C metal
25 mm SS-5 HBG M/C metal
20 mm SS-5 HBG M/C metal
12 mm SS-5 HBG M/C metal
10 mm SS-5 HBG M/C metal
6 mm SS-5 HBG M/C metal
Sand for Mortar
Sand for Filling
HYSD Steel (Fe-415)
6mm Mild Steel
Stuctural Steel
Cement
Hume pipes 300mm Dia., NP3

Source of Supply
Rayavaram
-- do --- do --- do --- do --- do --- do --- do --- do --- do --- do --- do -Km.5/100 of S-G Road
Rayavaram
-- do --- do --- do --- do --- do -Kulla
-- do --

Deduct
Lead
Initial
Machine
Blasting
Seigniorag stacking Toal Cost
in Conveyance cost less
crushing
charges
e charges charges for per Cum
Kms
stacking
charges
conveyance
50
50
50
50
50
50
50
50
50
50
50
50
21
50
50
50
50
50
50
46
46

401.50
401.50
401.50
401.50
401.50
401.50
401.50
401.50
401.50
401.50
401.50
401.50
219.00
401.50
401.50
401.50
401.50
401.50
401.50
340.80
340.80

23.00

351.30
381.30
491.30
73.30
491.30
821.30
836.30
681.30
551.30
421.30
225.30
216.30
50.50
491.30
821.30
836.30
681.30
551.30
421.30
169.50
54.50
45000.00
38500.00
44800.00
4500.00
724.00

70.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
70.00
0.00
0.00
70.00
70.00
70.00
70.00
70.00
70.00
0.00
0.00
0.00
0.00

0.00
0.00
0.00
0.00
122.83
205.33
209.08
170.33
137.83
105.33
56.33
0.00
0.00
122.83
205.33
209.08
170.33
137.83
105.33
0.00
0.00
0.00
0.00

45.00
45.00
45.00
45.00
45.00
45.00
45.00
45.00
45.00
45.00
45.00
45.00
20.00
45.00
45.00
45.00
45.00
45.00
45.00
36.00
36.00
0.00
0.00

0.00

0.00

0.00

-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-5.50
-8.70
-8.70
-8.70
-8.70
-8.70
-8.70
-5.50
-5.50

859.10
889.10
999.10
581.10
1121.93
1534.43
1553.18
1359.43
1196.93
1034.43
789.43
654.10
284.00
1121.93
1534.43
1553.18
1359.43
1196.93
1034.43
540.80
425.80

747.00

Sl.
No

Description of Metal

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Source of Supply
Dy. Executive Engineer (R&B),
(R&B) East Sub-divn., : Kakinada

Deduct
Lead
Initial
Machine
Blasting
Seigniorag stacking Toal Cost
in Conveyance cost less
crushing
charges
e charges charges for per Cum
Kms
stacking
charges
conveyance
Executive Engineer (R&B),
(R&B) Division : Kakinada

Name of the work


Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy
Form Centre in Kakinada Town limits at Railway Km 14.05 of Kakinada
Town Kakinada Port Section in E.G.Dist.

TYPICAL CROSS SECTION OF DRAIN

200MM

200MM

750 MM

V.C.C. (1:3:6)

300MM

500MM

300MM

250 MM

V.C.C. (1:3:6)

150 MM

Sand Filling
1100 MM

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the wor Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to
Dairy Form Centre in Kakinada Town limits at Railway Km 14.05 of
Kakinada Town Kakinada Port Section in E.G.Dist.
-:oOo:A) For HBG metal:
HBG metal from Rayavaram quarry
a) Cart track length =
b) Metalled road length:
From km
1 / 900
to
0 / 000
From km
0 / 000
to
6 / 800
From km
0 / 000
to
8 / 470
From km
17 / 400
to
0 / 000
From km
1 / 945
to
0 / 000
From km
12 / 830
to
0 / 000
From km
36 / 680
to
36 / 280
From km
0 / 000
to
0 / 400
Total metalled road length
d) Lead charges for ###

Yeleswaram - Jeddangi road


Yeleswaram - Yerravaram road
Yerravaram - Kirlampudi road
Samalkot - Prathipadu road
Samalkot - Uppada road
Kakinada - Rajahmundry road
Kathipudi - Pamarru road (NH.214)
Brahmarshi Road

kms lead ( including stacking charges)

B) For gravel:
Gravel quarry at Km.5/100 of S-G Road
a) Cart track length =
b) Metalled road length:
From km
/
to
/
From km
5 / 100
to
0 / 000
From km
13 / 900
to
0 / 000
From km
36 / 680
to
36 / 280
From km
0 / 000
to
0 / 400
c) Total lead
d) Lead charges for ###

of
of
of
of
of
of
of
of

of
of
of
of
of

Quarry to S-G road


Samalkota - Gokavaram road
Kakinada - Rajahmundry road
Kathipudi - Pamarru road (NH.214)
Brahmarshi Road

kms lead ( including stacking charges)

C) For Sand :
Sand from Kulla
a) Cart track length =
b) Metalled road length:
From Quarry to Alamuru - Kotipalli Road Km.17/090 (including Cart Track)
From km
0 / 000
to
4 / 200 of Kulla - Pamarru road
From km
6 / 895
to
4 / 695 of Gangavaram - Angara road
From km
8 / 400
to
0 / 000 of Draksharama - Paningapalli road
From km
23 / 935
to
25 / 200 of Dwarapudi - Yanam road
From km
28 / 000
to
1 / 000 of KANF Road
From km
37 / 680
to
36 / 280 of Kathipudi - Pamarru road (NH-214)
From km
0 / 000
to
0 / 400 of Brahmarshi Road
c) Total lead
d) Lead charges for ###

kms lead ( including stacking charges)

D) For Bitumen & Emulsion :


a) Lead from ex-factoryVisakha
b) Metalled road length:
From km
/
to
From km 382 / 400
to
261
From km
0 / 000
to
36
From km
0 / 000
to
0
c) Total lead

0.000 kms

=
=
=
=
=
=
=
=

kms
kms
kms
kms
kms
kms
kms
kms
kms
kms
cum

0.000 kms

1.900
6.800
8.470
17.400
1.945
12.830
0.400
0.400
50.145
Or say: 50.000
Rs. 401.50 /

=
1.000
=
5.100
= 13.900
=
0.400
=
0.400
= 20.800
Or say: 21.000
Rs. 219.00 /

kms
kms
kms
kms
kms
kms
kms
cum

0.000 kms

=
1.000
=
4.200
=
2.200
=
8.400
=
1.265
= 27.000
=
1.400
=
0.400
= 45.865
Or say: 46.000
Rs. 340.80 /

kms
kms
kms
kms
kms
kms
kms
kms
kms
kms
cum

to Kakinada
/
of Refinery to V-V road (NH.5)
=
1.600 kms
/ 800 of Vijayawada - Visakhapatnam road (NH.5)= 120.600 kms
/ 280 of Kathipudi - Pamarru road (NH.214)
= 36.280 kms
/ 400 of Brahmarshi Road
=
0.400 kms
= 158.880 kms

LEAD CALCULATION FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the wor Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to
Dairy Form Centre in Kakinada Town limits at Railway Km 14.05 of
Kakinada Town Kakinada Port Section in E.G.Dist.
-:oOo:Or say:
Asst. Executive Engineer (R&B),
(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

### kms

Executive Engineer (R&B),


(R&B) Division : Kakinada

QUARRY CHART FOR VARIOUS MATERIALS UPTO CENTER OF THE WORKING STRETCH
Name of the workConstruction of Road Over Bridge at Kakinada in lieu of
L.C.No.11 on Brahmarshi Street from NH 214 Junction at
Manasarovar Hotel to Dairy Form Centre in Kakinada Town limits
at Railway Km 14.05 of Kakinada Town Kakinada Port Section
in E.G.Dist.
A) HBG MATERIAL
RAYAVARAM (YELESWARAM) QUARRY
1/900

Y-J Road
0/0

0/0

Yeleswaram - Yerravaram Road


6/800

0/0

Yerravaram - Kirlampudi road


8/470

17/400

Samalkota - Prathipadu road


1/945

0/0

Samalkota - Pithapuram road

12/830

0/0

Kakinada - Rajahmundry road


0/000
36/680

A) GRAVEL

36/280

NH.214

Km.5/100 of S-G Road


5/100

Samalkota - Gokavaram road


13/900

0/0

Kakinada - Rajahmundry road


0/000
36/680

C) SAND

36/280

NH.214

KULLA (River Godavari)


0/0

Kulla - Pamarru Road


Gangavaram - Angara road

4/200
6/895

4/695

8/400

Draksharama - Paningapalli road


25/200

0/0
23/935

Dwarapudi - Yanam road

28/000

K.A.N.F. road
1/000
37/680

Asst. Executive Engineer (R&B),

36/280

NH.214

Dy. Executive Engineer (R&B),

Executive Engineer (R&B),

(R&B) East Section : Kakinada

(R&B) East Sub-divn., : Kakinada

(R&B) Division : Kakinada

Revised Cost of RCC Plain Ended pipes


The rates of RCC Plain ended pipes as per SSR 2008-09 are based on the raw materials costs.
Cement
Steel (MS Rods)

(C1)
(S1)

4,400
41,500

The revised raw materials costs i.e., the rates adopted in the estimate.
Cement
Steel (MS Rods)

(C2)
(S2)

4,500
44,800

Total quantity of Concrete required (as per IS 458 : 1988 Table 2 & 3 in Pg.7 & 8)
Dia
300 MM dia

NP3 Class pipes


Quantity per 1 RM

NP2 Class pipes


Quantity per 1 RM

NP2 Class Collars


Quantity per each

0.04274 Cum.
TTx0.340x1.000x0.040

0.03111 Cum.
TTx0.330x1.000x0.030

0.00424 Cum.
TTx0.300x0.150x0.030

Wc : Weight of Cement required (Kg.) per metre of pipe.


@ 360 Kgs. / Cum. as per IS 458 : 1988 Cl.4.5.1 Pg.3
Dia
300 MM dia

NP3 Class pipes

NP2 Class pipes

NP2 Class Collars

0.04274 x 360 Kgs


15.39 Kgs

0.03111 x 360 Kgs


11.20 Kgs

0.00424 x 360 Kgs


1.53 Kgs

Ws : Weight of MS Rods required (Kg.) per metre of pipe


(as per IS 458 : 1988 Table 2 & 3 Pg.7 & 8)
Dia

NP3 Class pipes

NP2 Class pipes

NP2 Class Collars

0.78 + 1.80
2.58 Kgs

0.78 + 0.79
1.57 Kgs

0.71 Kgs

300 MM dia

Revised Cost R1 : Variation (increase / decrease ) in cost (Rs. per metre)


due to change in the cost of M.S. Rods = (S2-S1)/1000 X Ws.
Dia
300 MM dia

NP3 Class pipes


(44,800 -41,500) /1000
x 2.58 Kgs.= Rs 8.51

NP2 Class pipes

NP2 Class Collars

(44,800 -41,500) /1000


x 1.57 Kgs.= Rs 5.18

(44,800 -41,500) /1000


x 0.71 Kgs.= Rs 2.34

Revised Cost R2 : Variation (increase / decrease ) in cost (Rs. per metre)


due to change in the cost of Cement = (C2-C1)/1000 X Wc.
Dia
300 MM dia

NP3 Class pipes

NP2 Class pipes

NP2 Class Collars

(4,500 -4,400) /1000


x15.39 Kgs.= Rs 1.54

(4,500 -4,400) /1000


x11.20 Kgs.= Rs 1.12

(4,500 -4,400) /1000


x1.53 Kgs.= Rs 0.15

NP2 Class pipes

NP2 Class Collars

Revised Cost = Cost as per the SSR + R1 + R2


Dia
300 MM dia

NP3 Class pipes


724.00

8.51
1.54
= Rs. 734.05

320.00
5.18
1.12
= Rs. 326.30

79.00

Rates of Np3 class pipes including conveyance


Dia

Lead

Lead Charges

Initial Rate

Rate per RM

2.34
0.15
= Rs. 81.49

300 MM dia

5 kms.

23.00

734.05

757.05

COST OF BITUMEN / MT
Name of Work
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy
Form Centre in Kakinada Town limits at Railway Km 14.05 of Kakinada
Town Kakinada Port Section in E.G.Dist.
Ref ::- For Bulk Bitumen 80/100, 60/70:- HPCL Price List With Effect From Dt.01.11.2008

Basic Price
Excise Duty @ 14.42%
Selling price
Add for Tax @ 4%
Fo Emulsion @ 12.5%
Depot price
Lead from
Visakhapatnam
159.00

Kms

Bulk 80/100 Gr.

Bulk 60/70 Gr.

Emulsion (MS)

Visakhapatnam

Visakhapatnam

Visakhapatnam

34,870.00

35,670.00

29,297.00

5,028.25
-----------------39,898.25

5,143.61
-----------------40,813.61

4,224.63
-----------------33,521.63

1,595.93

1,632.54

4,190.20

-----------------41,494.18

-----------------42,446.15

-----------------37,711.83

477.00

477.00

477.00

41,971.18

42,923.15

38,188.83

Lead charges for Bulk @


1.50

per KM

Asst. Executive Engineer (R&B),


(R&B) East Section : Kakinada

Dy. Executive Engineer (R&B),


(R&B) East Sub-divn., : Kakinada

Executive Engineer (R&B),


(R&B) Division : Kakinada

DATA FOR BRIDGE ITEMS


Name of Work ::-

Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on Brahmarshi


Street from NH 214 Junction at Manasarovar Hotel to Dairy Form Centre in
Kakinada Town limits at Railway Km 14.05 of Kakinada Town Kakinada Port
Section in E.G.Dist.

Quantity
1

Description of Item

Rate

per

Earthwork excavation in soils upto SDR by mechanical means for foundations of structures as per drawing and
technical specification including setting out, construction of shoring and bracing, removal of stumps and other
deleterious matter, dressing sides of bottom, back filling the excavation earth to the extent required etc.,
complete including seignioarge charges for finished item of work as per MoRT&H specification 304(4 th
Revision) and as directed by the Engineer-in-Charge

Unit : Cum
Page 323 of MoRT&H SDB
(a) Depth upto 3M excluding dewatering charges
Taking out put = 240 Cum
(A) Labour
0.32 day
8.00 day
25.00 %

Mate

188.00

day

Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

146.00
1228.16

day

(B) Machinery
240.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005

13.00

cum

(C) Seigniorage charges


240.00 Cum
Seigniorage charges

20.00

cum

(D) Over head charges @21% (25%-VAT) on (A) + (B)+( C)


(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 240 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

(b) Depth upto 3M including dewatering charges


(A) Labour
0.32 day
8.00 day
25.00 %

Taking out put = 240 Cum

Mate

188.00

day

Mazdoor unskilled
Extra for Corporation Area Allowance on Rs.

146.00
1228.16

day

13.00

cum

(B) Machinery
240.00 cum
Rate as per G.O. Ms No 10, Dt 26/7/2005
(C)
240.00
(D)
5.00
(E)
(F)
(G)

Seigniorage charges
Cum
Seigniorage charges
20.00
Dewateing charges on A+B
%
Dewateing charges on A+B
4655.20
Over head charges @21% (25%-VAT) on (A) + (B)+( C)+(D)
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 240 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

cum
cum

Quantity

Description of Item

Rate

per

Quantity
2

Description of Item

Rate

per

Providing Vibrated Cement Concrete (1:3:6) mix using 40mm size HBG crushed stone aggregate and fine
aggregate conforming to table 1000-2 of MoRT&H including cost, seigniorage conveyance of all materials to
site and labour charges, centering, machine mixing, laying, Vibrating, curing etc., including all other incidental
and operational charges of all T&P etc., complete for finished item of work as per MoRT&H specification
1500,1700, 2100 (4th Revision) and as directed by the Engineer-in-Charge as Levelling course under Footings.
Unit = cum
Page 331 of MoRT&H SDB
Taking output = 15 cum
(A)
0.64
1.00
15.00
25.00

Labour
nos
nos
nos
%

(B)
13.50
6.75
3.45

Material
cum
1121.93
Cost of 40mm SS-5 HBG M/C metal
cum
Sand at site
540.80
MT
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
hr
Water tanker 6 KL capacity
345.00
Total
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

6.00
6.00
2.00
(D)
21.00
(E)
(F)

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
2503.72

day
day
day

cum
cum
MT
hr
hr
hr

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4 th
Revision) for Abutment footings.
Unit = cum
Page 335 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75
4.13

Material
cum
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site

1121.93
1553.18
1196.93
540.80
4500.00

cum
cum
cum
cum
MT

Quantity

Description of Item
Total

Rate

per

Quantity
Description of Item
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
4.00
(E)
21.00
(F)
(G)

Rate

per

345.00
620.00

hr
hr

Form work
%
Form work @ 4% on (A)+(B)+( C)
49234.00
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine mixing,
laying in position,Compacting, Vibrating and curing including all other incidental and all other operational
charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2200 (4 th Revision) for
Abutment Sub structure .
Unit = cum
Page 335,455 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75
4.13

Material
cum
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
10.00
(E)
21.00
(F)
(G)

188.00
193.40
146.00
3371.78

day
day
day

1121.93
1553.18
1196.93
540.80
4500.00

cum
cum
cum
cum
MT

345.00
620.00

hr
hr

Form work
%
Form work @ 10% on (A)+(B)+( C)
49234.00
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

Cum

Quantity
5

Description of Item

Rate

per

Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the Engineer-in-Charge for Pier
foundation.
Unit = cum
Page 340,501 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.05

Material
cum
cum
cum
MT

6.00
6.00
(D)
3.75
(E)
21.00
(F)
(G)

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 3.75% on (A)+(B)+( C)
59924.31
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum M 25 Concrete
Rate to be adopted

cum
cum
cum
MT

hr
hr

Cum

Vibrated reinforced cement concrete M.25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the Engineer-in-Charge for Pier
Sub-structure, Pier Cap, Bedblocks and Backing walls.
Unit = cum
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

Page 340,501 of MoRT&H SDB


For Height upto 5.00 M

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.

188.00
193.40
146.00
3371.78

day
day
day

Quantity

Description of Item
Total

Rate

per

Quantity
(B)
8.10
5.40
6.75
6.05

Material
cum
cum
cum
MT

Rate

per

1553.18
1196.93
540.80
4500.00

cum
cum
cum
MT

Cost of 20mm SS-5 HBG M/C metal


Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
hr
Generator set 35 KVA
Total
To cater for extra lift
%
To cater for extra lift on (A)+(B)+( C)

345.00
620.00

hr
hr

59924.31

Cum

(E) Form work


10.00 %
Form work @ 10.00% on (A)+(B)+(C)+(D)

59924.31

Cum

6.00
6.00
(D)
0.00

(F)
21.00
(G)
(H)

Description of Item

Over head charges @ 21% (25%-VAT)


Add for Over head charges @ 21% on (A)+(B)+( C)+(D)+(E)
%
Total of (A) + (B)+( C)+(D)+(E)+(F)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum M 25 Concrete
Rate to be adopted

Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per drawing BD/1-69 (A) but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-Charge for Bearing
Pedestals.
Unit = cum
Page 477,492 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.10

Material
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

Cost of 20mm SS-5 HBG M/C metal


Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D) Form work
2.00 %
Form work @ 2% on (A)+(B)+(C)+(D)

188.00
193.40
146.00
3371.78

day
day
day

1553.18
1196.93
540.80
4500.00

cum
cum
cum
MT

345.00
620.00

hr
hr

60149.31

Cum

Quantity
Description of Item
Rate
(E) Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)+(D)
21.00 %
(F) Total of (A) + (B)+( C)+(D)
(G) Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum M 30 Concrete
Rate to be adopted
8

per

Vibrated reinforced cement concrete M 25 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including other incidental hire and operational charges of all T&P etc., complete as per approved
drawings and as directed during execution but excluding cost of steel and its fabrication charges for finished
item as per MoRT&H specification 1500,1600,1700 & 2200 (4 th revision ) and as directed by the Engineer-inCharge for T-beam slab Superstructure.
Unit = cum
Page 472 of MoRT&H SDB
Taking output = 15 cum
Height 5 M to 10 M
(A) Labour
0.86 nos
1.50 nos
20.00 nos
25.00 %
(B)
8.10
5.40
6.75
5.99

6.00
6.00
(D)
30.00
(E)
21.00
(F)
(G)

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Form work
%
Form work @ 30% on (A)+(B)+( C)
59654.31
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)+(D)
%
Total of (A) + (B)+( C)+(D)+(E)
Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
Rate for 1 cum
Rate to be adopted

cum

Material
cum
cum
cum
MT

cum
MT

hr
hr

Cum

Supplying, fitting and fixing in position true to line and level elestomeric bearing / neopran bearing conforming
to IRC 83 (Part-II) Section IX and clause 2005 of MORT&H Specifications complete including all accessaries
as per drawing and technical specification.
Unit = cum
13.14 Page 467 of MoRT&H SDB
Taking output = 15 cum

Quantity
Description of Item
Rate
per
Consideing an elastomeric bearing of size 500 x 400 x 96 mm for this analysis.
Overall volume - 19200 Cu.cm.
Volume of 6 nos. 488 x 388 x 4 mm size reinforcing steel plates = 4545 cu.cm.
Hence volume of elastometer = 14655 cu.cm.
(A)
0.06
1.00
0.50
25.00

Labour
nos
nos
nos
%

Mate
Mazdoor
Mazdoor skilled
Extra for Corporation Area Allowance on Rs.
Total

188.00
146.00
193.40
253.98

day
day
day

0.50
9600.00

cu.cm.
cum

(B) Material
Elastomeric bearing assembly consisting of 7
layers of elastomer bonded to 6 nos. internal
reinfocing steel laminates by the process of
vulcanisation, complete with all components as per
19200 cu.cm.
1.00 %

(C)
21.00
(D)
(E)

8455

Elastomeric beaing (P.R. Rate = 0.50 / cu.cm.)


Add 1 percent of cost of bearring assembly for
foudation anchorage bolts and consumables.
Total
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)
%
Total of (A) + (B)+( C)
Add Contractors Profit at 10% on (D)
Cost per 19200 cu.cm (D)+(E)
Rate for 19200 cu.cm
Bearing size 630 x 220 x 61mm
cu.cm.
Rate for bearing
Rate to be adopted

0.694 cu.cm.
(P.R.)

10 Vibrated reinforced cement concrete M 30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per drawing BD/1-69 (A) but excluding cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2702 (4th Revision) and as directed by the Engineer-in-Charge for wearing
coat over Deck slab.
Unit = cum
Page 477,492 of MoRT&H SDB
Taking output = 15 cum
(A)
0.90
1.50
21.00
25.00
(B)
8.10
5.40
6.75

Labour
nos
nos
nos
%

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

Material
cum
Cost of 20mm SS-5 HBG M/C metal
cum
Cost of 10mm SS-5 HBG M/C metal
cum
Sand at site

188.00
193.40
146.00
3525.30

day
day
day

1553.18
1196.93
540.80

cum
cum
cum

Quantity
6.10 MT

Description of Item
Cement at site
Total

Rate
4500.00

per
MT

Quantity
Description of Item
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
2.25
(D)
21.00
(E)
(F)

nos
Labour for cleaning deck slab concrete
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum M 30 Concrete
Rate to be adopted

Rate

per

345.00
620.00

hr
hr

146.00

day

11 Construction of precast VRCC railing of M30 grade using HBG crushed stone aggregate of size not exceeding
12 mm and fine aggregate conforming to table 1000-2 true to line and grade, tolerance of vertical RCC post not
to exceed 1 in 500, centre to centre spacing between vertical posts not to exceed 2000mm, leaving adequate
space between vertical posts for expansion including cost, seigniorage conveyance of all materials to site and
labour charges, centering, machine mixing, laying, vibrating, curing etc., including other incidental hire and
operational charges of all T&P as per approved drawings and as directed during execution but excluding cost
of steel and its fabrication charges as per approved drawings and technical specifications for finished item of
work as per MoRT&H Specification 2703, 1500, 1600, 1700(4th Revision)

Unit = 1 RM
Page 472,497 of MoRT&H SDB
Taking output = 17.07M span
Material
M20 grade VRCC
No. of vertical end posts = 2 x 0.30x 0.20 x0.90 =
Internal vertical posts = 8x0.18x0.20x0.90 =
hand rail in 3 tier = 17.07-(2x0.3+8x0.18)=15.03 RM
quantity of RCC = 2x15.03x0.115x0.165 =
Total Concrete =
VRCC M 30 Grade
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.10

Material
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

Cost of 12mm SS-5 HBG M/C metal


Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
Total
Cost per 15 cum (A)+(B)+( C)
Rate for 1 cum

0.1080
0.2592
0.8556
1.2228

188.00
193.40
146.00
3371.78

day
day
day

1359.43
1196.93
540.80
4500.00

cum
cum
cum
MT

345.00
620.00

hr
hr

Quantity
1.2228 Cum.

Description of Item
M.30 Grade Concrete

Rate
3905.33

per
Cum

Quantity
Description of Item
(D) Form work
10.00 %
Form work @ 10% on
(E) Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on
21.00 %
(F) Total of (A) + (B)+( C)+(D)+(E)
(G) Add Contractors Profit at 10% on (F)
Cost per 15 cum (F)+(G)
0.205 MT

HYSD Bar Reinforcement

Rate

per

4775.44

Cum

5252.98

49826.40

MT

Rate for 17.07 M


Cost per 1 RM =
Rate to be adopted

12 Vibrated reinforced cement concrete M.30 grade using 20mm & 10mm HBG crushed stone aggregate (Coarse
aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2) including cost,
seigniorage conveyance of all materials to site and labour charges, centering, machine mixing, laying, vibrating,
curing etc., including all other incidental and operational charges of all T&P etc., complete for finished item of
work as per Approved drawing but including cost of steel and its fabrication charges as per MoRT&H
specification 1500, 1600,1700, & 2704 (4th Revision) and as directed by the Engineer-in-Charge for
Approach slab.
Unit = cum
Page 340,501 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
5.40
6.75
6.10

Material
cum
cum
cum
MT

(C)
6.00
6.00
(A)
(B)
2.00
(C)
0.05
(D)
21.00
(E)
(F)

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

188.00
193.40
146.00
3371.78

day
day
day

1553.18
Cost of 20mm SS-5 HBG M/C metal
1196.93
Cost of 10mm SS-5 HBG M/C metal
Sand at site
540.80
Cement at site
4500.00
Total
Machinery
hr
Concrete mixer 0.4/0.28 cum
345.00
hr
Generator set 35 KVA
620.00
Total
Cement Concrete M30 Grade
60149.31 / 15
Form work
%
Form work @ 2% on (A)
4009.95
HYSD Bar reinforcement
MT
HYSD Bar reinforcement
49826.40
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 1 cum (E)+(F)

cum
cum
cum
MT

hr
hr

Cum
MT

Quantity

Description of Item
Rate to be adopted

Rate

per

13 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for foundations of R.C.C items.
Unit = MT
Page 448 of MoRT&H SDB
Taking output = 1 MT
(A)
0.40
2.00
6.00
25.00

Labour
nos
nos
nos
%

Mate
Black smith
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
1.05 MT
HYSD bars including overlaps
6.00 Kg
Binding wire
Total
(C) Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)
21.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

188.00
188.00
146.00
1327.20

day
day
day

45000.00
38500.00

MT
MT

14 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Sub structure of R.C.C items.
Unit = MT
Page 459,460 of MoRT&H SDB
Taking output = 1 MT
(A)
0.34
2.00
6.50
25.00

Labour
nos
nos
nos
%

Mate
Black smith
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
1.05 MT
HYSD bars including overlaps
6.00 Kg
Binding wire
Total
(C) Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)
21.00 %
(D) Total of (A) + (B)+( C)

188.00
188.00
146.00
1388.92

day
day
day

45000.00
38500.00

MT
MT

Quantity
Description of Item
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

Rate

per

15 Providing HYSD bars ( Fe-415 ) of different diameters, wrought and put up bars of all diameters including cost
and conveyance of steel to site and all labour charges for fabrication of reinforcement including cutting,
bending, binding rods, tying grills, placing them in position etc., complete including cost and conveyance of
binding wire and all handling charges and operational charges etc., and including over lapping welding if
required etc., complete for all R.C.C items for finished item of work as per standard drawings, as per the
directions of the Engineer-in-Charge and as per MoRT&H specification 1600 &2200 (4 th revision) and as per
I.S.1786 of 1985 for Super structure of R.C.C items.
Unit = MT
Page 489,490 of MoRT&H SDB
Taking output = 1 MT
(A)
0.44
3.00
8.00
25.00

Labour
nos
nos
nos
%

Mate
Black smith
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
1.05 MT
HYSD bars including overlaps
8.00 Kg
Binding wire
Total
(C) Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)
21.00 %
(D) Total of (A) + (B)+( C)
(E) Add Contractors Profit at 10% on (D)
Rate for 1 MT (D)+(E)
Rate to be adopted

188.00
188.00
146.00
1814.72

day
day
day

45000.00
38500.00

MT
MT

49826.40

16 Providing anti corrosive treatment to HYSD reinforcement with Fusion Bonded Epoxy Coating (FBEC) not
less than 175 microns thickness and upto 300 microns to reinforcement of all diameters as per IS 13620-1993
including testing of coating at plant. The rate is inclusive of cost on account of careful handling, PVC coated
binding wire instead of GI binding wire, touch up material supplied by coating agency, repair work,
transportation from the source of supply of steel to the plant and transportation of coated steel from the plant to
site of work, loading, unloading and traightening of bent rods etc., complete as per MoRT&H specification
No.1600 and as directed by the Engineer-in-charge.

1.00 MT
12.36 %

Rate as per SSR 2008-09 (Pg. 120)


Service Tax on
Rate for 1 MT
Rate to be adopted

9860.00
9860.00

MT

17 Providing weep holes in VCC Abutments, Return walls and wing walls with 100mm Diameter AC pipe
extending through the full width of the structure at 1.00m C/C in both horizontal and vertical direction so that
the weep holes in each horizontal direction is staggered from the weep holes laying above and below lines as
shown in drawing including cost and conveyance of the A.C pipes and labour charges for cutting to required
length, placing the pipe with a slope of about 1V : 20H towards stream side face etc., complete for finished item
of work for weep holes as per MoRT&H specification 2706 & 2200 (4 th Revision)

Quantity
Description of Item
Unit = RM
Taking output = 30 RM
Cement Mortor (1:3) (Out put = 1Cum)

Rate

per

Page 461,333 of MoRT&H SDB

Quantity
0.51
1.05

MT
cum

0.04
nos
0.90
nos
25.00 %

31.50
30.00
10.00

RM
nos
nos

0.05

cum

Description of Item
Material
Cost of Cement
Cost of Sand

Rate

per

4500.00
540.80

MT
cum

Labour
Mate
Mazdoor
Extra for Corporation Area Allowance on Rs.

188.00
146.00
138.92

day
day

35.00
10.00
3.50

RM
each
each

3036.49

cum

188.00
193.40
146.00
138.84

day
day
day

Cost per 1 Cum


(A) Material
Cost of 100mm Dia., AC pipe
MS clamps
collors for AC pipe (average) taking 10% of above
pipe rate
Cement mortor (1:3)

(B) Labour
0.03
nos
Mate
0.50
nos
Mason
0.25
nos
Mazdoor
25.00 %
Extra for Corporation Area Allowance on Rs.
Total
Add for Over head charges @ 21% on (A)+(B) i.e., on
(C)
(D)
Contractor's profit @ 10% on (A)+(B)+(C) i.e., on
Cost per 30 RM
Rate for 1 RM

1762.87
2133.07

(P.R.)

Say Rs

18 Supplying & fixing drainage spouts at site made of 210mm x 210mm water sput at top with 100mm dia GI
Drain spout and MS Plate of 12mm x 40mm x 6mm thick plates including cost & conveyance of all materials to
site and all labour charges for cutting bending & welding, placing in position, etc., complete for deck slab as per
Drawing No.BD / 1-69 & as directed by the Engineer-in-charge.

4.00
6.00
6.00
2.00

Unit = 1 No.
Taking output = 1 No.
(A) Material
Kg
Corrosion resistant Structural steel
including 5% wastage
Metre
GI pipe 100mm dia
nos
GI bolt 10 mm Dia
nos
Galvanised MS flat clamp

(B) Labour
For Fabrication
0.02
nos
Mate
0.02
nos
Skilled (Blacksmith, welder etc.)
0.02
nos
Mazdoor
For Fixing in position
0.01
nos
Mate
0.01
nos
Mason
0.20
nos
Mazdoor
25.00 %
Extra for Corporation Area Allowance on Rs.

44.80

Kg.

35.00
15.00
12.00

each
each
cum

188.00
193.40
146.00

day
day
day

188.00
193.40
146.00
43.56

day
day
day

Quantity

Description of Item

Rate

per

Total
5.00

(C) Add 5% on (A)+(B)


%
Add @ 5 per cent of cost of material and labour
for electrodes, cutting gas, sealant, anti-corrosive
bituminous paint, mild steel grating etc.
Add for Over head charges @ 21% on (A)+(B)+(C) i.e., on
Contractor's profit @ 10% on (A)+(B)+(C)+(D) i.e., on
Rate for 1 No.

(D)
(E)

557.65

585.53
708.49
(P.R.)

Say Rs

19 Providing and laying of a strip seal type expansion joint catering to maximum horizontal movement upto 70
mm, complete as per approved drawings and standard specifications to be installed by the manufacturer /
supplier or their authorised representative ensuring compliance to the manufacturer's instructions for
installation.
(Rate is taken from the approved rate of Gannavaram ROB Estimate)
(P.R.)
20 Providing and laying of filter media with granular materials / stone crushed aggregate satisfying the
requirements laid down in clause 2504.2.2 of MoRT&H specifications to athickness of not less than 600mm
with smaller size towards the soil and bigger size towards the wall and provided over the entire surface behind
the abutment, wing wall and return wall to the full height compacted to a firm condition including cost and
conveyance of all metal seignorage charges ,and all labour charges as directed by the departmental officers as
per drawing and Technical specifications as per clause 710.1.1 of IRC:78 and Clause 2200 of MoRT&H (4 th
Revision) for finished item of work.
Unit = cum
Page 463 of MoRT&H SDB
Taking output = 10 cum
(A)
0.32
7.00
1.00
25.00

Labour
nos
nos
nos
%

Mate
Mazdoor for filling watering, ramming etc
Mazdoor skilled
Extra for Corporation Area Allowance on Rs.
Total

188.00
146.00
193.40
1275.56

day
day
day

581.10
999.10

cum
cum

345.00

hr

(B) Material

6.00
6.00

0.06
(D)
21.00
(E)
(F)

Filter media of stone aggregate conforming


to clause 2504.2.2 of MoRT&H
cum
Cost of 150mm size IRC soling stone (HBG)
cum
Cost of 40mm size IRC HBG metal
Total
Machinery
hr
Water tanker 6 KL capacity
Total
Over head charges @ 21% (25%-VAT)
Add for Over head charges @ 21% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

Quantity

Description of Item

Rate

per

Appoaches
21 Vibrated cement concrete M 15 Grade Concrete using 40mm , 20mm and 10mm size HBG crushed stone
aggregate (Coarse aggregate conforming to table 1000-1 and fine aggregate conforming to table 1000-2)
including cost,seignorage and conveyance of all materials to site and all labour charges for machine
mixing,laying in position, Compacting , Vibrating and curing including all other incidental and all other
operational charges of T&P required etc., complete as per MoRT&H Specification 1500,1700, 2100 (4 th
Revision) for foundation leveling pad below the facing panel
Unit = cum
Page 335 of MoRT&H SDB
Taking output = 15 cum
(A)
0.86
1.50
20.00
25.00

Labour
nos
nos
nos
%

(B)
8.10
4.05
1.35
6.75
4.13

Material
cum
cum
cum
cum
MT

Mate
Mason
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

Cost of 40mm SS-5 HBG M/C metal


Cost of 20mm SS-5 HBG M/C metal
Cost of 10mm SS-5 HBG M/C metal
Sand at site
Cement at site
Total
Machinery
6.00 hr
Concrete mixer 0.4/0.28 cum
6.00 hr
Generator set 35 KVA
(D)
6.00
(E)
(F)

188.00
193.40
146.00
3371.78

day
day
day

1121.93
1553.18
1196.93
540.80
4500.00

cum
cum
cum
cum
MT

345.00
620.00

hr
hr

Over head charges @ 6% (10%-VAT)


Add for Over head charges @ 6% on (A)+(B)+( C)
%
Total of (A) + (B)+( C)+(D)
Add Contractors Profit at 10% on (E)
Cost per 15 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

22 Construction of Reinforced Soil Wall which includes designing, providing constructin drawing, supply and
erection of segmental blocks of minimum Grade M35, minimum thickness 300mm including approved soil
reinformecment consisting of punched and oriented HDPE Geogrid or High adherence metallic strips
galvanized to 1000 g/m of minimum dimension 40mm x 5mm with all accessories complete, as per the design
and drawings and technical specifications of the approved specialist firms technical experts doing the work and
as per the instruction of the Engineer-in-Charge.

Rate as per the quotation offered by M/S. Geosol


(Rate is taken from the approved rate of LC No.9 (Kakinada) ROB Estimate)

Quantity
Description of Item
Rate
per
23 Supply and placement of approved quanlity fill material, compaction 95% Procter Density of fill material as per
Specification in requisite layers including cost ,conveyance and seigniorage of all materials to site etc.,
complete as per Drawing and technical specifications for finished item of work and as directed by the
Engineer-in-charge of the work.
Unit = cum
Taking output = 10 cum
(A)
0.28
7.00
25.00

Labour
nos
nos
%

Mate
Mazdoor
Extra for Corporation Area Allowance on Rs.
Total

(B) Material
8.04 cum
Cost of Gravel (67%)
3.96 cum
Cost of Coarse Sand for filling (33%)
Total
Machinery
2.50 hr
Plate compactor/Power rammer
0.05 hr
Water tanker 6 KL capacity
Total
(D) Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
6.00 %
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

188.00
146.00
1074.64

day
day

284.00
425.80

cum
cum

40.00
345.00

hr
hr

24 Providing well graded drainage fill, drain pipes wrapped with geotextile, cost of hire and labour for plant /
machineries, dressing, leveling of slope etc., including engineering supervision all complete as per specification
and approved drawing as directed by Engineer-in-Charge.
Unit = cum
Taking output = 10 cum
(A)
0.32
7.00
1.00
25.00

Labour
nos
nos
nos
%

Mate
Mazdoor for filling watering, ramming etc
Mazdoor skilled
Extra for Corporation Area Allowance on Rs.
Total

188.00
146.00
193.40
1275.56

day
day
day

1196.93
1034.43
654.10

cum
cum
cum

345.00

hr

(B) Material

4.80
4.80
2.40

0.06
(D)
6.00

Filter media of stone aggregate conforming


to clause 2504.2.2 of MoRT&H
cum
Cost of 11.20mm size IRC HBG metal
cum
Cost of 5.60mm size IRC HBG metal
cum
Cost of 2.36mm and below IRC HBG metal
Total
Machinery
hr
Water tanker 6 KL capacity
Total
Over head charges @ 6% (10%-VAT)
Add for Over head charges @ 6% on (A)+(B)+( C)
%

Quantity
Description of Item
(E) Total of (A) + (B)+( C)+(D)
(F) Add Contractors Profit at 10% on (E)
Cost per 10 cum (E)+(F)
Rate for 1 cum
Rate to be adopted

Rate

per

No.11 on Brahmarshi
orm Centre in
n Kakinada Port

Amount

ures as per drawing and


val of stumps and other
e extent required etc.,
H specification 304(4 th

60.16
1168.00
307.04
1535.20
3120.00
4800.00
1985.59
11440.79
1144.08
12584.87
52.44
52.00
1 Cum

60.16
1168.00
307.04
1535.20
3120.00
4800.00
232.76
2034.47
11722.43
1172.24
12894.67
53.73
54.00

Amount
1 Cum

Amount

one aggregate and fine


ance of all materials to
ding all other incidental
MoRT&H specification
course under Footings.

120.32
193.40
2190.00
625.93
3129.65
15146.06
3650.40
15525.00
34321.46
2070.00
3720.00
690.00
6480.00

9225.53
53156.64
5315.66
58472.30
3898.15
3900.00
1 Cum
ze HBG crushed stone
ming to table 1000-2)
r charges for machine
ncidental and all other
n 1500,1700, 2100 (4 th

161.68
290.10
2920.00
842.95
4214.73
9087.63
6290.38
1615.86
3650.40
18585.00

Amount
39229.27

Amount
2070.00
3720.00
5790.00
1969.36
10752.71
61956.07
6195.61
68151.68
4543.45
4540.00
1 Cum

ze HBG crushed stone


ming to table 1000-2)
es for machine mixing,
nd all other operational
200 (4 th Revision) for

161.68
290.10
2920.00
842.95
4214.73
9087.63
6290.38
1615.86
3650.40
18585.00
39229.27
2070.00
3720.00
5790.00
4923.40
11373.05
65530.45
6553.05
72083.50
4805.57
4810.00
1 Cum

Amount

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
neer-in-Charge for Pier

161.68
290.10
2920.00
842.95
4214.73
12580.76
6463.42
3650.40
27225.00
49919.58
2070.00
3720.00
5790.00
2247.16
13056.01
75227.48
7522.75
82750.23
5516.68
5520.00
1 Cum

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
neer-in-Charge for Pier

of MoRT&H SDB

161.68
290.10
2920.00
842.95

Amount
4214.73

Amount
12580.76
6463.42
3650.40
27225.00
49919.58
2070.00
3720.00
5790.00
0.00
5992.43
13842.52
79759.26
7975.93
87735.19
5849.01
5850.00
1 Cum

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
r-in-Charge for Bearing

161.68
290.10
2920.00
842.95
4214.73
12580.76
6463.42
3650.40
27450.00
50144.58
2070.00
3720.00
5790.00
1202.99

Amount
12883.98
74236.28
7423.63
81659.91
5443.99
5440.00
1 Cum

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
mplete as per approved
on charges for finished
cted by the Engineer-in-

161.68
290.10
2920.00
842.95
4214.73
12580.76
6463.42
3650.40
26955.00
49649.58
2070.00
3720.00
5790.00
17896.29
16285.63
93836.23
9383.62
103219.85
6881.32
6880.00
1 Cum

ran bearing conforming


ncluding all accessaries

Amount

11.28
146.00
96.70
63.50
317.48

9600.00
96.00
9696.00
2102.83
12116.31
1211.63
13327.94
0.694
5867.77
5870.00
each

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
r-in-Charge for wearing

169.20
290.10
3066.00
881.33
4406.63
12580.76
6463.42
3650.40

Amount
27450.00
50144.58

Amount
2070.00
3720.00
5790.00
328.50
12740.64
73410.35
7341.04
80751.39
5383.43
5380.00
1 Cum

te of size not exceeding


of vertical RCC post not
0mm, leaving adequate
all materials to site and
ther incidental hire and
ution but excluding cost
ons for finished item of

cum
cum
cum
cum

161.68
290.10
2920.00
842.95
4214.73
11011.38
6463.42
3650.40
27450.00
48575.20
2070.00
3720.00
5790.00
58579.93
3905.33

Amount
4775.44

Amount
477.54
1103.13
6356.11
635.61
6991.72
10214.41
17206.13
1007.97
1010.00
1 RM

stone aggregate (Coarse


000-2) including cost,
ixing, laying, vibrating,
lete for finished item of
arges as per MoRT&H
Engineer-in-Charge for

161.68
290.10
2920.00
842.95
4214.73

12580.76
6463.42
3650.40
27450.00
50144.58
2070.00
3720.00
5790.00
4009.95
80.20
2491.32
1382.11
7963.58
796.36
8759.94

Amount
8760.00
1 Cum

diameters including cost


ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

75.20
376.00
876.00
331.80
1659.00
47250.00
231.00
47481.00
10319.40
59459.40
5945.94
65405.34
65410.00
1 MT

diameters including cost


ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

63.92
376.00
949.00
347.23
1736.15
47250.00
231.00
47481.00
10335.60
59552.75

Amount
5955.28
65508.03
65510.00
1 MT
diameters including cost
ment including cutting,
cost and conveyance of
ver lapping welding if
d drawings, as per the
4 th revision) and as per

82.72
564.00
1168.00
453.68
2268.40
47250.00
308.00
47558.00
10463.54
60289.94
6028.99
66318.93
66320.00
1 MT

y Coating (FBEC) not


s as per IS 13620-1993
l handling, PVC coated
agency, repair work,
d steel from the plant to
MoRT&H specification

9860.00
1218.70
11078.70
11080.00
1 MT

mm Diameter AC pipe
vertical direction so that
ove and below lines as
for cutting to required
mplete for finished item

Amount

of MoRT&H SDB

Amount
2295.00
567.84
2862.84
7.52
131.40
34.73
173.65
3036.49
1102.50
300.00
35.00
151.82
1589.32

5.64
96.70
36.50
34.71
173.55
370.20
213.31
2346.38
78.21
78.00
1 RM
op with 100mm dia GI
yance of all materials to
lete for deck slab as per

179.20
210.00
90.00
24.00
503.20
3.76
3.87
2.92
1.88
1.93
29.20
10.89

Amount
54.45
27.88

122.96
70.85
779.34
779.00
1 No.

ntal movement upto 70


by the manufacturer /
turer's instructions for

4500.00
1 RM

ggregate satisfying the


of not less than 600mm
he entire surface behind
tion including cost and
departmental officers as
2200 of MoRT&H (4 th

60.16
1022.00
193.40
318.89
1594.45

3486.60
5994.60
9481.20
20.70
20.70
2330.23
13426.58
1342.66
14769.24
1476.92
1480.00

Amount
1 Cum

ze HBG crushed stone


ming to table 1000-2)
r charges for machine
ncidental and all other
n 1500,1700, 2100 (4 th

161.68
290.10
2920.00
842.95
4214.73
9087.63
6290.38
1615.86
3650.40
18585.00
39229.27
2070.00
3720.00
5790.00
2954.04
52188.04
5218.80
57406.84
3827.12
3830.00
1 Cum

n drawing, supply and


ncluding approved soil
herence metallic strips
mplete, as per the design
erts doing the work and

4200.00
1 Sqm.

Amount
ty of fill material as per
materials to site etc.,
and as directed by the

52.64
1022.00
268.66
1343.30
2283.36
1686.17
3969.53
100.00
17.25
117.25
325.80
5755.88
575.59
6331.47
633.15
633.00
1 Cum

and labour for plant /


lete as per specification

60.16
1022.00
193.40
318.89
1594.45

5745.26
4965.26
1569.84
12280.36
20.70
20.70
833.73

Amount
14729.24
1472.92
16202.16
1620.22
1620.00
1 Cum

CERTIFICATE
Name of Work:
Construction of Road Over Bridge at Kakinada in lieu of L.C.No.11 on
Brahmarshi Street from NH 214 Junction at Manasarovar Hotel to Dairy Form
Centre in Kakinada Town limits at Railway Km 14.05 of Kakinada Town
Kakinada Port Section in E.G.Dist.
1) Certified that I have personally inspected the above road on
and the provisions made in the estimate for the above work are adequate and
essential and there is no Black top surface in the stretches proposed for
improvements.
2) Certified that the leads provided in the R.M.R of the estimate are shortest and there
is sufficient yield of good quality material from the quarries proposed in the estimate.
3) Certified that all the distances in the quarry map are correct.
4) Certified that the quarries provided are the nearest.
5) Certified that the routes shown in the quarry map are the shortest for the
transportation of the materials
6) Certified that all the materials can be easily quarried.
7) Certified that the description of all materials mentioned are correct to the best of my
knowledge.
8) Certified that side earth is not available. Hence formation of embankment is
proposed with Carted earth with 1 Km Lead.
9) Certified that crushers are available for crushing the HBG metal of size 40mm and
below and as such crushing charges are proposed for HBG metal 40mm and below.

Asst. Executive Engineer (R&B)


(R&B) East Section, Kakinada.

Dy. Executive Engineer (R&B) FAC,


(R&B) East Sub-divn., Kakinada

Executive Engineer (R&B)


(R&B) Division, Kakinada

Superintending Engineer (R&B)


(R&B) Circle, Kakinada

LEAD CHARGES
Earth/Gravel/
Sand
loading
10.00
unloading
8.50
stacking
5.50
0.25
50.00
0.5
75.00

Cost of Materials, Labour


Metal
12.80
8.70
8.70
110.00
110.00

1
2
3
4
5
6
7

100.00
106.00
112.00
118.00
124.00
130.00
136.00

120.00
126.00
132.00
138.00
144.00
150.00
156.00

8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40

142.00
148.00
154.00
160.00
166.00
172.00
178.00
184.00
190.00
196.00
202.00
208.00
214.00
219.00
224.00
229.00
234.00
239.00
244.00
249.00
254.00
259.00
264.00
268.80
273.60
278.40
283.20
288.00
292.80
297.60
302.40
307.20
312.00

162.00
168.00
174.00
180.00
186.00
192.00
198.00
204.00
210.00
216.00
222.00
228.00
234.00
239.75
245.50
251.25
257.00
262.75
268.50
274.25
280.00
285.75
291.50
297.00
302.50
308.00
313.50
319.00
324.50
330.00
335.50
341.00
346.50

Material Rates
60 to 63 mm IRC & MoRTH HBG metal
50 to 55 mm IRC & MoRTH HBG metal
40 to 45 mm IRC & MoRTH HBG metal
Roughstone 300mm (HBG)for revetment
Roughstone 225mm (HBG)for revetment
SS Revetment work 225mm
SS Revetment work 300mm
SS Revetment work 450mm
Laterite for Revetment 225mm
Laterite for Revetment 300mm
Jeddy stone above 450mm to 600mm
Quarry spall(Field picked metal)
Av. Of rate 25mm & 40mm
150 mm soling stone HBG metal
40 to 45 mm IRC & MoRTH HBG M/C metal
25 to 27 mm IRC & MoRTH HBG M/C metal
19 to 22 mm IRC & MoRTH HBG M/C metal
12 to 14 mm IRC & MoRTH HBG M/C metal
9.5 to 11.20 mm IRC & MoRTH HBG M/C metal
5 to 7 mm IRC & MoRTH HBG M/C metal
2.36 to 5 mm IRC & MoRTH HBG M/C metal
HBG Stone chips 2.36mm and below
Gravel
40 mm SS-5 m/c HBG metal
25 mm SS-5 m/c HBG metal
20 mm SS-5 m/c HBG metal
12 mm SS-5 m/c HBG metal
10 mm SS-5 m/c HBG metal
6 mm SS-5 m/c HBG metal
Sand for Mortar
Sand for Filling
HYSD Steel
Mild Steel
Cement
Mild Steel 6mm
Blasting charges
Blasting charges
Blasting charges for rough stone
Seigniorage charges
Metal
Gravel/earth
Sand
Labour Rates
Mate
Mazdoor skilled

41
42
43
44
45
46
47
48
49
50
51
52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90

316.80
321.60
326.40
331.20
336.00
340.80
345.60
350.40
355.20
360.00
364.60
369.20
373.80
378.40
383.00
387.60
392.20
396.80
401.40
406.00
410.60
415.20
419.80
424.40
429.00
433.60
438.20
442.80
447.40
452.00
456.60
461.20
465.80
470.40
475.00
479.60
484.20
488.80
493.40
498.00
502.40
506.80
511.20
515.60
520.00
524.40
528.80
533.20
537.60
542.00

352.00
357.50
363.00
368.50
374.00
379.50
385.00
390.50
396.00
401.50
406.50
411.50
416.50
421.50
426.50
431.50
436.50
441.50
446.50
451.50
456.50
461.50
466.50
471.50
476.50
481.50
486.50
491.50
496.50
501.50
506.50
511.50
516.50
521.50
526.50
531.50
536.50
541.50
546.50
551.50
556.25
561.00
565.75
570.50
575.25
580.00
584.75
589.50
594.25
599.00

Mazdoor unskilled
Machinery Rates
Dozer 80 HP for spreading @ 200 cum per hour
Motor grader 3.35M Blade @50 cum/Hr
Hydralic excavator
Front end loader 1 cum capacity
Tipper 5 cum
Vibratory roller 8T
smooth wheeled roller 8 Ton
Water tanker 6 KL
Tractor
Tractor with Rotavator
Tractor with ripper attachment @ 60 cum per hour
Air compressor 250 cfm
Wet mix plant of 60 tonne hr. capacity
Mechanical broom @ 1250 sqm/hr.
Bitumen pressure distributor @1750 sqm/hr
Emulsion pressure distributor @1750 sqm/hr
Hot mix plant 40 to 60 TPH
Mechanical Paver finisher 100 TPH
Hydraulic self propelled chip spreader @ 1500 sqm/hr.
Finish rolling with 6-8 tonne smooth wheeled tandem roller.
Pneumatic road Roller
GSB Plant 50 Cum
Generator 250 KVA
Generator set 125 KVA
Generator set 35 KVA
Concrete mixer 0.4/0.28 cum
Tipper 5.50 cum capacity per 10 Tonnes per tkm
Tipper 5 cum capacity for Soil, GSB, WMM, Hot mix
Plate compactor/Power rammer

Tipper 10Tonne capacity for carriage of stone


chips from stock pile on road side to chip
spreader

91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108
109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140

546.40
550.80
555.20
559.60
564.00
568.40
572.80
577.20
581.60
586.00
590.20
594.40
598.60
602.80
607.00
611.20
615.40
619.60
623.80
628.00
632.20
636.40
640.60
644.80
649.00
653.20
657.40
661.60
665.80
670.00
674.20
678.40
682.60
686.80
691.00
695.20
699.40
703.60
707.80
712.00
716.20
720.40
724.60
728.80
733.00
737.20
741.40
745.60
749.80
754.00

603.75
608.50
613.25
618.00
622.75
627.50
632.25
637.00
641.75
646.50
651.00
655.50
660.00
664.50
669.00
673.50
678.00
682.50
687.00
691.50
696.00
700.50
705.00
709.50
714.00
718.50
723.00
727.50
732.00
736.50
741.00
745.50
750.00
754.50
759.00
763.50
768.00
772.50
777.00
781.50
786.00
790.50
795.00
799.50
804.00
808.50
813.00
817.50
822.00
826.50

141
142
143
144
145
146
147
148
149
150

758.20
762.40
766.60
770.80
775.00
779.20
783.40
787.60
791.80
796.00

831.00
835.50
840.00
844.50
849.00
853.50
858.00
862.50
867.00
871.50

abour

360.00
390.00
500.00
136.00
117.00
71.00
95.00
114.00
98.00
114.00
156.00
39.75
82.00
500.00
830.00
845.00
690.00
560.00
430.00
234.00
225.00
56.00
500.00
830.00
845.00
690.00
560.00
430.00
175.00
60.00
45000.00
44800.00
4500.00
38500.00
70.00
67.00
45.00
20.00
36.00
188.00
193.40

09.2008

146.00
2760.00
2600.00
2250.00
1320.00
575.00
1550.00
540.00
345.00
345.00
345.00
345.00
370.00
1320.00
290.00
940.00
690.00
15525.00
1090.00
2070.00
1320.00
1035.00
920.00
1550.00
1090.00
620.00
345.00
4.50
4.50
40.00

Você também pode gostar