Escolar Documentos
Profissional Documentos
Cultura Documentos
From the work breakdown structure, a listing can be made of all the activities in
the project. This listing can be used as the basis for adding sequence and duration
information in later
steps.
2.
3.
Once the activities and their sequencing have been defined, the CPM diagram can
be drawn. CPM originally was developed as an activity on node (AON) network,
but some project planners prefer to specify the activities on the arcs.
The time required to complete each activity can be estimated using past
experience or the estimates of knowledgeable persons. CPM is a
deterministic model that does not take into account variation in the
completion time, so only one number is used for an activity's time
estimate.
The critical path is the longest-duration path through the network. The significance of the critical path is
that the activities that lie on it cannot be delayed without delaying the project. Because of its impact on
the entire project, critical path analysis is an important aspect of project planning.
The critical path can be identified by determining the following four parameters for each activity:
ES - earliest start time: the earliest time at which the activity can start given that its precedent
activities must be completed first.
EF - earliest finish time, equal to the earliest start time for the activity plus the time required to
complete the activity.
LF - latest finish time: the latest time at which the activity can be completed without delaying the
project.
LS - latest start time, equal to the latest finish time minus the time required to complete the activity.
The slack time for an activity is the time between its earliest and latest start time, or between its earliest
and latest finish time. Slack is the amount of time that an activity can be delayed past its earliest start or
earliest finish without delaying the project.
The critical path is the path through the project network in which none of the activities have slack, that is,
the path for which ES=LS and EF=LF for all activities in the path. A delay in the critical path delays the
project. Similarly, to accelerate the project it is necessary to reduce the total time required for the
activities in the critical path.
AOA /AON
Activity On Arc (AOA)
Activity
arc
arc
node
Completion
of activity
node
arc
Activity
B
node
10
D
C
F
E
H
G
Finish
Path
StartA C D F H Finish
StartA C E F H Finish
StartA C E G H Finish
StartB C D F H Finish
StartB C E G H Finish
StartB C E F H Finish
Length (weeks)
7+15+3+15+7=47
7+15+5+15+7=49
7+15+5+11+7=45
10+15+3+15+5=50
10+15+5+11+7=48
10+15+5+15+7=52
ACTIVITY
EARLY
START
EARLY
FINISH
DURATION
(TIME)
LATE
START
LATE
FINISH
Forward Pass
Early Finish:
Backward Pass
Late Start:
EF = ES + t
t = activity duration
LS = LF t
Slack, s = LS ES or LF EF
s=3
A 0 7
7 3 10
s=2
D 25 28
3 27 30
s=0
C 10 25
15 10 25
Start
s=0
F 30 45
15 30 45
s=0
E 25 30
5 25 30
s=0
B 0 10
10 0 10
Critical path:
Start-B-C-E-F-H-Finish
Completion time = 52 weeks
52 weeks
s=4
G 30 41
11 34 45
s=0
H 45 52
7 45 52
C
B
ES - EF
Forward
Start
0
Finish
Finish
10
20
30
40
LS - LF
C
B
50
E
Md Asnyat Asmat
Backward
16
Activity
Duration
ES
EF
LS
LF
Slack, s
(LS-ES)
Critical
activity?
A
B
C
D
E
F
G
H
7
10
15
3
5
15
11
7
0
0
10
25
25
30
30
45
7
10
25
28
30
45
41
52
3
0
10
27
25
30
34
45
10
10
25
30
30
45
45
52
3
0
0
2
0
0
4
0
No
Yes
Yes
No
Yes
Yes
No
Yes
Critical path:
Start-B-C-E-F-H-Finish
Completion time = 52 weeks
17
CPM Limitation
CPM requires experience, skill, and knowledge sufficient to provide. It was
developed for complex but fairly routine projects with minimal uncertainty
in the project completion times. For less routine projects there is more
uncertainty in the completion times, and this uncertainty limits the
usefulness of the deterministic CPM model. An alternative to CPM is the PERT
project planning model, which allows a range of durations to be specified for
each activity.
What are the advantages and disadvantages of CPM?