Escolar Documentos
Profissional Documentos
Cultura Documentos
CONTENTS
1.0
SITE LOGISITICS
2.0
3.0
4.0
MANAGEMENT STRUCTURE
5.0
6.0
1.0
SITE LOGISTICS
Project Restrictions
The proposed site has a number of restrictions inherent with its location with the
close proximity of the following buildings:Residential on Kingsmead West
Offices- Carrillion
Public footpath and highway to Green Park Road
Site Logistics
As part of our understanding of the project we have sought to understand the
logistical requirements for the same.
The appended logistics plan seeks to identify the proposed principles for
access, cranage, parking, site compound, public face, emergency procedures,
site security, dust and noise suppression and site safety.
Access
It is proposed to access the site through the rear on Kingsmead West and the
existing drop kerb adjacent to the Carrillion offices during the demolition phase.
Delivery vehicles during the construction phase will be limited and restricted on
Kingsmead West in accordance with the council working conditions for the first
sub structure phase of the project.
Access for the superstructure of the site will be from Green Park Rd.
Warning signage would be erected on the main approaches to the site, after
agreement with the Local highways Authority advising the public of the site
entrance.
Parking will be provided for site operatives during the demolition phase only.
During construction all operatives must use the public car parks.
For deliveries where multiple vehicles are needed e.g. Met sec frame/concrete
frame and bathroom pods, we would look to use an out of town holding area for
the vehicles only calling them into the site when needed.
Two parking bays will be provided for loading and unloading vehicles. Traffic will
be directed around the site to minimise disruption to the direction of traffic.
Banksman will be provided, where it is necessary to guide a large vehicle into
the site.
The logistics plan along with the Construction Phase Health and Safety Plan will
be updated and maintain relevance to the project as the scheme progresses.
2.0
Management Philosophy
Our intention would be to construct and manage the project with a single point
of contact and responsibility throughout. The Operations Manager has full
responsibility with regard to management and site staff, enabling the project to
be tendered, managed and constructed with personnel that have a record of
achievement with design and build schemes.
The Pre-Construction phase of the project will be managed by the Operations
Manager who will liaise with the Client and Design Team to produce a detailed
Pre-Construction Programme against which the project will then be monitored.
At the same time they will input into the design process providing design
suggestions, buildability solutions and Whole Life Costing advice and appraisals
with the aim of maximising the value of the projects. Once the design and cost
plans have been worked up to a sufficient level of detail then a detailed budget
will be prepared.
The Operations Manager would examine every aspect of the project to ensure
that the cost and proposal submitted, reflected accurately the clients
aspirations in both quality, timescale and sustainability. He would also highlight,
within the tender submission, any areas of technical concern, and where
appropriate offer suitable alternative solutions which would benefit the Client
and the scheme.
At contract award the onsite Project Delivery Team would be introduced. The
Project Team will be fully briefed on the proposed scheme by the Operations
Manager including details of the Clients requirements. The Operations
Manager continues with a hands on involvement throughout the project.
To ensure that the production and distribution of design is managed effectively,
and the level of quality was maintained a Design Co-ordinator would be
allocated to the project. They would act as the fulcrum for the design
consultants; the project team; the sub-contractors; and the client with regard to
the transmission of information and design.
Supported by rigorous systems and procedures the Project Manager, Design
Co-ordinator and Operations Manager would track, monitor, and ensure that
design information was available and released to all parties in accordance with
agreed requirements.
Once on site the Project Manager supported by Operations Manager would
work from the information supplied by the Design Team ensuring that the
requirements set out were strictly adhered to from a quality and workmanship
perspective. Running in tandem to this would be out QA procedures to ensure
that quality is monitored and audited for continuous improvement.
The Project Manager will control the works on site including:
Safety
Quality Assurance
On-site Client liaison
Sub-contractor co-ordination
Materials procurement and delivery co-ordination
Sequencing of Operations
Plant requisitioning and delivery co-ordination
The Project Manager will liaise with the Site Foreman and Trades Foreman to
co-ordinate builders work activities, deliveries of materials and specialist plant
and equipment.
Financial
Financial control will be co-ordinated by the Operations Manager, the Site
Surveyor / Commercial Manager and the Project Manager.
All orders are processed by the Supply Chain Manager in conjunction with the
project team. He will be responsible for the overall co-ordination of plant, and
material procurement.
The Project Surveyor will have responsibility for maintaining control of
payment to sub-contractors and direct employees based upon information from
the Project Manager and regular attendance on site to measure works
completed and materials on site for application for payment by the client.
Technical Co-ordination and Planning
At both the pre-construction and construction stages the Operations Manager
ordinate the production of the tender / contract programme and will at the
request of the site management team undertake short term programming
throughout the duration of the project. He will be responsible for the production
of the following programmes:
The suppliers and sub-contractors will input into the overall contract programme
with regard to design, procurement, delivery and installation periods to ensure
realistic and buildable periods are shown.
Compliance
The site management team will prepare, prior to commencement of the works,
the construction phase Health and Safety Plan based upon the information
available in the pre-tender Health and Safety Plan, site specific risk
assessments and site rules. This document will be forwarded to the planning
supervisor for review and agreement.
The site team will complete and forward a copy of the HSE notification form,
F10 to the local area HSE Offices. A copy will be retained and displayed on
site.
On completion of the project, all health and safety documentation will be
returned to our Head Office for inspection and archiving. Our Technical
Services Department in conjunction with the project team will co-ordinate and
forward to the Planning Supervisor the project Health and Safety File, this will
include all as built information.
Interface / Involvement with Existing Adjacent Business
Consideration to be given to the following issues:
The main site access will be off Green Park Rd, Bath.
The perimeter of the site compound / works areas will be secured with
2.4m high heras / timber hoarding fencing as necessary. Access gates will
be included as required.
Statutory site notices will be applied around the site including BEWARE
OF CONSTRUCTION TRAFFIC signs at the site entrance.
Sub-contractors will be made responsible for their materials and plant but
co-ordinated through the site team.
Hard Hat
All works will be carried out in accordance with current Health and Safety
Legislation, Codes of Practice etc.
All sites are issued as standard with a site safety pack, this conforms to
the current Health and Safety Legislation and includes:
For each element of the work site specific Health and Safety information
will be required, this will include:
Risk Assessments
COSHH Assessments
PPE Provisions
Emergency Procedures
Notices will be erected at all entrances to the site advising the public of the
works and warning them to be vigilant and to exercise caution.
All plant and equipment on site will be operated and banked as necessary
by trained personnel, familiar with the site requirements.
All personnel will be inducted prior to starting on-site to ensure that they
are aware of the site specific safety requirements, environmental controls
and emergency procedures.
All personnel arriving at site will be required to report to the site office to
sign the attendance register. This register will be used in the event of a
fire / emergency to check personnel on site.
The site will be occupied at all times during working hours and securely
locked out of hours.
Site visits to carry out safety inspection take place at a minimum of every
3 weeks
Training and guidance on safety issues
Consultancy
Reporting directly to the Anglo Holt Construction Board of Directors
3.0
Construct
Following the client demolition works we propose to access the site from the
previously formed access of Green Park Rd; this will form the main access and
egress for the project.
The perimeter of the site will be hoarded to prevent unauthorised access.
The building will be demolished in accordance with the approved method
statement. Any contaminated waste will be transported to a registered tip by a
registered haulier.
A cut and fill exercise will be carried out across the site to establish formation
level all surplus arising will be removed from site.
From the limited information available at this stage, it is assumed that there will
be a small amount of contaminated waste produced from the material displaced
from the piling and asbestos from within the building.
Superstructure
After the first stage of the ground works are complete a Luffing Tower Crane will
be erected.
The tower crane will be used to erect the main building to full construction height.
The tower crane will be used to load and unload vehicles and erect the remainder
of the superstructure to the building.
An external independent scaffold will be erected around the building, which will
follow up with the main frame of the building.
Brickwork cladding will be loaded out by crane and will follow in accordance with
the construction programme.
Pre-fabricated bathroom pods will be fitted as the frame and floors progress,
deliveries are coordinated with the closing up of the floors.
Scaffolding
We have included for a full perimeter scaffold to be erected progressively with the
frame. The scaffolding will be designed to allow for all alterations to facilitate
other trades working on the external faade.
Initial discussions with highways have been made, however a scaffold notice and
footpath closure will be required.
Roof
The roof will be constructed with be constructed using a combination of traditional
slate to the visible elevations and green roof to the rear elevations.
Chimneys will be manufactured off site and lifted into position with the crane.
All material for the roof will be loaded out by Crane.
External Envelope
The external envelope shall consist of Bath Stone, render and rubble stone to the
elevations as shown on the tender drawings, the brickwork.
The brickwork will be serviced by the tower crane and forklift truck on scaffold
loading bays.
The building will be serviced from the Tower Crane positioned as shown in the
Site Logistics plan along with a telescopic forklift and a materials goods hoist.
Internal Works
Windows will be fixed as the frame progresses to maintain water tightness as the
building is erected, internal works will commence two floors behind the frame
erection on a rolling programme consisting of.
Services 1st fix
Patresses & Noggings
Plaster Boarding & Insulation
Plaster Skimming / tape & Jointing
Carpentry 1st fix
Services 2nd Fix
Carpentry 2nd Fix
Decoration
Floor Finishes
Install Fitted Furniture
External Works
License fees and application form will be sent to the highways authority on
contract appointment for the Section 278 works, a plan for all traffic management
and sequencing of works will be put together and presented to the highways
authority, the works will be planned around approval from the highways authority
and the dismantling of the external scaffold.
Finishes
The carpeting, bed installation and snagging will commence from the fourth floor
and progress down to the ground floor to reduce the number of trades visiting
completed areas.
Throughout the construction period a close liaison with the highways and local
authority will be essential to ensure good relationships are maintained throughout
the project which should help to minimise any disruption which may be
unavoidable.
For detailed sequencing and phasing of the project please see our tender
Construction Programme.
4.0
MANAGEMENT STRUCTURE
Structural
Architects
Engineers
Hitchman Stone
/Anglo Holt
Brazier Holt
Specialists
Subcontractor
Design
Subcontractors
and Direct Labour
Commercial
Management
Simon Garland
H&S Manager
Site Project
Manager
Shaun Lyons
Site Manager
Gary Morton
Justin de Vere
5.0
Prepared by: SL
Date: 5/9/12
Information contained in this Traffic Management Plan must be project specific and be communicated to all subcontractors with our Risk Assessment Information.
A CDM Layout plan must be prepared showing the traffic management arrangements together with other welfare and emergency information.
Requirements.
Action by
whom and
workforce?
by date.
At induction and
prominent signage
At induction and
At induction
routes.
Primary Traffic Routes;
Establish one-way systems where possible.
Physical protection where pedestrians are at risk of being
struck by vehicles or their loads.
Establish safe crossing points.
At induction and
prominent signage
At induction
At induction and
prominent signage
At induction and
prominent signage
Induction and in
orders for deliveries
Footpath closure
At induction and
prominent signage
Traffic Management
Site activities will be carefully controlled and monitored by the site staff
to ensure that access routes remain clear and that progress of the
works are not interrupted.
Dirty vehicle wheels will be washed before they pass onto the public
highway.
6.0