Você está na página 1de 21

NATIONAL HIGHWAYS AUTHORITY OF

INDIA
(MINISTRY OF ROAD TRANSPORT & HIGHWAYS)
(Government of India)
FOUR LANING OF GOA/KARNATAKA BORDER TO
KUNDAPUR SECTION OF NH - 17 FROM KM
93.700 TO KM 283.300 IN THE STATE OF
KARNATAKA UNDER NHDP PHASE IV ON
DESIGN, BUILD, OPERATE, TRANSFER (DBFOT)
TOLL BASIS.

MONTHLY PROGRESS REPORT


MARCH & APRIL 2014
Independent Engineer
AECOM RODIC CONSULTANTS PVT.LTD.

Concessionaire
IRB WESTCOAST TOLLWAY PRIVATE LIMITED

Principal EPC Contractor


IRB INFRASTRUCTURE DEVELOPERS LIMITED

Associate EPC Contractor

Page

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

MODERN ROAD MAKERS PVT. LTD

TABLE OF CONTENTS
1.0

Location Plan.............................................................................................

2.0

Salient Features of Project..........................................................................

3.0

Executive Summary....................................................................................

13.
23.
3.
43.
53.

Genral
ProjectLain
AreaTindGolgy
mCealitndrEvo
ExnisgtRhofWay

3.6
Pavement Condition of the time of
award..6
3.7
Existing
Structures.6
4.0
Scope
of
Work.6
4.1
Broad
Scope
of
Work
&
Current
Status..6
5.0 Project Milestones.........................................................................................

15.

ProjectCmplniMs:

6.0
Physical
Progress
and
Financial
Progress 8

6.1
Physical
Progress.8
6.2
Financial
Progress9
7.0

Design & Engineering and Mobilization of Independent Engineer................

8.0Mobilization
Status
of
Plant
&
Machinery
10
9.0
Safety
Measures

..10
10.0 Weather Report........................................................................................
11.0 Project / Site Organization........................................................................
12.0 Drawing & Design Status..........................................................................
13.0 Event Diary..............................................................................................
14.0 Progress Photographs
15.0 Correspondence with IE & NHAI
16.0 ROB Status
IRB WestcoastTollway Pvt. Ltd.

Page 1

MONTHLY PROGRESS REPORT MARCH& APRIL 2014


17.0 Issues Concerned with NHAI
Appendices
Appendix A ------ Weather Report for the month of March and April,2014
Appendix B ------ Progress Strip Chart - Highway
Appendix C ------ Progress Strip Chart Structure
Appendix D ------ QA and QC Test Summary Structure
Appendix E ------ Details of Source of Material
Appendix F ------ Site Organization Chart (Concessionaire & EPC)
Appendix G ------Manpower Status
Appendix H ------Drawing & Design Status
Appendix I -------Correspondence with IE & NHAI
Appendix J -------Environmental Mintigation Report Measures
Appendix K -------Issue Raised with NHAI (LA and Utility Shifting)
Appendix L -------Event Diary

1.0

Location Plan

IRB WestcoastTollway Pvt. Ltd.

Page 2

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

2.0

Salient Features of Project

SR. NO.

PARTICULARS

1.

Name of Project

2.

Total Length of
Project

3.

Contract / Phase

4.

Client / Authority

5.

Concessionaire

6.

Independent
Engineer

7.
8.
9.
10.
11.
12.
13.
14.

Principal EPC
Contractor
Associate EPC
Contractor
Total Project Cost
Date of signing of
Concession
Agreement
Appointed date
Construction
Completion Period
Construction
Completion date
Concession Period

IRB WestcoastTollway Pvt. Ltd.

DERSCRIPTION

Four laning of Goa/Karnataka Border to


Kundapur Section of NH-17 From Km. 93.700
to Km. 283.300 in The State of Karnataka
Under NHDP Phase IV On Design, Build,
Operate, Transfer (DBFOT) Toll Basis.
187.240 kms. (Design Length)
NHDP Phase-IV.
National Highways Authority of India.
(Ministry of Road Transport & Highways).
M/s IRB WestCoastTollway Pvt. Ltd., Mumbai 400072
M/s. AECOM Asia Company Ltd., in
Association with RODIC Consultants Pvt. Ltd.,
Gurgaon
M/s. IRB Infrastructure Developers Ltd.,
Mumbai
M/s Modern Road Makers Pvt. Ltd., Mumbai.
INR 1655.01Cr.
25th March, 2013.
3rd March, 2014.
910 days from Appointed date
28/08/2016
28 Years commencing from Appointed date
(including construction period of 910days)

Page 3

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

3.0 Executive Summary


3.1

General

The existing 2-lane National Highway No. 66 (formerly NH-17) starts


from Panvel in Maharashtra and passes through Karnataka on west
coast before reaching to Edapally (near Cochin) in Kerala.

The

project road starts from Goa - Karnataka border (km 93.700) and
ends at Kundapur (km 283.300).The total length of project road is
189.600 km based on existing km stones. The project highway
alignment is located between Arabian Sea coast and Western ghats
in Karnataka. At few stretches the highway is close to the Arabian
Sea (within 500m). NH: 63 from Gootyjoins the project road near
Ankola at km 135.450 and NH: 206 from Tumkurjoins at Honnavar at
Km 195.450.
Land use along the highway is predominantly for agriculture.
Majority of the land is being used for wet crop viz, Paddy, Cashew
plantation. There are number of settlements all along the road. The
settlements are for Residential, Commercial, Schools, Hospitals,
Petrol stations, Religious structures etc. Major settlements are close
to the existing highway at number of locations, i.e. Karwar port from
Km 108.300 to Km 108.800 (500m), Seabird compound wall from Km
109.000 to Km 115.800 (7.800 km length) and Navy Fence on either
side of project road approx. from Km 132.050 to Km 135.000 (2.950
km length).
The project consists of Design, Build, Finance, Operation and Transfer
of National Highway. Development of project consists of Four laning
of Goa/Karnataka Border to KundapurSection of NH17 from Km

IRB WestcoastTollway Pvt. Ltd.

Page 4

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

93+700 to Km. 283+300 [ Design Length 187. 240 Km ] in the


State of Karnataka.
3.2

Project Location

The project highway alignment is located between Arabian Sea coast


and Western ghats. At few stretches the highway is close to the
Arabian Sea (within 500m). The project road from Goa - Karnataka
border passes towards South through number of congested locations
vizKarwar (km 106.700), Karwar port (km 108.800), Navys Sea bird
project, Amadalli (km 122.950), Kumata (km 174.400), Haladipura
(km 186.600), Honnavara (km 194.500), Kasarakod (km 197.850),
Shirali (km 227.450), Bhatkal (km 232.350), and other villages in
Karawar and Udupi districts before reaching to Kundapur (Km
283.300).
3.3

Area Terrain and Geology

Terrain is classified by general slope of the country across the


highway alignment. Based on this criterion the highway passes
through Plain terrain for 120.130 km length, Rolling terrain for
45.670 km length and Mountainous terrain for 24.200 km length.
The project highway alignment is located between Arabian Sea coast
and Western Ghats in Karnataka. At few stretches the highway is
close to the Arabian Sea (within 500m). The project road passes
towards South from Goa-Karnataka border through number of
congested towns/villages vizKarwar (km 106.700), Karwar port (km
108.800), Navys Sea bird project, Amadalli (km 124.000), Kumata
(km 174.400), Haladipura (km 186.600), Honnavara (km 194.500),
Kasarakod (km 197.850), Shirali (km 227.450), Bhatkal (km
232.350), Shirur (km.245.000), Byndur (km.250.000), Maravanthe
(km. 266.000), Tallur (km.279.500)and other villages in Karawar and
Udupi districts before reaching Kundapur (Km 283.300).
3.4

Climate and Environment

The climate along the road is generally hot and humid as it is along
the coast line of Arabian Sea. The average annual rainfall along the
project road is greater than 3,000 mm. The project road receives
very high rainfall during June to August. Annual rainfall and
IRB WestcoastTollway Pvt. Ltd.

Page 5

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

temperature details @ Karwar and Kundapur regions are given in


table below.
Place
Kundapur
Karwar

Temperature

Rainfall (mm)
Actual

Normal

2540
4027.5

3556
4042.8

Temperature ( C)
Minimum
Maximum
15 C
27 C

34 C
34 C

The climate along the project road is generally categorized as:


Month
March, April & May
June, July, August & September
October November, December,

Season
Summer season
Rainy season
Pleasant & Cool

January & February


3.5

Existing Right of Way

Existing RightofWay along the project road varies from approx 11 m in mountainous
terrain to approx 51 m in plain terrain.

3.6

Pavement Condition at the time of Award

The existing pavement condition based on visual observation varies


from Very poor to good.
3.7

Existing Structures

There are 660 nos. of CD structures present in 189.6 km stretch of


project road. These include 13 nos. major bridges, 41 nos. minor
bridges and 606 nos. culverts. Out of 13 major bridges, one major
bridge located @ km 196.200(across SharavathiRiver) is retrofitted.
Existing major/minor bridges and culverts are of 2-lane width.

4.0 Scope of Work


The broad scope of project is as below:
i)

Construction of the Project


Concession Agreement.

IRB WestcoastTollway Pvt. Ltd.

Page 6

Highway

as

described

in

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

ii)

Operation and Maintenance of the Project Highway in


accordance with the provisions of Agreement; and

iii)

Performance and fulfillment of all other obligations of the


Concessionaire in accordance with the provisions of this
Agreement.

4.1

Broad Scope of Work & Current Status

Unit

Proposed
Facility

Existi
ng
Facili
ty

Widening from 2 Lane


to 4 Lane.

Km

165.31

Realignment

Km

21.93

Service Road (Km)

Km

61.262

Both Sides

Longitudinal Drain

Km

61.262

Both Sides

Major Bridges

Nos.

14

13

Flyovers

Nos.

04

Vehicular Underpass

Nos.

03

02

Cattle underpass

Nos.

06

Pedestrian underpass

Nos.

13

10

Minor Bridges

Nos.

39

41

11

ROB

Nos.

02

02

12

RUB

Nos.

01

04

13

Box Culverts

Nos.

66

14

Slab Culverts

Nos.

122

128

15

Hume Pipe Culverts

Nos.

385

478

16

Twin Tunnel Tubes (02


Nos.)

Km.

1.144

Sr.
No

Description

IRB WestcoastTollway Pvt. Ltd.

Page 7

Remarks

New
Construction
26 Nos
Reconstruction,
96
Nos
Widening
304 Nos
Reconstruction,
81
Nos
Widening

MONTHLY PROGRESS REPORT MARCH& APRIL 2014

Sr.
No

Description

Unit

Proposed
Facility

Existi
ng
Facili
ty

17

Toll Plazas

Nos.

03

18

Rest Area

No.

03

19

Bus
Bays&
Shelter

Nos.

53

20

Truck Lay Byes

Nos.

04

Bus

5.0 Project Milestones

IRB WestcoastTollway Pvt. Ltd.

Page 8

Remarks

5.1
Sr.
No.

Project Completion Milestones:

Milestones

Milestone
I

Milestone
II

Milestone
III

Scheduled
FourLaning
date

Period
from
Appointm
ent date

Schedule
d date of
Mileston
e

Criteria for achievement of


Milestones

Aug 8 ,
2014

Concessionaire
shall
have
commenced
construction
of
Project Highway and expended
not less than 10% of the total
capital cost set forth in the
Financial Package.

April6 ,
2015

Concessionaire
shall
have
commenced construction of all
bridges and expended not less
than 30 % of the total capital cost
set forth in the Financial Package.

650 days

Decemb
er12 ,
2015

Concessionaire
shall
have
commenced
construction
of
project facilities and expended not
less than 70 % of the total capital
cost set forth in the Financial
Package.

910 days

August.
28 ,
2016

Concessionaire
shall
have
completed
Four-Laning
in
accordance with the Concession
Agreement.

180 days

400 days

6.0 Physical Progress & Financial Progress.


6.1 Physical Progress

Site Clearance

0.208%

Cumulative
Physical
Progress (in
%)
0.011%

Earth Work

8.132%

0.145%

Granular Sub-base Course & Base Course


(Non Bituminous)

7.194%

0.000%

Bituminous Course

26.630%

0.000%

Toll Plaza

2.711%

0.000%

Traffic Signs, Road Marking & Other Road


Appurtenances

3.146%

0.000%

Flyover

5.355%

0.385%

Item
No.

Item Description

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Weightage
(in %)

Page 9

Item
No.

Item Description

Weightage
(in %)

Cumulative
Physical
Progress (in
%)

0.824%

0.077%

ROB, RUB

Major Bridges

17.952%

1.795%

10

Minor Bridges

2.735%

0.400%

11

Underpasses

3.643%

0.682%

12

Vehicular Underpasses

1.313%

0.108%

13

Culverts

5.548%

0.000%

14

Drainage and Protective Works

5.240%

0.000%

15

Retaining Wall & Toe Wall

0.000%

0.000%

16

Repairs & Rehabilitation of Bridges

1.072%

0.000%

17

Maintenance of Roads

0.488%

0.000%

18

Electrical and Other Works

2.447%

0.000%

19

HTMS

0.440%

0.000%

20

Other & Miscellaneous Works

1.002%

0.000%

21

Tunnelling

1.987%

0.000%

22

Extra Items

1.933%

0.224%

100%

3.826%

TOTAL PHYSICAL PROGRES =


6.2 Financial Progress
Month
Mar-14
Apr-14
May-14
Jun-14
Jul-14
Aug-14
Sep-14
Oct-14
Nov-14

Achieved Progress
Monthly % of
Cumulative % of
Financial
Financial Progress
Progress
17.05%
17.05%
1.51%
18.56%

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 10

Month

Achieved Progress
Monthly % of
Cumulative % of
Financial
Financial Progress
Progress

Dec-14
Jan-15
Feb-15
Mar-15
Apr-15
May-15
Jun-15
Jul-15
Aug-15
Sep-15
Oct-15
Nov-15
Dec-15
Jan-16
Feb-16
Mar-16
Apr-16
May-16
Jun-16
Jul-16
Aug-16

b) S-Curve
See Appendix - M

7.0 Design & Engineering and Mobilization of


Independent Engineer
7a) Design & Engineering
The Associate EPC Contractors M/S Modern Road Makers Limited, have
retained the services of M/s L&T-Ramboll Consulting Engineers Limited and
M/s Aarvee Associates architects engineers & consultants Pvt. Ltd. for Design
and Engineering of this project.
7b) Mobilization of Independent Engineer (IE)
M/s. AECOM Asia Company Ltd., in Association with RODIC Consultants Pvt.
Ltd., Gurgaonhas been appointed by NHAI, ref: NHAI letter no.
12019/1/2012/PIU(Mnglr)/37 dated 27.03.14 as the Independent Engineer for
the project. M/s AECOM RODIC Consultants Pvt. Ltdhas mobilized their Key
Staff (Team Leader Cum Senior Highway Engineer, Resident Engineer, and

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 11

Bridge/Structural Engineer at Site, on18thMarch, 2014. They are functioning


fromtheir office at Kundapur.

8.0 Mobilization Status of Plant & Machinery


Sl.No
.

Category

Capacity

Deployed
at Site

Excavator with Bucket

60 - 80 Cum/Hr.

02

Excavator with Breaker

60 - 80 Cum/Hr.

01

JCB (3DX)

0.23 1.0 Cum

03

JCB (Wheel Loader, 430 Z)

1.75 Cum

01

Soil Compactor

10 T

01

Water Tanker

10 KL

01

Dumper

10 MT

04

40 KVA D.G. Set

02

25 KVA D.G. Set

02

Remarks

9.0 Safety Measures


Safety measures taken during the month that is at all the locations of NH- 66 (Formerly NH-17),
adequate safety measures i.e. barricades, warning signs, cautionary signs etc. at structures
locations and barricades, gunny bags, safety ribbons and cautionary boards etc. at excavated
locations of NH-17 as per stipulation of IRC as well as additional boards are also provided as
desired by NHAI/IE during site visit.

10.0

Weather Report
See in Appendix-A

11.0

Project / Site Organization

11.1 Site Organization Chart (Concessionaire & EPC) See in AppendixF


11.2 Manpower Status See in Appendix-G

12.0

Drawing & Design Status


See in Appendix-H

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 12

13.0
Sr.
No
.
1

Event Diary

Date
19.03.
2014

Officers
Visited /
Meeting
Conducted
Shri Ram Mishra
Shri K. M. Hegre
Shri. K.
Sriniwasrao
Shri. J.P.Nandi
Sh. B.R.Suresh

PDs Site Visit


2 03.04.1 Shri Ram Mishra

Designation

Organization

Project Dirctor

NHAI

Manager
(Tech.)
Team Leader

NHAI

Dy. Project
Head
General
Manager
(Projects)

IRB WTPL

IE

IRB WTPL

Project Dirctor

NHAI

Manager
(Tech.)
General
Manager
(Projects)

NHAI

Shri K. M. Hegre
Sh. B.R.Suresh

IRB WTPL

Remark
Meeting
held at PIUoffice,
NHAI,
Mangalore.
Points
discussed:
See in
Appendix L

Site visit
for
verificatio
n of Utility
Shifting
i.e.
Electrical&
Water
Supply
Shifting.

See
in
Appendix
-L

Meeting on 23.04.2014
3

23.04.20
14

Shri Ram Mishra

Project
Director
Shri K. M. Hegre
Manager
(Tech.)
Shri.
Srinivasa Team Leader
Rao. K
Shri. A.K.Singh
Resident
Engineer

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

NHAI
NHAI
IE
IE

Meeting
held at
PIUoffice,
NHAI,
Mangalor
e.
Points

Page 13

Shri. B.R.Suresh
Shri.
PramodSawalkar
Shri. R. Acharya

Shri. Prasad Joshi

14.0

GM(Project)
General
Manager
General
Manager
(Liaison)
EDP Incharge

IRB WTPL
IRB WTPL
IRB WTPL

discusse
d: See in
Appendi
x-L

IRB WTPL

Progress Photographs

Testing for Foundation at Aghanashini River km. 169+360

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 14

Testing for Foundation at Aghanashini River km. 169+360

Testing for Foundation at Haladi River km. 278+530

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 15

Testing for Foundation at Haladi River km. 279+540

Testing for Foundation at Kollur River km. 272+840

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 16

Testing for Foundation at Sharavathi River km. 194+515

Cleraing and grubbing (C&G) Stared at Ch. 255.750 to 256.100

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 17

Marking for Clearing and Gurbering work at at Ch. 255.750 to 256.100

Work in Progress for Culvert Work

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 18

Work in Progress for Culvert Work

Maintenance work (Potholes reparing) at Chainage 276+800

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 19

Maintenance work (Potholes repairing) at Ch. 272+840

15.0

Correspondence with IE & NHAI

See Appendix I

16.0

ROB Status:

The ROB alternative proposal is under consideration by IE, which would


be forwarded to KRCL Subsequently.

17.0

Issues Concerned with NHAI

See Appendix-K

AHMEDABAD VADODARA SUPER EXPRESS TOLWAY PVT.

Page 20

Você também pode gostar