Escolar Documentos
Profissional Documentos
Cultura Documentos
a r t i c l e
i n f o
Article history:
Received 21 October 2015
Received in revised form 22 January 2016
Accepted 24 January 2016
Available online 26 February 2016
Keywords:
Experience
Knowledge
Inspection
Maintenance
Risk assessment
Equipment failure
Intelligent pigging
Safety
Environment
Offshore production
a b s t r a c t
The proposed work is incorporated into the research theme concerning the maintenance and inspection
of sensitive facilities in production systems. It is essential to promote the methodological deployment
of inspection techniques to ensure the good functioning of services provided by complex production
systems as well as their different components. We use a risk-based inspection methodology offering
an organized analysis with knowledge sharing for collaborative possibilities in a multidisciplinary context and it consists of the following steps: data acquisition and information collection, failure analysis
(probability and consequences), risk assessment, inspection plan, mitigation and revaluation. The application of this methodology can improve the maintenance management strategies of industrial companies.
The inspection department is able to forecast its potential failure, root causes and impacts on the safe
operation of the considered production system, based on a reliable inventory of existing situations and
review options for continuous improvement in maintenance management. In particular, we addressed
the application of a Risk-Based Inspection (RBI) methodology in the French petroleum company with
operations on the west coast of central and southern Africa. The incorporation of expert knowledge into
risk assessment is helping to nd the best preventive plan for pipeline inspection in the case study.
2016 Elsevier Ltd. All rights reserved.
1. Introduction
The current management frameworks of industrial enterprises
must integrate engineering standards and recommended practices
to reect the increasing complexity of production systems. In addition, the legislation requires that enterprises comply with applicable normative rules by using industrial practices that are environmentally and logistically sustainable. In certain circumstances,
Abbreviations: Ath, Allowed minimum THickness; CMIMS, Computerized Maintenance and Inspection Management System; Cof, Consequence of the failure;
CL, Corrosion Likelihood; CR, Corrosion Rate; EFF, Effectiveness; ESD, Electrical
Schematic Diagram; FPSO, Floating Production, Storage and Ofoading; HSE, Health,
Safety and Environment; HV, High-Voltage; HMI, Humanmachine interface; LAY,
Lay-out; Lof, Likelihood of failure; LV, Low-Voltage; MAOP, Maximum Allowable
Operating Pressure; MOP, Maximum Operating Pressure; MOGA, Multi-Objective
Genetic Algorithm; NCL, Natural Corrosion Likelihood; P&ID, Piping and Instrumentation Diagram; PCS, Process Control System; PFD, Process Flow Diagram; PSS,
Process Safety System; PLC, Programmable Logic Controller; RBI, Risk-Based Inspection; RCM, Reliability Centred Maintenance; SLD, Single-Line Diagram; ST, State;
SLD/C, Structural design or construction failure Likehood; SLthird, Structural failure
third party Likehood; SLmec, Structural mechanical failure Likehood; SLnat, Structural natural failure Likehood; SL, Structure Likelihood; SAP, Systems, Applications
& Products in Data Processing; UFD, Utility Flow Diagram.
Tel.: +33 6 24 30 23 37; fax: +33 5 62 44 27 08.
E-mail address: Bernard.Kamsu-Foguem@enit.fr
http://dx.doi.org/10.1016/j.apor.2016.01.009
0141-1187/ 2016 Elsevier Ltd. All rights reserved.
the law obliges companies to make risk information (threat cryptograms and the associated risk and safety descriptions) available
on the industrial sites. The increasing complexity of oil and gas
installations and operations, along with growing public awareness
to ensure higher levels of safety, has put great pressure on the
designers and operators to nd innovative solutions to ensure safe
as well as economically viable operation [1]. Reliability and Maintenance with tools such as RCM (Reliability Centred Maintenance)
and RBI (Risk-Based Inspection) contribute to collaboratively working towards seeking reasonable and practical solutions in the industrial settings [2]. In scientic literature, there are different categories of risk analysis and risk-assessment methods and techniques
(qualitative, quantitative and hybrid approaches) [3]. A varied
range of methodologies presently in use for risk-based inspection
includes marketable and internal software packages particular to
explicit plants [4]. In the complex production systems, the work
package of maintenance engineering is important to ensure continuity of services, optimize production capacity, improve safety and
reduce the environmental impact. Risk Based Inspection (RBI) is an
interesting maintenance perspective with an incremental stepwise
procedure used to examine sensitive equipment such as pressure
vessels, heat exchangers and piping in complex industrial plants
[5]. RBI provides a modelling process for organizations to control its reliability, safety and health aspects, ensure maintenance
compliance and to iteratively improve the technical performance
2. Background
2.1. Practices of risk-based inspection
Risk-based Inspection (RBI) offers practical ways for the implementation of an inspection process that provides to maintenance
actors a method of assessing the probability and effect of failure,
evaluating risk level and generating the kinds of relevant actions
that can lead to development of required risk management policies
[7]. There are different illustrations of RBI practices which increase
cost effective actions and can be considered as promising developments to shift from a reactive to a proactive maintenance management in various domains. We mention as examples the implementation of risk assessment in civil engineering applications [8]. In the
petrochemical and chemical industries, the deployment of online
and ofine inspection procedures to equipment such as pipelines
has led to substantial improvements in operational reliability and
the prevention of incidents (e.g. Management of Corrosion) [9,10].
In nuclear engineering and design, there are current practices and
trends in the risk-based inspection and maintenance for safety
evaluation [11]. The RBI method was used to assess the risk of largescale crude oil tanks in order to determine the acceptable risk and
internal inspection interval of tanks [12]. There are some examples of the application of risk-based methods in industrial coal-red
boilers with some interesting results [13]. RBI programmes are also
established for reliability analysis purposes in heavy water plants
with the assessment of failure pressure and estimation of the frontier state functional analysis [14]. The RBI methods are also adopted
and useful in the offshore wind energy industry for the organization
of maintenance logistics with signicant inuences on important
cost parameters of energy production [1517].
In general, the majority of industrial applications of RBI methodologies are used in the renery systems and petrochemical sectors
[18]. RBI addresses clearly the threats (personnel death and injury,
damage to the environment and nancial loss) to the integrity
of the asset and it is performed for piping and vessels, including
heat exchangers, tanks, pressure vessels, and lters [19]. Pipeline
system inspections can be done either internally or externally as
133
134
Table 1
General consequence classication [21].
Class
Production
High
Medium
Low
Table 2
The classication of equipment according their technological complexity.
Technological complexity
Equipment
Low
Medium
High
Static equipment
without instruments
Pipelines
Storage tanks
Incinerators
...
All compressors
Gas turbines
Rotary hydraulic equipment
Electrical components (voltage >400 V)
3. Industrial challenge
In general, the maintenance and inspection activities are conducted in compliance with the considered enterprise policy with
the following objectives:
Safety and health of personnel and facilities
Care for the environment
Sustained operation and performance of the installations over
time
Maintain asset integrity
Retained investment capital value of plant and structures
Compliance with applicable local legislation
135
136
Table 3
The contents of various levels of the functional hierarchy.
Level 1 Site
Level 2 Sector
Level 3 System
Level 4 Unit
Level 6 Sub-Tag
The site is a geographical location of the equipment. For example, project facilities CLOV are located in block 17 with the code CLO.
The sector describes a set of the process system. This corresponds to a single installation section. For example for CLOV, we have the
following description.
Code
Designation
Description
Topside
All that is on the deck of the FPSO
FPSOT
Hull
Inside the shell
FPSOH
Accommodation
The living quarters
FPSOA
Buoy
Buoy of loading operations
BUOY
SUB
Subsea
Underwater workplaces
A system is a set of interdependent equipment sharing common functional characteristics. For example, the treatment of water from
the injection wells comprises all functional handling units contributing to the injection of water: ltration, treatment and injection.
A set of equipment dedicated to a specic process or a utility function (for example, water ltration within the water treatment
system). A unit is a part of the installation which is operatively independent. It is also an entity which may be controlled. The unit is
identied by a code of the subsystems.
The tag represents a unique functional identication of a device in a site. All equipment subject to maintenance, inspection or
certication must be tag (e.g. pumps, boats, boilers and, vessels). Tags are dened mainly during the engineering phase and are listed
on the following project documents: P&ID, PFD, UFD and Equipment List.
This concerns the creation of other sub-levels from the main-tag. The sub-tags can facilitate the description of instruments to identify.
An instrument, such as a pressure transmitter, is always connected to an automated control and safety. The instruments belong to one
of the following categories:
Process Control System (PCS) (e.g. electronic modules, Programmable Logic Controller (PLC), Humanmachine interface (HMI)).
Process Safety System (PSS) (e.g. valves and actuators).
Process Control Instrumentation (e.g. gauges, detectors, indicators, transmitters, switches).
137
Risk
ranking
Inspection
plan
Mitigation
(if any)
Probability
of failure
Reassessment
Fig. 2. The risk based inspection organization process [39].
138
Table 4
Relevant data concerning the internal part of pipelines.
Depth
Total
In body of pipe
Weld area
In body of pipe
Weld area
70%
60% to <70%
50% to <60%
40% to <50%
30% to <40%
20% to <30%
10% to <20%
1
1
5
20
59
357
2
21
23
7
1
1
7
41
82
364
Total
443
53
496
5. Analysis
5.1. Situation of internal part of petroleum pipelines
We are interested here only in the internal portion of the
pipelines. There are two points of corrosion by more than 50% deep.
The nominal wall thickness is 17.5 [mm] which can be reduced up
to 50 [%] as a result of corrosion.
The corrosion rate is calculated from thickness data available
from equipment inspections. In total there are 492 points of corrosion with varying depths below 70% (as described in Table 4).
The equivalent allowed maximum depth is 80%. Table 4 shows
certain relevant data concerning the internal part of pipelines. The
data presented in this table are real and they are collected by intelligent pigging that is a highly sophisticated instrument measuring
pipeline wall thickness and metal loss by direct measurement of
the thickness of the pipeline wall.
After the rst inspection of the internal part of pipelines,
corrosion is found with a dense and regular distribution of the deterioration at the base and along the internal parts. The inspection of
pipelines can detect metal loss and corrosion through electromagnetic waves.
The corrosion rate is calculated from thickness data available
from equipment inspections. However, if corrosion rates cannot be
determined from thickness inspection data, conservative estimates
may be established using expert opinions from knowledgeable
materials. The maximum corrosion depth in body of pipe is based
on Table 4 for the presence of one occurrence in the interval 60% to
<70% (0.64 * 17.5 = 11.2 mm). The result is a conservative value for
the estimated corrosion rate, but it is not always the case. There is
a clear distinction between corrosion rates in body and weld area.
The maximum corrosion depth in weld area is based on Table 4
for the presence of two occurrences in the interval 40% to <50%
(0.50 * 17.5 = 8.75 mm).
5.2. The realization of the implementation plan
Step 1: the identication of the probability of failure to establish a risk matrix. In the general, the probability of failure can be
determined as a linear combination of corrosion (i.e. environment)
and structural induced failure. The weights used in the linear combination depend on the contextual assumptions and inspection
techniques that are used in the risk based inspection methodology.
In the considered context, it is assumed that corrosion (i.e. environment) and structural induced failure have an equitable contribution
to pipeline failure. In addition, CL and SL are levels of probability
which are in between the numbers 1 and 5, 1 CL 5 and 1 SL 5
then 1 0.5 * CL + 0.5 * SL 5.
The level of probability is given by the following formula:
Likelihood of failure (Lof) = 50% CL + 50% SL.
139
Table 5
Relations between production loss and nancial consequence.
Production loss
Financial
consequence
5
4
3
2
1
140
CL
Interval
CL
Interval
CL
Interval
1
2
3
4
5
Max (15, Ti T0 )
10
5
3
2
1
2
3
4
5
Max (20, Ti T0 )
12
8
4
3
1
2
3
4
5
No inspection
15
10
5
Not applicable
Acknowledgments
The authors are grateful to Ms. Valerie Stevens for his proofreading and editing service. We also thank some anonymous reviewers
for their helpful feedback and observations on previous version of
the paper.
References
[1] Kamsu Foguem B, Rigal F, Mauget F. Mining association rules for the quality
improvement of the production process. Expert Syst Appl 2013;40(4):103445.
[2] Calixto E. Reliability and maintenance. Gas and oil reliability engineering; 2013.
p. 11967 [Chapter 3].
[3] Marhavilas PK, Koulouriotis D, Gemeni V. Risk analysis and assessment
methodologies in the work sites: on a review, classication and comparative
study of the scientic literature of the period 20002009. J Loss Prev Process
Ind 2011;24(5):477523.
[4] Khan FI, Sadiq R, Haddara MM. Risk-based inspection and maintenance (RBIM):
multi-attribute decision-making with aggregative risk analysis. Process Saf
Environ Prot 2004;82(6):398411.
[5] El-Reedy M. Risk-based inspection technique. Gulf Professional Publishing;
2012 [Chapter 8] ASIN: B00DGSWO4S.
[6] Sutton I. Maintenance and inspection. Plant design and operations; 2015. p.
2445 [Chapter 2].
141
[7] Bai Y, Bai Q. Risk-based inspection. Subsea pipeline integrity and risk management; 2014. p. 21332 [Chapter 9].
[8] Faber MH, Stewart MG. Risk assessment for civil engineering facilities: critical
overview and discussion. Reliab Eng Syst Saf 2003;80(2):17384.
[9] Britton CF. 4.36 Corrosion monitoring and inspection. Shreirs Corrosion, vol.
4; 2010. p. 311766.
[10] Richardson JA. 4.40 Management of corrosion in the petrochemical and chemical industries. Shreirs Corrosion, vol. 4; 2010. p. 320729.
[11] Jovanovic A. Risk-based inspection and maintenance in power and process
plants in Europe. Nucl Eng Des 2003;226(2):16582.
[12] Shuai J, Han K, Xu X. Risk-based inspection for large-scale crude oil tanks. J Loss
Prev Process Ind 2012;25(1):16675.
[13] Price JWH. 10 Risk-based inspection and life management in boilers in
coal power plants. Coal power plant materials and life assessment; 2014.
p. 26587.
[14] Santosh A, Vinod G, Shrivastava OP, Saraf RK, Ghosh AK, Kushwaha HS. Reliability analysis of pipelines carrying H2S for risk based inspection of heavy water
plants. Reliab Eng Syst Saf 2006;91(2):16370.
[15] Toft HS, Branner K, Berring P, Srensen JD. Defect distribution and reliability
assessment of wind turbine blades. Eng Struct 2011;33(1):17180.
[16] Nielsen JJ, Srensen JD. On risk-based operation and maintenance of offshore
wind turbine components. Reliab Eng Syst Saf 2011;96(1):21829.
[17] Shaee M. Maintenance logistics organization for offshore wind energy: current progress and future perspectives. Renew Energy 2015;77:18293.
[18] Chang M-K, Chang R-R, Shu C-M, Lin K-N. Application of risk based inspection in
renery and processing piping. J Loss Prev Process Ind 2005;18(46):397402.
[19] Recommended Practice DNV-RP-G101. Risk based inspection of offshore top
sides static mechanical equipment, DET NORSKE VERITAS (DNV); 2010.
[20] Recommended Practice DNV-RP-F116. Integrity management of submarine
pipeline systems, DET NORSKE VERITAS (DNV); 2009.
[21] NORSOK STANDARD Z-008. Criticality analysis for maintenance purposes
issued by NTS (Norwegian Technology Centre) Rev. 2; 2001.
[22] NORSOK STANDARD Z-008. Criticality analysis for maintenance purposes,
issued by NTS (Norwegian Technology Centre). 3rd ed; 2011.
[23] Kamsu Foguem B, Coudert T, Geneste L, Beler C. Knowledge formalization
in experience feedback processes: an ontology-based approach. Comput Ind
2008;59(7):694710.
[24] Kamsu-Foguem B. Knowledge-based support in Non-Destructive Testing
for health monitoring of aircraft structures. Adv Eng Inform (ADVEI)
2012;26(4):85969.
[25] Kamsu-Foguem B, Fonbeyin HA. Experience modeling with graphs encoded
knowledge for construction industry. Comput Ind 2015;70:7988.
[26] Kamsu-Foguem B, Noyes D. Graph-based reasoning in collaborative knowledge
management for industrial maintenance. Comput Ind 2013;64(8):9981013.
[27] Kamsu-Foguem B, Fondja Wandji Y, Tchuent-Foguem G, Tchoffa D. Experienced knowledge for the description of maintenance packages. J Manuf Syst
2014;37(Part 1):44855.
[28] Elaya Perumal K. Procedia Eng 2014;86:597605.
[29] Kamsu-Foguem B, Mathieu Y. Software architecture knowledge for intelligent
light maintenance. Adv Eng Softw 2014;67:12535.
[30] API. API RP 581 Risk based inspection technology. 2nd ed. Washington, DC:
American Petroleum Institute; 2008.
[31] Breuker J. A cognitive science perspective on knowledge acquisition. Int J Hum
Comput Stud 2013;71(2):17783.
[32] Abel M, Lima Silva LA, Campbell JA, De Ros LF. Knowledge acquisition
and interpretation problem-solving methods for visual expertise: S study of
petroleum-reservoir evaluation. J Pet Sci Eng 2005;47(12):5169.
[33] Berg H-P, Gersinska R, Sievers J. Procedure for probabilistic safety assessment of
leaks and breaks of piping systems. Int J Press Vessels Pip 2010;87(23):949.
[34] Wei W, Cheng G, Hu H, Zhou Q. Risk analysis of corrosion failures of equipment
in rening and petrochemical plants based on fuzzy set theory. Eng Fail Anal
2013;32:2334.
[35] Singh M, Markeset T. A methodology for risk-based inspection planning of
oil and gas pipes based on fuzzy logic framework. Eng Fail Anal 2009;16(7):
2098113.
[36] Saidi E, Anvaripour B, Jaderi F, Nabhani N. Fuzzy risk modeling of process
operations in the oil and gas reneries. J Loss Prev Process Ind 2014;30:6373.
[37] Arunraj NS, Maiti J. Risk-based maintenance techniques and applications. J
Hazard Mater 2007;142(3):65361.
[38] das Chagas Moura M, Lins ID, Droguett EL, Soares RF, Pascual R. A multiobjective genetic algorithm for determining efcient risk-based inspection
programs. Reliab Eng Syst Saf 2015;133:25365.
[39] API. API RP 580 Recommended practice for risk-based inspection. 2nd ed.
Washington, DC: American Petroleum Institute; 2009.
[40] ISO. ISO 17776 Petroleum and natural gas industries offshore production
installations guidelines on tools and techniques for hazard identication and
risk assessment. 1st ed. Geneva, Switzerland: The International Organization
for Standardization (ISO); 2000.
[41] Potes Ruiz PA, Kamsu Foguem B, Grabot B. Generating knowledge in maintenance from experience feedback. Knowl-Based Syst 2014;68:420.
[42] Potes Ruiz PA, Kamsu Foguem B, Noyes D. Knowledge reuse integrating the collaboration from experts in industrial maintenance management. Knowl-Based
Syst 2013;50:17186.
[43] Jabrouni H, Kamsu Foguem B, Geneste L, Vaysse C. Analysis reuse exploiting
taxonomical information and belief assignment in industrial problem solving.
Comput Ind 2013;64(8):103544.
142