Escolar Documentos
Profissional Documentos
Cultura Documentos
96
Web-splitting cracks have received a good deal of attention in the literature. Previous research has focused on
the causes,1,2 design models,36 reject/repair criteria,7 and
control of web-splitting cracks.3,8,9 Research presented in
this paper adds to the body of knowledge by comparing
various detailing schemes for controlling or impeding websplitting cracks. Schemes included in the research program
were vertical end-region reinforcement as required by the
2010 American Association of State Highway and Transportation Officials AASHTO LRFD Bridge Design Specifications,10 increased end-region vertical reinforcement
using 1 in. (25 mm) diameter bars, vertical end-region
posttensioning, and partial debonding of 45% of prestressing strands.
Figure 1. End-region splitting cracks (enhanced) in test specimens. Note: CT = control specimen; LB = specimen with large reinforcing bars; PT = vertically
posttensioned specimen; SL = specimen with 23 strands partially shielding.
PCI Journal | S p r i n g 2014
97
Specimen design
and construction
Two 63 in. (1600 mm) deep Florida I-beam (FIB-63) test
girders were used in this project. Both of the beams were
49 ft 6 in. (15.1 m) long and had a total initial prestressing
force of 2280 kip (10,150 kN). Each end of each girder
was uniquely detailed and is referred to in this paper as
a distinct specimen. Essential details and basic material
properties are presented in this paper. A more comprehensive discussion of specimen design and construction can be
found in Ross et al.11 Specimens were given the labels CT,
SL, PT, and LB.
Specimen CT was the control specimen and was detailed
to exceed the area of splitting resistance reinforcement
required by LRFD by approximately 8%. In total 16 no. 5
(no. 16M) bars were placed in the end region.
Specimen SL was located at the opposite end of specimen
CT and had the same quantity of end-region reinforcement.
Of the 52 strands in SL, 23 were partially shielded using
plastic sheathing for 5 ft (1.5 m) from the end of the beam.
This moved the transfer length for the shielded strands
away from the end and reduced the tensile stresses in SL
that affected web-splitting cracks.
The end of specimen PT was vertically posttensioned prior
to prestress transfer to counteract vertical tensile stresses
and end-region cracking. The area of end reinforcement
in PT, including posttension rods, was 38% less than in
control specimen CT.
Prestressing in specimens PT, LB, and CT was intentionally designed to exceed the longitudinal stress limits from
LRFD specifications section 5.9.4.1 with the intention of
promoting the end-region cracking to amplify the effects
of varying the end-region detailing. Maximum calculated
longitudinal stresses (after transfer) in the end region of
these specimens were 4.4 ksi (30 MPa) compression and
1 ksi (7 MPa) tension. These stresses exceeded the
compression limit by 22% and the tension limit by 70%.
Because 45% of the strands in SL were shielded, the longitudinal end-region stresses in SL were approximately half
of the stresses in the other specimens.
Specimens CT and SL both had 16 no. 5 (no. 16M) vertical
bars placed within 16.5 in. (420 mm) of the end. Of these
bars, 12 were placed within 9.5 in. (240 mm) of the end.
This quantity of reinforcement exceeded the area of steel
required by LRFD specifications by 8% for specimen CT
and by 94% for specimen SL.
Vertical reinforcement at the end of specimen PT included
six 58 in. (16 mm) diameter posttensioned all-thread rods
and four no. 5 (no. 16M) bars. The area of vertical reinforcement in specimen PT was 38% less than in specimen
CT and 32% less than required by LRFD specifications.
Polyvinyl chloride pipes were used as ungrouted posttensioning ducts for the rods. Pipes stopped 15 in. (380 mm)
above the bearing plate to allow for development of the
rods. To further aid in development, nuts were placed at the
bottom of each rod. The top of the rods passed through a
3
4 in. (19 mm) thick steel plate, which sat on the top flange.
Posttensioning was applied prior to prestress transfer and
was accomplished by tightening nuts against the steel plate
on the top flange (Fig. 3).
Details
98
designed to test the effects of excessive shielding on endregion cracking and shear capacity.
Figure 2. Specimen details. Note: CT = control specimen; LB = specimen with large reinforcing bars; PT = vertically posttensioned specimen; SL = specimen with
23 strands partially shielded. No. 4 = 13M; no. 5 = 16M; 1 in. = 25.4 mm; 1 ft = 0.305 m; 1 kip = 4.448 kN.
PCI Journal | S p r i n g 2014
99
All specimens were designed for testing without cast-inplace concrete topping slabs because they would have
increased specimen shear capacities beyond the capabilities of the available load test equipment. Because slabs
were not used, vertical reinforcement was developed using
hooks in the top flange. The top flange did not provide
code-specified cover requirements for the hooks but was
d
ne
io
s
ten
ry
a
bru
Fe
ry
rua
13
17
ry
a
bru
e
rF
21
20 fe
ry trans
a
ru
a
S
eb tress to 24
ec
F
t
e
d
r
0
es
e
nc
ov g, pr ary 2
m
Co
u
n
e
i
r
s r on Feb
rm si
6
22
Fo stten tions
ch ril 9
ch
r
r
o
c
a
a
p
P pe
n M ion M ion A
Ins
tio
t
t
c
c
c
pe
pe spe
Ins
In
Ins
ds
n
tra
Feb
eb
F
st
March
2012
April
June
e1
un to 13
J
ab 1
o l une
t
13
d nJ
to
e
k
5
c tio
e
Tru pec
un
J
s
g
In
tin
tes
d
a
Lo
May
9 ft 4.5 in.
Load
42 ft 10.5 in.
10 x 32 in. bearing pad
at each support
First setup
9 ft 4.5 in.
Test procedures
Strain and crack data were collected throughout the test
program. Strain data are not discussed in this paper but
are discussed in Ross et al.11 Figure 4 lists the dates that
crack data were collected by visual inspection. Visual
inspections included marking cracks with a crayon and
documenting locations and lengths by photograph. Crack
widths were measured at one or two locations along each
crack using a microscope with a precision of +/ 0.001 in.
(0.025 mm).
Posttension forces in two rods in specimen PT were monitored using load cells positioned between the nut and the
bearing plate (Fig. 3). Force data were continuously logged
during posttensioning and during prestress transfer.
Load, displacement, concrete strain, and strand slip data
were continuously monitored and logged during load testing using a computerized data acquisition system. Load
data were collected from load cells at the load point. Vertical displacements were obtained using linear variable differential transformers (LVDTs) placed above each support
and at the load point. Concrete strain data were collected
from gauges bonded to the concrete surface. Strand slip
relative to the concrete was measured using linear potentiometers mounted on selected strands.
Load tests were conducted on both ends of each girder,
that is, on each specimen. Specimens were loaded in
three-point bending at a shear spantodepth ratio of approximately 2.0 (Fig. 5). After the first end (specimen) was
tested, the supports and load point were moved and the
opposite end was tested.
Load was applied to specimens using side-by-side hydraulic actuators. Load rate was approximately 400 lb/second
(180 kg/second) and was controlled by adjusting a pump
that pressurized the hydraulic system. Load was distributed
from the actuators to the girders through steel plates and
a 10 30 in. (250 760 mm) bearing pad. For specimen
LB, the bearing pad at the load point was oriented with
the 30 in. (760 mm) dimension perpendicular to the span
length. In this orientation, the load was distributed transversely across the top flange, resulting in an undesirable
Load
7.5
in.
42 ft 10.5 in.
Second setup
Figure 5. Test setup. 1 in. = 25.4 mm; 1 ft = 0.305 m.
101
Specimen CT
0 1 2
4
feet
Specimen SL
During
prestress
transfer
1 days
after
transfer
30 days
after
transfer
Before
load testing
112 days
after transfer
Specimen PT
Specimen LB
During
prestress
transfer
1 days
after
transfer
30 days
after
transfer
Before
load testing
112 days
after transfer
Figure 6. Crack growth. Note: blue lines = previously observed cracks; cross-hatched areas = areas not observed because of beam fromwork; red lines = newly
observed cracks; CT = control specimen, SL = specimen with 23 strands partially shielded, PT = vertically posttensioned, specimen LB = specimen with large
reinforcing bars. 1 ft = 0.305 m.
102
300
1.50
336
288
261
186
200
Area, in.2
Length, in.
400
1.13
CT
SL
PT
LB
0.00
Avg.
0.006
0.006
0.004
0.003
0.003
Width, in.
Width, in.
0.74
CT
SL
PT
LB
Avg.
0.016
0.008
0.012
0.012
0.008
0.008
0.008
0.006
0.004
0.002
0.000
1.04
0.004
0.94
1.00
0.50
100
0
1.34
CT
SL
PT
LB
0.000
CT
SL
PT
LB
Figure 7. Web-splitting crack data. Note: CT = control specimen; LB = specimen with large reinforcing bars; PT = vertically posttensioned specimen; SL = specimen
with 23 strands partially shielded; Vn LRFD = nominal shear capacity based on AASHTO LRFD specifications. 1 in. = 25.4 mm.
103
900
800
800
700
700
600
600
Shear, kip
Shear, kip
900
500
400
VnLRFD
500
400
CT
300
200
SL
200
100
PT
100
300
0.02
0.04
0.06
0.08
0.1
0.12
Slip, in.
CT
SL
PT
LB
VnLRFD
LB had unique
boundary conditions
0
0.2
0.4
0.6
0.8
Displacement, in.
Figure 8. Shear displacement and strand slip. Note: Specimen LB was excluded from slip graph due to minimal slip. CT = control specimen; LB = specimen with
large reinforcing bars; PT = vertically posttensioned specimen; SL = specimen with 23 strands partially shielded; Vn LRFD = nominal shear capacity based on AASHTO
LRFD. 1 in. = 25.4 mm; 1 kip = 4.448 kN.
104
loading in each specimen was always a web crack forming between the load point and the support. Discussions of
load, slip, and first cracking are presented in the following
sections for each specimen.
Specimen CT The load-displacement response of the
control specimen CT was approximately linear-elastic during loading (Fig. 8). The first crack formed in the web at a
superimposed shear of 350 kip (1560 kN). Additional web
cracks formed at greater loads; however, flexural cracks
were not observed.
Strand slip in specimen CT was negligible until the superimposed shear reached approximately 550 kip
(2450 kN). Slip increased gradually beyond 550 kip, reaching a maximum slip of 0.016 in. (0.41 mm) at peak load.
Specimen CT failed in a brittle manner at a shear of
773 kip (3440 kN). At this load, the web crushed in dramatic fashion with concrete spalling off the girder. Failure
was categorized as a web-shear failure (Fig. 9). After
testing it was observed that the top hooks of the vertical
reinforcement experienced breakout failure due to insufficient cover in the top flange. Top hooks from the vertical
reinforcement were embedded in the relatively thin top
flange because a topping slab was not cast on the specimen. It is not known whether the hook failure precipitated
or was a byproduct of the web failure. The bearing pad at
the load point punched through the top flange at peak load.
105
Conclusion
Load
LVDT
each side
Bearing pad
Punching cracks at
flange-web interface
Figure 10. Punching failure specimen LB. Note: LB = specimen with large
reinforcing bars; LVDT = linear variable differential transformer.
106
End-region reinforcement per LRFD specifications requirements was the least effective scheme
in terms of total crack length and total crack area.
This scheme did, however, limit web cracks to a
maximum width of 0.008 in. (0.20 mm).
Strand shielding was an effective means of controlling web-splitting cracks. Shielding in specimen SL effected a 29% reduction in crack length
and a 22% reduction in average crack width
relative to the control specimen.
Strand shielding in specimen SL resulted in bondshear failure and the lowest ultimate capacity of
any specimen. Bond-shear failure occurred because specimen SL had insufficient fully bonded
strands to prevent strand slip after cracks interrupted the strand development length.
During load testing, inclined web cracks in specimen SL initiated at a load 30% to 45% lower than
in the other specimens. The lower cracking load
in specimen SL occurred due to decreased endregion stresses affected by strand shielding.
Increasing the area of vertical end-region reinforcement was effective in controlling websplitting cracks. Specimen LB had 27% more
end-region reinforcement than the control specimen. The additional reinforcement effected a 10%
reduction in web crack length and a 23% reduction in average web crack width relative to the
control specimen.
Vertical posttensioning in the end region of specimen PT did not affect load capacity. Specimen
PT supported the largest load of any specimen.
Failure of specimen PT could not be reached due
to limitations of the testing equipment.
Acknowledgments
The authors would like to acknowledge the Florida Department of Transportation for sponsoring this research. Sam
Fallaha, PE, of the Florida Department of Transportation
served as project manager. Testing was conducted at the
Florida Department of Transportation Marcus Ansley
Structures Research Center and benefited from assistance
of the centers staff. Williss participation in this research
was partially funded by National Science Foundation grant
1011478.
References
1. Gergely P., M. A. Sozen, and C. P. Siess. 1963. The Effect
of Reinforcement on Anchorage Zone Cracks in Prestressed
Concrete Members. University of Illinois structural research
series no. 271. Champaign, IL: University of Illinois.
2. Schlaich J., K. Schfer, and M. Jennewein. 1987. Toward a Consistent Design of Structural Concrete. PCI
107
Abstract
This paper reports on a study comparing four detailing schemes for controlling end-region web-splitting
cracks: end reinforcement per AASHTO LRFD specifications, large-diameter end reinforcement, vertical
end-region posttensioning, and partial debonding of
45% of prestressing strands. Crack locations, lengths,
and widths in 63 in. (1600 mm) deep Florida I-beams
(FIB-63) were monitored during transfer and in the
months following prestress transfer. Crack data were
quantified and compared to determine the relative effectiveness of each scheme in controlling web cracking. Specimens were then load tested to determine the
effect of each scheme on ultimate capacity. All three
modified details resulted in reduced web cracking
compared with the standard detail.
Keywords
Beam, girder, bridge, debonding, design method, end
crack, end region, posttensioning, reinforcement.
Review policy
This paper was reviewed in accordance with the
Precast/Prestressed Concrete Institutes peer-review
process.
Reader comments
Please address and reader comments to journal@pci
.org or Precast/Prestressed Concrete Institute, c/o PCI
Journal, 200 W. Adams St., Suite 2100, Chicago, IL
60606. J
108