Escolar Documentos
Profissional Documentos
Cultura Documentos
Page No.
TITLE PAGE
TABLE OF CONTENTS
1.0
PURPOSE
2.0
SCOPE
3.0
DEFINITIONS
4.0
5.0
RESPONSIBILITIES
6.0
7.0
QUALITY CONTROL
8.0
TESTING PROCEDURE
9.0
DOCUMENTATION
10
DISCIPLINE :
ELECTRICAL
TITLE
1.0
PURPOSE
To ensure that the LV MCCs are installed in accordance with design
specifications, that their characteristics are within applicable standards and
manufacturers tolerances.
2.0
SCOPE
This procedure shall apply during the site acceptance testing of LV MCCs.
3.0
DEFINITIONS
3.1
3.2
3.3
3.5
C.E.
C.M.
T.T.
Q.C.
4.0
4.1
4.2
4.3
5.0
RESPONSIBILITIES
Commissioning Engineer
Construction Manager
Testing Technician
Quality Control
5.1 The Commissioning Engineer (C.E.) shall be responsible for preparing the testing plan,
for the observance of all safety precautions required by the JAL Kent Safety Plan,
for supervising the testing activities.
5.2 The Testing Technicians (T.T.) shall be responsible for carrying out the tests, recording
the test values.
3
5.3
The QC Department shall be responsible for conducting reviews of the test records
to ensure that all tests have been performed in accordance with the approved
inspection and test plan.
6.0
7.0
Quality Control
The Commissioning Engineer shall prepare the testing plan that will include the
equipment to be tested, the tests to be performed, the test equipment to be used,
the test procedure to be applied and the test records to be used. Based on the
testing plan, in coordination with the Construction Manager a testing schedule will
be developed.
The Commissioning Engineer shall organize, supervise and verify the
implementation of the testing schedule.
Any defects or variances from the approved specifications and standards will be
noted during the testing and shall be informed to the Construction Department by
the Inspection Report.
The Testing Technician shall use the pre-commissioning forms as checklists and to
record the results of the testing. The forms shall be the quality record documents
to identify that the inspection and testing has taken place.
TESTING PROCEDURE
The following shall be the guidelines for the testing personnel during the inspection
and testing of LV MCCs.
The test will be performed on the main bus and neutral/grounding bus joints.
Identify the joints to be tested. Ensure they have been torque-checked and that the
bolts are marked.
Check that the contact surfaces for the current and voltage probes are clean and dry.
Check that the instrument probes are clean and dry.
Check that the microohmmeter is switched off during making connections.
Ground the microohmmeter.
Connect the current and voltage cables, with
respect to the polarities, as in fig. 1. Always
connect the voltage cables inside the current
cables.
Switch on the microohmmeter. Increase the
current to the desired value. Read the
resistance value.
Compare measured values with manufacturers
specifications; compare results between
different connections. Differences greater than
50% between connections should be
investigated.
Fig. 1
The phasing test is performed in order to check the continuity of main bus system and
the correct sequence of phases.
Disconnect all the cables and equipment connected to the main bus and rack-out the
PT drawers in order to achieve complete isolation of the main bus.
6
Ensure that the main bus phases are not shorted together and that they are not
connected to ground.
Check that the phase identification labels correspond to the main bus arrangement and
vendor drawings. Ensure the phase sequence of the main bus corresponds with other
associated equipment such as busducts and cables.
Connect the battery box, at one end of the main bus:
0V to earth
4.5V to phase A
9V to phase B
13.5V to phase C
Using a multimeter, check if at the other end of the main bus the voltages for each
phase are correct.
Repeat the test for all the sections.
8.4
(a)
(b)
Fig. 2
Fig. 4
Contactor closed
Fig. 5
9.0
DOCUMENTATION
9.1
9.2