Escolar Documentos
Profissional Documentos
Cultura Documentos
Kris Brosens
Triconsult N.V., Lummen, Belgium
Johan Dereymaeker
tDNE N.V., t. De Neef Engineering, Heist-op-den-Berg, Belgium
ABSTRACT: Prestressing the external reinforcement has several advantages compared to the passive
system: the strength of CFRP (Carbon Fibre Reinforcement Polymer) is used more efficiently, the crack
size and crack distances are decreased and the element has a higher stiffness. However the application of laminate prestressing on the construction site is complex and time consuming. As a consequence, the technique is
rarely applied. A novel prestressing system is proposed. It aims to overcome the practical drawbacks of existing
systems: reduced distance between concrete and laminate, ease of anchorage, reduced number of operations and
a transferable force of 200 kN. An anchor block with curved slot in which the laminate is clamped with wedges
is proposed. Experiments demonstrate that the system is technically feasible.
INTRODUCTION
2
2.1
NOVEL SYSTEM
Requirements for a convenient prestressing
system
1175
The new system is designed and tested for a maximum transferable force of 200 kN. Calculations in
ultimate limit state and serviceability limit state of
real cases show that a prestressing force up to 100 kN
would satisfy for an economical application of the
prestressing technique [Brosens, 2005a]. The higher
prestressing force is needed because of possible creep
losses and slip, and for to ensure a sufficient safety
margin.
2.2
3.1
Simplified system
Figure 1.
anchor.
EXPERIMENTAL STUDY
1176
Figure 2.
Simplified system.
3.3
Figure 4.
The maximum transferable force of the clamping device is tested by means of tensile tests. In the
anchor block, a CFRP-laminate (100 1.4 mm,
E = 150 GPa, fu = 2000MPa) is blocked by means of
flat or rounded wedges. To reduce production costs
of the prototype anchors, the anchor block is divided
into two parts which are bolted together. Two kinds
of anchor blocks are used: one with a thickness of
40 mm (2 20 mm) and another with an increased
thickness of 50 mm (2 25 mm).
In the first six tests, Figure 5a, the two parts of the
anchor block are fixed to the upper head of the testing
device by means of 2 steel plates and 4 threaded bars.
In the mid part of the bar ( 20 mm, length 250 mm),
the two parts are bolted together with a prestressing
force of about 50 kN on each bolt. At both sides of the
clamping system, steel plates are used to transfer the
testing force to the anchor. Deformations are recorded
by means of LVDT (linear voltage differential transformer). In the anchor block, the laminate is blocked
by means of the wedges. The wedges are manually
pressed in the anchor block. The other head of the
(a)
For the analysis, a laminate of 100 mm 1.4 mm is
assumed. The anchor block and the wedges are made
of steel. On the laminate, a tensile force is applied
through a uniform displacement at a distance of
100 mm from the clamping device. The laminate is
not treated and the wedges are flat. A prestressing
force of 150 kN is assumed. The results of an ideal
situation are presented in Figure 3.
In this ideal situation, it is assumed that no friction
is present between the wedge and the anchor block.
The friction coefficient between wedges and anchor
block equals zero. In case of pressure in the interface,
the laminate can not move. In case of tension, the
laminate is mobile.
The numerical results show that the laminate is not
uniformly blocked. Tensile stresses locally reach high
(b)
1177
Test setup
Clamp Layer* Wedge** Fmax Opening Mode of failure
1
2
3
4
5
6
7
8
9
10
*
40
40
40
40
50
50
50
50
50
50
A
S
S
C
C
C
C
A
f
r
r
r
r
f
f+p
r+p
f+p
f+p
10
78
110
143
166
208
138
198
175
178
0.86
0.77
2.60
1.28
2.82
0.05
0.08
0.01
0.05
slipping of
laminate
shear failure in
laminate
clamping
assymetric
cardan
1178
Bolt
Glue
Fmax
Failure mode
No tab or
bolts
Glue
102
Glue
1
2
1
2
Glue
Glue
109
114
136
132
117*
191
Numerical anchorage
capacity
In concrete
1a
1b
2
3
4
5
In concrete
Bolts pulled out
Bolt prematurely pulled out
In concrete
CONCLUSIONS
The test results are presented in Table 2. Test specimen 4 failed premature due to insufficient adhesion
of the chemical anchor and is therefore excluded.
Two trends can be observed:
tab and glue versus only glue.
The maximum transferable force can be calculated [Brosens, 2001] if no tab or bolts are used.
1179
1180