Escolar Documentos
Profissional Documentos
Cultura Documentos
AREVA at a glance
The US-EPR
Conclusion
to a reliable, economical
and low-carbon energy mix
AREVA Group
2012 Key Figures
9.342Bn in Annual Revenues
45.4Bn in Backlog
spending
47,000 Employees Including:
900 Specialty Experts
2,700 Scientists & Researchers
6,500 in worlds largest
nuclear in-house EPC team
continents
US EPR Bruno BLOTAS
Conference The future of nuclear energy Mexico 29 May 2013
4 EPR
Under construction
AREVA at a glance
The US-EPR
Conclusion
Bell Bend
COL in Phase A of NRC Safety Review (4
phases total)
1st phase of environmental review is
complete
NRC approval anticipated 6-12 months
after DC rulemaking
10
11
12
13
14
AREVA at a glance
The US-EPR
Conclusion
15
Reactor
Building
Containment Line
-7 m to +16 m
2007
2008
2009
Lifting of the
Reactor Dome
Reactor Pressure
Vessel introduced
2010
2011
Site connected to
national grid
Fuel handling
equipment installed
2012
2013
16
Olkiluoto 3
I&C
I&C overall architecture approved by STUK
Test concept approval process on going
Licensing
Master List for Operating License Application documentation
delivered to TVO
Commissioning
All pools and surge tanks in the nuclear island
17
March 13
CRDM installation on-going
April 13
Refueling machine
electrical installation ongoing
18
2007
2008
Installation of the
pressurizer relief tank
EBS pumps
Start of
Piping Erection installed
2009
2010
First operational
cabinet installed
2011
2012
2013
19
Flamanville 3
Installation of
containment liner
Reinforcement work
completed
awaiting concreting
Flamanville 3
Installation works ongoing
Copyright EDF
May 13
May 13
21
LOI to create a JV
in Nuclear Reactor
Signature of
Engineering
the Contract
2007
2008
First Concrete
TS2
First
Concrete TS1
2009
1st
2010
TS1:
RPV installed
TS1
1st liner lifted
TS2
liner lifted
2011
TS2:
Dome lifted
TS1:
Dome lifted
2013
2012
22
Taishan 1 & 2
Taishan 2
AREVA scope
Procurement: more than 95% orders made
Engineering: more than 86% completed
Main components
Unit 1: all primary heavy components
Installation of
containment liner
23
Taishan 2
Dome lifting
Copyright
TNPJVC
Copyright TNPJVC
September 12
Dome lifting
US EPR Bruno BLOTAS
Conference The future of nuclear energy Mexico 29 May 2013
24
Taishan 1 & 2
Equipment and Fuel manufacturing progressing
Copyright TNPJVC
Copyright TNPJVC
March 13
First Fuel Assemby
produced for TSN 1
May 13
First TSN 2 Steam Generator
manufactured by Dongfang
shipped to Taishan
25
EPR reactor
Lessons learned process achievements
Evolution between
OL3 and Taishan
Engineering
- 60 %
Construction
Duration of construction
(from 1st concrete to dome
installation)
- 50 %
Procurement
- 65 %
Total
- 40 %
26
2007
2009
2012
NNSA
2015
ONR/
27
ONGOING BIDS
(BILATERAL)
UPCOMING
OPPORTUNITIES
ESKOM
EDF
TVO
Hinkley Point C
Units 1-2
OL4
CGNPC
JAEC
PGE
Saudi Arabia
GDF Suez Iberdrola
Taishan 3-4
Vattenfall
NPCIL
Jaitapur 1-2
CEZ
Temelin 3-4
EVN
NA-SA
EUAS
Sinop 1-2-3-4
MNPC
UAE
EDF - Calvert Cliff 3
PPL - Bell Bend
Duke Energy - Piketon
Canada
Hungary
28
AREVA at a glance
The US-EPR
Conclusion
29
Conclusion
The overall financing situation is difficult and limits projects
30
Visiten www.areva.com
31
32
Muchas gracias
33