Escolar Documentos
Profissional Documentos
Cultura Documentos
Minerals Engineering
journal homepage: www.elsevier.com/locate/mineng
Mine operating costs and the potential impacts of energy and grinding
James A. Curry, Mansel J.L. Ismay, Graeme J. Jameson
Centre for Multiphase Processes, The University of Newcastle, Callaghan, NSW 2308, Australia
a r t i c l e
i n f o
Article history:
Received 29 May 2013
Accepted 22 October 2013
Available online 27 November 2013
Keywords:
Mine operating cost
Mining
Milling
Flotation
Cost breakdown
a b s t r a c t
An understanding of the breakdown of mine costs is an important tool for researchers and developers
who seek to place novel cost-reducing unit operations in the wider general cost context. This paper provides a breakdown of operating costs in 63 mines by dividing them into three main categories: mining,
milling, and general and administrative (G & A) costs. The study looks at patterns in mining type, mill
processing type, mineral type, and the differences between costs expressed in feasibility studies vs. operating mines. The paper explores the reasons for the relationships observed and then presents a total average mine cost breakdown. It was found that the mean relative mining and milling costs did not differ
signicantly, and that on average they had equal shares of the total enterprise operating costs. Effects
of mine and mineral type were observed, with underground milling costs being signicantly less than
open pit milling costs and gold mines occupying a signicantly larger share of mine operating costs than
copper-containing mines. The overall relative operating costs were found to be in the ratios between
(43:43:14) and (45:45:10) (Mine:Mill:G & A). A treatment of potential unit operations and innovative
technologies is provided at the conclusion of the paper, including coarse particle recovery by otation
and novel grinding technologies.
2013 Published by Elsevier Ltd.
Contents
1.
2.
3.
4.
5.
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Methodology. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.1.
Sample . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
2.2.
Data analysis . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Results and discussion . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.1.
Overall distribution . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.2.
Mine type. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.3.
Processing type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.4.
Ore type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.5.
Effect of report type . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.6.
Effect of time . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
3.7.
Other effects . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Potential cost savings measures . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Conclusion and recommendations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Appendix A.
List of mines . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Appendix B.
Studied mine reports . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
References . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
1. Introduction
Technological innovation has played an historically important
role in improving the commercial viability of mining operations
Corresponding author. Tel.: +61 2 4921 6181; fax: +61 2 4960 1445.
E-mail address: Graeme.Jameson@newcastle.edu.au (G.J. Jameson).
0892-6875/$ - see front matter 2013 Published by Elsevier Ltd.
http://dx.doi.org/10.1016/j.mineng.2013.10.020
70
71
71
71
72
72
73
74
74
74
74
75
75
76
77
78
80
71
Nomenclature
P80
72
Table 1
Costs included in each category.
Category
Costs
Mining
Milling
Drilling, blasting, loading, hauling, equipment maintenance and repair, mine overheads, mine specic labour requirements
Power, grinding media and mill linings, consumables, reagents, equipment maintenance and repair, maintenance materials, milling
specic labour, milling overheads
Management costs, stafng for human resources, environment, health and safety, training, communications, community relations, camp
and catering, mobile equipment, insurance
tion), ore type (all copper, and gold but no copper) and report type
(feasibility vs. preliminary vs. operating). Of course, within each
group, the allocation to Mine, Mill and G & A costs could be inuenced by one or more factors within other groups, and there is
insufcient data to test all interaction effects. With the data available, multivariate between-subjects ANOVAs were performed on
the data containing more than two groups using Type III sumsof-squares to account for variable sub-sample sizes. For categories
in which there were only two groups for comparison, for example,
processing type or ore type, independent-samples t-tests were
undertaken. Sub-samples of a minimum of nine data points, i.e.
mine sites, were compared, with groupings containing fewer data
points excluded from the analysis. Using this minimum sample
size criterion, analyses by mine location were excluded. Factorial
analyses were also excluded on the basis that combined groupings
produced sub-sample sizes that were too small to yield reliable
inferences concerning interaction effects.
Reports were dened as containing open pit or underground as
stated. Mines that contained a single set of operating costs for both
underground and open pit mines were dened as both (i.e. containing both underground and open pit). Reports in which underground and open pit operations were given two separate sets of
operating costs were treated as separate installations. Operations
containing otation at some point in the processing were classied
as otation, whereas operations containing no otation were classied as no otation. The aforementioned information was obtained from process owsheets, or otherwise explicitly stated in
the body of the report.
Ore type was dened by the target elements for saleable production. Reports were divided into preliminary, feasibility and
operating depending upon the status of the project. Pre-feasibility
and preliminary economic reports were classied as preliminary.
Reports that explicitly stated they were feasibility studies were
classied as feasibility. Reports were classied as operating if
they were based on currently operating mines, as stated in the
report.
The annual change in operating costs over the LOM was analysed on a case-by case-basis for those mine reports that included
them. Selected data sets were correlated to determine if the change
in relative costs varied signicantly from zero for the LOM.
Fig. 1. Boxplots indicating distribution of Mining, Milling and G & A. Solid and
dotted lines represent the median and mean respectively.
Table 2
Summary of descriptive statistics for overall relative mine cost distribution (N = 65).
Mine
Mill
G&A
Mean (%)
Median (%)
Range (%)
43.2
43.5
13.3
43.1
43.7
11.0
57.9
60.3
39.3
3.4
3.8
2.2
73
Table 3
Summary of descriptive statistics for overall relative mine cost distribution with
outliers removed (N = 61).
Mine
Mill
General and
Administration (G & A)
Mean
(%)
Median
(%)
Range
(%)
95% Condence
interval
43.3
45.0
11.7
43.6
45.2
10.9
57.9
55.4
26.4
3.7
3.7
1.7
Table 4
Summary of data by mining type (N = 61).
n
Mean (%)
Median (%)
Mine
Both
Open pit
Underground
11
41
9
47.9
40.3
51.5
47.7
42.3
55.6
5.9
4.6
11.4
Mill
Both
Open pit
Underground
11
41
9
39.3
48.9
34.1
39.0
49.5
35.1
6.6
4.6
8.3
11.7
9.5
14.6
4.9
1.9
5.5
Mean (%)
Median (%)
Mine
Flotation
No otation
37
24
41.6
46.0
42.3
51.5
4.3
6.8
Mill
Flotation
No otation
37
24
46.3
43.0
47.5
40.0
4.5
6.8
10.6
11.3
2.4
2.3
74
Table 7
Summary of data by report type (N = 61).
Mean (%)
Median (%)
Mine
Preliminary
Feasibility
Operating
17
19
25
45.9
41.2
43.2
43.6
43.0
45.3
7.4
6.6
6.1
Mill
Preliminary
Feasibility
Operating
17
19
25
45.2
47.4
43.1
44.8
47.5
39.8
7.6
6.1
6.5
7.8
9.5
13.7
2.4
3.7
2.5
Table 6
Summary of data by ore type, divided into copper and gold ores (N = 54).
n
Mean (%)
Median (%)
Mine
Gold
Copper
30
24
48.1
37.8
49.5
38.5
4.4
5.8
Mill
Gold
Copper
30
24
41.0
46.4
40.0
47.5
5.0
7.1
9.5
13.0
2.6
4.3
75
Greater relative Mine costs during the early and middle stages
of the mine life may be explained in light of stockpiling. Mines typically produce more ore during these stages than the mill is able to
process, in order to maintain a constant stockpile for the mill in the
event of disruptions in the mine operations. The end of mine pattern, where relative Milling costs increase and relative Mining
costs decrease, may be explained in light of the phase-out of mining operations. During this period, mining activities are gradually
decreased, as the mill continues to process the stockpiles built up
over the life of the mine. Strip ratios may improve for open pit
mines, as there is less waste material to move, reducing the relative cost of the mine side. If the data are split between this
phase-out period and the preceding normal operations, it can be
seen that during normal operations the relative Mining and Milling
costs follow a slope that does not differ signicantly from zero
(p > 0.05). The same is observed with the relative G & A costs,
which remain constant throughout the life of the mine.
3.7. Other effects
The relative contributions of Mining, Milling and G & A to enterprise costs produce distributions, the variances of which may be
attributed to the specic circumstances of each mine. Analyses of
mine location and head grade, that are proposed to exert an effect
on the distribution of mine costs, were omitted from the present
study due to insufcient data subsets. The lack of these analyses
makes it difcult to generalise the ndings across different locations and head grades, and it is suggested that these be the focus
of future research aiming to identify common trends in the distribution of mine costs.
4. Potential cost savings measures
This study has found that in general the relative Mining and
Milling costs of a given operation do not signicantly differ, and
generally fall within the range of 43:43:14 to 45:45:10 (Mine:Mill:G & A). In addition, G & A costs were found to be consistently
lower than both Milling and Mining costs. Due to the signicant
proportion of Mine and Mill costs, cost saving measures should be
focussed on these areas. Milling in particular represents an area
of potential savings due to increased attention in recent times focussed on the reduction in comminution costs in mineral processing (Daniel and Lewis-Gray, 2011). In a summary of comminution
needs for reduced energy use, Daniel and Lewis-Gray indicated that
pre-concentration, greater emphasis on crushing, improved grinding technologies and mineral separations at coarser grind sizes
are required to achieve signicant savings in overall comminution
costs. This section will examine potential savings to Mine and Mill
costs, with a special reference to coarse particle recovery. Other pa-
76
pers in the literature analyse the impact of other areas where potential improvements can be made, both economically and environmentally (La Nauze and Temos, 2002; Norgate et al., 2007; Evans
et al., 2009; Norgate and Haque, 2010; Norgate and Jahanshahi,
2010; Norgate and Jahanshahi, 2011; Gunson et al., 2012).
Mine automation and tele-operation are two areas that may
bring about a step-change in the reduction of mining operating
costs (Fisher and Schnittger, 2012). The chief benets of automation
include potential savings in energy and consumables (such as
explosives), labour savings, greater efciency and improved maintenance with reduced downtime. The development of semi-autonomous drills, for example, has improved the ability to engineer rock
fragmentation whilst minimising the generation of waste material
and the need to redrill. In addition, a number of sites, including El
Teniente and Kurina have begun to implement driverless trucks,
which are claimed to reduce route efciency and driver downtime.
Pre-concentration is a technique that has been employed in the
past to recover liberated minerals at coarser grind sizes. The most
notable techniques include gravity separation and ash otation,
which are currently in use at a number of mills (e.g. Butcher
et al., 2011). The former is limited to minerals that are signicantly
denser than the gangue material, such as gold, whereas the latter
relies on well liberated fast-oating material. A number of other
ore sorting techniques have recently been proposed to be implemented in underground mines, including X-ray transmission, optical material recognition and the use of induction sensors (Murphy
et al., 2012). It has been estimated that effective ore sorting
techniques may improve mine efciency by 20% (CSIRO, 2012).
The extent of savings obtained from these technologies in preconcentration remains an active area of research that may improve
the cost structure of both mine and mill.
Innovation in particle reduction technologies has been an
area of active research for some time, with new grinding technologies such as the IsaMill and high pressure grinding rolls
(HPGRs). HPGRs in particular show promise in improving the
efciency of grinding at the head of the circuit, where the
greatest savings may be made. Daniel et al. (2010), for example,
showed that the replacement of a SAG mill with a HPGR in a
conventional SAG-Ball circuit may reduce grinding energy consumption by 1520%. Taking into account additional savings,
such as media and liner wear, the authors found that a grinding
cost saving of 2535% was potentially achievable with the use
of HPGRs in such conventional circuits. Other studies have
found the applicability of HPGRs dependent on ore characteristics (e.g. Amelunxen and Meadows, 2011). HPGR technology remains a fertile area for achieving signicantly reduced
comminution costs.
Savings to milling operations will ultimately be limited by the
particle size at which effective separations may occur. The recovery
of base metal sulphide minerals relies extensively on the use of otation as the key separation technique, which, until recently, has
been typically limited by P80 values of the range 100200 lm.
The advantage of separating particles at such a large size is that
the costs of grinding energy and associated elements such as mill
linings and grinding media, are closely related to the nal grind
size. Thus if it is possible to grind the ore to a coarse size, in the
range for example of 4001000 lm, separate the particles containing valuable minerals, and then regrind only these particles to a nal size suitable for conventional otation machines, there would
be very signicant cost savings. From the results obtained in the
current survey, where the cost ratio of (Mining:Milling:G & A) is
(43:43:14), Table 2, a 20% saving in the cost of running the mill will
result in a 9% saving in the running costs of the whole enterprise.
Step changes in coarse particle separation technology have recently been published. Both suggest that the upper limit of otation may be extended up to 1 mm. Jameson (2010) showed
results for the otation of galena in a uidized bed otation column, demonstrating that it was possible to obtain high recoveries
at particle sizes of up to 1 mm approximately. The feed to this column, known as the NovaCell, is in the range 4001000 lm top size.
Coarse particles settle in the base of the vessel, where they are uidised by an upow of aerated liquid. The ow in the vessel is slow,
which favours the formation of stable bubble-particle aggregates.
The NovaCell has a conventional froth layer, which assists in the
drainage of entrained particles back into the cell. More recently,
Awatey et al. (2013) have described experiments with the HydroFloat, an air-assisted teeter-bed separator. High recoveries have
been achieved with the separation of sphalerite particles up to
1 mm in diameter. In both studies, the valuable mineral was fully
liberated. The true test of these new coarse particle technologies
will be in the otation of composites. Currently there exists no conclusive evidence that these technologies can achieve the same
recoveries with poorly liberated sulphide minerals up to 1 mm,
although recent research suggests that the effect of composites
on recovery in gentle environments may be less than previously
thought. There is good evidence to suggest that the poor performance of conventional otation machines with coarse particles
owes less to poor liberation and more to the effects of machine
hydrodynamics (Jameson, 2012). Thus, the effect of mineral
liberation on the effectiveness of new coarse particle otation
technologies is a key area requiring attention.
It is likely that a combination of the aforementioned technologies across the mine and mill will be required to achieve signicant
savings for a given operation. Of the technologies discussed, each
will be amenable to specic conditions of a given mine, and may
not necessarily extend to all potential operations. However, it has
been shown in this study that the average proportion of mine
and mill operating costs for a given operation do not differ significantly, so it can be expected that on average, savings to either the
mill or mine are likely to translate well to the overall economics of
a given mining operation.
5. Conclusion and recommendations
Analysis of published data has shown that overall relative
mine and mill costs on average are not signicantly different
for hard rock mining operations in general, and constitute the
bulk of the overall mine cost. G & A costs were found to occupy
a much smaller proportion of the total mine cost compared with
the mine and mill. In general, the overall breakdown of costs was
estimated to be within the range of (43:43:14) and (45:45:10)
(Mine:Mill:G & A). Signicant differences in relative Milling costs
were found to exist between underground and open pit mines,
and in Mining and G & A costs, between gold-only mines and
all mines containing copper. No signicant differences were found
between relative costs on the basis of processing type or report
type. Despite diverging Mine and Mill costs at the beginning
and end of the mine life, these relative costs were found to be
constant throughout a large fraction of the life of the operation.
G & A costs remained constant throughout the life of the mine.
This study has provided a basic overview of the distribution of
operating costs across 63 mines. Although signicant differences
were found to exist between mine type and ore type sub-samples,
further research is required to clarify these effects. Furthermore,
detailed simulations examining the potential savings in operating
costs are recommended to better clarify the benets of the technologies discussed in this paper.
77
Country
Mine
(%)
Mill
(%)
G&A
(%)
Mine type
Process
type
Ore type
Report type
Agbaou
Ivory Coast
67.4
20.7
11.9
Open pit
Au
Feasibility
Amulsar
Armenia
64.1
31.1
4.8
Open pit
AuAg
Feasibility
Aurizona
Brazil
48.7
40.3
11.0
Open pit
Au
Operating
Authier
Bushranger
Cadia Valley
Canada
Australia
Australia
55.2
13.2
60.4
32.9
75.9
27.9
11.9
10.9
11.7
Open pit
Open pit
Both
Li
AuAgCu
Au
Preliminary
Preliminary
Operating
Caariaco Norte
Cerro Casale
Cerro Maricunga
Peru
Chile
Chile
43.6
35.3
54.3
49.5
39.0
37.9
6.9
25.7
7.8
Open pit
Both
Open pit
AuAgCu
AuCu
Au
Preliminary
Feasibility
Preliminary
CMD
Copler
Chile
Turkey
36.8
21.7
56.9
69.3
6.3
9.0
Open pit
Open pit
AuAgCu
AuAgCuS
Operating
Operating
Cordero
Cortez
Mexico
Chile
27.9
54.2
64.1
37.8
8.0
7.9
Open pit
Open pit
AuAgPbZn
Au
Preliminary
Operating
Deer Horn
Del Toro
Didipio
Donlin Creek
Duncan Lake
Canada
Mexico
Phillipines
USA
Canada
53.0
55.6
47.7
45.4
59.6
37.6
40.1
37.3
49.3
28.4
9.3
4.2
15.0
5.2
12.0
Open pit
Underground
Both
Open pit
Open pit
AuAgTe
AuAgPbZn
AuCu
Au
Fe
Preliminary
Feasibility
Feasibility
Feasibility
Preliminary
Eagles Nest
Canada
38.9
37.4
23.7
Underground
No
otation
No
otation
No
otation
Flotation
Flotation
No
otation
Flotation
Flotation
No
otation
Flotation
No
otation
Flotation
No
otation
Flotation
Flotation
Flotation
Flotation
No
otation
Flotation
Feasibility
El Morro
Fosterville
Goldstrike
Chile
Australia
USA
36.1
56.1
55.1
46.6
34.4
39.8
17.3
9.6
5.1
Open pit
Both
Both
AuCuNiPt
Pd
AuCu
Au
Au
Feasibility
Operating
Operating
Gosowong
Indonesia
49.7
19.2
31.1
Underground
AuAg
Operating
Hasbrouck
USA
31.6
60.1
8.3
Open pit
AuAg
Feasibility
Hosco
Hycroft
Canada
USA
47.9
31.0
49.7
64.2
2.4
4.8
Open pit
Open pit
Au
AuAg
Feasibility
Operating
Kamoa
Kansanshi
Kemco
Kwanika
La Encantada
La Parilla
(Combined)
La Parilla (Oxide
OP)
Lac a Paul
Lagunas Norte
DR of Congo
Zambia
Thailand
Canada
Mexico
Mexico
68.5
37.7
64.9
43.1
41.9
36.3
21.0
56.6
29.4
51.3
17.9
45.2
10.5
5.7
5.7
5.6
40.2
18.5
Underground
Open pit
Underground
Both
Underground
Underground
Cu
Cu
AgPbZn
AuAgCuMo
AgPbZn
AuAgPbZn
Preliminary
Feasibility
Preliminary
Preliminary
Operating
Operating
Mexico
26.6
68.9
4.5
Open pit
AuAgPbZn
Operating
Canada
Peru
29.1
54.2
65.8
32.1
5.1
13.7
Open pit
Open pit
P
AuAg
Preliminary
Operating
Lihir
Los Filos
40.5
58.7
30.8
23.1
28.7
18.2
Open pit
Both
Au
AuAg
Operating
Operating
Los Santos
Lumwana
Marcona
Miraores
Spain
Zambia
Peru
Colombia
10.6
42.5
23.8
40.8
71.1
3.9
10.5
54.3
18.3
41.6
6.7
4.9
Open pit
Open pit
Open pit
Both
W
Cu
Cu
Au
Operating
Operating
Feasibility
Preliminary
Flotation
Flotation
No
otation
No
otation
No
otation
Flotation
No
otation
Flotation
Flotation
Flotation
Flotation
Flotation
Flotation
No
otation
Flotation
No
otation
Flotation
No
otation
Flotation
Flotation
Flotation
Flotation
78
(continued)
Project
Country
Mine
(%)
Mill
(%)
G&A
(%)
Mine type
Process
type
Ore type
Report type
Mount Hope
Osborne (OP)
Osborne (UG)
Oyu Tolgoi
Passendro
43.0
50.2
64.2
36.4
44.3
47.5
35.6
21.2
48.2
43.7
9.5
14.2
14.6
15.4
12.0
Open pit
Open pit
Underground
Both
Open pit
Feasibility
Operating
Operating
Feasibility
Feasibility
31.5
12.2
50.3
76.1
18.2
11.7
Open pit
Open pit
AgSnZn
AuAgCu
Operating
Feasibility
Rainy River
Canada
48.3
45.4
6.3
Both
AuAg
Feasibility
Sabodala
Senegal
40.2
48.2
11.6
Open pit
Au
Operating
San Jorge
San Martin
Santa Rita
Shymanivske
Springpole
Argentina
Mexico
Brazil
Ukraine
Canada
32.1
30.2
45.3
47.3
35.7
29.9
52.3
35.6
50.1
52.8
38.0
17.5
19.1
2.6
11.5
Open pit
Underground
Open pit
Open pit
Open pit
AuCu
AgPbZn
Ni
Fe
AuAg
Feasibility
Operating
Operating
Feasibility
Preliminary
Taca Taca
Tasiast
Argentina
Mauritania
49.2
29.3
44.8
50.6
6.0
20.1
Open pit
Open pit
AuCuMo
Au
Preliminary
Operating
Telfer
Tenke Fungurume
Australia
DR of Congo
45.6
20.2
32.1
51.7
22.3
28.1
Both
Open pit
AuCu
CuCo
Operating
Feasibility
Toroparu
Trinidad/Taunus
Guyana
Mexico
42.3
58.6
51.0
36.0
6.7
5.4
Open pit
Open pit
AuCu
Au
Preliminary
Preliminary
Veladero
Argentina
63.2
21.4
15.4
Open pit
AuAg
Operating
WaGolpu
Wasamac
41.1
63.6
35.1
25.4
23.8
11.0
Underground
Underground
AuAgCu
Au
Preliminary
Operating
Zaldivar
Chile
26.6
62.8
10.6
Open pit
Flotation
Flotation
Flotation
Flotation
No
otation
Flotation
No
otation
No
otation
No
otation
Flotation
Flotation
Flotation
Flotation
No
otation
Flotation
No
otation
Flotation
No
otation
Flotation
No
otation
No
otation
Flotation
No
otation
Flotation
Mo
AuCu
AuCu
AuAgCu
Au
Pirquitas
Pueblo Viejo
USA
Australia
Australia
Mongolia
Central African
Republic
Argentina
Dominican Republic
Cu
Operating
Dupere, M., Gagne, J., Gagnon, G., & Baril, F. (SGS Canada Inc.).
(2013). Preliminary Economic Assessment of Authier Lithium Property, Quebec, Canada, NI-43-101.
Duplessis, C., Cassoff, J., Rivard, S., Bilodeau, M., Buchanan, M., &
Skiadas, N. (2013). Technical Report Phosphate Resource Estimation update 2013 of the Lac a Paul Property Deposit, NI
43-101.
Ebbels, A-M., Faireld, P., Lewis, R., & Munro, P. (SRK Consulting). (2012). Technical Report for Osborne Copper-Gold Project
located in northwest Queensland region of Australia, NI
43-101.
Elfen, S., Davis, B., & Scott, K. (Ausenco). (2013). Taca Taca copper/gold molybdenum project: Preliminary economic assessment.
Evans, L., Ehasoo, G., & Altman, K.A. (Roscoe Postle Associates
Inc.). (2012). Technical Report on the Lagunas Norte Mine, La Libertad Region, Peru.
Evans, L., Ehasoo, G., & Altman, K.A. (Roscoe Postle Associates
Inc.). (2012). Technical Report on the Veladero Mine, San Juan
Province, Argentina.
Evans, L., & Lambert, R.J. (Roscoe Postle Associates Inc.). (2012).
Technical Report on the Zaldivar Mine, Region II, Chile.
Fisher, A., Moran, A., Spiller, D.; Evans, D., Yang, D., Garcia, D.,
Rodrigues, F., Daviess, F., Marrou, J., Mountjoy, K., Clarke, P., &
Chapel, T. (SRK Consulting). (2013). Prefeasibility Study of the
Toroparu Gold Project, Upper Puruni River Area, Guyana, NI 43-101.
Flint, D.C., Kunkel, K., Gorman, M.G., Moore, D.B., & Wilson, S.E.
(Allied Nevada Gold Corp. & Scott E. Wilson Consulting, Inc.).
(2012). Technical Report Allied Nevada Gold Corp. Hasbrouck
Property, Tonopah, Nevada, USA.
Flint, D.C., Gorman, M.G., Harris, D., Moore, D.B., Peterson, A.T.,
& Wilson, S.E. (Allied Nevada Gold Corp. & Scott E. Wilson Consulting, Inc.). (2012). Technical Report Allied Nevada Gold Corp.
Hycroft Mine, Winnemucca, Nevada, USA.
Gauthier, J., Galarneau, Y., Lavigne, M., Adam, D., Lance, S., &
Hardie, C. (Roscoe Postle Associates Inc.). (2012). Technical
Report on the Wasamac Project, Rouyn-Noranda, Quebec, Canada.
Grandillo, A., Live, P., Thomassin, Y., & Dupere, M. (BBA). (2012).
Feasibility study of the Hosco deposit Joanna Gold Project NI 43101.
Gray, J., & Robillard, H. (Moose Mountain Technical Services).
(2013). Technical Report for the Kwanika Property, Preliminary
Economic Assessment, NI 43-101.
Greig, D.D., Board, W., Oliver, R., Johnston, A., Schlitt, J., David,
D., Yang, D.Y., Kerr, T.F., Grbovic, B., & Sanford, A. (GRD Minproc). (2009). Marcona Copper Property Mina Justa Project Denitive Feasibility Study Technical Report NI 43-101.
Greig, D., de Brito Mello, R., Miranda, D., Vargas G., & Fuentas, J.
(GRD Minproc). (2009). San Jorge Copper Concentrator Project
Preliminary Assessment Technical Report.
Greig, D.D., & Manfrino, A. (GRD Minproc). (2003). The Kansanshi
Copper Project Northwestern Province Zambia.
Guzman, C., Magri, E., & Wells, J. (2013). Preliminary Economic
Assessment for the Cerro Maricunga Oxide Gold Project, III Region,
Chile, NI-43-101.
Hanson, K., Seibel, G., Allard, S., Wortman, G., & Kozak, A. (AMEC
Inc). (2009). Nova Gold Resources Inc. Donlin Creek Gold Project,
Alaska, USA NI 43-101 Technical Report.
Hardie, C., Runnels, D., Live, P., Daniel, S., Ritchie, D., Coulson, A.,
Cole, G., El-Rassi, D., & Tolfree, D. (BBA). (2013). Feasibility study
of the Rainy River gold project, Ontario, Canada, NI 43-101.
Henderson, R.D. (Kinross Gold Corporation). (2008). Cerro Casale
Project Northern Chile NI 43-101 Technical Report.
Huss, C., Snider, J., Marek, J., Parshley, J., & Drielick, T. (2008).
Mount Hope Project Molybdenum Mine and Process Plant Feasibility Study, NI 43-101.
79
Inwood, N., Smith, R., & Guzman, C. (Coffey Mining Pty Ltd).
(2011). Santa Rita Project, Brazil Technical Report.
Keller, G., Patrick, G., Welhener, H., Kiel, R., Lemke, P., Eyre, J., &
Keane, J. (AMC Consultants Ltd). (2013). Amulsar Gold Project,
Armenia: Technical Report Mineral Resource Update and Reserve
Estimate Update, NI 43-101.
Lambert, R., Gow, N., Hampton, A., & Gochnour, L. (Roscoe Postle
Associates Inc.). (2012). Technical Report on the El Morro Project,
Region III, Chile, NI 43-101.
Lane, R., Giroux, G., & Meintjes, T. (2013). Preliminary Economic
Assessment for the Deer Horn Gold-Silver-Tellurium Property, NI
43-101.
Llorca, J., & Schunke, N. (Mining Plus Pty Ltd). (2012). Fosterville
Technical Report, Victoria, Australia, NI 43-101.
Lopez, L. (Pincock Allen & Holt). (2012). Technical Report for the
Del Toro Silver Mine, Zacatecas State, Mexico, NI 43-101.
Lopez, L. (Rune Pincock Minarco). (2013). Technical Report for
the San Martin Silver Mine, State of Jalisco, Mexico, NI 43-101.
Lowe, A., Leach, T., & Serra, B. (SRK Consulting Inc.). (2012). Preliminary economic assessment of Miraores property, Quinchia district, Colombia, NI 43-101.
Mah, P., Reyes, A., Lindeman, D., Mach, L., & Haggan, T. (2013).
Technical Report: Aurizona resource and reserve update Brazil,
NI 43-101.
Moore, C.M., Bergen, R.D., Valliant, W.W., Collins, S.E., & Altman,
K.A. (Roscoe Postle Associates Inc.). (2012). Technical Report on
the Goldstrike Mine, Eureka and Elko Counties, State of Nevada,
U.S.A.
Moore, C.M., Danio, J.R., & Altman, K.A. (Roscoe Postle Associates Inc.). (2012). Technical Report on the Lumwana Mine, North
Western Province, Republic of Zambia.
Moorhead, C., & Cantrell, R. (AMC Mining Consultants (Canada)
Ltd). (2011). Technical Report on the Wa-Golpu Property in
Morobe Province Papua New Guinea.
Nilsson, J., Simpson, R.G., & McKenzie, W. (2011). Technical
Report Expansion Feasibility Study for the Tenke Fungurume Mine,
Katanga Province, Democratic Republic of Congo.
Parker, H., Seibel, G., David, D., Peters, B., Jakubec, J., & Lawson,
M. (SRK Consulting/ AMC Consultants Pty Ltd). (2013). Kamoa
Copper Project Technical Report on Updated Mineral Resource
Estimate, NI 43-101.
Parker, R., Brady, B., Hayden, A., & Watts, G. (A.C.A. Howe International Ltd). (2013). Technical Report and Preliminary Economic
Assessment of the Kemco Project, Thailand.
Peters, B., Jackson, S., Chance, A., Jakubec, J., & David, D. (AMC
Consultants Pty Ltd). (2012). Oyu Tolgoi Project IDOP Technical
Report.
Peters, B., Sylvester, S., Bridges, M., & Riles, A. (AMC Consultants
Pty Ltd). (2013). 2013 Oyu Tolgoi Project Technical Report Turquoise Hill Resources Ltd.
Redden, R., & Moore, J. (2011). Technical Report for the Didipio
Project, Luzon, Phillipines, NI 43-101.
Sedore, M., & Masterman, G. (Kinross Gold Corporation). (2012).
Tasiast Mine Mauritania 43-101F1 Technical Report.
Senior, N., Bundo, P., & Swart, H. (2011). Passendro Gold Project
Bankable Feasibility Study Optimisation and Update Summary
Report.
Spiering, R., Gorjian, M., Ehsani, R., Burris, P., Puritch, E., Risto, R.,
& Kociumbas, M. (Worley Parsons). (2012). Feasibility Study of
the Shymanivske Iron Ore Deposit, NI 43-101.
Stephenson, P.R., Shannon, J.M., OConnor, B., Riles, A., & Ebrahimi, A. (AMC Mining Consultants (Canada) Ltd). (2010). Sabodala
Gold Project Senegal, West Africa Technical Report.
Stewart, R., & Fazzini, J. (Dundee Securities Ltd). (2012). Lachlan
Star Limited A Season for CMD.
80
Swanson, B., Johnson, M., Olin, E., Nowak, M., & Willow, M. (SRK
Consulting). (2012). Preliminary Economic Assessment of Trinidad/Taunus Project, Sinaloa, Mexico, NI 43-101.
Thomas, D., Melnyk, J., Lipiec, T., & Kozak, A. (Amec). (2011).
Caariaco Project Technical Report on Pre-Feasibility Progress
Report, NI 43-101.
Thomas, M., & Moorhead, C. (AMC Mining Consultants (Canada)
Ltd). (2011). Technical Report on the Cadia Valley Operations
Property in New South Wales Australia.
Wanless, M., Theart, H., Sturgeon, M., Senior, N., Grant-Stuart,
D., & Rowland, A. (SRK Consulting). (2012). Agbaou Gold Mine
Technical Report, NI 43-101.
Welhener, H. (Independent Mining Consultants Inc.). (2012).
Cordero Project June 2012 Mineral Resource Update, Chihuaha,
Mexico.
Wheeler, A. (2012). Technical Report on the Mineral Resources
and Reserves of the Los Santos Mine Project, Spain, NI 43-101.
References
Amelunxen, P., Meadows, D., 2011. Not another HPGR trade-off study! Minerals and
Metallurgical Processing 28 (1), 17.
Awatey, B., Thanasekaran, H., Kohmuench, J., Skinner, W., Zanin, M., 2013.
Optimization of operating parameters for coarse sphalerite otation in the
HydroFloat uidised-bed separator. Minerals Engineering 5051, 99105.
Ballantyne, G.R., Powell, M.S., Tiang, M. (2012). Proportion of energy attributable to
comminution. In: Proceedings of 11th Mill Operators Conference 2012, Hobart,
October 2012, pp. 2530.
Butcher, A., Cunningham, R., Edwards, K., Lye, A., Simmons, J., Stegman, C., Wyllie,
A., 2011. Northparkes Mines. AMMOP.
Costa Lima, G.A., Suslick, S.B., 2006. Estimating the volatility of mining projects
considering price and operating cost uncertainties. Resources Policy 31 (2), 86
94.
Crowson, P., 2003. Mine size and the structure of costs. Resources Policy 29 (12),
1536.
Crowson, P., 2012. Some observations on copper yields and ore grades. Resources
Policy 37 (1), 5972.
CSIRO, 2012. Ore sorting: sound technology making waves. <http://www.csiro.au/
Portals/Publications/Magazines/resourceful/Issue-2/2-sound-technology.aspx>.
(Wednesday, 28th August, 2013).
Daniel, M., Lewis-Gray, E., 2011. Comminution efciency attracts attention. The
AusIMM Bulletin, October, 2030.
Daniel, M., Lane, G., McLean, E. (2010). Efciency, economics, energy and emissions
emerging criteria for comminution circuit decision making. In: International
Mineral Processing Congress, 610 September, 35233531.
Evans, C.L., Coulter, B.L., Wightman, E., & Burrows, A.S. (2009). Improving energy
efciency across mineral processing and smelting operations a new approach.
In: Proceedings of SDIMI Conference, Gold Coast, July 2009, pp. 913.
Fisher, B., Schnittger, S. (2012). Autonomous and remote operation technologies in
the mining industries: Benets and costs. BAE, Report 12.1: Canberra.
Gunson, A.J., Klein, B., Veiga, M., Dunbar, S., 2012. Reducing mine water
requirements. Journal of Cleaner Production 21 (1), 7182.
Jameson, G.J., 2010. New directions in otation machine design. Minerals
Engineering 23 (1113), 835841.
Jameson, G.G., 2012. The effect of surface liberation and particle size on otation
rate constants. Minerals Engineering 3638, 132137.
La Nauze, R.D., & Temos, J., 2002. Technologies for Sustainable Operations. In: CMMI
Congress, Cairns, May 2002, pp. 2733.
Murphy, B., van Zyl, J., Domingo, G. (2012). Underground preconcentration by ore
sorting and coarse gravity separation. In: Narrow Vein Mining Conference, 26
27 March.
Norgate, T., Haque, N., 2010. Energy and greenhouse gas impacts of mining and
mineral processing operations. Journal of Cleaner Production 18 (3), 266274.
Norgate, T., Jahanshahi, S., 2010. Improving the sustainability of primary metal
production the need for a life cycle approach. In: Proceedings of XXV
International Mineral Processing Conference (IMPC) 2010, Brisbane, September
2010, pp. 35753584.
Norgate, T., Jahanshahi, S., 2011. Reducing the greenhouse gas footprint of primary
metal production: where should the focus be? Minerals Engineering 24 (14),
15631570.
Norgate, T.E., Jahanshahi, S., Rankin, W.J., 2007. Assessing the environmental impact
of metal production processes. Journal of Cleaner Production 15 (89), 838848.