Escolar Documentos
Profissional Documentos
Cultura Documentos
Consultation Paper
Energy Regulatory Commission
December
2015
Copyright Castalia Limited. All rights reserved. Castalia is not liable for any loss caused by reliance on this
document. Castalia is a part of the worldwide Castalia Advisory Group.
Table of Contents
1
1.1
1.2
1.3
Consultation Process
2.1
2.2
2.3
2.1.2
2.1.3
2.1.4
2.1.5
2.2.1
2.2.2
2.3.1
Assessment of options
2.3.2
10
2.3.3
10
2.3.4
10
2.3.5
10
Appendices
Appendix A Capex benchmark model ........................................................................12
Tables
Table A.1: Comparison of Benchmark Capex Model to Actual
Capex Approvals
12
13
Figures
Figure 2.1: NEA HarmonisationOption One
11
2
3
4
5
We have been engaged by the Energy Regulatory Commission (ERC) to address the
process for the approval of the capital expenditure plans of the Electricity Cooperatives
(ECs), proposing measures for a more streamlined and efficient process for future
approvals.
6
7
8
1.1
There have been long delays in the approval of Capex plans and there is currently a large
backlog.
9
10
11
12
The reasons for these delays are many and include variable quality of submissions from
the ECs and the long public consultation and legal approval processes. However, the key
problem is that all proposals, regardless of risk are reviewed in the same complex and
detailed process.
13
14
15
16
17
The proposed changes to the processing of Capex plans will make the process more
efficient and streamlined as the level of review will be tailored to the level of risk. The
level of risk will be assessed as being both the probability that expenditure in the Capex
plan is unreasonable and/or the potential impact of such unreasonable expenditure being
passed on to consumers.
18
19
1.2
20
21
Stage One is a proposal level evaluation that categorises proposals as low, medium or
high risk according to three objective criteria:
22
23
24
25
Those applications categorised as low risk will be approved at the proposal level.
26
27
28
Stage Two takes those categorised as medium or high risk and subjects them to a
more detailed assessment at the project level using the following components:
29
options considered;
30
demand forecasts;
31
32
economic evaluation.
33
34
Stage Two for medium risk plans is detailed in Section 2.2 and for high risk plans in
Section 2.3.
35
36
37
The calculation of the RFSC Charge is linked to the ERC approval of an ECs Capex
plans. A separate consultation paper will be issued on the proposed changes to setting
the RFSC charge.
38
1.3
Consultation Process
2
3
The aim of this consultation is to get feedback on our proposed changes to the Capex
approval process.
4
5
6
7
8
All interested parties are invited to submit their comments on this consultation paper on
or before 12th February, 2016. Electronic copies may be sent to tariffs.erc.gov.ph. This
consultation paper may be downloaded at the ERC website www.erc.gov.ph or may be
photocopied at cost at the ERC Main Office at the Docket Section, 18th Floor, Pacific
Center Building, San Miguel Avenue, Pasig City.
9
10
2
3
4
For Capex approvals the proposal is for a risk based approach, categorising applications
as low, medium or high risk based on objective criteria. The criteria will include both
primary criteria and secondary criteria.
Those applications categorised as low risk will be approved at the proposal level.
6
7
Those categorised as medium or high risk will be subject to a more detailed assessment at
the project level.
8
9
10
This process applies to the review and approval of scheduled multi-year Capex proposals
for ECs. It assumes that ECs submit multi-year capex proposals in groups, with each
group to submit in separate years.
11
12
13
14
15
16
17
Stage 1 assesses whether there is a high risk that the Capex proposals exceed the
reasonable needs of the EC. Proposals that are assessed to be low risk are approved at
this stage. Other proposals are classified as either medium or high risk and subject to a
more detailed second stage analysis.
18
19
20
21
22
23
24
25
Stage 1 places considerable reliance on the consistency with the program of works in an
EICPM approved by NEA. This will require greater coordination between NEA and
ERC. Stage 2 assesses the individual projects within the overall proposal in terms of the
option analysis, demand forecasts, technical analysis, and economic analysis. While the
structure of the process is the same for medium and high risk projects, the extent of
scrutiny is greater for high risk projects. The scrutiny of projects in high risk proposals
assesses the details of the supporting analysis and is similar to the current level of analysis
of Capex proposals.
26
27
28
29
30
31
32
The primary objective of a review is to reduce the risk of overspending. Furthermore, the
review process may delay projects and increase the risk of underspending. Hence, the
reviews should be focussed on higher risk proposals. The consequences of over-spending
and under-spending on Capex are the same across the high, medium and low risk
projects but the likelihoods are different. In the absence of a review the likelihood of
overspending is greatest for the high risk proposals and lowest for the low risk projects.
Hence, substantially greater scrutiny is applied to high risk proposals.
33
34
35
36
37
38
The assessment criteria fit closely with the requirements of the Planning Manual. Hence
adoption of this approach would not weaken the ERCs commitment to the proper
implementation of the planning manual, but it would make the testing of its application
through the Capex approval process more streamlined. Some modification of the ERCs
existing rule on the review of Capex programs would be required but this would not be
substantial.
39
2.1
40
41
42
43
1
2
3
4
5
6
7
8
9
10
11
12
Capex proposals that meet this criteria will be assessed as low risk if they meet all the
other criteria. Those proposals that do not meet this criteria will be assessed as high risk.
Given the proposed coordination of the submission of Capex proposals it is expected
that most ECs will meet this criteria if their Capex planning process is well managed and
they meet the procedural requirements.
13
14
15
16
Currently ECs submit Capex proposals to NEA as part of the EICPM every second year
in January and these are approved by the end of March. ERC does not have the
resources to process applications from half the ECs concurrently. Hence, it is proposed
that NEA and ERC harmonise the applications to a three year cycle.
17
The two options for synchronisation are shown in Figure 2.1 and Figure 2.2:
18
19
20
2
3
4
5
6
7
8
9
The benchmark cost model is tailored to the specific cost drivers of each EC. In
principle a cost function will:
10
11
12
13
14
15
16
We have tested a number of different cost models using known drivers of network
capital costs. All cost models were tested against recently approved Capex plans to assess
the predicative power of different models, the significance of cost drivers and to ensure
each coefficient has the correct sign.
17
18
19
An initial model to estimate reasonable capex needs has been developed and shows that
physical measures of the core network assets (network length and substation capacity) are
the best predictors of Capex needs.
20
21
22
23
A non-linear model is preferred to a linear model, given that network costs are non-linear
and because a log-log model is the best fit to the diminishing returns from economies of
scale. The proposed Capex Model will use two core network attributes to calculate a
benchmark for each EC:
24
Based on regression analysis, the benchmark Capex spend will be calculated as follows:
4
[
5
6
7
8
9
10
Growth and asset age measures were not statistically significant in our initial analysis but
may be included in the future to improve the overall performance of the model. The
Capex model will be continually developed and refined over time in a transparent process
so that ECs understand how it is used in the risk categorisation of proposals. A detailed
review of the Capex benchmark model is provided in Appendix A.
11
12
13
14
The aim of the model is to provide a guide to the typical level of Capex that would be
reasonable. Inevitably there will be cycles in Capex so that exceeding the benchmark does
not mean that the program is necessarily too high. But it will provide an indicator of
where further analysis (Stage Two) is warranted.
15
16
17
18
If the Capex proposals are higher than the benchmark they will be assessed as medium
risk as long as they meet both secondary criteria. Otherwise they will be assessed as high
risk. We expect that typically half or more of the proposals would be below the
benchmark.
19
20
21
22
Are KPIs met? (e.g. submission of data and compliance returns); and
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
2
3
4
5
6
7
8
9
10
This is because they have been assessed as being consistent with an approved EICPM,
below the Capex benchmark for a reasonable level of expenditure and have been judged
to have above average quality of justification and analysis.
11
12
13
14
15
16
A compliance check with the EICPM is an important measure for reducing ERCs
current burden and to accelerate the approval process. This is because, it incentives the
ECs to submit fully compliant Capex proposal submissions, and avoids unnecessary
interactions in gathering missing information. ECs that do not conform to the EICPM,
would face a more rigorous review of their Capex submission and delays in receiving
ERC approval.
17
2.2
2
3
4
5
6
7
8
9
10
For those Capex plans that are categorised as medium risk, each of the components of
the underlying analysis is tested against objective, transparent criteriathrough a series
of Yes or No questions. This means that the extent of judgement required is
minimised and detailed analysis of the supporting material is not required. This will
facilitate prompt review and decision-making and standardised decision documents. The
questions focus on the key requirements of the EC Distribution Utility Planning Manual
(ECDUPM). ECs whose Capex programs comply with the requirements of the
ECDUPM should be able to readily demonstrate compliance with the assessment criteria
for medium risk proposals.
11
12
The key difference from the Stage 1 assessment is that the Stage 2 assessment happens at
the project level.
13
14
15
options considered;
16
demand forecasts;
17
18
economic evaluation.
19
20
21
22
23
24
A key part of the assessment will be the reliance on NEAs assessment of the demand
forecasts. This will be made possible by coordinating the submission of Capex proposals
with the EICPM as discussed in Section 2.1.1. NEA places considerable emphasis on the
assessment of the demand forecasts and ensuring the forecasts are consistent with the
requirements of the planning manual. Hence, it is proposed to draw upon this rather
than duplicating the effort of NEA.
25
26
27
No
No
Are options
evaluated?
Yes
No
No
Is demand
forecast
reasonable?
Yes
No
No
Is technical
analysis
adequate?
Yes
No
No
Are economic
evaluations
provided?
Test: Is an economic
evaluation provided?
Yes
Reject
2
3
4
5
6
7
8
9
10
11
12
13
14
15
2.3
Approve
This process has the same structure as the assessment of projects in medium risk
proposals but requires a more detailed qualitative assessment of the components, other
than the demand forecast component. The level of analysis may also vary according to
the size of the project. That is, the larger or more unusual projects should be subject to
closer scrutiny than smaller or routine projects.
2.3.1 Assessment of options
Unlike the medium risk assessment, the ERC will consider not just whether options are
considered but whether the options are appropriate. That is, do the options cover a
set of alternatives that are likely to meet the identified needs and include the best
available options? This does not require the reviewing engineer to undertake the option
analysis but if it is determined that the options are deficient it will be necessary to show
1
2
in what way they are and identify or excluded options that could have been considered.
In practice this is likely to be the most critical part of the evaluation of the projects.
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
Whether the assumed costs of the proposal and options considered are
reasonable;
22
23
Whether the other assumptions that may be used (e.g. discount rate, project
life, and value of lost load) are reasonable; and
24
Whether the analysis supports the proposal over the alternative options.
25
26
27
This focuses the assessment on the methodology and assumptions. The reviewing
engineer would not normally undertake a detailed review of the underlying models unless
the results raise significant questions about the modelling.
28
29
30
10
No
No
Are options
evaluated?
Yes
No
No
Are the
forecasting
models valid?
Yes
No
No
Is technical
analysis
adequate?
Yes
No
No
Are economic
evaluations
valid?
Yes
2
3
4
Reject
Approve
11
EC Acronym
Regulatory
Period
Total Annual
Capex
Approved
Annual
Benchmark
Capex
Variance
AKELCO
2011-2014
41,698,425
63,210,063
51.6%
ASELCO
2011-2013
20,067,089
53,758,919
167.9%
BOHECO II
2011-2014
45,179,360
41,247,827
-8.7%
CANORECO
2010-2014
31,281,111
41,125,910
31.5%
CEBECO I
2014-2018
52,697,961
60,777,917
15.3%
CELCO
2011-2015
3,516,308
2,472,516
-29.7%
CENPELCO
2011-2014
139,503,425
84,564,144
-39.4%
COTELCO
2012-2015
104,213,816
91,358,854
-12.3%
DIELCO
2012-2016
1,871,743
4,716,841
152.0%
10
FICELCO
2011-2015
12,011,318
13,048,544
8.6%
11
FLECO
2011-2014
52,867,089
13,067,593
-75.3%
12
GUIMELCO
2011-2015
16,874,809
9,627,116
-42.9%
13
ILECO II
2012-2013
59,421,046
40,551,718
-31.8%
14
ISELCO II
2011-2015
67,846,860
34,044,893
-49.8%
15
MORESCO I
2011-2014
209,093,055
73,427,510
-64.9%
16
ORMECO
2012-2016
73,230,715
87,372,300
19.3%
17
PRESCO
2010-2013
4,151,599
5,029,895
21.2%
18
PROSIELCO
2011-2015
4,281,836
4,898,268
14.4%
19
SORECO II
2011-2011
6,669,964
20,200,562
202.9%
20
ZAMCELCO
2009-2013
19,111,457
61,102,471
219.7%
21
ZAMSURECO II
2011-2014
62,695,734
39,879,596
-36.4%
3
4
5
6
7
8
9
10
11
12
13
12
1
2
3
0.8535
R Square
0.72846
Adjusted R Square
0.69829
Standard Error
0.31309
21
SS
4.73361
2.3668
Residual
18.
1.76451
0.09803
Total
20.
6.49811
Coefficients
Intercept
4
5
6
MS
2.
Standard Error
LCL
24.14411
UCL
p-level
0.00001
t Stat
p-level
H0 (10%) rejected?
4.017
0.8915
2.47109
5.56291
4.5059
0.00027
Yes
Log(Ckt length)
0.78844
0.3468
0.18706
1.38982
2.27343
0.03548
Yes
Log(SS)
0.50061
0.25437
0.05951
0.94171
1.96802
0.06467
Yes
7
8
9
10
13
T: +1 (202) 466-6790
F: +1 (202) 466-6797
1747 Pennsylvania Avenue
NW 12th Floor
WASHINGTON DC 20006
United States of America
T: +1 (646) 632-3770
F: +1 (212) 682-0278
200 Park Avenue Suite 1744
NEW YORK NY 10166
United States of America
T: +61 (2) 9231 6862
F: +61 (2) 9231 3847
Level 1 Kyle House
27 31 Macquarie Place
SYDNEY NSW 2000
Australia
T: +64 (4) 913 2800
F: +64 (4) 913 2808
Level 2, 88 The Terrace
PO Box 10-225
WELLINGTON 6143
New Zealand
T: +57 (1) 646 6626
F: +57 (1) 646 6850
Calle 100 No. 7-33
Torre 1, Piso 14
BOGOT
Colombia
T: +33 (1) 45 27 24 55
F: +33 (1) 45 20 17 69
7 Rue Claude Chahu
PARIS 75116
France
------------- www.castalia-advisors.com