Você está na página 1de 43

Chapter 2

CONCRETE WORKS AT THE


CONSTRUCTION SITE

Introduction:
i. This topic introduces the students to the
preparation, transportation, casting, placing,
compaction and treatment of concrete at the
construction site.
ii. To understand the standard testing for trial
mixture for ready mix concrete.
http://modul2poli.blogspot.com/

2.1.1 SEGREGATION IN CONCRETE


1. SEGREGATION is when the coarse and fine aggregate, and cement paste,
become separated.

2. Segregation may happen when the concrete is mixed, transported, placed or


compacted.
3. Segregation makes the concrete weaker, less durable and will leave a poor
surface finish.
4. Concrete will segregate for the following reasons:
a)

If the mix is very dry, the coarse aggregate tend to separate.

b) If the mix is very wet, the grout i.e. Cement and water tend to separate.
c)

If specific gravity of coarse and fine aggregate differs segregation


increases.

d) Over vibration is prone to segregation.

http://modul2poli.blogspot.com/

5. To avoid segregation:
a) Check the concrete is not 'too wet' or 'too dry'.
b) Make sure the concrete is properly mixed.
c)

It is important that the concrete is mixed at the correct speed in a transit


mixer for at least two minutes immediately prior to discharge.

d) The concrete should be placed as soon as possible.


e) When transporting the mix, load carefully.
f)

If placing concrete straight from a truck, pour vertically and never let the
concrete fall more than one-and-a-half metres.

g) Always pour new concrete into the face of concrete already in place.

h) When compacting with a poker vibrator, make sure to use it carefully.


i)

Never spread concrete sideways with a poker vibrator as this may cause
segregation of the mix.

j)

Always be sure to vibrate concrete evenly.


http://modul2poli.blogspot.com/

2.1.2 BLEEDING IN CONCRETE


1. BLEEDING is a form of segregation where water rise to surface of
freshly placed concrete.
2. During compacting and until the cement-paste has harden it is
natural tendency for the solid particles to move downward and

displace water.
3. It is expressed as total settlement per unit weight of concrete and
cause plastic shrinkage cracking.
4. Bleeding can be reduced by finer cement, high alkali, high C3A and
addition of calcium chloride.

5. It can also be reduce for high temperature and with the use of
pozzolans, aluminum powder and air entraining agent.
http://modul2poli.blogspot.com/

2.2 WET CONCRETE


2.2.1

DEFINITION OF WET CONCRETE:

Is a mixture of water, cement, aggregate and admixture.

The constituents materials should be uniformly distributed after mixing


within the concrete mass during handling and placing.

2.2.2

CONCRETE MIX IN WET CONCRETE:

A CONCRETE MIX is designed to produce concrete that can be easily


placed at the lowest cost.

The concrete must be workable and cohesive when plastic, then set and
harden to give strong and durable concrete.

The mix design must consider the environment that the concrete will be
in; i.e. exposure to sea water, trucks, cars, forklifts, foot traffic or extremes
of hot and cold.

http://modul2poli.blogspot.com/

2.2.3

WORKABILITY IN WET CONCRETE:


1)

Workability means how easy it is to:


a)

PLACE,

b) HANDLE,
c)

COMPACT and

d) FINISH a concrete mix.


2)

Concrete that is stiff or dry may be difficult to Handle, Place, Compact, and
Finish and, if not constructed properly, will not be as strong or durable
when finally hardened.

3)

A SLUMP AND VEBE Test can be used to measure the workability of


concrete.

4)

Workability is affected by:


a)

THE AMOUNT OF CEMENT PASTE


The cement paste is the soft or liquid part of the concrete mix. The
more paste mixed with the coarse and fine aggregates, the more
workable a mix.

http://modul2poli.blogspot.com/

b)

THE AGGREGATE GRADING

5)

6)

Well-graded, smooth, rounded aggregates improve the workability of a mix.

To make a more workable mix:


a)

Add more CEMENT PASTE.

b)

Use WELL GRADED aggregates.

c)

Use an ADMIXTURE.

THE WATER TO CEMENT RATIO: Too much water and not enough cement means concrete will be
weaker and less durable. The water to cement ratio (W/C) is the weight of the water divided by the
weight of cement. The lower the ratio, the stronger concrete is.

http://modul2poli.blogspot.com/

2.2.4

TEST ON WORKABILITY OF CONCRETE:


1)

There are two main types of workability test:


a)

SLUMP TEST.

b) VEBE TEST.

http://modul2poli.blogspot.com/

http://modul2poli.blogspot.com/

2.3 HARDENED CONCRETE


2.3.1

CONCRETE STATES:
a)

Have three (3) different states in concrete:

Plastic (knowingly as wet concrete)

Setting.

Hardening

(knowingly as
hardened concrete)

b) Plastic State:

When the concrete is first mixed it is like 'bread dough'.

It is soft and can be worked or molded into different shapes.

In this state concrete is called PLASTIC.

Concrete is plastic during placing and compaction.

The most important properties of plastic concrete are workability and


cohesiveness.

A worker will sink into plastic concrete.

http://modul2poli.blogspot.com/

c)

Setting State:
Concrete then begins to stiffen.
The stiffening of concrete, when it is no longer soft, is called SETTING.
Setting takes place after compaction and during finishing.
Concrete that is sloppy or wet may be easy to place but will be more
difficult to finish.
A worker leaves footprints in setting concrete.

d)

Hardening State:
After concrete has set it begins to gain strength and harden.
The properties of hardened concrete are strength and durability.
Hardened concrete will have no footprints on it if walked on.

D
http://modul2poli.blogspot.com/

2.3.2

CRITERIA OF HARDENED CONCRETE

a) COMPRESSION STRENGTH
Definition: The values of concrete strength where the results of number
cube test that failure not exceed 5%.
Characteristic strength of concrete is determined only at the age of 28

days & consisted of ordinary Portland Cement.


For controlled purposes, the cube test will be held on fresh concrete
mix to determine whether it will achieve the required strength of

concrete at the age of 28 days.


b) TENSILE/BENDING STRENGTH
The tensile strength of concrete is usually taken into account 1 / 10 of
compressive strength but different aggregates cause large variations.
Compression Test is used to determine tensile strength.
http://modul2poli.blogspot.com/

c) DURABILITY STRENGTH
The ability of concrete to resist weathering action, chemical attack, fire
resistant and abrasion while maintaining its desired engineering properties.

In reinforced concrete and prestressed concrete, the steel protection from


corrosion is influenced by the thickness of concrete cover and permeability of
concrete.
In certain circumstances, the durability can be obtained by using high quality
concrete and used of specific cement.
d) PERMEABILITY (KEBOLEHTELAPAN)
The low permeability of concrete is essential for increase the resistance of
cooled, chemical attack and protects steel from corrosion.
To obtain a low permeability, the concrete should be fully compressed and
make a good preservation.
Permeability can also be reduced by using water content or add cement

content.
http://modul2poli.blogspot.com/

e) RESISTENT TO WEATHER AND CHEMICAL REACTION


Portland cement concrete is often attacked by acids such as organic acids and others
especially when food processing is carried out. Example: vinegar, water chemical and

water fruits.
Normally, chemical elements that attack concrete is salt sulfate.
The resistance of concrete from sulfate attack depends on the type of cement used,

cement content and water-cement ratio.


f) CHANGING OF SHAPE/REFORMATION OF SHAPE
As other materials, the concrete will also experience expansion and shrinkage due to
temperature change.
The main component for changing of hardened concrete are as follows:
Elastic deformation that occurs at that time and depending on the value of applied
stress.
Drying shrinkage that occurs in a long time and does not depend on the stresses in
the concrete.
Creeping occurred in the long run, but depending on the value of the concrete
stresses.

http://modul2poli.blogspot.com/

g) SHRINKAGE
Shrinkage of concrete depends on the amount of drying that occurs.
Thus, it is affected by humidity and air temperature, air flow rate on the surface and the rate
of surface area and volume of concrete.
In normal conditions, shrinkage is influenced by the amount of water in the concrete during
the mixing and the cement content.
For a small concrete, usually assumed that half of the drying occurs in one of the first month

and the balance within six months after.


h) CREEPING
Creep of concrete depends on the value of the stresses in it.
For stresses up to 1/3 of the cube strength by assuming creep is proportional to the stress.
Creep is affected by temperature and humidity, the cement content in concrete, water
cement ratio, cement type and nature of aggregates.
The mass of concrete also has some influence on the creep, but much less than its effect on
shrinkage.
The parameters used to evaluate the creep is the ratio of applied stress on the strength of
concrete cubes at one time point.
http://modul2poli.blogspot.com/

i) FIRE RESISTANT
Functionally, concrete exhibits good fire resistance characteristic and thermal
properties.

Its surface patterns can be easily varied to take on the surface features of the
enclosing formwork.
Its structural properties can be varied to match required compressive strength

design level, density, early strength gain to allow quick removal of forms and low
heat characteristic during curing to reduce shrinkage and cracking.

http://modul2poli.blogspot.com/

2.3.3

STANDARD TESTING IN TERMS TO DETERMINE THE STRENGTH


AND WORKABILITY OF CONCRETE MIXTURES

a) SLUMP TEST
TOOLS: Standard slump cone (100 mm top diameter x 200 mm bottom diameter x
300 mm high), Small scoop, Bullet-nosed rod (600 mm long x 16 mm diameter),
Ruler and slump plate (500 mm x 500 mm).
METHODS:

http://modul2poli.blogspot.com/

http://modul2poli.blogspot.com/

2.4

PREPARATION OF CONCRETE AT SITE

2.4.1

BATCHING METHOD OF CONCRETE:


1. Is the selection of a proper mix is based on the kind of work or exposure
condition the concrete will subjected to.

2. The design of concrete mix involves the determination of the most economical
and practical combination of ingredients to make the concrete workable in its
plastic state and to make it develop the required qualities when hardened.
3. The methods of proportioning concrete mixes can either be done by weight or
by volume.
4. The choice of proper batching system are:
a) Size of job.
b) Required production rate.

c) Required standards of batching performance.


http://modul2poli.blogspot.com/

2.4.1.1

WEIGHT BATCHING
1.

It used for most large and important jobs the batching of materials.

2.

In weight batching, the weight of surface water carried by the wet aggregate
must be taken into account.

3.

Batching by weight eliminates error due to variations in the properties of voids


contained in a specific volume, especially with the batching of sand.

4.

The batching equipment falls into three (3) general categories, namely:
a)

Manual Batching All operations of weighing and batching of concrete

ingredients are done manually. Used for small jobs only.


b)

Semiautomatic Batching the aggregate bin gates for charging batchers


are opened by manually operated switches. Gates are closed automatically

when the designed weight material has been delivered.


c)

Automatic Batching In which all scales for the materials are electrically
activated by a single switch and complete autographic records are made of
the weight of each material in each batch.

5.

The batching plant generally comprises of 2, 3, 4 or 6 compartment bins of


several capacities together with a supporting system.
http://modul2poli.blogspot.com/

2.4.1.2

VOLUME BATCHING
1.

For most small jobs, volume batching is adopted, i.e. the amount of each solid
ingredients is measured by loose volume using measuring boxes, gauge box, hopper
or wheel barrows.

2.

The accuracy of any method of measurement in which a gauge box or hopper is filled

a certain level depends on:


a)

Bulking of sand.

b)

The closeness with which the material packs.

c)

If the material packs closely with few air voids, the solid volume of material is
greater than if the material is packed loosely.

3.

In volume batching, it is generally advisable to set the volumes in term of whole beg
of cement.

4.

Sources of error in volume batching of aggregate are:


a)

Variations in the solid volume of aggregate contained in a specified measured


volume. It can be minimized although it is difficult to eliminate it.

b)

Error in measured volume. This error can reduced by careful attention to the
type of measure.
http://modul2poli.blogspot.com/

2.4.2 MIXING OF CONCRETE:


1. Objective of mixing is to coat the surface of all aggregate particles
with the cement paste and blend the ingredients into a uniform
mass.
2. Since the natural occurring materials have variables properties, the
human factor becomes important.
3. The human should monitor visually the workability, homogeneity

and cohesiveness of each mix, as well as the consistency of


production.
4. Concrete mixing is usually done by mechanical means called mixer,
but sometimes the mixing of concrete is done by hand.
5. Machine mixing is more efficient and economical compared to hand

mixing.

http://modul2poli.blogspot.com/

2.4.2.1 MACHINE MIXING:


1. It can either be in rotation or stirring operation.
2. The rotation operation is used in tilting drum mixer, non-tilting drum mixture, dual drum

mixer and continuous mixer, while the stirring operation is used in a pan type mixer.
3. Tilting Drum Mixer:
a)

A tilting drum mixer is one whose drum in which mixing take place is tilted for
discharging.

b)

The drum is conical or bowl shaped with internal vanes, and the discharge is rapid
and unsegregated so that these mixers are suitable for mixes of low workability and
for those containing large size aggregate.

4. Non-Tilting Drum Mixer:


a)

A non tilting drum is one in which the axis of the mixer is always horizontal and
discharge take place by inserting a chute into the drum or by reversing the direction
or rotation of drum.

b)

Because of slow rate of discharge, some segregation may occur.


http://modul2poli.blogspot.com/

5. Dual Drum Mixer:


a)

A dual drum is sometimes used in highway construction.

b)

Here there are two drums in series, concrete being mixed part of the time in one

and then transferred to the other for the remainder of the mixing time before
discharging.
6. Continuous Mixer:

a)

These are fed automatically by a continuous


weigh-batching system.

5
4

6
http://modul2poli.blogspot.com/

2.4.2.2 HAND MIXING:


1. There are many occasions when the concrete has to be mixed with
hand, and because of this case uniformity is more difficult to
achieve, therefore particular care and effort are necessary.
2. The aggregate should be separated in a uniform layer on a hard,
clean and non-porous base.

3. Cement is then should be spread over the aggregate and the dry
material are mixed turning over from one end of the heap to another
and cutting with a shovel until the mix appear uniform.
4. The water is gradually added to trough formed by the uniform dry
mix and the mix is turned over until a homogeneous mixture of

uniform colour and consistency is obtained.


http://modul2poli.blogspot.com/

2.5

TRANSPORTING OF CONCRETE

2.5.1

METHOD OF TRANSPORTING CONCRETE:


1.

The method used to transport concrete depends on which one is the


lowest cost and easiest for the job size.

2.

On small jobs, a wheelbarrow is the easiest way to transport concrete.

3.

However, concrete can be handled and transported by many methods,


including use of chutes, a concrete truck, a concrete pump and a
crane.

4.

The main consideration is selecting the type of equipment to be used


is an economic one, however, certain jobs require specialized
equipment and thus the cost is a secondary consideration.

5.

The other considerations are; the segregation of aggregate, loss of


entrained air, loss of cement paste, change in slump and accumulation
of harmful materials.
http://modul2poli.blogspot.com/

WHEELBARROW

CONCRETE
TRUCK

CHUTE (PELONGSOR)

CONCRETE PUMP
http://modul2poli.blogspot.com/

CRANE

A) CHUTE (Pelongsor):
1.

Chute used to transport concrete from top to bottom without a part separation.

2.

It made from PVC pipes or sometimes made of wood and metal.

3.

The length of chute is limited to only 3m long.

4.

It diameter approximately 300mm.

B) CONCRETE PUMP:

1.

The use of pumps is one method that is quick, clean and economical, if carefully
planned.

2.

Using the pipes 6 which is pumped from the concrete mix. Used for a large

quantity of concrete.
3.

Can carry as far as 30m to 50m vertically and 300m to 500m horizontal
direction.

4.

Consists of two types either in plunger pump or squeeze pump.

5.

The concrete pump is usually used if there is problems like this:


a)

The location of construction sites in urban areas is crowded, difficult to

use the truck and transportation equipment.


http://modul2poli.blogspot.com/

b) Limited road facilities.


c) Construction site near the existing building, difficulty entering the area or the
storage problem of raw materials.

d) The site location is not suitable for heavy machinery.


e) Lack of labor. The use of machinery tends for maximized productivity.
f) The contingency of project and need of permanent construction.

g) The construction of structures that is too high.


C)

CRANE:
1.

There are two types of crane namely as Tower Crane Bucket and Mobile Crane
Bucket.

2.

Mobile Crane Bucket Used for large projects and the construction of structures that
are very high. Where concrete is included in a large container equipped with a trap
door (pintu kolong) in the bottom and covered directly through the skip (langkau).

3.

Tower Crane Bucket Tower cranes used for building higher than 30 meters. Mobile
cranes are only limited to buildings with a height of 20 meters. Using skip depends on
the size of the load. Skip size is limited to a maximum size of 0:57m or 1394kg.
http://modul2poli.blogspot.com/

2.5.2

READY MIX CONCRETE:

1. If instead of being batched and mixed on site, concrete is delivered for placing from a central
plant. It is referred to as ready-mixed or pre-mixed concrete.

2. This type of concrete is used extensively abroad as it offers numerous advantages in comparison
with other methods of manufacture:
a)

Close quality control of batching which reduces the variability of the desired properties of
hardened concrete.

b)

Use on congested sites or in highway construction where there is little space for a mixing
plant and aggregate stockpiles;

c)

Use of agitator trucks to ensure care in transportation, thus prevention segregation and
maintaining workability

d)

Convenience when small quantities of concrete or intermittent placing is required.

4. There are two categories of ready-mixed concrete: central-mixed and transit mixed or truck

mixed.
5. In the first category, mixing is done in a central plant and then concrete is transported in an
agitator truck.
6. In the second category, the materials are batched at a central plant but are mixed in a truck.
http://modul2poli.blogspot.com/

2.6

PLACING OF CONCRETE

1. To secure a good concrete, it is necessary to make certain proportions, such as:


a)

The ready mixed concrete must be placed as near to its final position as possible,
so that it is not too stiff to work.

b)

When placing concrete, be careful not to damage or move formwork &


reinforcement.

c)

Start placing from the corners of the formwork or, in the case of a sloping site,
from the lowest level.

d)

Water should not be added after the concrete has left the mixer.

e)

When placing concrete, care should be taken to drop the concrete vertically and
not great at height. Never allow the concrete to fall more than 1 to 1.5 meters.

f)

The forms must be examined for correct alignment and adequate rigidity to
withstand weight of concrete.

g)

The forms must be checked for tightness to avoid any loss of mortar which may
result in honeycombing.
http://modul2poli.blogspot.com/

h)

Wood form should be moistened before the concrete is placed, otherwise it will
absorb water from concrete and swell.

i)

In addition, the forms should be oiled or lacquered to make form removal easier.

j)

The inside of the form must be cleaned and treated with release agent to
facilitate their removal when concrete is set.

k)

Avoid movement of reinforcing steel when placing the concrete.

l)

Make sure reinforcing steel is clean and free of loose rust or mill scale at the
time concrete is placed.

http://modul2poli.blogspot.com/

2.7

COMPACTING OF CONCRETE

1. WHAT IS COMPACTION: Compaction is done by shaking, or vibrating, the concrete which


liquefies it, allowing the trapped air to rise out. The concrete settles, filling all the space in the
forms.
2. WHEN TO COMPACT: Compaction must be done as concrete is placed, while it is still plastic.
Never let concrete dry-out and stiffen because it will be too hard to compact.
3. WHY COMPACT: Properly compacted concrete is more dense, strong and durable. Off-form
finishes will also be better.
4. Method of compaction can either be hand compaction or machine compaction:
a)

Hand Rodding.

b)

Machine Compaction. Examples are: Internal Vibrator Pocker, External Vibrator

Clamped to Formwork and Platform.


2.7.1

HAND COMPACTION
1.

Hand compaction methods consists of rodding, tamping and spading with suitable
tools.

2.

Concrete mix that normally use for hand compaction are of fairly workable mix if the
sections are at narrow and the reinforcement closely packed.
http://modul2poli.blogspot.com/

2.7.2

MACHINE COMPACTION:

(A) EXTERNAL VIBRATOR:


I.

SCREEDING:
Screeding levels and compacts thin concrete slabs and the top layers of
thicker slabs.
A screed board will not compact the concrete very well.
Mechanical vibration or hand rodding is required to provide adequate
compaction.

http://modul2poli.blogspot.com/

II. THE MECHANICAL SCREED:


Concrete is screeded TWICE.
The first screed levels the concrete roughly and compacts it.
The second screed levels and compacts the concrete more.
The screed is pulled along the top of the forms by two workers.
Always keep a small amount, or surcharge, of concrete, in front of both
beams of the screed to avoid holes forming in the surface.
If a hollow develops, the screed will not compact the concrete. The
mechanical screed compacts the concrete as it vibrates.

http://modul2poli.blogspot.com/

(B) INTERNAL VIBRATOR:


Internal vibration is done with a mechanical vibrator or
poker vibrator. The POKER is put into concrete and

vibrates it from the inside.


I.

METHODS:
Make sure there are enough workers so some can compact while others

continue to place.
Put the poker into the concrete QUICKLY.
Take the poker out very SLOWLY otherwise a hole, or weak spot, may be left

in the concrete.

http://modul2poli.blogspot.com/

The SIZE of the poker determines how much concrete is vibrated at one time.
The area vibrated at one time is called the RADIUS OF ACTION.
This can be seen by over what radius air bubbles rise to the surface.
The radius of action will be greater with a LARGER poker and more-workable
concrete.
Always compact in a definite pattern so the radius of action overlaps and covers the
whole area of the concrete.
The poker should be long enough to reach and enter into the layers of concrete under
the one being compacted.
II. PRECAUTIONS:
Taking the poker out TOO QUICKLY will leave a hole in the concrete.
To close the hole, vibrate near the hole and take the poker out VERY SLOWLY.
NEVER touch the form face with the poker as it can damage the formwork and the

concrete.
NEVER touch the reinforcement with the poker.
NEVER spread or move concrete sideways with the poker, always use a shovel.

NEVER leave the poker running when not in use.

http://modul2poli.blogspot.com/

III. HOW LONG TO COMPACT:


For concrete of average workability (ie slump of 80 mm) with a poker size
between 2575 mm, concrete should usually be vibrated for between 5 and 15
seconds.
It is worse to UNDER-VIBRATE than to OVER-VIBRATE concrete.

http://modul2poli.blogspot.com/

2.8

CURING OF CONCRETE

(A) WHAT IS CURING:


i.

Curing means to cover the concrete so it stays MOIST.

ii. By keeping concrete moist the bond between the paste and the aggregates gets
stronger.
iii. Concrete doesnt harden properly if it is left to dry out.
(B) WHEN TO CURE:
i.

Curing is done just after finishing the concrete surface, as soon as it will not be
damaged.

ii. When curing, leave the formwork in place to help reduce water loss. In hot weather
(above 30C), or during high winds and low humidity, concrete can dry out easily.
iii. In these conditions take extra care while curing.
(C)

WHY CURE:
i.

Concrete that is cured are LESS LIKELY TO CRACK, More DURABLE and STRONGER.

ii. Cured concrete has a surface that wears better, lasts longer and better protects the
steel reinforcement. The concrete can carry more weight without breaking.
http://modul2poli.blogspot.com/

(D) HOW TO CURE:


I.

WATER CURING:

Curing by flooding, ponding or mist spraying is widely used.

It is the most effective curing method for the prevention of mix water

evaporation.

This method is not always practical, however because of job conditions.

Continuous sprinkling with water is also excellent method of curing.

http://modul2poli.blogspot.com/

II.

COVER WITH PLASTIC SHEET:

Another way to cure concrete is to cover with PLASTIC SHEETS to slow down
water loss.

This method is easy and cheap.

The only problem is that the sheets may cause concrete to become darker in
places.

To avoid this keep concrete EVENLY moist.

The sheets must be held down to stop them blowing away and the concrete
surface drying out.

The sheets can be overlapped and stuck together and/or held down with
sand, timber or bricks.

Always check under the plastic from time to time to make sure the concrete is
EVENLY moist.

If it feels dry, sprinkle with water and put back the plastic sheets carefully.

Condensation on the underside of the plastic is a good sign.


http://modul2poli.blogspot.com/

III. CHEMICAL MEMBRANES:

Chemical can be sprayed on the surface to cure concrete.

Liquid membrane-forming curing compounds retard or prevent the


evaporation of moisture from the concrete.

The chemical application should be made as soon as the concrete is finished.

If there is any delay in the application, the concrete must be kept moist until
the membrane is applied.

The membrane curing compound must not be applied when there is free
water on the surface or after the concrete is dry.

Sodium silicate solution is one of the chemical curing.

http://modul2poli.blogspot.com/

IV. STEAM CURING:

In steam curing, the heating of the concrete products is caused by steam


either at low or high pressure.

The method ensures even heating of products all over, even if the space
between the stacked precast concrete products is very small.

Steam curing is more favorable to mix of concrete with low water cement
ratio than mixes with higher water-cement ratio.

(E)

HOW LONG TO CURE


a)

Concrete keeps getting HARDER AND STRONGER over TIME.

b)

Household concrete jobs MUST be cured for at least 3 DAYS.

c)

For better strength and durability, cure concrete for 7 DAYS.

d)

The LONGER concrete is cured, the closer it will be to its best possible
strength and durability.

http://modul2poli.blogspot.com/

Você também pode gostar