BATON ROUGE PIPING MULTI- WORKSHARE EXECUTION PLAN FEL3

JACOBS PROJECT NO. 64RH0006 (PES 870 Tier 3 Project)

REVISION: A
DATE: 10/18/2016

PIPING WORKSHARE EXECUTION PLAN


1.0 Piping Workshare Overview
Jacobs will utilize staff in the Baton Rouge (BTR), Mt Laurel (MTL) and Baroda,
India (VAR) offices to execute the piping design and engineering for PES 870
(Tier 3) Project. BTR will function as the lead site and will bear the primary
responsibility for performance against the project schedule and budget as well as
technical quality. The BTR leads will be responsible for ensuring that the final
engineering and design packages conform to client requirements and applicable
codes. All work shall be designed in accordance with the PES Engineering
Practices guidelines and applicable US Codes and Standards and Jacobs
Standard Operating Procedures, including the JSTEPS Work Process flow
diagrams, as applicable to the project.
The piping scope is and will be limited to aboveground piping. Underground
piping will be designed by Jacobs Civil/Structural design group. All piping design
shall use the basic Intergraph Plant Design System (PDS) 3D software. Stress
Analysis will follow the Jacobs standard procedures.
2.0 Workshare Responsibilities and Work Areas
The project piping scope is defined as two separate areas; FCBW and DDU. The
piping design for both areas will be conducted solely in the VAR office.
The BTR Piping activities include:
Design support
1. Home office design reviews.
2. Maintain all control documents (PFDs, P&ID redlines, Line List, Tie-In
List, Specialty items list and Equipment Arrangements).
3. Coordinate and communicate with the Jacobs workshare offices
regarding all piping design activities and deliverables for the project.
4. Daily review and prompt resolution for items requested via the Piping
Design Needs List.
5. Establish priorities of work.
6. Participate in both internal and formal client PDS model reviews to
provide input, approval, and recommendations for design.
7. Coordinate follow-up activities to the model reviews.
8. Perform final approval of all piping designed in the VAR office.
9. Issue all piping deliverables and drawings. (P&IDs, Line List, Tie-In
List, Specialty Item List, Plot Plans, Isometric, Demolition drawings,
Equipment Arrangement drawings, and Steam Tracing Packages)
Administration/Coordination/General
1.
2.
3.
4.

Conduct Squad Checks and Vendor Data Reviews to ensure


compliance with design requirements and specifications.
Develop and maintain the BTR Deliverable Status Report, Effort Hour
Forecast Report, schedule, schedule updates, and staffing plans.
Provide management, supervision and leadership for the BTR Piping
group.
Provide general engineering administrative support to the Project
Team as required.

BATON ROUGE PIPING MULTI- WORKSHARE EXECUTION PLAN FEL3


JACOBS PROJECT NO. 64RH0006 (PES 870 Tier 3 Project)

REVISION: A
DATE: 10/18/2016

The Mt Laurel Piping activities include:


Design support
1.
2.
3.

Locate, tag & obtain client approval for all tie-ins.


Perform field design work & provide field sketches as needed.
Participate in Piping Layouts and Studies if requested by the BTR
Piping Lead.

The VAR activities include:


Design and Engineering support
1.
2.
3.
4.
5.
6.
7.
8.
9.

10.
11.

Perform piping design and stress analysis. BTR VAR will issue the
stress packages after completion.
Perform PDS interactive and batch interference checks (clash) as well
as LFM clash checks.
Provide markups of the P&IDs, line list and other control documents to
the BTR office for review and inclusion into the MMU set.
Draft all P&ID pickups and back check prior to issue.
Extract, update and check all equipment location drawings for the
project.
Assemble all demo packages for the project. This will include modeling
and extracting of demo isos.
Assemble all steam tracing packages for the project.
Maintain a day to day status in the PDM progressing database for all
VAR activities.
Use the Piping Design Needs List for identifying needs from the BTR
office. Emails are OK for notification but are not to be used as the
record.
Prepare stress files for Level 1 and Level 2 calculations. See the
Stress Procedure for formatting.
Participate in Piping Layouts and Studies if requested by the BTR
Piping Lead.

Administration/Coordination/General
12.
13.

Assist with vendor data reviews.


Develop and maintain the VAR Deliverable Status Report, Effort Hour
Forecast Report, schedule updates, and staffing plans.
14. Provide management supervision and leadership for the VAR Piping
group.
3.0 Study Models
Study Models will be used when routing or scope changes or studies are
required. Routing changes or studies shall be authorized in advance by the BTR
Piping Lead. The change or study will be modeled in a study model for review
and approval. After approval it can then be copied into the project model.

BATON ROUGE PIPING MULTI- WORKSHARE EXECUTION PLAN FEL3


JACOBS PROJECT NO. 64RH0006 (PES 870 Tier 3 Project)

REVISION: A
DATE: 10/18/2016

4.0 Interoffice Model Reviews


During FEL3 BTR will monitor the design by means of Smart Plant Review.
When VAR has designated lines ready for model review the date is entered into
PDM progressing. BTR will validate the lines are ready for the model review and
enter the date into PDM progressing.
5.0 Stress Analysis
VAR is responsible for stress analysis of all lines in accordance with the
procedures and technical guidelines. BTR will review and approve all stress
analysis performed by VAR for completeness, uniformity and conformance with
project specifications.
All isometrics will be extracted and reviewed by VAR piping design before
submitting for stress analysis.
Final stress analysis files are to be posted in JPI and issued by the BTR VAR
Piping Engineering Lead.
6.0 Internal Approval Model Reviews
BTR will conduct the internal approval model reviews in accordance with the
project schedule. Comments from the reviews will be tagged during the review
and sent to VAR for confirmation and incorporation into the models. Tagged
comments are to be resolved prior to the next model review.
7.0 Client Approval Model Reviews
BTR will conduct the internal approval model reviews in accordance with the
project schedule. Comments from the reviews will be tagged during the review
and sent to VAR for confirmation and incorporation into the models. Tagged
comments are to be resolved prior to the next model review.
An agenda shall be prepared by the BTR Piping Lead prior to each Model review
and distributed to the attendees. The agenda will be comprised of a list of lines/
isos as extracted from the PDM progressing database.
BTR will document which lines have gone thru the model review by entering the
appropriate date in the PDM progressing database.
VAR Piping will keep track of areas and lines that have been reviewed and are
being reviewed in the scheduled review by way of highlighted P&IDs. Proper
color coding is to be followed to distinguish between approved, reviewed and
offered lines.
A copy of the Master Mark-up P&IDs, Equipment Location Drawings and any
applicable equipment drawings shall be made available for the model review
session.

BATON ROUGE PIPING MULTI- WORKSHARE EXECUTION PLAN FEL3


JACOBS PROJECT NO. 64RH0006 (PES 870 Tier 3 Project)

REVISION: A
DATE: 10/18/2016

Table 1
Piping Work Sharing Responsibility Matrix
FCBW and DDU
NON-PDS

PDS

Engineering

Design

Line List

BTR

BTR/VAR

Tie-In List

BTR

BTR/VAR

Specialty Item List

BTR

BTR/VAR

Engineering

Design

Remarks

Piping

Equipment arrangements

VAR

VAR

Revised equipment arrangements

VAR

VAR

New Index Area Drawings

BTR

Underground Piping Plans

By CIVIL

Demolition documents

VAR

Field Trips

BTR/MTL

VAR

Isometrics, IFC

N/A

Piping Plans

N/A

PDS Model - One Line Studies

See Remarks

PDS Model - Detail

VAR

Specialty Item Datasheets

N/A

Piping and Valve Specifications

BTR

Pipe Supports Standards

BTR

Stress Isometrics

VAR

PDS Standards
Pipe Stress Loads IFD (for C/S )
Structural & Mechanical use)

Only when authorized by the


BTR Piping Lead. The Office
will then be determined.

VAR
BTR

BTR

BATON ROUGE PIPING MULTI- WORKSHARE EXECUTION PLAN FEL3


JACOBS PROJECT NO. 64RH0006 (PES 870 Tier 3 Project)

REVISION: A
DATE: 10/18/2016

FCBW and DDU


NON-PDS

PDS

Engineering

Design

Steam Tracing

BTR

VAR

Pipe stress Analysis

VAR

P&IDs

BTR

VAR

Engineering

Design

Remarks

VAR

BTR will update and maintain


the P&ID MMUs. India will
draft them.