Escolar Documentos
Profissional Documentos
Cultura Documentos
2) The canal was passing from northern part of the state to southern part of the state.
Purvanchal dam/Purvanchal Power Station was constructed in such a way that water
level was increased to such level that flow of water could be maintained with same
pressure even till last part of the canal. Entire states electricity requirement was
fulfilled from the same Purvanchal Hydral Power Station. On the other hand the canal
was fulfilling the irrigational requirement of entire state from northern side to southern
side of the state.
3) However state of Purvanchal was reorganized into two different states, one was named
as Southern Purvanchal and the other state was named as Northern Purvanchal under
the State Re-organization Act 1956. The State was divided in such a way that both
states had got almost same territorial area and the population of both newly formed
states was almost same.
2
4) After partition of the state Purvanchal, the control of release of water from dam and
release of electricity from the Purvanchal Hydral Power Station came under complete
control of Northern Purvanchal state therefore what quantity of water and electricity
could be allowed to be parted by Northern Purvanchal State for utilization of Southern
Purvanchal state, also was within the control of Northern Purvanchal state. From the
dam 20500 cusecs of water used to be released per day in canal so that 1000 cusecs of
water per day used to reach to Southern Purvanchal State. The Purvanchal Hydral
Power Station used to produce 2000 MW of electricity and 1000 MW of electricity
used to be supplied from the Purvanchal Hydral Power Station to Southern Purvanchal
State. At the time of partition of state one agreement was executed by newly formed
states that the cost of production of electricity at Purvanchal Hydral Power Station and
cost for maintaining the canal would be shared by both states equally.
6) The farmers of Southern Purvanchal State were protesting and were asking the state
government of Suouthern Purvanchal State to intervene in the matter to ensure that
3
electricity and water problem may not continue and politically both the States could
settle the dispute amicably. However the state government of Southern Purvanchal
State could not resolve the issue inspite of the fact that they had approached the
government of Northern Purvanchal State several times for restoring the earlier sharing
of water and electricity. Nevertheless the government of Southern Purvanchal State was
not taking appropriate legal step to ensure restoring supply of 1000 MW electricity to
Southern Purvanchal State as well as for release of 10000 cusecs of water per day in
the cannel for use of Southern Purvanchal State for irrigational purpose.
8) One of the farmer RamKrishna.P of Southern Purvanchal State filed one Public
Interest litigation before Federal Court praying to give direction to both Central
Government of Union of Indus Land and Government of Northern Purvanchal State
for restoring the supply 1000MW of electricity from Purvanchal Power Station and
restore the 10000 cusecs of water in the canal running in Southern Purvanchal State.
Note:- Union of Indus Land has Federal Court similar to that of Supreme Court of India.
Similarly the Constitution of the Union of Indus Land is similar to that of the Constitution of
India. Various Acts which are in force in Union of Indus Land are same Union of India are
identical. Thus there are similarities in the laws, judicial system and Centre State relations.