Escolar Documentos
Profissional Documentos
Cultura Documentos
FOR
ORCHID CROWN TOWERS, DADAR AT MUMBAI
TEAM :
PROJECT:
MEP CONSULTANT:
CLIENT:
D. B. Realty
D. B. House, Gen. A. K. Vaidya Marg,
Goregaon (E),
Mumbai 400 063
India
MUMBAI OFFICE:
DEVELOPERS:
M/s. Real Gem Buildtech Private Limited
DESIGN CONSULTANT:
M/s HAFEEZ CONTRACTOR
29/Bank Street, Bombay 400023
Ph: 22661920
MASTER INDEX
1.
1
2
3
4
Introduction
Concept Design Report
Scope of Services
Codes & Standards
Site Wide Design conditions
2.
1
2
3
3.
HVAC
A.1
A.2
1.
2.
3.
4.
5.
6.
Project Description
Design Objectives
General
Site location
Temperature & Humidity
Design data and parameters
External design conditions
Noise levels
7.
8.
9.
10.
11.
12.
4.
ELECTRICAL
5.
D.1
D.2
D.3
D.4
6.
1
2
3
4
5
6
FIRE ENGINEERING
Introduction
Means of Escape
Compartmentation & Structural Fire Protection
Fire Safety Systems
Smoke Ventilation & Control
Fire Service Access And Facilities
1. INTRODUCTION
* Background
M/s Pankaj Dharkar & Associates has been engaged as the Building Services Consultants for ORCHID CROWN Residential Tower
and related facilities.
2. Scope of Services
The MEP scope of services generally includes the following:
HVAC
Domestic water services (including recycled water)
Foul water drainage (Internal)
Sprinkler layouts
Internal lighting (specialist architectural and faade lighting by others)
Electrical power systems
Standby power systems
Smoke management systems
Definition of relevant utility loads
Services Installation
Transformers
Standby Generators
Low Voltage Electrical Distribution
Interior Lighting Installation
Emergency Lighting
Car Park Lighting
Fire Detection & Alarm Systems,
including Public Address system
Lightning Protection
Earthing
BS EN 10056:2; ASPE
NFPA 10, 12, 13, 14, 15, 20
NFPA 58
10
Services Strategy
Mid Level Technical Floors
The location of meter rooms has been carefully considered to co-ordinate with the structure. The main mid level technical floors
are located at every Refuge levels which house the electrical meter room. The primary incoming electrical substation consists of 2
Substation provided by the BEST and is tentatively suggested at the Recreation Ground. The location would be confirmed after the
CFO approvals.
11
1.
2.
3.
4.
5.
6.
Power supplies to life safety equipment shall be provided to local prevailing codes. Redundancy will be incorporated into the
design of the power to life safety equipment with cabling meeting required standards for fire resistance, mechanical protection and
fire compartmentation.
Disconnect switches, breakers or automatic transfer switches associated with supplying power to life safety equipment shall
interface with the building management system and/or fire alarm system via a control circuit.
Status will be required for the respective position, and generate both a central and/or local alarm when the main power or
control circuit is defeated. Alarm shall visually and audibly indicate the fault.
All penetrations through fire resistance walls are to be fire stopped to meet the required resistance level of the element being
penetrated.
12
Electrical Requirements:
13
3. HVAC
14
GENERAL
A.1. Project Description
1. Project is ORCHID CROWN Residential building located at prime location of Mumbai at Dadar. The building is designed by
renowned Architect M/s Hafeez Contractor based at Mumbai.
2. The building consists of 14 car parking levels, 1 landscape level, 1 Podium level and 52 levels of residential apartment
levels including 9 refuge levels and 4 levels for service purposes.
3. The HVAC services are distributed over facility floors and basements. The mechanical ventilation fans for toilet & kitchen
areas are being planned on intermediate refuge levels. The common areas like lift lobby / entrance lobby at various levels
are being envisaged to be air conditioned with VRF system. The system description and advantages are being discussed
in the subsequent paragraphs. The ancillary HVAC components and systems viz. TFAs, mechanical ventilation units will
be placed suitably and location shall be decided during design development.
A.2. Design Objectives
1. To evolve an energy efficient design and engineering of HVAC system
1. General Requirements
1. Air conditioning & Ventilation systems to be designed & installed in accordance with the latest recommendations of
ASHRAE and in confirmation with the latest International Building code, all local and National codes and the requirement
of agencies exercising jurisdiction over work at the project.
2. All piping systems shall be complete with hangers, anchors, guides, valves, strainers, expansion tanks, vents, insulation,
etc.
15
3. All duct systems shall be complete with hangers, volume dampers, fire dampers, smoke dampers, filters, diffusers,
grilles, registers, insulation, etc.
4. All equipment shall be complete with vibration isolation, starters, control wiring, painting, insulation, etc.
5. All systems shall be fully tested and balanced.
6. All water systems shall be fully balanced.
7. The entire installations, commissioning and performance evaluation procedures shall be predetermined and documented.
2. Site Location:
The site is located near Dadar in the city of Mumbai. The area is densely populated and is a desirable location comprising of
mostly low to medium rise residential buildings in contrast to the high rise towers of Worli in the vicinity.
3. Temperature & Humidity:Mumbais weather is characteristically humid all year round, except for a few short periods in the winter. The Mumbai region
has little seasonal fluctuation of temperature due to the moderating effect of the coastal region; air temperature can reach up to
34C in the summer months and as low as 17C in the cooler months. The combination of high humidity and hot temperatures
make conditions quite uncomfortable in summer months, particularly during the months of May and June. The cool season from
December to February however, sees temperatures drop to levels comparable to that of European summers which helps to make
the environment pleasant.
Monsoon season is from June to September and brings almost all of Mumbais annual rainfall with strong Westerly wind and
continued high humidity levels. Typically the diurnal range is 9C. Strong solar radiation causes evaporation from the coastal
region, which is not precipitated but suspended in the air, thus causing high humidity levels. The effects, although slightly reduced
are experienced in the Mumbai region. Generally, winds are locally caused by the unequal heating of land and sea surfaces off
the sea towards land in the day and vice versa at night.
16
6. Noise Levels
External noise levels shall comply with the following,
At site Boundary: Ambient level as close to the existing level as possible
At 1.5m from all air intake and discharge louvers NR50
17
8. Basis of Design :
U-values:
Wall : Average U-value of 0.077 Btu/hr ft2 0F considered for external insulated walls.
Roof : U-value of Exposed Insulated Roof considered is 0.072 Btu/hr ft2 0F.
Partition :
Ceiling with Non Ac Area Above
Floor with Non Ac Area Below
Partition Wall
:
:
:
0.48
0.48
0.40
18
Each lift lobby / entrance lobby will have Cassette / Ductable /Floor / hiwall mounted type indoor unit suiting to interior requirements
having fan, coil and filter housed in a cabinet. All these indoor units will be connected to a group of outdoor units through refrigerant
and communication cables. High quality refrigerant joints, refrigerant piping and cabling will be laid through shaft to the terrace
level/ intermediate mechanical floor levels.
Outdoor units will be located at the intermediate refuge level/ mechanical floor levels of the
building; sufficient maintenance and air circulation space will be available surrounding the
outdoor units. The TFA units could be connected to VRF outdoor units.
ENVIORNMENT FRIENDLY :
The modern VRF system used HCFC free R 410A refrigerant as a media. Hence it does not
contribute to ozone depletion. Also due to its high COP especially at the part load condition,
commonly prevailing in residential application. VRF system has lower global warming impact on
Environment.
19
NOISE LEVEL :
Capacity
%
100
8 hours
(Initial Setting)
50
Load Operation
%
sound dB
Indoor units posses very low sound level in the range of 32 d to 38 dB., in
addition outdoor units are also reasonably quiet and sound level of ODU are
in the range of 60 dB. Moreover VRF outdoor unit have very advance NIGHT
QUIET MODE , which brings down noise level of outdoor units up to 13 dB
when capacity requirement is lower during night operation. This can be achieved
by both auto and manual mode.
0
58
10 hours
(Initial Setting)
Night Mode
max. - 8dB ( 10HP)
50
8:00
12:00
16:00
20:00
0:00
Night mode
starts
4:00
8:00
Night mode
ends
Mode 2. Manual
Exact starting time and ending
time can be input by an
external time clock, or other
device.
Mode 3.Combined
Combination of either of the
above modes, depending on
47
the needs.
VRV-Long Piping
5m
Actual
piping length
150 m
50 m
40 m
Equivalent
Piping length
175 m
15 m
21
20
SHAFT SPACE :
VRF system involves comparatively very small ref. pipe diameter; approximately 1/3 of that of
chilled water system. This results in less shaft space utilization and good amount of shaft space is
left for other utilities.
1/3
4 units max.
iPU
intelligent Processing Unit
Local
Controller
HRV
50
21
INDIVIDUAL CONTROL :
VRF is a completely variable system and has negligible fixed energy components. This
characteristic makes it highly suitable for application such as this, which has constantly
changing occupancy of a bldg. It provides each room with independent control, allows
system shutdown in rooms where No Air-conditioning is required and accordingly power
consumption of the system will reduce proportionately. It has characteristic of better
energy efficiency at part load condition, which is normally the case in Hotel bldg.
Individual controllability
An energy-efficient, comfort-providing system that conditions only when
and where it is called for: Automatic capacity control by inverter.
Central A/C System
VRV System
EASY MAINTENANCE:
17
INV
Stop
BackBack-up by
setting on RC
Running
INV
Alarm is
indicated
on the RC
Broken
INV
It is completely self diagnostic system and generates error codes on remote Control display
indicating the type of error occurred. Also this being modular system doesnt need only
standby equipments because if one compressor is malfunctioning, other takes over
emergency operation. If an outdoor units malfunction, another provides emergency
operation till repair.
The broken
compressor
can be
repaired
while the
remaining
units are still
operating.
Continue running
INV
INV
INV
40
22
Measurements guide
23
5. ARI 110-2002
6. ASHRAE 1991
10. SMACNA-1990
13. SMACNA-1989
16. ANSI/ASHRAE/52.1-1992
24
23. ANSI/ASHRAE-51-1985
24. ANSI-UL-555-1990
Fire dampers
25. NFPA
ANSI/AMCA-210-1985
Refrigeration piping
30. ASHRAE
Refrigeration oil
31. ANSI/UL/1963-1991
32. ANSI/ASHRAE/111-1988
33. SMACNA
25
residential buildings
36. ASHRAE 15-1994
Copper and copper alloy rolled plates for condensers and heat
exchanges
26
PVC Insulated cables for voltage upto 1100V with copper and
aluminium conductors respectively
EARTHING:
48. IS 3043 -1966
MOTORS:
49. IS 325
NOISE & VENTILATION:
50. IS 9901 Part I & Part II Part 9-1991 :
convention
53. Is 14259 1995
56. IS 4729
27
Gaskets
water (Amendment 2)
64. IS 10981 1993
28
TERMINAL INSULATION:
76. IS 3346 1990
VENTILATION:
29
4. ELECTRICAL
30
The electrical system will be designed in accordance with National Building Code of India. The electrical design will be based upon
the following electrical supply criteria
Medium Voltage (MV) 33kV / 3 phase / 50 Hertz
11kV / 3 phase / 50 Hertz
Low Voltage (LV 3 phase) 415 V / 3 phase, 4 Wire / 50 Hertz
Low Voltage (LV 1 phase) 230 V / 1 phase / 50 Hertz
ELECTRICAL DESIGN
1.
2.
31
3.
Essential/emergency lighting
Stair pressurisation
Lifts ( Fire fighting and evacuation purposes)
32
In addition, standby power generation typically supports essential applications to ensure that the building functions in a
manner that is conducive to the operators final requirements in the event of mains power failure or disruption from the
electricity network supply.
Generator Configuration
The D.G. sets will be an coupled directly to an alternator to produce a three phase, 0.415 kV, 50Hz output which will allow
non-essential loads to be shed when the standby generators are in use.
Each standby generation system will comprise:
Cabling associated with this distribution is recommended to be housed in a separate fire rated shaft to the mains supply.
Switching between mains and generator supply could occur on the LV side;
Due to the nature of the electrical load distribution and the configuration of the electrical system, it is recommended that
the generators are located external to the building allowing ease of ventilation, limiting fuel supply runs, noise and vibration
problems and ease in extraction of fumes.
33
The electrical system will be designed in accordance with the IS, BS and the standards dictated by National Building Code
of India, 2005.
34
National Electricity Act of 1910 and rules issued there under revised up to date.
Special Attention should be given to Rule No. 50.
Regulations for electrical equipment in building issued by The Bombay Regional Council of insurance Association of
India.
35
The switchboards will be specified for safety, operation and life in line with the load and nature of the building.
The LV switchboards will be provided with spare breakers (approximately 20%).
Typically the technical floors will serve a number of floors within the building. The main low voltage distribution from the
technical floors will be provided based on having an LV riser within each of the 3 cores serving the adjacent segment. Sub
main distribution will comprise sub main cabling to items of plant and equipment and rising busbar distribution systems.
36
The main LV distribution switch panels will comply with category Form 4 construction and be manufactured to BS EN 60439
1. It is generally expected that all LV distribution panels will be bottom entry/top exit, and that access for maintenance and
future modifications will all be carried out from the front of the panels.
Power supplies to life safety systems will be designed with two independent feeds to system with an automatic transfer
switch (ATS) able to detect power failure, initiate transfer to alternate supply and monitor incoming power.
Power Quality
Power factor at the supply intake point should be maintained at better than 0.95 lagging. Allowance will be made for power
factor correction equipment on LV switchboards. Connection points and CTs will be provided to allow future power factor
correction or active harmonic filters to be installed at each main LV Switchboard.
Space for active harmonic filters will be provided to eliminate harmful harmonics that can cause nuisance tripping,
overheating and damage to equipment.
The load assignment across the 3 phases will be as evenly distributed as possible to prevent load imbalance.
Metering
Metering will be provided on LV switchboards and will cover the main incoming supply as well as required outgoing ways. All
metering will be supplied with volt free contacts to allow remote monitoring by the BMS
system.
Metering will be provided to monitor the usage and quality of the power system. Power metering will have two primary
functions
Energy metering
Power quality monitoring
37
Metering will be provided on a tiered basis with meters at high level switchboards and critical systems provided with a
higher functionality to enable full detailed analysis while general distribution boards downstream having less functionality,
but still meeting the key requirements for system performance analysis.
The design of the metering is to be such that it permits a full breakdown of the power consumed by the building.
Sub tenant utility metering will need to be provided in accordance with the local electricity supply authority to areas such as
the serviced apartment. Local metering close to LV supply will need to be provided.
Further discussions are required with the local authority.
Small Power Services
The distribution boards will be located throughout the building to serve local lighting and power requirements.
Distribution boards will mainly be 3 phase, 4 pole, allowing for ease of load sharing across the phases. Distribution
boards will be located in dedicated electrical cupboards and plant rooms and sized adequately to serve the immediate
vicinity with allowance for 20% spare capacity.
Distribution boards will be:
Provided with outgoing Miniature Circuit Breakers or Residual Current Circuit Breakers with/without Overcurrent
(MCBs, RCBs, and RCBOs) to suit final circuit.
Provided with top, bottom or side entry/exit for LV cables and connections
Local indication on incomer and breakers for open, closed and trip.
Manufactured to BS EN 60439 1 or local prevailing code, whichever is more stringent.
38
Generally small power services to the buildings will be distributed in electrical trunking system mounted in ceiling voids and
floor screeds and in conduits for final distribution to accessories and outlet points. In order to aid rewire ability, conduits will
be surface mounted where installed in ceiling voids and concealed in the building fabric where located in visible areas and
floor screed. Single and multicore FRLS (Flame Retardant Low Smoke) cabling will be used for final circuits and sub mains.
The system will be fully tested in accordance with BS 7671, Requirements for Electrical Installations and applicable local
codes of practice.
6. Lighting
The lighting installation will be designed in accordance National Standards, British Standards and/or local prevailing code
requirements. Any particular Client or Architect requirements will need to be relayed and agreed upon.
High efficacy energy efficient lamps and light sources will be primary choice on selection throughout the project.
Common lamp sources will be used where possible to simplify maintenance and reduce the range of spare lamps stocked.
Lighting to the different areas of the buildings is covered under the relevant sections of this report.
Lighting within the car parking areas, service corridors and plant rooms will be surface mounted or suspended fluorescent
IP65 corrosion resistant linear fluorescent luminaires with protective diffusers.
Specialist lighting design for the Front of House (FOH) and public areas will be designed by the lighting consultant.
The lighting consultant will be responsible for meeting any relevant lighting levels and energy efficiencies to meet
environmental standards aspired. The demarcation between specialist lighting area and MEP Consultants responsibility
needs to be confirmed.
39
Lighting Levels
Lighting levels for the various areas are tabulated below and generally follow the National Building Code of India
recommendations, also tabled is the Light Power Density recommended by ASHRAE which is being used as a guide for LEED
certification and was applied to the building load assessment.
Lighting Controls
Where appropriate lighting control systems will be installed to maximize energy efficiency. Controls will include local manual
switching.
Emergency Lighting
The emergency lighting system will be designed to provide safe passage from the building in the event of a mains failure
and will be sized to power up 10-15% of the lighting load. Emergency lighting will have centralised control where
possible for ease of monitoring and maintenance.
The lighting will be designed to local authority regulations and NFPA 5000. A minimum of 10 Lux will be provided on the
centre line of escape routes, with routes up to 2m wide 50% of the route will be lit to 5 Lux. The emergency lighting system
will be capable of continuous operation for a minimum of 1 hours (90 minutes).
All areas within each building will be provided with maintained illuminated emergency exit signage which complies with the
aforementioned standard to indicate escape routes and exits. All emergency lighting will be co-ordinated with egress routes
to external ground, access to plant rooms, fire fighting equipment and main plant areas.
The emergency lighting system will be by means of static inverter located in strategic locations throughout the building to
support chosen normal ambient fittings in the event of local circuit failure.
These static inverter systems will comprise of maintenance free lead acid batteries, charger, inverter and control equipment.
The size of the units can only be determined on completion of the lighting design and receipt of luminaries specifications
from specialist designer.
The emergency lighting system will be complete with an automatic testing system. All cabling will be fire rated.
MEP DESIGN BASIS REPORT FOR ORCHID CROWN TOWERS AT MUMBAI
40
7. Lightning Protection
The building will be provided with a non isolated Lightning Protection System (LPS) that complies to BS EN 62305, NFC-17102 and local prevailing code requirements. The system will comprise of a lightning protection network utilising the building
fabric Where possible including the tower's structural columns as down conductors, and the structural foundations/piles as
earth terminations.
The LPS will be designed to protect against damage to the following:
Building structure
Living beings
Equipment
The LPS will comprise a Faraday Cage system comprising four main elements as follows:
The LPS will need to be interconnected to the structure and other building systems to achieve one equipotential system. The
LPS will therefore need to be bonded to the following:
41
It is envisaged the air termination network will comprise of a network bonding the structure at the upper roof levels located
at corners, exposed points and edges in accordance with BS EN 62305.
The extent of lightning protection at the upper levels of the building will need to be further reviewed and studies
undertaken. The investigations will also need to include the potential likelihood of side strikes due to the height of the
building. Close coordination will also be required with the faade designers to integrate the lightning protection network into
the faade rather than developing separate systems.
The down conductor network will utilise the reinforcing bar network in the building structure.
The earth termination network will be provided by the building foundations, which allow the lightning protection down
conductors to be suitably connected to earth.
Test links points at ground level will be cast into the building columns and located at clearly identified points accessible by
maintenance staff. These points will enable the overall earth resistance of the building structure to be tested as well as
providing facilities connecting additional earth pits to the system should post construction tests prove these to be necessary.
Surge suppression and protection system may be required further design review will be required. Surge suppression if
required will be installed at all incoming power supply points and their condition will be remotely monitored. Surge diverters
for secondary protection will be provided in accordance with the Lightning Protection risk assessment for the facility.
8. Earthing System
Earthing will be provided in accordance with the requirements of BS 7430, BS 7671 and/or IS 3043, whichever is deemed
more stringent. The distance between 2 earthpits shall be 2 metres wherever possible. The earthing system will be designed
to protect against the risk of an electric shock and to protect equipment/systems.
42
The following elements will be connected to the buildings main earth system:
The earthing system will be connected to the general mass of earth by connection to the building structural foundations.
Each LV switchroom will be fitted with a wall mounted main earth bar, for general connection of earthing systems within the
area. The earth bar will incorporate a proprietary link facility to enable disconnection for testing. The LV earthing system has
separate earth pits.
Extent of the clean earth requirement to specialist systems to be determined however recommended that a separate clean
earthing installation will be provided to the incoming telephone services room.
Chemical earthing shall be adopted as they are maintenance free for 15 years.
The final arrangement of the site earthing system will be subject to discussions and approval by the local electricity
authority.
43
A.
APPLICABLE IS STANDARDS
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
IS:1248-1986
IS:3072-1975
IS:3043
IS:4047-1977
IS:8106-1966
IS:4237-1967
IS:2147-1962
IS:8084-1972
IS:2675-1983
IS:8828-1978
44
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
IS:9926-1981
IS:1554 (PART I)
IS:3961(PART II)
IS:2982
IS:8130
IS:3975
IS:5831
IS:1753
IS:4288
IS: 961
IS: 732
IS: 1646
IS:1653
IS:2667
IS:3480
IS:3837
IS:694
IS:2509
IS:6946
IS:1293
IS:8180
45
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
INSTALLATION
IS:9537-1980
IS:3419
IS:3854
PLUGS
SHUNT CAPACITORS FOR POWER SYSTEMS
HRC CARTRIDGE FUSES AND LINKS UP TO 660 VOLTS
GENERAL AND SAFETY REQUIREMENT FOR LIGHTING
FITTINGS
CODE OF PRACTICE FOR LIGHTING PUBLIC THOROUGH
FARES
WATERPROOF ELECTRIC LIGHTING FITTINGS
WATER TIGHT ELECTRIC LIGHTING FITTING
MILD STEEL TUBULAR AND OTHER WROUGHT STEEL PIPE
FITTING
LUMINARIES FOR STREET LIGHT
HRC FUSES HAVING RUPTURING CAPACITY OF 90 KA
EXHAUST FAN
CLASS I CEILING FAN
DANGER NOTICE BOARDS
IS:6538
IS:2834-1954
IS:2208
IS:1913-1969
IS:2944-1981
IS:3528
IS:3553-1966
IS:1239-1958
IS:2149-1970
IS:9224
IS:2312-1967
IS:374-1979
IS: 2551
ANNEXURE 1:
ELECTRICAL LOAD SHEET
46
5. WATER MANAGEMENT,
PUBLIC HEALTH &
SANITATION
47
48
D.2 Assumptions
49
50
Domestic cold
No.
A
Description
B
1
2
3
Wing A
Wing B
Wing C
4
5
6
7BHK
6 BHK
5 BHK
5 BHK (17
Flats)
Flats/floor
C
Persons/flat
D
No. of
floors
E
10
11
12
Typical
flats
Duplex
flats
F=CxDxE
LPCD
G
LPD
H=FxG
LPCD
J
TYPICAL FLOORS
12.00
40.00
1,920.00
100.00 192,000.00 60.00
10.00
40.00
1,600.00
100.00 160,000.00 60.00
10.00
40.00
1,200.00
100.00 120,000.00 60.00
Total for typical floors
4,720.00
472,000.00
FLOORS WITH DUPLEX APARTMENTS
Wing A
1.00
14.00
6.00
84.00
100.00
8,400.00 60.00
1.00
12.00
6.00
72.00
100.00
7,200.00 60.00
1.00
10.00
5.00
50.00
100.00
5,000.00 60.00
Total for duplex in wing A
206.00
20,600.00
Wing B
17.00
10.00
170.00
100.00
17,000.00 60.00
4.00
4.00
3.00
Domestic hot
88.00
10.00
26.00
12.00
Flushing
Total Pax
170.00
LPD
K=FxJ
LPCD
L
LPD
M=FxL
115,200.00
96,000.00
72,000.00
283,200.00
40.00
40.00
40.00
76,800.00
64,000.00
48,000.00
188,800.00
384,000.00
320,000.00
240,000.00
944,000.00
5,040.00
4,320.00
3,000.00
12,360.00
40.00
40.00
40.00
3,360.00
2,880.00
2,000.00
8,240.00
16,800.00
14,400.00
10,000.00
41,200.00
10,200.00
40.00
6,800.00
34,000.00
6,800.00
34,000.00
35,200.00
176,000.00
12,480.00
47,680.00
60,000.00
62,400.00
238,400.00
300,000.00
2,000.00
11,000.00
251,520.00
3,000.00
19,800.00
1,257,600.00
17,000.00
Wing C
100.00
88,000.00
60.00
52,800.00
312.00
1,192.00
100.00
31,200.00
119,200.00
150,000.00
60.00
18,720.00
71,520.00
90,000.00
200.00
440.00
6,288.00
5.00
20.00
1,000.00
8,800.00
628,800.00
880.00
Water
reqmt
LIT
N=H+K+M
10,200.00
40.00
40.00
10.00
25.00
377,280.00
51
Flushing
Total
1,006,080.00
251,520.00
1,257,600.00
1,509,120.00
377,280.00
1,886,400.00
9,678.73 sqm
10.00 lit/sqm/day
96,787.30 lit/day
Say
97,000.00 lit/day
251,520.00
lit/day
97,000.00
lit/day
348,520.00
lit/day
613,544.00
lit/day
52
Total Pax
F=CxDxE
LPCD
LPD
H=FxG
1 Wing A
4.00
5.00
55.00
1,100.00
90.00
99,000.00
2 Wing B
4.00
5.00
55.00
1,100.00
90.00
99,000.00
3 Wing C
4.00
5.00
55.00
1,100.00
90.00
99,000.00
3,300.00
297,000.00
1,006,080.00 lit/day
297,000.00 lit/day
709,080.00 lit/day
Tanker capacity
15,000.00 lit
No. of tankers/day
47.27
Say
50.00
53
54
Description
Capacity (lit)
One day
1.5 day
1,188,000.00
1,782,000.00
243,900.00
365,850.00
1,431,900.00
2,147,850.00
Water from bore-wells / tankers (raw water) shall be brought to the building at approximately 1 m below ground level in raw water tank.
Water supplied by Municipal Corporation shall be stored in the domestic water tank.
From raw water tank, water shall be fed to suitable water treatment plant by means of feed pumps and stored in the fire water tank,
overflow of which shall be given in domestic water tank. This water shall be used for all domestic purposes such as, cooking, drinking and
all other domestic purposes. The treatment for raw water will consist of filtration through pressure sand filters, activated carbon filters.
Water treatment philosophy shall be detailed out based on the chemical and physical analysis of water from bore wells / tankers.
There shall be a proper system to receive 60 to 65 tankers daily with well planned entry and exits so as not to disturb the overall traffic
movement within and outside the premises. We also suggest entering into a long term agreement with reliable tanker suppliers providing
consistent quality of water. Since fresh water deficit is supplemented with bore wells, it is suggested to have a resistively test and hydrogeological survey to ensure good quality consistent water supply throughout the year. Standby bore wells shall also be planned for the
same. The water received everyday shall be randomly checked for physical, chemical and microbial analysis to ensure that water quality is
maintained.
MEP DESIGN BASIS REPORT FOR ORCHID CROWN TOWERS AT MUMBAI
55
Recycled water:
Water treated by STP is termed as recycled water. It shall be collected in the underground tank meant for the same and shall be supplied
to all the WCs and urinals for flushing, and for irrigation.
Water Distribution and Supply System:
The entire building shall be divided in various zones for water supply system as follows:
No.
1.
2.
3.
Zoning
Zone - 1
Zone - 2
Zone 3
Location of Break
System of Water
Pressure tank
Supply
Hydro-pneumatic
at Level 18
tanks
pumping system
Residential Level -19 to Level 38 and filling tank at Level Service floor at Level 18
Hydro-pneumatic
39
pumping system
Hydro-pneumatic
pumping system
IMPORTANT NOTE: This zoning is based on the present sections and levels. It will be further fine tuned with the final
architectural sections and levels.
There shall be a separate pumping and distribution system for domestic and flushing water. The break pressure tanks shall be of adequate
capacity to cater the requirement of the floors they shall be servicing.
56
There shall be three different tanks for three different types of water as explained above and there shall be three separate and
independent pumping systems for these three different types of water.
Hydro-pneumatic pressure boosting system comprising of 2 working and 1 standby pumps shall be installed in the pump room near the
tanks, which will feed water to each facility at pressures between 2.5 kg/cm2 to 4.5 kg/cm2. Gravity supply of water from break pressure
tanks shall be designed to feed water to each facility at pressures between 2.5 kg/cm2 to 4.5 kg/cm2. This type of water supply system shall
be followed for all three different types of water.
Small capacity make up tanks, at terrace/roof level, are proposed for domestic and flushing water so as to ensure continuous flow of water
to each facility even during DG change over periods during electricity failures
D.3.B. Generation and distribution of hot water and steam:
The hot water requirement for all residences shall be catered by central water heating system kept at MEP floors. The water heaters shall
be suitably designed to heat ambient water by 40 deg C. The total capacity of water heaters shall be 400,000 KCal/hr.
D.3.C. Sewerage Disposal System
General
Client shall check if there is any municipal sewer line in the abutting road and the pipe diameter, invert level and depth of the said man hole
chamber shall be furnished for designing the final connection to the sewer line. Provision shall be made for future connection and by-pass of
sewage treatment plant.
A sewage treatment plant shall be provided. Client has confirmed that the treated sewage and wastewater will be re-used flushing and
irrigation.
Provision shall be made to dispose the sludge generated after STP into the nearby existing drainage manhole of corporation. Alternatively,
sludge can be dried using filter press or centrifuge within our premises and dried sludge can be used as manure for irrigation.
57
Sewerage Disposal
The waste water and soil water shall be collected from toilet blocks / kitchen to main drainage network.
From toilets and kitchen, soil and wastewater shall be passed through gully trap chamber before connecting the same to main drainage
line.
Waste water from kitchens and pantry shall be passed through a grease trap before connecting to the drainage network.
The main drainage line shall discharge the soil and wastewater to sewage treatment plant for recycling the water for re use. The recycled
water shall be used for flushing, irrigation and for HVAC make up after softening.
58
No.
Description
Extended Aeration
SAFF
FAB
Chemical
MBR
Treatment Plants
1
Type of Treatment
Based on suspended
Based on attached
Based on attached
Based on continuous
Based on
growth of bacteria
growth process
growth process
batch process
activated
sludge process
with ultra
filtration
No.
Description
Extended Aeration
SAFF
FAB
Chemical
MBR
Treatment Plants
2
No Media required
treatment
Utilizes plastic
Utilizes
media floating in
fixed in position
membranes
chemical
for treatment
sewage
formulations
3
Final Clarifier
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
No
< 3000
No criterion
No criterion
required?
4
Tertiary Filter
required?
5
6
MLSS (mg/l)
M.L.S.S. monitoring
Required
Not Required
Not Required
No criterion as it
15,000 -
works on physio
20,000
chemical reactions
Required
such as precipitation,
disinfection,
59
flocculation &
clarification
7
Footprint area
Large
3-5 times
smaller
8
9
No.
Process Stability
Retention Time
Description
Highly Sensitive to
Medium Sensitive
Medium Sensitive to
Medium Sensitive to
Not Sensitive
Sludge Bulking
to Sludge Bulking
Sludge Bulking
Sludge Bulking
to upsets
20 - 24 hrs
6 - 8 hrs
6 - 8 hrs
6 - 8 hrs
Extended Aeration
SAFF
FAB
Required
Not Required
Not Required
Not Required
Not Required
Chemical
Treatment Plants
4 - 6 hrs
MBR
10
Sludge Recycling
11
Power Consumption
High
Medium
Medium
High
High
12
Ease of Maintenance
Difficult
Easy
Easy
Easy
Easy
13
Ease of Operation
Difficult
Easy
Easy
Easy
Easy
14
Energy Cost
High
Medium
Medium
High
High
15
Useful for
No
Yes
Yes
Yes
Yes
modification /
capacity extension
of existing STP ?
60
16
High
Medium
Medium
Very High
Very Low
Yes
Yes
Yes
Yes
No
Required
Required
Required
Required
Not Required
Extended Aeration
SAFF
FAB
High
Low
Low
Low
Low
Ineffective
Ineffective
Ineffective
Effective
Effective
High
Moderate
Moderate
Not required
pre-treatment / post
treatment
17
Requirement of
Continuous
monitoring for the
treatment plant
18
Chlorination
No.
Description
19
Environmental Aspect
Chemical
Treatment Plants
MBR
of sewage treatment
a) Sludge Production
b) Reduction of Coliform
c) Use of Coagulants
and Flocculants
a chemical process
plant
d) Use of Chlorine
e) Residual Chlorine
Required as per
Required as per
Required as per
sewage load
sewage load
sewage load
Yes
Yes
Yes
High
Yes
Not required
No
Presence in treated
water
61
f) Quality of Treated
Moderate
Good
Good
Good
Best of all
Bad
Moderate
Moderate
Moderate
Good
Moderate
Moderate
Moderate
Moderate
Recycled water
g) Overall Cleanliness of
the plant area
20
Dependency on the
vendor for routine
operation
chemicals
procurement
Effluent Characteristics
The effluent generated during activities contains mainly:
1. Suspended / colloidal organic components like food waste, toilet flushing, basins and hand wash, etc.
2. Dissolved organic components
3. Dissolved inorganic solids of cleaning chemicals
350 cum/day
PH
78
BOD
COD
O&G -
~ 60 mg/l
TSS
300 mg/l
62
Flow
300 cum/day
PH
78
BOD
< 5 mg/l
COD
< 30 mg/l
O&G
< 5 mg/l
TSS
< 5 mg/l
Assumptions
1. No other parameter which exceeds the treated sewage limits or which is hazardous in nature, will affect the biological process is
present in the raw sewage.
2. The oil present is in free-floating form.
Process Description
The brief process description for MBR sewage treatment process is as follows:
1. Sewage from main drain line is collected through gravity pipes into a screen chamber. This manually cleaned screen is provided to
remove floating and big size particles, which may choke the pumps and pipe lines.
2. Screened sewage is then passed through equalization tank to homogenize the sewage quality and also even out flow fluctuations
and feed sewage of uniform quality at constant rate to subsequent treatment units. Air mixing is also provided to mix the contents
of the equalization tank. A coarse bubble aeration grid is provided to distribute air uniformly at the base of the equalization tank.
3. After above treatment, raw sewage is fed into aeration basin.
4. In aeration tank MLSS (mixed liquor suspended solids) in the range of 12000 to 15000 mg/l are maintained. The high amount of
bacteria gives better and complete removal of organic matter from the raw sewage in relatively small area. Oxygen required for the
63
bacteria is supplied through the blower. The air is used both for scouring of membranes and supplying oxygen to bacteria.
5. The filtration is carried out by the suction pump directly sucking permeates water. The permeate water produced is clear and
devoid of bacteria and viruses to the minimum levels.
6. As the membranes are continuously under operation, they are polluted with organic or inorganic substances. Hence, chemical
cleaning is carried out once in two to three months for removing substances polluting and clogging the membranes. Normal
cleaners used are sodium hypo chloride and citric acid.
64
7. As conventional treatment systems require disinfections with chlorine, it needs to be removed completely before applying on to
gardens or for green belt development. Otherwise, high amount of residual chlorine may damage the plants. Also, disinfection with
any disinfectant does not remove organisms, it only inactivates them. The effect depends on the amount of disinfectant used, the
quality of filtration applied, the retention time available for oxidation and the existence or non-existence of other competing
reaction partners (scavenging). As MBR acts like a physical barrier, it does completely remove bacteria and viruses up to a degree
of 4 - 6 log removal (104 to 106 times reduction), independent of type or life form of organism. It also helps in complete retention
of biomass in the aeration basin.
8. As the system has minimum units, it requires less chemical cost and power consumption when compared to conventional systems.
9. As chlorination is not required, MBR does not produce disinfection by-products or bad odors.
10. The energy consumption of MBR is extremely low (0.30 kwh/m3) and the treated domestic effluents has a four to six log
(99.99%) removal of total coliform. The MBR system does not require the use of chemicals, thereby making it extremely safe
during operation and re-use.
Area requirement
Approximate area required for STP will be 300 sqm.
Design Criteria
1. Maximum intensity of rainfall is assumed as 101.4 mm/hr.
2. Average Co-efficient of Run-off is taken as 0.90.
3. Road camber is taken as 1:100 for concrete roads starting from center.
4. Surface slope as minimum 1:500.
65
Rain water pipes / spouts will be provided from terraces to ground level for taking out the rainwater.
2.
Slope of natural ground and infiltration capacity of open ground within the plot will not be sufficient to absorb / dispose off surface
water.
3.
Looking to rain intensity in the vicinity, storm water is proposed to be disposed off through a network of channels, pipes and
chambers / catch basins.
4.
The rainwater from the terraces will be disposed off through channels / pipe network.
5.
A grating at the main entrance will be provided to prevent entry of outside rainwater to the premises.
6.
Ground shall have minimum 1:500 surface slopes towards storm water collection system.
Design Criteria
Broadly, there are two options for rain water harvesting:
1. 100% percolation / infiltration of the rain water to raise the sub-soil water levels and no reuse.
2. Maximum possible storage of rain water falling in the said premises and re-using the same for flushing, air-conditioning and irrigation,
surplus water to be used for percolation / infiltration.
The first option of 100% percolation / infiltration is possible only in the places where dry sub-soil aquifers are available so that the ground
water table is recharged. This option doesnt give the immediate benefit of water to the society, but over a period of time maintains or
increases the water table of the area.
Second option of storage of rain water and then re-using the same with suitable treatment is more advantageous in the present scenario
where we are facing shortages of water. The stored rain water can be re-used for air-conditioning, flushing and irrigation. In this case, the
66
initial rains are allowed to drain away in the harvesting well or city drainage so as to clean the storm water network and achieve clearer and
better quality of rain water for usage.
Depending upon the space availability and ground water conditions, we will decide the exact system for rain water harvesting.
D.3.G. Sanitary Fixtures and Water management system Fittings:
Since this is a high end project, the best quality fittings as approved by architect shall be used.
Water saver taps, push type fittings for basins / sinks / urinals shall be used.
Water less urinals shall be used in some of the executive areas to reduce the water consumption.
Water Supply Network: Copper pipes shall be used for all internal hot and cold domestic water lines for hotel. C-PVC/PE-AL-PE pipes shall be
used for all the internal flushing water supply lines. Galvanised Iron pipes shall be used for all lines in the plumbing shafts for hotel. Suitable
insulation and protection will be provided to all the water supply lines at terraces and in ducts. Hot water lines will be suitably insulated to
prevent heat losses. CPVC pipes will be used for supply of RO / purified water. On terrace, UV stabilized CPVC pipes will be used and proper
protection will be given.
Sewerage Disposal System: Glazed stoneware pipes and RCC pipes with PCC haunch shall be used for external drainage system with proper
gradient and brick masonry chambers/manholes with CI covers and steps, shall be constructed at all junctions of sewer lines and at point of
change in direction of flow. For vertical soil and waste drainage lines, centrifugal cast iron pipes with drip seal / lead caulked joints shall be
used. For all suspended drainage pipe lines within the building, C.I LA class pipes shall be used with proper gradient.
67
Rain Water Disposal System: RCC pipes with PCC haunch shall be used for external storm water disposal system with proper gradient and
brick masonry chambers/manholes with grating / covers and steps at all junctions of storm drain lines and at point of change in direction of
flow. On driveways and landscape areas, properly designed storm water channels shall be provided as per the landscape features. For vertical
rain water down take lines, centrifugal cast iron pipes with drip seal / lead caulked joints shall be used. For all suspended storm water drain
pipe lines within the building, C.I LA class pipes shall be used with proper gradient.
Water Tanks / Pumps: Underground water tank will be constructed in R.C.C. with CI manholes / steps and MS ladders. All pumps will be
vertical / horizontal submersible pumps with control panel and variable frequency driven.
Sanitary Fixtures / Water management system Fittings: Being a high end project, the best quality fittings as approved by architect will
be used. Water saver taps, push type fittings for basins / sinks / urinals, low volume dual flush cisterns will be used to reduce water
consumption.
The details of other water management system materials and finishes will be worked out at the stage of finalization of the design.
68
6. Fire Engineering
69
Project Brief:
The Proposed ORCHID CROWN residential Building located at Mumbai is having Residential Blocks of Ground + 73 Floors (3
Blocks), Rehab Building having Ground + 22 & Ground + 14 (For Car Parking). The Height of the Residential blocks is 304.5m
approximately.
1.1 Introduction
The following Fire Engineering Concept report has been produced by PANKAJ DHARKAR ASSOCIATES for the ORCHID CROWN
project in Mumbai. The purpose of this report is to provide the client and the design team with an appreciation of the key fire
safety provisions necessary within the building at this stage in the developments design. This report will also subsequently be used
for submission to the Chief Fire Officer (CFO) for his consideration when issuing a No Objection Certificate (NOC) for the project.
The overall fire safety concepts for the building described within this report will deal with the means of escape strategy within the
tower and the interaction with the physical fire safety features proposed within the building, such as Compartmentation and fire
separation. In addition to these elements, the active fire safety features, such as sprinkler protection and smoke control, will be
introduced along with the buildings proposed fire-fighting strategy.
1.1.1 Design Assumptions and Fire Safety Systems Design Criteria
The design of ORCHID CROWN must follow the appropriate fire safety codes for a building of this nature. While a series of fire
safety codes are enforced within Mumbai, none were specifically designed to be applied to buildings of the height of ORCHID
CROWN (the development being approximately 304m tall) and therefore it is considered that the only method by which an
appropriate fire safety design for the tower can be derived is by the use of a fire engineered approach. It is proposed that India
fire safety codes of practice will form the basis of this fire engineered approach and where the recommendations within this guide
are considered unsuitable to be applied to the building, supplementary sources of information will be referenced as appropriate.
The basic parameters for the fire safety design of ORCHID CROWN will be therefore be the following local fire safety codes;
National Building Code of India Part IV Fire & Life Safety 2005
70
Practicing Engineers Architects and Town Planners Association (India) in Association with Mumbai Fire Brigade (Municipal
Corporation of Greater Mumbai) Handbook on Fire Safety in High Rise and Special Type Buildings 1999
Note: this document includes Additional Fire Protection Requirements for Multi-Storey High Rise & Special Buildings Appendix
VIII (Regulation 43)
Fire safety systems within the building will be designed to a selection of appropriate standards as indicated below:
Fire Alarm System
Sprinkler System
Portable Fire
Extinguishers
Emergency
Lighting
Fire resistance of
elements
Fire Service
Access & Facilities
Fire-fighting Lifts
As per NBC
Car Park
Ventilation
As per NBC
71
72
Residential apartments
Car Park
Mercantile
73
15m
30m
Note 1: When measuring travel distance within the residential portions of the building, travel from nonhabitable rooms (e.g.
bathrooms, toilets, enclosed kitchens, cupboards, dressing rooms etc.) will not be considered.
Note 2: Measurement of travel distance will terminate at either a final exit (on the ground floor) or on the upper floors at either the
door into the protected stair or the door into a protected lobby or corridor where provided.
74
2.1.4 Staircases
As currently required by the CFO, the two escape stairs provided throughout the tower element of the building will be a minimum
of 2m each in width.
No exit shall be less than 1000mm except in assembly areas where this is increased to 2000mm
25
50
75
Mercantile (Group F)
50
60
75
Assembly (Group D)
40
50
60
50
60
75
Occupants per Unit Exit Width for Stairs, & Doors to be Applied to ORCHID CROWN.
2.1.5 Refuge Areas Code Compliant Recommendations
As a high-rise residential building, a series of Refuge Areas are required throughout the tower, to be used as shelters for use by
evacuees exiting the building, or for use by the Fire Service to form staging areas when entering the building.
In the main, the refuges will be located behind one of the escape cores within one of the towers wings. The appropriate code
recommendations, for the number/location/size of the Refuge Areas provided is given below;
The first Refuge Area is to be provided on the first floor above 24m from ground level. Subsequent
75
76
To facilitate the effective evacuation of people from the refuge positions, a voice communication system will be provided which will
enable the occupants of each refuge to alert the buildings management team that they are in need of assistance.
The disabled evacuation strategy for the development requires to be further developed by the buildings management team with a
structured policy/procedure to enable its effective operation.
2.1.7 Exit Signs
Self illuminating, electrically operated, exit signs will be provided on all floors indicating the direction of escape in accordance with
NBC.
3.0 Compartmentation & Structural Fire Protection
3.1 Structural Fire Protection
Element
3
3
3
3
2
2
77
Columns
Supporting more than one floor, columns, or other bearing
walls
Supporting one floor only
Supporting roofs only
Beams, Slabs, Plate Girders, Trusses, and Arches
Supporting more than one floor, columns, or other bearing
walls
Supporting one floor only
Supporting roofs only
Floors
Roofs
Interior Non-bearing Walls
Top Spire
Fire Refuge Areas (Walls)
Staircases
Walls
Ceilings
Corridor Walls
Lift Enclosure (Walls)
Compartment Walls
Service Ducts/Risers & Lift Machine Rooms
Transformer, Switchgear & Generator Rooms (Walls)
AHU Rooms
3
2
2
3
2
2
2
1
0
0
2
3
2
1
2
2
2
4
1
Table for Fire Resistance Rating of Structural Members & Other Elements of Construction
3.2 Compartmentation & Fire Separation
Compartmentation will be provided between each different purpose group within the building ie. between the buildings different
uses.
As a high rise building, compartment floors will be provided at every floor level to prevent fire spread between storeys, thus
preventing full building involvement in fire.
MEP DESIGN BASIS REPORT FOR ORCHID CROWN TOWERS AT MUMBAI
78
2 hours
Corridors doors
2 hours
Lift Enclosures
Landing Doors
Car Doors
1 hour
hour
2 hours
2 hours
1 hour
79
Figure shows Location of Areas of Fire Resistant Faade Required to Prevent External Fire Spread
3.6 Staircase Enclosure Protection
The internal enclosing walls of staircases shall be of brick or RCC construction with a minimum fire resistance of 2 hours. All
enclosed stairs shall be accessed via a lobby with both doors (lobby & stair door) having a minimum fire resistance of 30 minutes.
Staircases will be mechanically pressurised throughout in according to NBC.
80
81
Rooms containing other types electrical equipment should be sprinkler protected or provided with an alternative fire suppression
system. Such alternative fire suppression systems should be installed in accordance with the appropriate standard, as listed below.
Fire Suppression System
Installation
Standard
NFPA 11
NFPA 12
NFPA 15
NFPA 16
NFPA 17
NFPA 17A
NFPA 750
82
The system will be provided with outlets within every escape stair enclosure (or protected lobby associated with each escape stair
enclosure). Additional outlets will be provided where the most remote portion of a floor or storey is more than 60m, measured
along a route suitable for laying hose, from a hose connection point.
The fire protection system for the internal part of the building will be supplied by to sets of three fire pumps (2 x electrical and 1 x
Diesel) drawing from a dedicated water storage tank with an effective water capacity to supply the fire systems.
4.4 Hose Reel System
A hose reel system will be installed within the building such that every part of the floor area is within 30 meters of a hose reel. The
hose reels will be provided within either the protected stair enclosure, or the associated protected lobby, within a recessed area
such that its presence does not reduce the effective width of the escape route. The provision of a hose reel system within the
building is predominately for use by the building's occupants (prior to fire brigade arrival) and not for use by fire-fighters who will
use their own hoses/equipment and the wet rising main provided in the fire-fighting lobby.
4.5 Fire Extinguishers
Portable fire extinguishers are to be provided throughout all areas of the buildings in accordance to NBC 2005.
4.6 Fire Alarm & Detection
All parts of the building will be provided with a fully addressable automatic fire detection system and an emergency voice
alarm/communication system or evacuation sounders as appropriate. The design, installation and testing of the system should be
in accordance with NFPA / NBC and will meet the criteria specified for high-rise buildings.
The system will be designed to sound the alarm on the floors that require evacuation.
4.7 Backup Power Supplies
An alternative source of LV/HV power will be provided from either two separate sub-stations or a diesel generator of adequate
capacity for all necessary life safety & fire-fighting systems.
MEP DESIGN BASIS REPORT FOR ORCHID CROWN TOWERS AT MUMBAI
83
84
85
86