Project Name: Construction of AL-WAJH 380/132/33/13.

8 KV BSP Substation
Contract No. : 4400006924
Project Schedule
ID

TaskName
1
2
3
4
5
6
7
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91

Duration

Start

Finish

AL WAJH 380/132/33/13.8kV BSP Substation at AL WAJH Ci756.9 days 27/12/2015


GENERAL
756.9 days 27/12/2015
Award of Contract
1 day 27/12/2015
Kick off meeting
1 day 19/01/2016
Technical Completion (TCC)
0 days 27/12/2017
Preliminary Acceptance (PAC)
0 days 27/02/2018
Final Acceptance (FAC)
0 days 27/05/2018
EQUIPMENT DELIVERY
380kV GIS + LCC Panel
380kV Hybrid GIS + LCC Panel
132kV GIS + LCC Panel
502MVA 380/132 kV Power Transformer
132/33 kV Power Transformer
132/13.8kV Power Transformer
13.8/0.4kV, Station Service Transformer
Oil Immersed Reactors, 33KV trough 380kV
Air core series reactor, 13.8KV through 380kV
132kV XLPE Cables
132kV Cable Splice & Termination Kits
33kV and 13.8kV Cables
33kV and 13.8kV Termination Kits
33kV Capacitor
13.8kV Capacitor
33kV Metal Clad Switchgear
13.8kV Metal Clad Switchgear
380kV 132kV, 33kV &13.8kV Surge Arresters

186 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days

31/07/2016
03/01/2017
03/01/2017
31/01/2017
12/01/2017
12/01/2017
12/01/2017
23/01/2017
04/01/2017
29/12/2016
27/11/2016
03/01/2017
14/12/2016
29/01/2017
26/12/2016
28/12/2016
04/03/2017
04/03/2017
21/01/2017

015
N
27/05/2018 '15
27/05/2018 '15

Half1,2016
J
M
M

Half2,2016
J
S
N

27/12/2015
19/01/2016
27/12/2017
27/02/2018
27/05/2018
05/03/2017
03/01/2017
03/01/2017
31/01/2017
12/01/2017
12/01/2017
12/01/2017
23/01/2017
04/01/2017
29/12/2016
27/11/2016
03/01/2017
14/12/2016
29/01/2017
26/12/2016
28/12/2016
04/03/2017
04/03/2017
21/01/2017

31Jul'16

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Page1of15

Half1,2018
J
M
M

27Dec'17
27Feb'18
27

InactiveTask

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

27
27

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

05Mar'17
03Jan'17
03Jan'17
31Jan'17
12Jan'17
12Jan'17
12Jan'17
23Jan'17
04Jan'17
29Dec'16
27Nov'16
03Jan'17
14Dec'16
29Jan'17
26Dec'16
28Dec'16
04Mar'17
04Mar'17
21Jan'17

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
182
183
184
185
186
187
188
189
190
191
192

TaskName

Duration

Start

Finish

Control Relay & Protection Panels / SAS Panels


Annunciator System
LV Power & Control Cables (PVC/XLPE)
LV Cable Termination
Shielded Instrumentation Cables
LVAC System
Earthing Materials
Lighting and Small Power
Battery & Battery Charger
Cable Trays
Fault Recorders
HVAC System
Fire Fighting System
EOT Crane
Telecommunication Panel

0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days
0 days

04/02/2017
27/02/2017
01/12/2016
25/02/2017
17/12/2016
30/01/2017
31/07/2016
17/01/2017
29/01/2017
29/10/2016
16/01/2017
05/03/2017
18/01/2017
03/12/2016
22/02/2017

PROCUREMENT AND DELIVERY


VENDOR APPROVAL AND PURCHASE ORDER
380kV GIS + LCC Panel
Vendor Proposal and Approval
Placement of P.O

322 days
79 days
14 days
7 days
7 days

24/02/2016
24/02/2016
27/02/2016
27/02/2016
06/03/2016

380kV Hybrid GIS + LCC Panel


Vendor Proposal and Approval
Placement of P.O

14 days 27/02/2016
7 days 27/02/2016
7 days 06/03/2016

132kV GIS + LCC Panel


Vendor Proposal and Approval
Placement of P.O

14 days 24/02/2016
7 days 24/02/2016
7 days 03/03/2016

015
Half1,2016
Half2,2016
Half1,2017
Half2,2017
N
J
M
M
J
S
N
J
M
M
J
S
N
04Feb'17
04/02/2017
27Feb'17
27/02/2017
01Dec'16
01/12/2016
25Feb'17
25/02/2017
17Dec'16
17/12/2016
30Jan'17
30/01/2017
31Jul'16
31/07/2016
17Jan'17
17/01/2017
29Jan'17
29/01/2017
29Oct'16
29/10/2016
16Jan'17
16/01/2017
05Mar'17
05/03/2017
18Jan'17
18/01/2017
03Dec'16
03/12/2016
22Feb'17
22/02/2017
05Mar'17
05/03/2017 4Feb'16
4Feb'16
25May'16
25/05/2016
13Mar'16
13/03/2016 7Feb'16
05/03/2016
13/03/2016
13/03/2016 7Feb'16
05/03/2016
13/03/2016
10/03/2016 4Feb'16

13Mar'16

10Mar'16

02/03/2016
10/03/2016

Task

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half1,2018
J
M
M

Page2of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218

TaskName

Duration

Start

Finish

502MVA 380/132 kV Power Transformer


Vendor Proposal and Approval
Placement of P.O

21 days 24/02/2016
14 days 24/02/2016
7 days 12/03/2016

132/33 kV Power Transformer


Vendor Proposal and Approval
Placement of P.O

21 days 24/02/2016
14 days 24/02/2016
7 days 12/03/2016

132/13.8kV Power Transformer


Vendor Proposal and Approval
Placement of P.O

21 days 24/02/2016
14 days 24/02/2016
7 days 12/03/2016

13.8/0.4kV, Station Service Transformer


Vendor Proposal and Approval
Placement of P.O

28 days 27/02/2016
21 days 27/02/2016
7 days 22/03/2016

Oil Immersed Reactors, 33KV trough 380kV


Vendor Proposal and Approval
Placement of P.O

21 days 24/02/2016
14 days 24/02/2016
7 days 12/03/2016

Air core series reactor, 13.8KV through 380kV


Vendor Proposal and Approval
Placement of P.O

28 days 27/02/2016
21 days 27/02/2016
7 days 22/03/2016

132kV XLPE Cables


Vendor Proposal and Approval
Placement of P.O

28 days 24/02/2016
21 days 24/02/2016
7 days 20/03/2016

132kV Cable Splice & Termination Kits


Vendor Proposal and Approval
Placement of P.O

28 days 27/02/2016
21 days 27/02/2016
7 days 22/03/2016

33kV and 13.8kV Cables


Vendor Proposal and Approval

28 days 13/03/2016
21 days 13/03/2016

015
Half1,2016
Half2,2016
N
J
M
M
J
S
N
19Mar'16
19/03/20164Feb'16

19/03/2016 4Feb'16
10/03/2016
19/03/2016
19/03/2016 4Feb'16

Half1,2018
J
M
M

19Mar'16

19Mar'16

10/03/2016
19/03/2016
29/03/2016 7Feb'16
21/03/2016
29/03/2016
19/03/2016 4Feb'16

29Mar'16

19Mar'16

10/03/2016
19/03/2016
29/03/2016 7Feb'16
21/03/2016
29/03/2016
27/03/2016 4Feb'16

29Mar'16

27Mar'16

19/03/2016
27/03/2016
29/03/2016 7Feb'16
21/03/2016
29/03/2016
13/04/201613Mar'16

29Mar'16

13Apr'16

05/04/2016

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

10/03/2016
19/03/2016

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

Page3of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
219
220
221
222
223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244

TaskName

Duration
Placement of P.O

7 days

Start

Finish

06/04/2016

33kV and 13.8kV Termination Kits


Vendor Proposal and Approval
Placement of P.O

37 days 13/03/2016
30 days 13/03/2016
7 days 17/04/2016

33kV Capacitor
Vendor Proposal and Approval
Placement of P.O

28 days 02/03/2016
21 days 02/03/2016
7 days 27/03/2016

13.8kV Capacitor
Vendor Proposal and Approval
Placement of P.O

28 days 05/03/2016
21 days 05/03/2016
7 days 29/03/2016

33kV Metal Clad Switchgear


Vendor Proposal and Approval
Placement of P.O

28 days 24/02/2016
21 days 24/02/2016
7 days 20/03/2016

13.8kV Metal Clad Switchgear


Vendor Proposal and Approval
Placement of P.O

28 days 24/02/2016
21 days 24/02/2016
7 days 20/03/2016

380kV 132kV, 33kV &13.8kV Surge Arresters


Vendor Proposal and Approval
Placement of P.O

37 days 13/03/2016
30 days 13/03/2016
7 days 17/04/2016

Control Relay & Protection Panels / SAS Panels


Vendor Proposal and Approval
Placement of P.O

37 days 01/03/2016
30 days 01/03/2016
7 days 05/04/2016

Annunciator System
Vendor Proposal and Approval
Placement of P.O

37 days 13/03/2016
30 days 13/03/2016
7 days 17/04/2016

LV Power & Control Cables (PVC/XLPE)

37 days 01/03/2016

015
Half1,2016
Half2,2016
N
J
M
M
J
S
N
13/04/2016
24Apr'16
24/04/201613Mar'16

03/04/2016 2Mar'16
26/03/2016
03/04/2016
05/04/201605Mar'16

Half1,2018
J
M
M

03Apr'16

05Apr'16

28/03/2016
05/04/2016
27/03/2016 4Feb'16
19/03/2016
27/03/2016
27/03/2016 4Feb'16

27Mar'16

27Mar'16

19/03/2016
27/03/2016
24/04/201613Mar'16
16/04/2016
24/04/2016
12/04/2016 1Mar'16

24Apr'16

12Apr'16

04/04/2016
12/04/2016
24/04/201613Mar'16
16/04/2016
24/04/2016
12/04/2016 1Mar'16

24Apr'16

12Apr'16

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

16/04/2016
24/04/2016

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

Page4of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270

TaskName

Duration

Start

Finish

015
Half1,2016
Half2,2016
N
J
M
M
J
S
N
04/04/2016
12/04/2016
18Apr'16
18/04/201607Mar'16

Vendor Proposal and Approval


Placement of P.O

30 days 01/03/2016
7 days 05/04/2016

LV Cable Termination
Vendor Proposal and Approval
Placement of P.O

37 days 07/03/2016
30 days 07/03/2016
7 days 11/04/2016

Shielded Instrumentation Cables


Vendor Proposal and Approval
Placement of P.O

37 days 07/03/2016
30 days 07/03/2016
7 days 11/04/2016

LVAC System
Vendor Proposal and Approval
Placement of P.O

28 days 13/03/2016
21 days 13/03/2016
7 days 06/04/2016

Earthing Materials
Vendor Proposal and Approval
Placement of P.O

21 days 24/02/2016
14 days 24/02/2016
7 days 12/03/2016

Lighting and Small Power


Vendor Proposal and Approval
Placement of P.O

37 days 13/04/2016
30 days 13/04/2016
7 days 18/05/2016

25/05/2016
17/05/2016
25/05/2016

Battery & Battery Charger


Vendor Proposal and Approval
Placement of P.O

37 days 01/03/2016
30 days 01/03/2016
7 days 05/04/2016

Cable Trays
Vendor Proposal and Approval
Placement of P.O

28 days 30/03/2016
21 days 30/03/2016
7 days 24/04/2016

12/04/2016 1Mar'16
04/04/2016
12/04/2016
01/05/2016 30Mar'16

Fault Recorders
Vendor Proposal and Approval
Placement of P.O

37 days 13/03/2016
30 days 13/03/2016
7 days 17/04/2016

10/04/2016
18/04/2016
18/04/201607Mar'16

Half1,2018
J
M
M

10/04/2016
18/04/2016
13/04/201613Mar'16
05/04/2016
13/04/2016
19/03/2016 4Feb'16

13Apr'16

19Mar'16

10/03/2016
19/03/2016
13Apr'16

25May'16

12Apr'16

01May'16

23/04/2016
01/05/2016
24/04/201613Mar'16
16/04/2016
24/04/2016

24Apr'16

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

18Apr'16

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

Page5of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
271
272
273
274
275
276
277
278
279
280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296

TaskName

Duration

Start

Finish

HVAC System
Vendor Proposal and Approval
Placement of P.O

37 days 05/04/2016
30 days 05/04/2016
7 days 10/05/2016

Fire Fighting System


Vendor Proposal and Approval
Placement of P.O

28 days 01/03/2016
21 days 01/03/2016
7 days 26/03/2016

EOT Crane
Vendor Proposal and Approval
Placement of P.O

28 days 11/04/2016
21 days 11/04/2016
7 days 05/05/2016

Telecommunication Panel
Vendor Proposal and Approval
Placement of P.O

28 days 13/03/2016
21 days 13/03/2016
7 days 06/04/2016

DELIVERY
380kV GIS + LCC Panel
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

301 days
240 days
28 days
35 days
137 days
20 days
30 days
10 days

20/03/2016
30/03/2016
30/03/2016
02/05/2016
12/06/2016
26/10/2016
19/11/2016
24/12/2016

380kV Hybrid GIS + LCC Panel


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight

240 days
28 days
35 days
137 days
20 days
30 days

30/03/2016
30/03/2016
02/05/2016
12/06/2016
26/10/2016
19/11/2016

015
Half1,2016
Half2,2016
N
J
M
M
J
S
N
17May'16
17/05/2016 05Apr'16

02/04/2016 1Mar'16
24/03/2016
02/04/2016
12/05/2016 11Apr'16

Half1,2018
J
M
M

02Apr'16

12May'16

04/05/2016
12/05/2016
13/04/201613Mar'16
05/04/2016
13/04/2016
05/03/2017 20Mar'16
03/01/2017 30Mar'16

13Apr'16

05Mar'17
03Jan'17

01/05/2016
11/06/2016
17/11/2016
17/11/2016
22/12/2016
03/01/2017
03/01/2017 30Mar'16
01/05/2016
11/06/2016
17/11/2016
17/11/2016
22/12/2016

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

09/05/2016
17/05/2016

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

Page6of15

03Jan'17

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322

TaskName

Duration
Shipment Port Clearance & Receipt at site

Start

Finish

10 days 24/12/2016

015
Half1,2016
N
J
M
M
03/01/2017
31/01/2017 28Mar'16

Half2,2016
J
S
N

Half1,2017
J
M
M

132kV GIS + LCC Panel


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

266 days
28 days
28 days
150 days
20 days
30 days
10 days

28/03/2016
28/03/2016
30/04/2016
01/06/2016
23/11/2016
17/12/2016
21/01/2017

502MVA 380/132 kV Power Transformer


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

236 days
28 days
28 days
120 days
20 days
30 days
10 days

13/04/2016
13/04/2016
16/05/2016
18/06/2016
05/11/2016
28/11/2016
02/01/2017

12/01/2017
15/05/2016
16/06/2016
03/11/2016
27/11/2016
01/01/2017
12/01/2017

13Apr'16

12Jan'17

132/33 kV Power Transformer


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

236 days
28 days
28 days
120 days
20 days
30 days
10 days

13/04/2016
13/04/2016
16/05/2016
18/06/2016
05/11/2016
28/11/2016
02/01/2017

12/01/2017
15/05/2016
16/06/2016
03/11/2016
27/11/2016
01/01/2017
12/01/2017

13Apr'16

12Jan'17

132/13.8kV Power Transformer


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing

236 days
28 days
28 days
120 days

13/04/2016
13/04/2016
16/05/2016
18/06/2016

12/01/2017
15/05/2016
16/06/2016
03/11/2016

13Apr'16

12Jan'17

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half1,2018
J
M
M

31Jan'17

28/04/2016
31/05/2016
22/11/2016
15/12/2016
19/01/2017
31/01/2017

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half2,2017
J
S
N

Page7of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
323
324
325
326
327
328
329
330
331
332
333
334
335
336
337
338
339
340
341
342
343
344
345
346
347
348

TaskName

Duration
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

Start

Finish

20 days 05/11/2016
30 days 28/11/2016
10 days 02/01/2017

015
N
27/11/2016
01/01/2017
12/01/2017

Half1,2016
J
M
M

Half2,2016
J
S
N

Half1,2017
J
M
M

13.8/0.4kV, Station Service Transformer


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

236 days
28 days
28 days
120 days
20 days
30 days
10 days

24/04/2016
24/04/2016
26/05/2016
28/06/2016
15/11/2016
08/12/2016
12/01/2017

23/01/2017
25/05/2016
27/06/2016
14/11/2016
07/12/2016
11/01/2017
23/01/2017

Oil Immersed Reactors, 33KV trough 380kV


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

236 days
28 days
28 days
120 days
20 days
30 days
10 days

05/04/2016
05/04/2016
08/05/2016
09/06/2016
27/10/2016
20/11/2016
25/12/2016

04/01/2017
07/05/2016
08/06/2016
26/10/2016
19/11/2016
24/12/2016
04/01/2017

05Apr'16

04Jan'17

Air core series reactor, 13.8KV through 380kV


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

236 days
28 days
28 days
120 days
20 days
30 days
10 days

30/03/2016
30/03/2016
02/05/2016
04/06/2016
22/10/2016
14/11/2016
19/12/2016

29Dec'16

132kV XLPE Cables


Technical Submission to SEC

210 days 28/03/2016


25 days 28/03/2016

29/12/2016 30Mar'16
01/05/2016
02/06/2016
20/10/2016
13/11/2016
18/12/2016
29/12/2016
27/11/2016 28Mar'16

24Apr'16

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half1,2018
J
M
M

23Jan'17

27Nov'16

25/04/2016

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half2,2017
J
S
N

Page8of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374

TaskName

Duration
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

Start

Finish

015
Half1,2016
N
J
M
M
05/06/2016
18/09/2016
11/10/2016
15/11/2016
27/11/2016
03/01/2017 30Mar'16

35 days
90 days
20 days
30 days
10 days

26/04/2016
06/06/2016
19/09/2016
12/10/2016
16/11/2016

132kV Cable Splice & Termination Kits


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

240 days
25 days
35 days
120 days
20 days
30 days
10 days

30/03/2016
30/03/2016
28/04/2016
08/06/2016
26/10/2016
19/11/2016
24/12/2016

33kV and 13.8kV Cables


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

210 days
25 days
35 days
90 days
20 days
30 days
10 days

14/04/2016
14/04/2016
14/05/2016
23/06/2016
06/10/2016
30/10/2016
04/12/2016

14/12/2016
12/05/2016
22/06/2016
05/10/2016
29/10/2016
03/12/2016
14/12/2016

33kV and 13.8kV Termination Kits


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

240 days
25 days
35 days
120 days
20 days
30 days
10 days

25/04/2016
25/04/2016
24/05/2016
04/07/2016
21/11/2016
14/12/2016
18/01/2017

29/01/2017
23/05/2016
03/07/2016
20/11/2016
13/12/2016
17/01/2017
29/01/2017

Half2,2016
J
S
N

14Apr'16

25Apr'16

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

Half1,2018
J
M
M

03Jan'17

27/04/2016
07/06/2016
25/10/2016
17/11/2016
22/12/2016
03/01/2017

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

Page9of15

14Dec'16

29Jan'17

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393
394
395
396
397
398
399
400

TaskName

Duration

Start

Finish

015
Half1,2016
N
J
M
M
26/12/2016 04Apr'16

33kV Capacitor
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

229 days
21 days
28 days
120 days
20 days
30 days
10 days

04/04/2016
04/04/2016
28/04/2016
31/05/2016
18/10/2016
10/11/2016
15/12/2016

13.8kV Capacitor
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

229 days
21 days
28 days
120 days
20 days
30 days
10 days

06/04/2016
06/04/2016
01/05/2016
02/06/2016
20/10/2016
13/11/2016
18/12/2016

28/12/2016
30/04/2016
01/06/2016
19/10/2016
12/11/2016
17/12/2016
28/12/2016

33kV Metal Clad Switchgear


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

293 days
28 days
35 days
170 days
20 days
30 days
10 days

28/03/2016
28/03/2016
30/04/2016
09/06/2016
25/12/2016
17/01/2017
21/02/2017

13.8kV Metal Clad Switchgear


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance

293 days
28 days
35 days
170 days
20 days

28/03/2016
28/03/2016
30/04/2016
09/06/2016
25/12/2016

04/03/2017 28Mar'16
28/04/2016
08/06/2016
24/12/2016
16/01/2017
20/02/2017
04/03/2017
04/03/2017 28Mar'16

Half2,2016
J
S
N

06Apr'16

Half1,2018
J
M
M

28Dec'16

04Mar'17

04Mar'17

28/04/2016
08/06/2016
24/12/2016
16/01/2017

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

27/04/2016
30/05/2016
17/10/2016
09/11/2016
14/12/2016
26/12/2016

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M
26Dec'16

Page10of15

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426

TaskName

Duration
Freight
Shipment Port Clearance & Receipt at site

Start

Finish

30 days 17/01/2017
10 days 21/02/2017

015
N
20/02/2017
04/03/2017

Half1,2016
J
M
M

Half2,2016
J
S
N

380kV 132kV, 33kV &13.8kV Surge Arresters


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

233 days
25 days
28 days
120 days
20 days
30 days
10 days

25/04/2016
25/04/2016
24/05/2016
26/06/2016
13/11/2016
06/12/2016
10/01/2017

21/01/2017
23/05/2016
25/06/2016
12/11/2016
05/12/2016
09/01/2017
21/01/2017

Control Relay & Protection Panels / SAS Panels


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

255 days
10 days
35 days
150 days
20 days
30 days
10 days

13/04/2016
13/04/2016
25/04/2016
05/06/2016
27/11/2016
20/12/2016
24/01/2017

04/02/2017
24/04/2016
04/06/2016
26/11/2016
19/12/2016
23/01/2017
04/02/2017

Annunciator System
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

265 days
20 days
35 days
150 days
20 days
30 days
10 days

25/04/2016
25/04/2016
18/05/2016
28/06/2016
20/12/2016
12/01/2017
16/02/2017

27/02/2017
17/05/2016
27/06/2016
19/12/2016
11/01/2017
15/02/2017
27/02/2017

LV Power & Control Cables (PVC/XLPE)


Technical Submission to SEC
Technical Submission Approval from SEC

200 days 13/04/2016


20 days 13/04/2016
30 days 07/05/2016

01/12/2016
05/05/2016
09/06/2016

Task

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Page11of15

25Apr'16

13Apr'16

25Apr'16

13Apr'16

Half1,2017
J
M
M

Half2,2017
J
S
N

Half1,2018
J
M
M

21Jan'17

04Feb'17

27Feb'17

01Dec'16

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450
451
452

TaskName

Duration

Start

Finish

90 days
20 days
30 days
10 days

11/06/2016
24/09/2016
17/10/2016
21/11/2016

015
N
22/09/2016
16/10/2016
20/11/2016
01/12/2016

LV Cable Termination
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

268 days
28 days
30 days
150 days
20 days
30 days
10 days

19/04/2016
19/04/2016
22/05/2016
26/06/2016
18/12/2016
10/01/2017
14/02/2017

25/02/2017
21/05/2016
25/06/2016
17/12/2016
09/01/2017
13/02/2017
25/02/2017

19Apr'16

Shielded Instrumentation Cables


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

208 days
28 days
30 days
90 days
20 days
30 days
10 days

19/04/2016
19/04/2016
22/05/2016
26/06/2016
09/10/2016
01/11/2016
06/12/2016

17/12/2016
21/05/2016
25/06/2016
08/10/2016
31/10/2016
05/12/2016
17/12/2016

19Apr'16

LVAC System
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

250 days
30 days
40 days
120 days
20 days
30 days
10 days

14/04/2016
14/04/2016
19/05/2016
05/07/2016
22/11/2016
15/12/2016
19/01/2017

30/01/2017
18/05/2016
04/07/2016
21/11/2016
14/12/2016
18/01/2017
30/01/2017

14Apr'16

Earthing Materials

115 days 20/03/2016

Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

Half1,2016
J
M
M

Half2,2016
J
S
N

31/07/2016 20Mar'16

Task

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Page12of15

Half1,2017
J
M
M

Half2,2017
J
S
N

Half1,2018
J
M
M

25Feb'17

17Dec'16

30Jan'17

31Jul'16

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478

TaskName

Duration

Start

Finish

10 days
15 days
60 days
10 days
10 days
10 days

20/03/2016
31/03/2016
18/04/2016
27/06/2016
09/07/2016
20/07/2016

015
N
30/03/2016
17/04/2016
26/06/2016
07/07/2016
19/07/2016
31/07/2016

Lighting and Small Power


Technical Submission to SEC
Technical Submission Approval from SEC
Purchase of Materials
FAT & Dispatch Clearance
Packing at manufacture's works
Delivery & Receipt at site

203 days
20 days
25 days
90 days
20 days
20 days
10 days

26/05/2016
26/05/2016
19/06/2016
08/08/2016
21/11/2016
14/12/2016
07/01/2017

17/01/2017
18/06/2016
17/07/2016
20/11/2016
13/12/2016
05/01/2017
17/01/2017

Battery & Battery Charger


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

250 days
30 days
40 days
120 days
20 days
30 days
10 days

13/04/2016
13/04/2016
18/05/2016
04/07/2016
21/11/2016
14/12/2016
18/01/2017

29/01/2017
17/05/2016
03/07/2016
20/11/2016
13/12/2016
17/01/2017
29/01/2017

Cable Trays
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Packing at manufacture's works

155 days
20 days
25 days
60 days
20 days
20 days

02/05/2016
02/05/2016
25/05/2016
23/06/2016
01/09/2016
25/09/2016

29/10/2016
24/05/2016
22/06/2016
31/08/2016
24/09/2016
17/10/2016

Technical Submission to SEC


Technical Submission Approval from SEC
Purchase of Materials
FAT & Dispatch Clearance
Packing at manufacture's works
Delivery & Receipt at site

Half1,2016
J
M
M

Half2,2016
J
S
N

26May'16

13Apr'16

02May'16

Task

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Page13of15

Half1,2017
J
M
M

Half2,2017
J
S
N

Half1,2018
J
M
M

17Jan'17

29Jan'17

29Oct'16

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504

TaskName

Duration
Delivery & Receipt at site

Start

Finish

10 days 18/10/2016

015
N
29/10/2016

Fault Recorders
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

229 days
14 days
35 days
120 days
20 days
30 days
10 days

25/04/2016
25/04/2016
11/05/2016
21/06/2016
08/11/2016
01/12/2016
05/01/2017

16/01/2017
10/05/2016
20/06/2016
07/11/2016
30/11/2016
04/01/2017
16/01/2017

HVAC System
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

250 days
27 days
25 days
120 days
20 days
30 days
10 days

18/05/2016
18/05/2016
19/06/2016
08/08/2016
26/12/2016
18/01/2017
22/02/2017

05/03/2017
18/06/2016
17/07/2016
25/12/2016
17/01/2017
21/02/2017
05/03/2017

Fire Fighting System


Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

250 days
30 days
40 days
120 days
20 days
30 days
10 days

03/04/2016
03/04/2016
08/05/2016
23/06/2016
10/11/2016
04/12/2016
08/01/2017

18/01/2017
07/05/2016
22/06/2016
09/11/2016
03/12/2016
07/01/2017
18/01/2017

EOT Crane
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing

175 days
20 days
25 days
80 days

14/05/2016
14/05/2016
06/06/2016
05/07/2016

03/12/2016
05/06/2016
04/07/2016
05/10/2016

Half1,2016
J
M
M

Half2,2016
J
S
N

25Apr'16

18May'16

03Apr'16

14May'16

Task

InactiveTask

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Page14of15

Half1,2017
J
M
M

Half2,2017
J
S
N

Half1,2018
J
M
M

16Jan'17

05Mar'17

18Jan'17

03Dec'16

Planning Department

Project Name: Construction of AL-WAJH 380/132/33/13.8 KV BSP Substation


Contract No. : 4400006924
Project Schedule
ID
505
506
507
508
509
510
511
512
513
514
2068
2122
2123
2125
2126
2127
2128
2129
2130
2131
2132

TaskName

Duration
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

Telecommunication Panel
Technical Submission to SEC
Technical Submission Approval from SEC
Manufacturing
FAT & Dispatch Clearance
Freight
Shipment Port Clearance & Receipt at site

Start

Finish

20 days 06/10/2016
20 days 30/10/2016
10 days 22/11/2016

015
Half1,2016
N
J
M
M
29/10/2016
21/11/2016
03/12/2016
22/02/2017 14Apr'16

270 days
25 days
35 days
150 days
20 days
30 days
10 days

14/04/2016
14/04/2016
14/05/2016
23/06/2016
15/12/2016
08/01/2017
12/02/2017

129 days
0 days
60 days
49 days
49 days
14 days
60 days
0 days
0 days

02/07/2017
27/12/2017
30/12/2017
04/01/2018
10/01/2018
14/02/2018
30/12/2017
27/02/2018
27/02/2018

27/12/2017
27/12/2017
27/02/2018
21/02/2018
27/02/2018
27/02/2018
27/02/2018
27/02/2018
27/02/2018

Final Acceptance
90 days 27/02/2018
Handing Over Procedures and Final Acceptance of the Wo 90 days 27/02/2018

27/05/2018
27/05/2018

Testing and Commissioning


Completion of Testing & Commissioning Activities
Preliminary Acceptance
Final O&M Submission
Operational Spare Parts Submission
Miscellaneous Requirements
Dismantling of Unused Equipment's
Complete Demobilization
Preliminary Acceptance

Half2,2016
J
S
N

Half1,2018
J
M
M

22Feb'17

02Jul'17
30Dec'17

Startonly

Split

InactiveMilestone

Finishonly

InactiveSummary

Deadline

ManualTask

Critical

Durationonly

CriticalSplit

ExternalTasks

ManualSummaryRollup

Progress

ExternalMilestone

ManualSummary

ManualProgress

Page15of15

27Dec'17
27Dec'17
27Feb'18

27Feb'18

InactiveTask

Revision: 06 | Issue No.: 07 | Issue Date: 25/04/2016

Half2,2017
J
S
N

12/05/2016
22/06/2016
14/12/2016
07/01/2017
11/02/2017
22/02/2017

Task

Milestone
Project:380/132/33/13.8kVALWAJH 001
Summary
Date:25/04/2016
ProjectSummary

Half1,2017
J
M
M

27Feb'18
27Feb'18
27

Planning Department