Você está na página 1de 1

Proposal for 15th Floor Pent House.

Previoulsy Proposed ONU

ONU
Proposed ONU and FDB-2
FDB-2

Previoulsy Proposed FDB-1

Emergency Escape Route

Emergency Escape Route

24/7 Accessible Service Rooms


Note: All drawings should
be Re-submitted to
official departments to
obtain approvals again,
as per the new design,
Previous approval are not
valid anymore.

SMDB

Previoulsy Proposed FDB-2

Proposed SMDB and FDB-1

FDB-1

Previoulsy Proposed ONU

1. Electrical Room, Telephone Room, Water Meter Room, Should be accessible 24/7 for Authorities and Maintenance Staff.
2. Since the Architectural Layout only show the Lift lobby as Public access area, the Emergency Escape route is not Accessible, at least one stair case
should be accessible for the public area as escape route.
3. The existing location of FDB-1 and FDB-2 is attached to wash room/wet area, which is not acceptable by ADDC.
4. One ONU can fulfil the requirements for the Pent House, and the location to be shifted from the bed room to common accessible place.
5. For Electrical load, One Sub Main Db and two Final Db's are proposed to fulfil the requiremnts, shown on the drawing.
6. Cables Feeding the DB's can be easily passed through the Lift Lobby, by means of Cable tray above the false ceiling.

Submitted by:Engr. Mahboob Alam


Dated: 02-Nov-2016