Escolar Documentos
Profissional Documentos
Cultura Documentos
Instructor introduction.
2.
3.
4.
Week 1 timetable
2.
3.
State the outcome or end result and the main stakeholders of each
phase of the process
4.
5.
6.
8.
9.
10.
11.
12.
Explain the main HSE hazards and loss prevention measures taken in
drilling operations.
Source rock
Migration
Reservoir rock
Quantity
Trap
Source rock
Permeability, different in
different directions.
Size matters!
Drive
Water Drive
Sandstone porosity
10
Limestone porosity
11
Traps
Stratigraphic
Copyright 2006, NExT, All rights reserved
Anticline
12
Exploration
Field Production
Field Abandonment
cash flow
time
data management
Exploration
Copyright 2006, NExT, All rights reserved
Appraisal
Development
Production
13
Determine Lithology
14
So How do we Start ?
Sink an oil well
Problem - COST
1.
2.
3.
15
Problem
Where do we start ?
Geologists walk around looking at rocks
Measure PHYSICAL properties of the Earth - GEOPHYSICS
16
17
18
2.
3.
4.
5.
6.
Training wells.
19
2.
Dig cellar
Install conductor pipe
Prepare support pad for rig,
camp etc
Build roads, fencing, dig pits
Sometimes drill water well
20
21
22
Purposes;
1. Bring return fluid to the rig.
2. Support a diverter.
3. Prevent washing out surface soil.
23
Purposes;
1. Deepen the well.
2. Allow a surface casing.
24
Purposes;
1. Use a blowout preventer (BOP).
2. Protect freshwater sources.
3. Reduce losses.
25
Purposes;
1. Deepen the well.
26
Purposes;
1. Increased shoe strength to drill
ahead.
2. Protect drilled hole.
3. Case off kickoff.
27
Purposes;
1. Penetrate the reservoir.
2. Allow a pocket below the reservoir
(logging, casing, drop guns).
3. Run logs to measure reservoir
properties.
28
Purposes;
1.
2.
3.
4.
29
Purposes;
1. Allow hydrocarbon production.
2. Form a conduit for tools to be run.
30
31
Production Testing
Information obtained;
fluid types
maximum flow rate
rate at which sand is produced
reservoir characteristics.
32
Pressure vs Time
33
34
2.
3.
4.
35
2.
3.
36
Abandon wells.
2.
Remove infrastructure
(if not used by other projects).
3.
Restore environment.
37
Exploration Drilling
Appraisal /Development Drilling
field management & planning
Field Production
Field Abandonment
time
data management
Copyright 2006, NExT, All rights reserved
Exploration
Appraisal
Development
Production
38
Elastic Strength
Subsurface formations;
Formation lithology
Formation depths
Formation pressures and
temperatures
Pore fluids
Rock stresses
Electric logging results (day 5)
Core samples (day 5)
10
0
Youngs
70
100 0 Friction Angle
Modulus
Poissons
Ratio
20
UCS
400
Stress DirectionhS
Stress
200 W
MPa
1.0
fault ?
PR
UCS
Pp
Sh
SH
SV
Regional
Trend
39
2.
3.
Costs
4.
12000
13500
13000
40
2.
3.
4.
5.
41
42
43
Cantilever deck
V door
Pipe racks
Choke manifold
Poorboy degasser
Drawworks
Copyright 2006, NExT, All rights reserved
44
47
48
49
Rig types
50
51
52
Breaks down into small packages for moving (6000 lbs max)
53
54
55
56
57
58
59
60
61
62
Drilling organisation
63
Project Manager
Project
Well Engineer
Testing FSM
Dowell FSM
Coordinator
QHSE Engineer
Anadrill FSM
Wireline FSM
Wellsite Supervisor
Rig site
Sub-Contractors
Testing
IPM Representatives
Dowell
Anadrill
Wireline
Suppliers
Service Companies
65
Rig crew
Driller is in charge
66
Drilling time
vs depth
67
68
Examples;
Surveying the rig location
Mobilising the rig to the wellsite
69
Examples;
Casing and accessories
Drillbits
Drilling fluid
70
Examples;
71
Onshore
2007
$400,000
Ultra Deep
Daily Rig Cost
1998 $180,000
1999 $180,000
2007
$100,000
2007
$650,000
JMA
Copyright 2006, NExT, All rights reserved
72
Examples;
Office costs including secretaries, stationary etc.
Logistic bases and supply depots.
73
Examples;
Stuck pipe
Fishing
74
Fixed
Depth dependent
Time dependent
Overhead (or Support)
Contingency
75
Air transport.
76
1.
2.
Well planning.
77
1.
Well planning.
2.
3.
78
1.
Well planning.
2.
3.
4.
Time dependent.
79
1.
Well planning.
2.
3.
Time dependent.
4.
Contingency.
80
81
Example AFE
82
Exercise
Look at the well cost spreadsheet and see the effect of the
following changes.
1. Increase time related costs by 10% and see the % total figure
increase. Restore the dayrate.
2. Increase depth related costs by 10% and see the % total
figure increase. Restore the TD.
3. Increase the contingency probabilities by 10%
and see the % total figure increase.
83
Exercise Solution
84
85
REDUCE
exposure
RECORD
risk register
ASSESS
exposure
MANAGE
remaining
risk
86
Identify risks
Risk = probability of event leading to injury, loss of assets or environmental damage
87
88
Assess exposure
PROBABILITY
89
Exposure matrix
1 Very High
1 High
1 Medium
1
ow
90
Risk register
1.
Hazard description
2.
Hazard effect
3.
4.
Assumptions
5.
6.
Prevention
7.
Recognition
8.
Mitigation/Cure
9.
Risk owner
10.
11.
91
92
93
94
Management
STOP system
HAZID
HAZOP
Permit to Work
Management policies
Safety Case
Safety Alerts
Training
Experienced Supervisors
95
96
Exposure to chemicals.
97
Day 1 review
98
2.
3.
State the outcome or end result and the main stakeholders of each
phase of the process
4.
5.
6.
99
8.
9.
10.
11.
12.
Explain the main HSE hazards and loss prevention measures taken in
drilling operations.
100
Drilling Fundamentals
Created by Steve Devereux CEng, Drilling Consultant
Presented by Arthur Dacre M.Sc. ExCalibre Limited
2.
3.
4.
5.
Define the terms: Limit Test and Leak Off Test and explain their
applications in drilling
102
8.
9.
10.
103
3 Classification of Rocks
Rock-forming Source of
process
material
IGNEOUS
SEDIMENTARY
METAMORPHIC
Weathering and
erosion of rocks
exposed at surface
Crystallization
(Solidification of melt)
Sedimentation, burial
and lithification
Recrystallization in
solid state of new
minerals
104
Igneous Rocks
Basalt
Gabbro
Examples
Rhyolite
Copyright 2006, NExT, All rights reserved
Granite
105
Breccia
Examples
Sandstone
Copyright 2006, NExT, All rights reserved
Shale
106
Metamorphic Rocks
Examples
Mica schist
Marble
Gneiss
Slate
Quartzite
107
Sedimentary rocks
109
110
Sandstones, conglomerates,
11% of the total.
Sedimentary Environments
Glacier
Lake
Tidal flat
Desert
River
Delta
Organic reef
Continental shelf
Beach
Continental slope
Deep sea
112
Drilling shales
113
Drilling limestone
114
Drilling coal
115
Drilling salts
116
Drilling Sandstones
117
Drilling geology
118
Formation Pressures
119
Pressure; hydrostatic
Pressure = 0.03604 1 =
0.03604 psi.
120
Pressure; hydrostatic
121
Pressure; hydrostatic
Pressure h depth.
Pressure depth = gradient
Depth x gradient = pressure
10,000 x 0.4325 = 4325 psi.
Pressure at 6000?
122
Pressure; hydrostatic
Pressure h depth.
Pressure depth = gradient
Depth x gradient = pressure
10,000 x 0.4325 = 4325 psi.
Pressure at 6000 =
6000 x 0.4325 = 2595 psi.
123
Pressure vs depth
124
125
126
127
128
129
130
131
132
133
Calculations
Convert the following mud densities into pressure gradients.
1. 13.5ppg
2. 16.0ppg
3. 12.0ppg
0.702 psi/ft
0.832 psi/ft
0.624 psi/ft
Convert the following gradients into mud densities
1. 0.806 psi/ft 2. 0.598 psi/ft 3. 0.494 psi/ft
15.5ppg
11.5ppg
9.5ppg
Calculate the hydrostatic pressure for the following
9.5ppg mud at 9,000ftmd/8000fttvd
= 3,952 psi
15.5ppg mud at 18,500fttvd/21,000ftmd
= 14,911 psi
0.889 psi/ft mud at 11,000ftmd/9,000fttvd = 8,001 psi
Copyright 2006, NExT, All rights reserved
135
136
137
Imperial units are pounds per square inch (psi) for both.
138
Stresses in Rock
139
Overburden stress
141
142
143
144
145
Fracture pressure
= 750+ (0.5 x 6000) = 3,750 psi.
Fracture gradient =
3,750 6,000 = 0.625 psi/ft.
146
Fracture pressure
= 750+ (0.5 x 6000) = 3,750 psi.
Fracture gradient
= 3,750 6,000 = 0.625 psi/ft.
147
Fracture pressure
= 750+ (0.5 x 6000) = 3,750 psi.
Fracture pressure
= 850+ (0.5 x 7000) = 4,350 psi.
Fracture gradient
= 3,750 6,000 = 0.625 psi/ft.
Fracture gradient =
4,350 7,000 = 0.621 psi/ft.
148
These pressure/stress
profiles are important in
well design.
149
150
Kick - definition
151
Casing Points
The predicted pore pressure
from seismic is shown
The predicted fracture
pressure from seismic is then
added.
Finally mud weights are added
which fit between the pore and
fracture pressures gradients.
From this the casing points are
selected and Kick Tolerances
are calculated.
This helps to reduce the risk of
blowouts from kicks and
influxes, but is not a
guarantee!
Copyright 2006, NExT, All rights reserved
152
Kick Intensity
The intensity of the kick is how much
the mud weight would need to be
increased to control the new formation
pressure.
Example:
Old mud weight
Pf1 = 12.0ppg
Mud hydrostatic
pressure
0.5ppg
Pf1 Pf2
Copyright 2006, NExT, All rights reserved
153
Hydrostatic Pressure
7.48 cu/ft
= .052
144 sq ins
154
Kick Definitions
Induced Kick - zero SIDP.
155
Formation Test
Leak-Off Test and Equivalent Mud Weight Test
Prudent drilling practices require that the formation exposed below the last casing string
be pressure tested for well control integrity. The test may be to a specified equivalent mud
weight or to the formation frac or leak-off value. The results of the leak-off test limits
mud weights to be used at later depths and may alter the planned casing for the well. The
test also indicated the quality of the cement job.
1200
Leak-Off @ 1000 psi
Pressure, psi
1000
800
600
400
200
Example:
Casing Test
Leak-Off Test
10 20 30 40 50 60 70 80 90 100
158
Kick Tolerance
When a gas influx has entered a well there are 2 critical locations
for the influx:When the influx is at the bottom of the well. In this case the
SICP must not exceed the MAASP, if the formation has not
fractured at the casing shoe.
When the influx has been circulated up to the casing shoe, by a
constant bottom hole pressure method. In this case, the pressure
at the choke must not exceed the MAASP.
160
Kick causes
161
Immediate actions
162
163
165
166
167
169
170
171
172
Kick Tolerance 1
173
Kick Tolerance 2
174
Kick Tolerance 3
175
Kick tolerance
176
Wellbore Instability
177
178
Stuck pipe
Problems drilling and deviating
Problems tripping
Problems logging
Problems running casing
Inadequate cement jobs
Excessive generation of solids from the well
179
Shale Hydration
180
Reactive shales
181
Fractured rock
182
183
Erosion
184
185
186
DANGER
RISKY
SAFE
TOO HIGH
TOO LOW
MUD WEIGHT
Pp
3total
TENSILE
FAILURE
COMPRESSIVE
& SHEAR FAILURE
Copyright 2006, NExT, All rights reserved
187
Elongated Hole
188
Rule of Thumb
189
190
Day 2 review
191
2.
3.
4.
5.
Define the terms: Limit Test and Leak Off Test and explain their
applications in drilling
192
8.
9.
10.
193
2.
3.
4.
Describe a typical drillstring & BHA and explain the functions of the
main components.
5.
6.
Define casing and state two drilling related reasons for setting casing
7.
195
196
Stabiliser
Drill bit
197
Drillpipe
3 component
parts;
Pipe body
Tooljoint box
Tooljoint pin
198
Drillcollars
Used to;
Put weight on the drillbit while keeping the drillpipe in tension.
Control directional performance.
199
Crossovers
200
Jar
201
Stabilisers
202
Drillbits
Different types;
203
204
205
Well Design
Completion
Deviation
Casing & cement
Well fluids
Wellhead
206
Completion
207
Deviation
Field development
wells
208
209
210
Stabiliser
positions and
sizes control build,
hold or drop of the
wellbore.
211
212
Directional plan
213
Horizontal well
Multilateral wells
Multiple wells from one surface location
214
215
Sidetracking
Drainage/re-drill
Copyright 2006, NExT, All rights reserved
Fault Controlling
Multilaterals
216
Wellpath considerations
1.
2.
Achieving all the targets most efficiently from the surface location.
3.
4.
5.
6.
7.
In situ stresses.
8.
217
218
Platform offshore
Subsea wellhead
219
Wellhead
1. The wellhead is a collection of valves and other equipment
which terminate the well at the surface. All the casings are
suspended in the wellhead system, as is the completion
tubing. It has to withstand high stresses and high
pressures from the well.
2. It has to allow electrical cables to pass through if downhole
electric pumps are used, plus hydraulic lines for subsurface
safety valves. So the wellhead is an expensive and
complex piece of equipment.
3. The type of wellhead used reflects the environment that the
well is situated in. On a land well or a fixed offshore
platform, similar wellheads can be used.
Copyright 2006, NExT, All rights reserved
220
221
Xmas tree
Tubing hanger
Casing hangers
222
Tubing hanger
Electrical cable
for submersible pump
Casing hanger
223
Mudline Hangers
about 15ft below
the seabed
Copyright 2006, NExT, All rights reserved
224
225
Casing Hangers
226
227
Tubing Hangers
228
Wear Bushing
229
Seal Assembly
Test Port
Copyright 2006, NExT, All rights reserved
230
Subsea Wellheads
Well Head Selection
correct pressure rating
ease of operation
cost
operator preferences
High Pressure
Wellhead
Wellhead Housing
231
232
233
2.
3.
4.
5.
6.
7.
234
235
Casing Design inc cement specs & mud density . 3-15 days
236
237
Seabed conditions
238
239
240
Manufacturing tolerances
241
Grade designations
242
Grade markings
243
Specifying a casing
244
245
2.
3.
246
5.
When the design is checked for approval, the assumptions and decisions
made can be validated.
If the design has to be revised lateR, the design can be revised taking into
account all of the original decisions.
247
248
Casing Point
Selection
251
Casing Manufacture
252
Float Equipment
253
Running Casing
254
255
Review
256
257
258
Mixing cement
94 lbs
sack of
cement
powder
5 gallons
of water
Neat
cement
259
PRISM
, rate, p
260
Cementing Unit
261
Re-circulating Mixer
262
Key factors;
1. Complete mud removal.
2. Sufficient long term compressive and shear
strength.
3. Maintenance of primary well control.
4. Zonal isolation between zones and to
surface.
5. Impermeability; gas entrainment.
6. Avoid losses / fracturing during placement.
263
Centralisation
Flow regime
Pipe movement
264
5000
Compressive strength (psi)
at 3,000 psi UCA
Compressive
strength at 320F
4000
Compressive
strength at 350F
3000
2000
Thickening
time at 350F
(5hr, 27min)
1000
0
0
10
15
20
25
30
35
40
Time (hr)
265
266
Zonal isolation
Shale
Fresh Water
bearing Formation
Copyright 2006, NExT, All rights reserved
267
268
Cement
higher density gradient than mud higher hydrostatic
pressure.
More viscous than mud higher pressure losses.
Smaller annulus than during drilling higher pressure losses.
269
Key factors;
1.
2.
3.
4.
5.
6.
270
Cement additives
271
Cementing programme
272
273
274
275
Day 3 review
276
2.
3.
4.
Describe a typical drillstring & BHA and explain the functions of the
main components.
5.
6.
Define casing and state two drilling related reasons for setting casing
7.
277
9.
10.
11.
12.
13.
14.
278
287
8.
9.
10.
11.
12.
288
Maximise Progress
Minimise Problems
Minimise Reservoir Damage
Select technical solutions leading to the lowest well cost, not
the lowest solution cost.
289
290
Dissolved chemicals
Salts to reduce shale hydration or allow drilling salts
Caustic Soda, Calcium Hydroxide
Polymers
291
292
293
Mud programme
294
295
296
297
Skin factor, s
298
2.
3.
4.
299
2.
3.
300
Solids Blocking
301
Shale swelling
302
303
Drilling problems
1.
2.
Stuck pipe.
3.
Fishing.
304
305
Losses; definition
306
307
Pressure condition
Surge pressures
Kick
FIT
308
Pathways
309
310
If the depth of the total loss zone is known, the pressure can
be calculated.
311
Example
121/4 hole, 5 drillpipe. Loss zone
suspected on bottom at 10,000.
0.6 psi/ft mud, 0.433 psi/ft water.
Annulus topped up with 30 bbls of
water.
Pressure in loss zone = addition of
fluid hydrostatic pressures
Height of water Hw = 30/0.1214
Hw = 247
Pp = Hww + Hmm = 5960 psi
312
Exercise
121/4 hole, 5 drillpipe. Loss zone
suspected on bottom at 10,000.
0.6 psi/ft mud, 0.433 psi/ft water.
Annulus topped up with 30 bbls of
water.
Pressure in loss zone = addition of
fluid hydrostatic pressures
Height of water Hw = 30/0.1214
Hw = 247
Pp = Hww + Hmm = 5960 psi
313
Answer
121/4 hole, 5 drillpipe. Loss zone
suspected on bottom at 10,000.
0.6 psi/ft mud, 0.433 psi/ft water.
Annulus topped up with 30 bbls of
water.
Pressure in loss zone = addition of
fluid hydrostatic pressures
Height of water Hw = 30/0.1214
Hw = 247
Pp = Hww + Hmm = 5960 psi
314
Lost circulation
Any questions?
315
316
317
318
Hole Geometry
Stiff BHA
319
Solids buildup
Avoid by;
1. Good hole cleaning practices.
320
Avoid by;
Good housekeeping.
Keep the rotary table covered.
Be careful when working on BOP etc.
Most often stuck while POH. First action, try to jar down.
321
Differential sticking
Overbalance.
Filter cake.
Stationary pipe.
Wall Contact.
322
323
Stuck pipe
Any questions?
324
325
Fishing - definition
326
4 main causes
Stuck pipe
Junk
Workover
327
328
Stuck pipe
Prevention;
Dont get stuck!
329
330
Workover
Sometimes a well has to have the completion string removed, possibly to
repair damage, or change the completion configuration, or to abandon the
well. These operations often involve planned fishing when the
completion cannot simply be pulled out. Over time, solids can settle
around the lower part of the completion, sticking it in place. The tubing
can be cut and then a fishing assembly run on drillstring to latch on to the
fish and put great force on it.
331
Stuck pipe
Junk
Workover
Any questions?
332
Situation diagram
333
Outside catch tools are very strong - often stronger than the
drillpipe.
334
335
Used when there is not much annular clearance but the fish
has a large open ID (casing).
Inside catch tools are not very strong - the strength is limited
by the strength of the inner mandrel.
336
Releasing Spear
An overshot in reverse.
Grip increases as pull increases
Grip releases with RH torque
Not so strong in tension, can
lightly jar only
Allows circulation through the
fish
Can be released downhole
without damaging the fish
337
Barrel may be used to move over the junk and close below it.
338
Main characteristics;
A ball is dropped which diverts
the fluid flow around and up
inside the tool.
Spring loaded fingers allow the
junk in but not out.
Ideal for drillbit cones.
339
Fishing
Any questions?
340
341
342
343
344
345
Rams
346
Annular preventer
347
348
Options;
1. Baryte plug; heavy slug that
settles out on the bottom to
stop flow. Well might be
saved.
2. Cement plug; keep mixing and
pumping cement into the well
until flow stops. Well lost.
3. Relief well. Takes months,
costs million$.
349
Any questions?
350
351
352
Real-Time Drilling
z In real time operations, a close multi-disciplinary team works
together with real-time wellsite information streaming in to
the operations center, where it is analyzed and decisions
made with access to lots of high quality data.
z The onshore operations center becomes a virtual part of the
rig. All the major drilling parameters are relayed in real time
to the operations center, which can be anywhere in the
world. Better and faster decisions result in better progress,
fewer problems and therefore improved Return on
Investment.
Copyright 2006, NExT, All rights reserved
353
354
355
356
Visualization,
communication,
decisions
Collaborative well
placement
Earth-driven
drilling optimization
Model-based
surveillance
Transmission
Real-time capture
357
Petrophysical analysis
RT log data
3-way VC
Clients
Geosteering Correlation
Inform 3D
Modeling
Reporting
RT Structural
Dip Analysis
358
Day 4 review
359
2.
3.
4.
360
6.
7.
8.
9.
361
363
364
Mud Logging
365
Mud Logging
366
Pumps
Pits/tanks
Mixing devices
Contaminants removal
equipment, and
Flow conduits
367
368
Gas Analysis
369
Mud Logging
370
371
372
Wireline Logs
Wireline Logs
Electric Logging
375
Resistivity
376
Porosity
377
Sonic Log
378
Density Log
379
Neutron Log
Neutron logs are porosity logs that
measure the hydrogen ion
concentration in a formation. In clean
formations (i.e.... shale-free) where the
porosity is filled with water or oil, the
neutron log measures liquid-filled
porosity.
Whenever pores are filled with gas
rather than oil or water, neutron
porosity will be lowered. This occurs
because there is less concentration of
hydrogen in gas compared to oil or
water. A lowering of neutron porosity by
gas is called gas effect.
Neutron log responses vary, depending
on: (1) differences in detector types,
(2) spacing between source and
detector
(3) lithology-i.e. sandstone, limestone,
and dolomite.
Copyright 2006, NExT, All rights reserved
380
Gamma Ray
381
Is there an indication of
formation invasion or damage?
382
USIT Tool
MDT
LWD
Logging While Drilling
386
LWD
387
LWD
Associated Risks
Rental Cost
Lost in Hole or Damage Beyond Repair Charges
Increased BHA length (potential for stuck pipe)
Dependent upon other rig mechanisms to be functioning
optimally (Mud condition, Mud pumps, Mud Density)
Complex technology subjected to rigorous working
environment. MTBF!
388
LWD Tool
389
LWD Tool
390
391
392
393
Powerdrive Video
394
Schlumberger Powerdrive
395
Schlumberger Powerdrive
396
Schlumberger Powerdrive
397
Schlumberger Powerdrive
398
Geosteering
399
GeoSteering
400
Geosteering Assemblies
401
Geosteering
402
Geosteering
Benefits of Geosteering
Enhanced oil recovery through optimum placement of borehole
in reservoir in the high permeability sections.
Reservoir fluid production control borehole above oil/water
contact and below oil/gas contact.
Less borehole required for equivalent production
403
Geosteering
404
405
406
407
408
409
410
411
412
414
415
416
417
418
419
Well Testing
420
Well Testing
421
Well Testing
Well Fluids
Low Pressure Oil
Separator Gas
Water
422
Perforating
Two Methods
Wireline Conveyed Guns
Tubing Conveyed Guns
423
Perforating
1. Firing head options include electric line, pressure, or mechanical systems.
Firing options include pressure activated for both wireline and tubing
conveyed systems, either by differential or applied pressure, and with or
without time delay devices.
2. Wireline perforating is common; the well can be perforated after nippling up
the Xmas tree.
3. Perforating Underbalanced to backsurge and clean up the perforation
tunnels is achieved by using coiled tubing to displace out fluid from the
tubing. The disadvantages include the limit on the size of the guns to an OD
that will pass through the tubing, and the maximum weight (length) of the
gun assembly per run.
4. Due to the small size of the charge, the guns must be held against the
casing wall for sufficient penetration; this restricts the gun to 0 phasing,
which reduces productivity compared to 90 phasing. The restricted gun
size may also give below optimum perforation depth.
Copyright 2006, NExT, All rights reserved
424
Perforating
Perforation length
Perforation diameter.
Shot density
Angular phasing
425
Perforating Charges
426
Gun Phasing
427
428
429
Completions
430
Well Completions
There Are Three Basic Types Of Completion
431
Well Completions
432
Well Completions
Basic
completion
More
versatile
completion
433
Well Completions
z
434
Well Completions
Completion Design Example 1
Consider the following casing schematic. The objective is to design
a completion string for this well with following basic functional
requirements:
z To provide optimum flowing conditions
z To protect the casing from well fluids
z To contain reservoir pressure in an emergency
z To enable down hole chemical injection
z To enable the well to be put in a safe condition prior to
removing the production conduit (i.e. to be killed)
z To enable routine downhole operations.
NOTE: The above functional requirements are not exhaustive.
Copyright 2006, NExT, All rights reserved
435
Well Completions
A completion string that fulfils
these functional
requirements is illustrated on
the right hand diagram. It is
important to realize this
example design is only a
solution and not the solution.
This design is called a single
zone single string
completion.
Copyright 2006, NExT, All rights reserved
More
versatile
completion
436
Well Completions
Components of a Simple Completion
Xmas Tree
Production Casing
Production Tubing
Packer
Tail Pipe
437
Well Completions
Xmas Tree
438
Well Completions
Tubing Hanger
439
Well Completions
Downhole Safety Valves
440
Well Completions
Packer
Permanent Packer
441
Well Completions
Tubing
Tubing Connections
442
Intelligent Completions
443
Intelligent Completions
Basic Equipment
Downhole Sensors
To measure the desired parameters in the well
Controls
To reconfigure the downhole tools
Telemetry
To convey data to and from the surface
444
Intelligent Completions
445
Intelligent Completion
Intelligent Well Schematic
446
Intelligent Completions
Example of Selective Zone Production
Demonstration of gas
zone being produced
and being shut off
from surface
controlled equipment.
447
Well Abandonment/Suspension
448
449
Well Suspension
450
Suspended well
451
Well Abandonment
452
Well Abandonment
453
Well Abandonment
454
Day 5 review
455
2.
3.
4.
5.
6.
7.
8.
456
10.
11.
12.
13.
14.
457
This is a closed book test. Please put away your notes and
handouts now.