Ref. No.: PEM.009.J231.

16(S)
Project

B+G+5 Commercial/Residential Bldg at Majan

Consultant :

M/s ATI

Client

Mr. Salah Abdelrahman Bukthair

Subject

Time Frame for Fire Fighting Work

Completion Mechanical program of work for MAJAN Project


Fire Fighting Works

Activity

Slab Work

Area

Required Period
for one floor

Basement

3 days

2-Mar-17

5-Mar-17

GF

3 days

22-Mar-17

24-Mar-17

1st Floor

3 days

10-Apr-17

12-Apr-17

2nd Floor

3 days

29-Apr-17

1-May-17

3rd Floor

3 days

18-May-17

20-May-17

4th Floor

3 days

6-Jun-17

8-Jun-17

5th Floor

3 days

25-Jun-17

27-Jun-17

20 days

27-Apr-17

16-May-17

Basement

Main Header & Branching

Pressure Test

Sprinkler Fixing

Fire Pump Installation


FM 200 SYSTEM

Testing & Commissioning

Assumed Starting
Date

Assumed Ending
Date

GF

18 days

16-May-17

2-Jun-17

1st Floor

15days

30-May-17

14-Jun-17

2nd Floor

15 days

19-Jun-17

3-Jul-17

3rd Floor

15 days

8-Jul-17

22-Jul-17

4th Floor

15 days

27-Jul-17

10-Aug-17

5th Floor

15 days

13-Aug-17

27-Aug-17

Basement

2 days

17-May-17

18-May-17

GF

2 days

3-Jun-17

4-Jun-17

1st Floor

2 days

15-Jun-17

16-Jun-17

2nd Floor

2 days

4-Jul-17

5-Jul-17

3rd Floor

2 days

22-Jul-17

23-Jul-17

4th Floor

2 days

11-Aug-17

12-Aug-17

5th Floor

2 days

28-Aug-17

29-Aug-17

Basement

6 days

6-Aug-17

11-Aug-17

GF

6 days

12-Aug-17

17-Aug-17

1st Floor

6 days

22-Aug-17

27-Jun-17

2nd Floor

6 days

1-Sep-17

6-Sep-17

3rd Floor

6 days

11-Sep-17

16-Sep-17

4th Floor

6 days

21-Sep-17

26-Sep-17

5th Floor

6 days

1-Oct-17

6-Oct-17

Pump Room

15 days

23-Sep-17

7-Oct-17

GF

15 Ddays

11-Oct-17

25-Oct-17

Basement

3 days

8-Oct-17

11-Oct-17

GF
1st Floor
2nd Floor
3rd Floor
4th Floor
5th Floor

3 days
3 days
3 days
3 days
3 days
3 days

12-Oct-17
15-Oct-17
18-Oct-17
21-Oct-17
24-Oct-17
27-Oct-17

14-Oct-17
17-Oct-17
20-Oct-17
23-Oct-17
26-Oct-17
29-Oct-17

work for MAJAN Project

Required Activity by other

After Plywood

After Plastering

Block Work

After Plaster Work

After Plaster Work

Remark

Ref. No.: PEM.012.J231.16(S)


Project

B+G+5 Commercial/Residential Bldg at Majan

Consultant :

M/s ATI

Client

Mr. Salah Abdelrahman Bukthair

Subject

Time Frame for Fire Alarm & Emergency Work

Completion Electrical program of work for Red Residence


Fire Alarm & Emergen

S.N

Activity

Slab Piping

Wall Piping

Cabling

Fixing of Devices

Fixing of FACP & EL Light Panels

Testing & Commissioning

Assumed Starting
Date

Assumed Ending
Date

Area

Required Period

Basement

4 days

3-Mar-17

6-Mar-17

GF

4 days

22-Mar-17

25-Mar-17

1st Floor

4 days

10-Apr-17

13-Apr-17

2nd Floor

4 days

29-Apr-17

2-May-17

3rd Floor

4 days

18-May-17

21-May-17

4th Floor

4 days

6-Jun-17

9-Jun-17

5th Floor

4 days

25-Jun-17

28-Jun-17

GF

4days

25-Apr-17

28-Apr-17

1st Floor

4days

14-May-17

17-May-17

2nd Floor

4days

2-Jun-17

5-Jun-17

3rd Floor

4days

21-Jun-17

24-Jun-17

4th Floor

4days

11-Jul-17

13-Jul-17

5th Floor

4days

27-Jul-17

30-Jul-17

GF

07 days

17-May-17

23-May-17

1st Floor

07 days

1-Jun-17

7-Jun-17

2nd Floor

07 days

19-Jun-17

25-Jun-17

3rd Floor

07 days

8-Jul-17

14-Jul-17

4th Floor

07 days

27-Jul-17

2-Jul-17

5th Floor

07 days

13-Aug-17

19-Aug-17

Basement

07 days

10-May-17

16-May-17

GF

4 days

12-Aug-17

15-Aug-17

1st Floor

4 days

22-Aug-17

25-Aug-17

2nd Floor

4 days

1-Sep-17

4-Sep-17

3rd Floor

4 days

11-Sep-17

14-Sep-17

4th Floor

4 days

21-Sep-17

24-Sep-17

5th Floor

4 days

1-Oct-17

4-Oct-17

Basement

12 days

1-Aug-17

12-Aug-17

GF

7 days

5-Oct-17

11-Oct-17

21 days

11-Oct-17

31-Oct-17

of work for Red Residence Project

Required Activity
by other

Remark

1- Plywood
2-steel layers

Block Work

Block Work

False Ceiling

our program related


with other
activities,so any
delay by other will
affect our program
of work and starting
date along with the
ending date will be
shifted accordingly.