CHAPTER NO.

LOADING UNLOADING AND STACKING

DESCRIPTION OF ITEM NO 1: Loading or unloading into or from Railway


Wagons lead within one chain Shingle, sand,
ballast, surkhi ashes, kankar, brick bats, coal.
Lime or 1000 Nos. tiles size 12"x6"x2" or
9"x4½"x1½" properly laid and stacked.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.00 No 140.00 P. Day 140.00

Total 140.00
Sundries 10.00 Percent 14.00
Total 154.00

Contractor's Profit & Overheads 20.00 Percent 30.80


Total 184.80

Item Rates

Labour Rate Per 100 Cft Rs. 147.84 Say 147.85

Labour Rate Per Cum Rs. 52.22 Say 52.20

Page 1
DESCRIPTION OF ITEM NO 2: Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.

a) Bricks 10" size.

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.25 No 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 1000 Nos Rs. 184.80 Say 184.80

Page 2
Item No. 2 Loading or unloading bricks into or from Railway
Wagons laid and stacked lead within one chain.

b) Bricks 9" or smaller size.

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Bricks
Labour

Unskilled Cooly 1.00 No 140.00 P. Day 140.00

Total 140.00
Sundries 10.00 Percent 14.00
Total 154.00

Contractor's Profit & Overheads 20.00 Percent 30.80


Total 184.80

Item Rates

Labour Rate Per 1000 Nos Rs. 147.84 Say 147.85

Page 3
DESCRIPTION OF ITEM NO 3: Loading or unloading into or from Railway
Wagons cement in bags (from inside or outside
the go-down) and stacking within one chain.

Detail Unit Rate (British System) per 100 Bags

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Bags
Labour

Unskilled Cooly 1.25 No 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 100 Bags Rs. 184.80 Say 184.80

Page 4
DESCRIPTION OF ITEM NO 4: Loading or unloading into of from Railway
Wagons empty cement bags (from inside or
outside the go-down) and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour

Unskilled Cooly 0.12 No 140.00 P. Day 16.80

Total 16.80
Sundries 10.00 Percent 1.68
Total 18.48

Contractor's Profit & Overheads 20.00 Percent 3.70


Total 22.18

Item Rates

Labour Rate Per 100 Nos Rs. 22.18 17.74 Say 17.75
125

Page 5
DESCRIPTION OF ITEM NO 5: Loading or unloading into or from Railway
Wagons (from inside or outside the go-down) and
stacking white lime in bags.

Detail Unit Rate (British System) per 100 Mds

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour

Unskilled Cooly 0.75 No 140.00 P. Day 105.00

Total 105.00
Sundries 10.00 Percent 10.50
Total 115.50

Contractor's Profit & Overheads 20.00 Percent 23.10


Total 138.60

Item Rates

Labour Rate Per 100 Mds Rs. 110.88 Say 110.90

Labour Rate Per 100 Kg Rs. 2.97 Say 2.95

Page 6
DESCRIPTION OF ITEM NO 6: Loading or unloading into or from Railway
Wagons structural steel, joists, broad, narrow or
meter gauge rail and rail fastening etc.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Ton
Labour

Unskilled Cooly 0.60 No 140.00 P. Day 84.00

Total 84.00
Sundries 10.00 Percent 8.40
Total 92.40

Contractor's Profit & Overheads 20.00 Percent 18.48


Total 110.88

Item Rates

Labour Rate Per Ton Rs. 88.70 Say 88.70


Labour Rate per Tonne Rs. 87.30 Say 87.30

Page 7
DESCRIPTION OF ITEM NO 7: Loading or unloading 45 gallons drum full into
or from Railway Wagons lead upto one chain.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Unskilled Cooly 0.06 No 140.00 P. Day 8.40

Total 8.40
Sundries 10.00 Percent 0.84
Total 9.24

Contractor's Profit & Overheads 20.00 Percent 1.85


Total 11.09

Item Rates

Labour Rate Per Each Rs. 11.09 Say 11.10

Page 8
DESCRIPTION OF ITEM NO 8: Loading or unloading packages or stock of all
sorts upto I cwt. except cement in jute or paper
bags.

Detail Unit Rate (British System) per Each

Qty Rate
Per Unit (Rs.) Amount (Rs.)

Labour

Unskilled Cooly 0.03 No 140.00 P. Day 4.20

Total 4.20
Sundries 10.00 Percent 0.42
Total 4.62

Contractor's Profit & Overheads 20.00 Percent 0.92


Total 5.54

Item Rates

Labour Rate Per Each No. Rs. 5.54 Say 5.55

Page 9
DESCRIPTION OF ITEM NO 9: Loading or unloading sleepers other than wooden
including stacking lead within one chan in.

a) Broad gauge sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos.
Labour

Unskilled Cooly 2.50 Nos 140.00 P. Day 350.00

Total 350.00
Sundries 10.00 Percent 35.00
Total 385.00

Contractor's Profit & Overheads 20.00 Percent 77.00


Total 462.00

Item Rates

Labour Rate Per 100 Nos Rs. 369.60 Say 369.60

Page 10
Item No. 9 Loading or unloading sleepers other than wooden
including stacking load within one chan in.

b) Metre guage and narrow guage sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 1.25 No 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 100 Nos Rs. 184.80 Say 184.80

Page 11
DESCRIPTION OF ITEM NO 10: Loading or unloading timber logs or timber for
shuttering into or from Railway Wagons of any
gauge including stacking, lead within one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 20 Ton
Labour

Unskilled Cooly 5.00 Nos 140.00 P. Day 700.00

Total 700.00
Sundries 10.00 Percent 70.00
Total 770.00

Contractor's Profit & Overheads 20.00 Percent 154.00


Total 924.00

Item Rates

Labour Rate Per Ton Rs. 46.20 Say 46.20


Per Tonne Rs. 45.47 Say 45.45

Page 12
DESCRIPTION OF ITEM NO 11: Loading or unloading bhoosa in Railway Wagons
lead upto 150 feet.

Detail Unit Rate (British System) per 100 Mds

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Mds
Labour

Unskilled Cooly 3.00 Nos 140.00 P. Day 420.00

Total 420.00
Sundries 10.00 Percent 42.00
Total 462.00

Contractor's Profit & Overheads 20.00 Percent 92.40


Total 554.40

Item Rates

Labour Rate Per 100 Mds. Rs. 443.52 Say 443.50

Labour Rate Per 100 Kg Rs. 11.88 Say 11.90

Page 13
DESCRIPTION OF ITEM NO 12: Loading or unloading timber scrap or wooden
plugs into or from Railway Wagons and stacking
within one chain lead.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1.25 Ton
Labour

Unskilled Cooly 0.50 No 140.00 P. Day 70.00

Total 70.00
Sundries 10.00 Percent 7.00
Total 77.00

Contractor's Profit & Overheads 20.00 Percent 15.40


Total 92.40

Item Rates

Labour Rate Per Ton Rs. 73.92 Say 73.90


Labour Rate Per Tonne Rs. 72.75 Say 72.75

Page 14
DESCRIPTION OF ITEM NO 13: Loading or unloading pitching stone or spawl
from Railway Wagons of any gauge (including
clearing 5 feet away from the rail)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour

Unskilled Cooly 0.37 No 140.00 P. Day 51.80

Total 51.80
Sundries 10.00 Percent 5.18
Total 56.98

Contractor's Profit & Overheads 20.00 Percent 11.40


Total 68.38

Item Rates

Labour Rate Per 100 Cft Rs. 54.70 Say 54.70

Labour Rate Per Cum Rs. 19.32 Say 19.30

Page 15
DESCRIPTION OF ITEM NO 14: Loading or unloading building stone (including
clearing 5 feet away from rails)

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft.
Labour

Unskilled Cooly 0.48 No 140.00 P. Day 67.20

Total 67.20
Sundries 10.00 Percent 6.72
Total 73.92

Contractor's Profit & Overheads 20.00 Percent 14.78


Total 88.70

Item Rates

Labour Rate Per 100 Cft Rs. 70.96 Say 70.95

Labour Rate Per Cum Rs. 25.06 Say 25.05

Page 16
DESCRIPTION OF ITEM NO 15: Unloading oil, bitumen tar etc.

a) Crude oil (to be pumped from tank wagon, into


tank).

Detail Unit Rate (British System) per 1000 Gln

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour

Unskilled Cooly 1.25 No 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80

Labour Rate Per 100 Liters Rs. 4.07 Say 4.05

Page 17
Item No. 15 Unloading oil, bitumen tar etc.

b) Crude oil (drained by gravity).

Detail Unit Rate (British System) per 1000 Gln

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1250 Gallons
Labour

Unskilled Cooly 1.25 No 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 1000 Gln. Rs. 184.80 Say 184.80

Labour Rate Per 100 Liters Rs. 4.07 Say 4.05

Page 18
Item No. 15 Unloading oil, bitumen tar etc.

c) Crude oil materials from Railway Wagons.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour

Unskilled Cooly 0.16 No 140.00 P. Day 22.40

Total 22.40
Sundries 10.00 Percent 2.24
Total 24.64

Contractor's Profit & Overheads 20.00 Percent 4.93


Total 29.57

Item Rates

Labour Rate Per 100 Cft Rs. 23.65 Say 23.65

Labour Rate Per Cum Rs. 8.35 Say 8.35

Page 19
Item No. 15 Unloading oil, bitumen tar etc.

d) Fuel oil from tank into empty drums and stacking


within one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 45 Ton
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per Ton Rs. 65.71 Say 65.70


Labour Rate Per Tonne Rs. 64.67 Say 64.65

Page 20
Item No. 15 Unloading oil, bitumen tar etc.

e) Petrol (2 gallon tin)

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 0.63 Nos 140.00 P. Day 88.20

Total 88.20
Sundries 10.00 Percent 8.82
Total 97.02

Contractor's Profit & Overheads 20.00 Percent 19.40


Total 116.42

Item Rates

Labour Rate Per 100 Nos Rs. 93.14 Say 93.15

Page 21
Item No. 15 Unloading oil, bitumen tar etc.

f) Kerosine oil (4 gallons tin).

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 1.25 Nos 140.00 P. Day 175.00

Total 175.00
Sundries 10.00 Percent 17.50
Total 192.50

Contractor's Profit & Overheads 20.00 Percent 38.50


Total 231.00

Item Rates

Labour Rate Per 100 Nos Rs. 184.80 Say 184.80

Page 22
DESCRIPTION OF ITEM NO 16: Removing and stacking within one chain lead.

a) Stones, Spawl, Brick Bats, shingle, sand, lime.


Surki, ashes, Kankar & Coal etc.

Detail Unit Rate (British System) per 100 Cft

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Cft
Labour

Unskilled Cooly 0.50 No 140.00 P. Day 70.00

Total 70.00
Sundries 10.00 Percent 7.00
Total 77.00

Contractor's Profit & Overheads 20.00 Percent 15.40


Total 92.40

Item Rates

Labour Rate Per 100 Cft Rs. 73.92 Say 73.90

Labour Rate Per Cum Rs. 26.11 Say 26.10

Page 23
Item No. 16 Removing and stacking within one chain lead.

b) Bricks

Detail Unit Rate (British System) per 1000 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 15,000 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 1000 Nos Rs. 197.12 Say 197.10

Page 24
Item No. 16 Removing and stacking within one chain lead.

c) Broad gauge wooden sleepers

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,500 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 118.27 Say 118.25

Page 25
Item No. 16 Removing and stacking within one chain lead.

d) Metre gauge or narrow gauge wooden sleepers.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 4,200 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 70.40 Say 70.40

Page 26
Item No. 16 Removing and stacking within one chain lead.

e) Rails, girders, pipes, cement etc.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 90 Ton
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per Ton Rs. 32.85 Say 32.85


Labour Rate Per Tonne Rs. 32.33 Say 32.35

Page 27
Item No. 16 Removing and stacking within one chain lead.

f) Bridge and crossing timber etc.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 750 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 394.24 Say 394.25

Page 28
DESCRIPTION OF ITEM NO 17: Loading into Wagons Girders, Rails, permanent
way material (except wooden sleepers) iron work,
M.S. Bars, Pipes, etc. including lead one chain
and stacking inside Wagons.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 40 Ton
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per Ton Rs. 73.92 Say 73.90


Labour Rate Per Tonne Rs. 72.75 Say 72.75

Page 29
DESCRIPTION OF ITEM NO 18: Unloading from Wagons Girders, Rails,
permanent way material (except wooden sleepers)
iron work, M.S. Bars, Pipes, etc. lead upto one
chain but excluding stacking.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 70 Ton
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per Ton Rs. 42.24 Say 42.25


Labour Rate Per Tonne Rs. 41.57 Say 41.55

Page 30
DESCRIPTION OF ITEM NO 19: Loading into Wagons, wooden broad gauge
sleepers including one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 1,000 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 295.68 Say 295.70

Page 31
DESCRIPTION OF ITEM NO 20: Unloading wooden broad gauge sleepers from
Wagons including one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,100 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 140.80 Say 140.80

Page 32
DESCRIPTION OF ITEM NO 21: Loading metre gauge or narrow gauge wooden
sleepers including one chain lead and stacking
inside Wagons.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 2,000 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 147.84 Say 147.85

Page 33
DESCRIPTION OF ITEM NO 22: Unloading metre gauge or narrow gauge wooden
sleepers including one chain lead but excluding
stacking

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 3,800 Nos
Labour

Unskilled Cooly 16.00 Nos 140.00 P. Day 2,240.00

Total 2,240.00
Sundries 10.00 Percent 224.00
Total 2,464.00

Contractor's Profit & Overheads 20.00 Percent 492.80


Total 2,956.80

Item Rates

Labour Rate Per 100 Nos Rs. 77.81 Say 77.80

Page 34
DESCRIPTION OF ITEM NO 23: Loading Bridge and grossing timber including
one chain lead and stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 4.00 Nos 140.00 P. Day 560.00

Total 560.00
Sundries 10.00 Percent 56.00
Total 616.00

Contractor's Profit & Overheads 20.00 Percent 123.20


Total 739.20

Item Rates

Labour Rate Per 100 Nos Rs. 591.36 Say 591.35

Page 35
DESCRIPTION OF ITEM NO 24: Unloading Bridge and crossing timber including
one chain lead but excluding stacking.

Detail Unit Rate (British System) per 100 Nos

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 125 Nos
Labour

Unskilled Cooly 2.00 Nos 140.00 P. Day 280.00

Total 280.00
Sundries 10.00 Percent 28.00
Total 308.00

Contractor's Profit & Overheads 20.00 Percent 61.60


Total 369.60

Item Rates

Labour Rate Per 100 Nos Rs. 295.68 Say 295.70

NOTE :

Rate for loading and unloading for Mobile trucks/ boats, item 1-15 will be 80%
of the rate of Railway Wagons.

Page 36
DESCRIPTION OF ITEM NO 25: Loading or unloading bitumen, asphalt or tar in
drums, into or from Railway Wagons lead upto
one chain.

Detail Unit Rate (British System) per Ton

Qty Rate
Per Unit (Rs.) Amount (Rs.)
Rate Analysis for 25 Ton
Labour

Unskilled Cooly 6.00 Nos 140.00 P. Day 840.00

Total 840.00
Sundries 10.00 Percent 84.00
Total 924.00

Contractor's Profit & Overheads 20.00 Percent 184.80


Total 1,108.80

Item Rates

Labour Rate Per Ton Rs. 44.35 Say 44.35


Labour Rate Per Tonne Rs. 43.65 Say 43.65

Page 37