RENCANA ANGGARAN PENDAPATAN DAN BIAYA OPERASIONAL

I. PENDAPATAN :
NILAI KONTRAK PENGURUGAN TANAH MERAH : 5.000.000 M3. x Rp. 72.000,- 72.000 5.000.000 = Rp. 360.000.000.000

II. BIAYA OPERASIONAL (PENGELUARAN PROYEK) :


A. BIAYA RITASE DUMP TRUCK DAN QUARRY :
1 DUMP TRUCK :
SEWA : 135 UNIT x Rp. 30.000.000,- x 11 BULAN = Rp. 44.550.000.000
BBM : 20 LTR/TRIP x 250.000 TRIP x Rp. 6.000,- = Rp. 30.000.000.000
SUPIR : Rp. 250.000,-/HARI x 334 HARI x 135 UNIT = Rp. 11.272.500.000
= Rp. 85.822.500.000
2 EXCAVATOR :
SEWA : 10 UNIT x 3.340 JAM x Rp. 140.000,- / JAM = Rp. 4.676.000.000
BBM : 20 LTR x 3.340 JAM x 10 UNIT x Rp. 6.000,- = Rp. 4.008.000.000
OPERATOR : Rp. 250.000,-/HARI x 334 HARI x 10 UNIT = Rp. 835.000.000
= Rp. 9.519.000.000
3 PEMBELIAN TANAH MERAH :
: 250.000 DUMP (RIT) x Rp. 125.000,-/DUMP = Rp. 31.250.000.000
JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY : = Rp. 126.591.500.000

B. BIAYA PEMADATAN :
1 SEWA ALAT :
- BULDOZER D6 : 6 UNIT x 3.340 JAM x Rp. 135.000,-/JAM = Rp. 2.705.400.000
- COMPACTOR/VIBRO R. : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911.820.000
- MOTOR GRADER : 3 UNIT x 2.338 JAM x Rp. 130.000,-/JAM = Rp. 911.820.000
- SHEEP FOOT ROLLER : 1 UNIT x 500 JAM x Rp. 135.000,-/JAM = Rp. 67.500.000
- TRUK TANGKI AIR : 2 UNIT x Rp. 20.000.000,- x 11 BULAN = Rp. 440.000.000
= Rp. 5.036.540.000
2 BBM ALAT :
- BULDOZER D6 : 20 LTR x 3.340 JAM x 6 UNIT x Rp. 6.000,- = Rp. 2.404.800.000
- COMPACTOR/VIBRO R. : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631.260.000
- MOTOR GRADER : 15 LTR x 2.338 JAM x 3 UNIT x Rp. 6.000,- = Rp. 631.260.000
- SHEEP FOOT ROLLER : 15 LTR x 500 JAM x 1 UNIT x Rp. 6.000,- = Rp. 45.000.000
- TRUK TANGKI AIR : 80 LTR x 334 HARI x 2 UNIT x Rp. 6.000,- = Rp. 320.640.000
= Rp. 4.032.960.000
3 OPERATOR ALAT :
- BULDOZER D6 : Rp. 250.000,-/HARI x 334 HARI x 6 UNIT = Rp. 501.000.000
- COMPACTOR/VIBRO R. : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168.000.000
- MOTOR GRADER : Rp. 250.000,-/HARI x 224 HARI x 3 UNIT = Rp. 168.000.000
- SHEEP FOOT ROLLER : Rp. 250.000,-/HARI x 50 HARI x 1 UNIT = Rp. 12.500.000
- TRUK TANGKI AIR : Rp. 250.000,-/HARI x 334 HARI x 2 UNIT = Rp. 167.000.000
= Rp. 1.016.500.000
JUMLAH BIAYA PEMADATAN : = Rp. 10.086.000.000

C. BIAYA PEMOTONGAN DARI MAIN KONTRAKTOR :


UNTUK BIAYA PPH PAJAK KONSTRUKSI DAN BIAYA ADMINISTRASI : 5.000.000 M3. x Rp. 12.000,-/M3. = Rp. 60.000.000.000

D. BIAYA PERSIAPAN / PENDAHULUAN PROYEK :


1 BIAYA BIKIN DIREKSI KIT / SITE OFFICE = Rp. 75.000.000
2 BIAYA MOBILISASI DAN DEMOBILISASI PERALATAN & PERSONIL = Rp. 230.000.000
3 BIAYA PENGUKURAN LEVELING TANAH DASAR = Rp. 100.000.000
4 BIAYA BIKIN JALAN AKSES DARI QUARRY KE JALAN UMUM = Rp. 3.500.000.000
5 BIAYA PEMATANGAN LAHAN SEPANJANG LOKASI KERJA = Rp. 2.750.000.000
6 BIAYA OVERHEAD PROYEK, BIAYA COMMISIONING TEST PEMADATAN DAN BIAYA TAK TERDUGA LAINNYA
= Rp. 3.345.000.000
JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK : = Rp. 10.000.000.000

REKAPITULASI :

PENDAPATAN : = Rp. 360.000.000.000

BIAYA OPERASIONAL (PENGELUARAN PROYEK) :


A. JUMLAH BIAYA RITASE DUMP TRUCK DAN QUARRY = Rp. 126.591.500.000
B. JUMLAH BIAYA PEMADATAN = Rp. 10.086.000.000
C. JUMLAH PEMOTONGAN OLEH MAIN KONTRAKTOR = Rp. 60.000.000.000
D. JUMLAH BIAYA PERSIAPAN / PENDAHULUAN PROYEK = Rp. 10.000.000.000
= Rp. 206.677.500.000
KEUNTUNGAN KOTOR PROYEK : = Rp. 153.322.500.000

NOTE : BELUM TERMASUK FEE SUKSES UNTUK PIHAK MEDIASI.-

CILEGON, 12 DESEMBER 2009.