CRU Computer Rentals

Sanjay Jharkharia

1
Sanjay Jharkharia, IIMK 1
A Review of Case Facts

2
Sanjay Jharkharia, IIMK 2
Case: CRU Computer Rentals
Flow Chart
Status 40
30%
Ship Receiving Repairs
70%

Status 24 15%
Parts
places
Status 41
order
Customer Pre-Config
Receives
from
Supplier
Status 32

Ship Config Repairs


Status 20 Status 42
Sanjay Jharkharia 3

3
Sanjay Jharkharia, IIMK 3
Case: Process Flow Diagram (1996 Situation)
Status 40
30%
Ship Receiving Repairs
500 1000
70%

Status 24 15% 500 Parts


1500 places
Parts order
Demand:
Status 41
Customer 1000 / week Pre-Config
T: 8 weeks T=1 week Receives
from
Supplier Supplier

Status 32

Ship Config Repairs


2000 500
Status 20 Status 42
Sanjay Jharkharia 4

4
Sanjay Jharkharia, IIMK 4
Decision Options
Continue with reduce demand of 600 units per week and dispose off
the extra units
Have a sales drive to increase the demand to 1400 units per week

Sanjay Jharkharia 5

5
Sanjay Jharkharia, IIMK 5
CRU Situation in 1996
Customer term 8Wk, Demand 1000 Units/Wk

Customer Receiving Status Status Status Status Status


24 40 41 42 20

Throughput 1,000 1,000 700 300+10 405 405 1,000


(units/week) 5=405

Inventory 8,000 500 1,500 1,000 500+40 500 2,000


(units) 5=905

Flow time 8.0 0.5 2.14 2.47 2.23 1.23 2


(weeks)

Sanjay Jharkharia 6

6
Sanjay Jharkharia, IIMK 6
CRU Situation in 1996:
Financial Performance
Number of units on rent = 8,000
Total number of units = 14,405
Utilization = 0.56 (56%)
Revenue rate = 8,000 x 30 = $240,000/wk
Variable Cost rate = 25 x 1,000 (R) + 25 x 1,000 (S)
+ 4x700x.85 + 150 x 405 = $113,130/wk
Contribution Margin (Revenue-Cost) = $126,870/wk
Depreciation = 14,405 x ($1000/156wks) =
$92,340/wk
Profit = $34,530/wk
Sanjay Jharkharia 7

7
Sanjay Jharkharia, IIMK 7
CRU Situation in 1997
Buffer sizes Unchanged, Demand =1400 Units/Wk

Custom Receivi Status Status Status Status Status


er ng 24 40 41 42 20

Throughput 1,400 1,400 980 567 567 567 1,400


(units/week)

Inventory 8,000 500 1,500 1,000 905 500 2,800


(units)

Flow time 5.7 0.36 1.53 1.76 1.60 0.88 2


(weeks)

8
Sanjay Jharkharia, IIMK 8
CRU Situation in 1997: Financials
Buffer Sizes Unchanged, Demand = 1400 Units/Wk

Number of units on rent = 8,000


Total number of units = 15,205
Utilization = 0.53 (53%)
Revenue = 4,800 x 30 + 3,200 x 35 = $256,000/wk
Cost = 25 x 1,400 (R) + 25 x 1,400 (S) + 4x980 x .85
+ 150 x 567 = $158,382/wk
Contribution Margin = $97,618/wk
Depreciation = 15,205 x (1000/156) = $97,468/wk
Profit = $150/wk

Sanjay Jharkharia 9

9
Sanjay Jharkharia, IIMK 9
CRU Situation in 1997
Flow times Unchanged, Demand =1400 Units/Wk

Customer Receiving Status Status Status Status Status


24 40 41 42 20

Throughput 1,400 1,400 980 567 567 567 1,400


(units/week)

Inventory 8,000 700 2,100 1,400 1,267 700 2,800


(units)

Flow time 5.7 0.5 2.14 2.47 2.23 1.23 2


(weeks)

Sanjay Jharkharia 10

10
Sanjay Jharkharia, IIMK 10
CRU Situation in 1997:
Flow Times Unchanged, Demand = 1400 Units/Wk

Number of units on rent = 8,000


Total number of units = 16,967
Utilization = 0.47 (47%)
Revenue = 4,800 x 30 + 3,200 x 35 = $256,000/wk
Cost = 25 x 1,400 (R) + 25 x 1,400 (S) + 4 x 980x .85
+ 150 x 567 = $158,382/wk
Contribution Margin= $97,618/wk
Depreciation = 16,967 x (1000/156) = $108,763/wk
Profit = -($11,145/wk) i.e. loss

Sanjay Jharkharia 11

11
Sanjay Jharkharia, IIMK 11
CRU Potential Situation in 1997
Without sales drive and flow times unchanged, Demand of
600 Units/Wk

Customer Receiving Status Status Status Status Status


24 40 41 42 20

Throughput
(units/week)

Inventory
(units)

Flow time
(weeks)

Sanjay Jharkharia 12

12
Sanjay Jharkharia, IIMK 12
CRU Potential situation in 1997: Complete it

Without sales drive, Demand = 600 Units/Wk.


Number of units on rent =
Total number of units =
Utilization =
Revenue =
Cost
Contribution Margin =
Depreciation =
Profit =

Sanjay Jharkharia 13

13
Sanjay Jharkharia, IIMK 13
What to do now?
Continue with the reduced demand of 600 units per week and
dispose off the extra units
Have a sales drive to increase the demand to 1400 units per week

Sanjay Jharkharia 14

14
Sanjay Jharkharia, IIMK 14
Assignment

Solve the questions as given at the end of the case


especially Q. # 6.

Sanjay Jharkharia 15

15
Sanjay Jharkharia, IIMK 15