Bill Of Quantities
Name of Road :Dipeni khola culvert Contract Notice No. : 10/071/72
Name of work : Slab Culvert Construction Contract No.: DRODMK/3371574/071-72/076

S.N. Description of Works Unit Quantity Rate/Unit Rate per unit in words Amount Remarks

1 General Works
Insurance for the loss of damage to works,plant,
1.1 material, equipment,property and personnel injury or LS 1.00 -
death.
Diversion of Traffic ,Traffic control and safety
measures as specificied (Flagmen, Traffic Signs,
Diversion etc. ) including construction and
1.2
maintenance of diversion road as directed by the
LS 1.00 -
Engineer during and after construction at three
place.
2 Slab Culvert Construction Work
Dismantling Bridge, culvert and other
structures including stockpiling the reusable
materials and diposal of usable materials
2.1 m3 224.50 -
within 50 m lead for
(a) Plain cement concrete, 1:4:8 or leaner mix

Earthwork in excavation for foundation for


2.2 m3 51.46 -
the abutment pier and wing wall in all type of
soil including
Providing cofferdam
,laying construction,
and levelling river
of dry stone
2.3 m3 45.85 -
soling all complete(SS 905)
Bill Of Quantities
Name of Road :Dipeni khola culvert Contract Notice No. : 10/071/72
Name of work : Slab Culvert Construction Contract No.: DRODMK/3371574/071-72/076

S.N. Description of Works Unit Quantity Rate/Unit Rate per unit in words Amount Remarks

Providing and placing cement concrete for the


foundation and footing etc.including 3
2.4 m 55.64 -
compaction, curing, testing and lead. etc.all
complete as per specification and drawing. ii)
M15/40
Providing(SS 2000)
and placing cement concrete for the
super structure, deck slab, girder etc.including
compaction, curing, testing and lead .etc. all
2.5 m3 34.46 -
complete as per specification & standard
drawing. i) M 25/20 (SS 2000)

Providing, preparing and installing form work


including necessary supports and removing
2.6 after completion for walls & vertical surface of m2 288.68 -
slab and beam.(SS 1804, SS 1805)

Providing, preparing and installing form work


for slab structure including staging ( false
2.7 work) and removing after completion all m2 40.80 -
complete (SS 1804, SS 1805)

Providing & Laying Tar felt (double fold) on


2.8 m2 10.20 -
abutement caps
Providing and laying Reinforcement including
cutting, bending, binding, fixing in position etc.
2.9 all complete as per specification and standard Kg 2256.81 -
drawing. (SS 2000)
Bill Of Quantities
Name of Road :Dipeni khola culvert Contract Notice No. : 10/071/72
Name of work : Slab Culvert Construction Contract No.: DRODMK/3371574/071-72/076

S.N. Description of Works Unit Quantity Rate/Unit Rate per unit in words Amount Remarks

Providing and placing plum-concrete with 70%


M 15/40 concrete and 30% boulders/stones as
2.10 per specification. Lead 30m, lift 1.5m using m3 118.86 -
concrete mixer and vibrator.

Providing and laying random rubble masonry


in 1:4 cement - sand mortar including
2.11 preparation of mortar, curing, testing etc.all m3 91.78 -
complete as per specification. (SS 2602, SS
2603)
Bill Of Quantities
Name of Road :Dipeni khola culvert Contract Notice No. : 10/071/72
Name of work : Slab Culvert Construction Contract No.: DRODMK/3371574/071-72/076

S.N. Description of Works Unit Quantity Rate/Unit Rate per unit in words Amount Remarks

Back filling in layers with filter material


3
2.12 including compaction and watering etc.all m 14.60 -
complete (SS 908)
Back filling in layers in foundation pits,
trenches, etc, with common material including
2.13 m3 900.00 -
compaction and watering etc.all complete (SS
908)
Providing supplying and installation of 50mm
2.14 dai GI pipes for railings Rm 48.00 -
laying, heavy zinc coated GI mesh wire
10SWG, Selvedge wire 8SWG & Binding wire
2.15 12SWG,fabricating boxes in hexagonal mesh m3 95.00 -
size 100mmx120mm, supply & filling stones,
lying lids all complete works [2400]
Providing, laying, spreading, watering, levelling
and compaction of natural sand gravel subbase
2.16 grading as per table 12.1 of standard m3 270.00 -
specification lead upto 10m
Proving and laying RCC pipes of diameter 600 mm
(internal) with or without collars jointed with stiff mixture of
2.17 cement mortar in the proportion of
RM 7.50 -
1 : 2 ( 1 cement : 2 fine sand ) , lead upto 100m.
Total -
Grand Total With VAT (in words NRs.)
Authorized Signature Of the Bidder Seal of the Bidder
Name of firm:
Name: Designation: Date:
Notes : 1 The numbers enclosed in the bracket in the particulars represent DOR Standard Specifications Section Number.
2 Rates quoted are considered exclusive of VAT
3 Rates shall include all costs incurred for testing as per Standard Specification and QAP.