Escolar Documentos
Profissional Documentos
Cultura Documentos
: CPRI/ECDD/ EA/76/10
Report
Submitted to
on
ENERGY AUDIT AT JOJOBERA TPS UNIT 3, 120 MW
(Po No 5300076114 )
Submitted by
DECEMBER 2010
Project Summary
07 Contact Person (project M. Siddhartha Bhatt, Additional Director (EC & DD)
implementing agency): Central Power Research Institute,
P.B. No. 8066, Sir C.V.Raman Road,
Sadashivanagar Sub-P.O.,
Bangalore-560080
Tel: 080-23604682, 23604736
FAX: 080-23604682/23601213
E-mail:msb@cpri.in; msbhatt1@yahoo.co. in
10 Scope of work: 1: To assess the achievable station heat rate and improvements
1
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
12 Power station:
Jojobera TPS, Tata Power Jamshedpur
2
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
EXECUTIVE SUMMARY
This study presents the results of the tests on major equipment (boiler, turbine,
generator, heat exchangers, condenser, auxiliaries, etc.) of Unit No. 3 at TPC-G,
Jojobera.
The gross overall efficiency of the Unit 3 TG set is 33.4 % against the design
efficiency of 38.2 %. The gross overall TG heat rate (TG HR) is 2577.1 kcal/kWh
at the test load of 100 % and representative GCV as compared to the design heat
rate of 2253.7 kcal/kWh. The TG heat rate considers the boiler, turbine and
generator efficiencies. The deviation in the test TG heat rate from the design value is
as follows:
Unit 3
Test UHR 2577.07 kcal/kWh
DHR 2253.7 kcal/kWh
Dev due to Boiler 48.1 kcal/kWh
Dev due to Turbine 274.8 kcal/kWh
Dev due to Generator 0.5 kcal/kWh
Test efficiency 33.4 %
Design efficiency 38.2 %
Overall difference 4.8 %
Overall difference 323.4 kcal/kWh
The deviation in the test TG heat rate is 323.4 kcal/kWh which can be attributed to
48.1 kcal/kWh due to the boiler, 274.8 due to the turbine and 0.5 kcal/kWh due to
the generator. Hence the turbine is the component leading to maximum losses.
Unit 3
Test UHR 2577.07 kcal/kWh
Test Efficiency 33.4 %
HR-Seasonal dev 0 kcal/kWh
HR-Cycling dev 26.00 kcal/kWh
HR-Dev DM 29.49 kcal/kWh
HR-Dev-rejects 8.04 kcal/kWh
HR-Dev-MS& RH pipe 2.7 kcal/kWh
Annual unit HR 2643.3 kcal/kWh
Annual Efficiency 32.5 %
3
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The annual unit heat rate (UHR) of the unit considering all factors such as load
factor, DM water make up to account for steam for non-motive applications, rejects,
energy consumption in hot, warm and cold starts; seasonal variations is 2643.3
kcal/kWh for Unit 3. Since during the test coal of representative GCV is fired, the
heat rate also accounts for quality of coal fired. Hence the UHR adequately
represents the annual heat consumption in the unit.
Medium term measures include smart soot blowing system, VFDs for pumps and
fans, heat recovery devices and heaters; energy efficient BFPs, CEPs and CWPs, etc..
Long term measures include IP & LP turbine retrofits & up gradation of DCS.
The suggested measures for energy efficiency are given under the summary of
recommendations. The recommendations have been classified under immediate,
medium and long term measures based on their investment criteria and time period
required for implementation.
4
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
SUMMARY OF RECOMMENDATIONS
Immediate term measures
5
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
6
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
7
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
8
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
SUMMARY OF RECOMMENDATIONS
Medium term measures
Sl. Anticipated Anticipated Time Pay
No Recommendations reduction in investment, frame for back
. heat rate, Rs. (lakhs) implement period,
kcal/kWh* ation, months
months +
01 Energy efficient BFP Process 100 12
cartridges improvement
02 Energy efficient CEPs and Process 200 8
CWPs improvement
03 Improvements in the mills: Process 40 6
Strain gauge under the improvement
bearing supports for on-line
weight of the mill; dynamic
classifier; noise level
monitoring; steam supply
system for quenching; coal
mill performance evaluation
one in a month using
isokinetic sampler.
04 Smart soot blower Process 100 12
system. improvement
Total 10 440 - 52
*As compared to present test annual UHR
+ Benefits of life extension also.
9
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
SUMMARY OF RECOMMENDATIONS
10
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
CONTENT (Volume 1)
Page
Nos.
1.0 INTRODUCTION 1
1.1 Energy audit
1.2 Scope of the energy audit
1.3 Period of the experimental work
1.4 Design rating of major equipment
1.5 Age and service period
1.6 Current level of performance measured
2.0 BOILERS AND ASSOCIATED EQUIPMENT 4
2.1 Coal analysis and boiler efficiency tests
2.2 Boiler Temperature & pressure survey
2.3 Boiler and Associated Systems-Component wise analysis
of Performance; equipment assessment for damage,
restriction, de-rating and loss
3.0 TURBINE GENERATOR 13
3.1 Turbine Efficiency Tests
3.2 Turbine Temperature and pressure survey
3.3 Turbine & associated systemsComponent wise analysis
of performance; equipment assessment for damage,
restriction, de-rating and loss
4.0 CONDENSER & COOLING TOWER-ANALYSIS OF PERFORMANCE 17
5.0 STEAM AUDIT AND STEAM UTILIZATION SYSTEM- ANALYSIS OF 18
PERFORMANCE; EQUIPMENT ASSESSMENT FOR DAMAGE,
RESTRICTION, DE-RATING AND LOSS
6.0 CAPACITY ADEQUACY ANALYSIS OF AUXILIARY EQUIPMENTS 19
7.0 FORCED OUTAGE & START UP ANALYSIS 19
8.0 OPERATION & MAINTENANCE PRACTICES 20
8.1 Operational practices
8.2 Maintenance practices
8.2.1 Day to day maintenance
8.2.2 Annual and capital overhauls
9.0 OVERALL SYSTEM 28
9.1 Test heat rate at 100 % load
9.2 Heat consumption due to steam lost to non-motive
applications represented by DM make up
9.3 Heat consumption due to cycling/abnormal operation-
start up and shut down
11
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
12
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
13
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Abbreviations/Nomenclature
14
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
ID Inside diameter
IDF Induced draft fan
IED Intelligent electronic device
IP Intermediate pressure
IPT Intermediate pressure turbine
KPI Key performance indicators
LDO Light diesel oil
LE Life extension
LP Low pressure
LPT Low pressure turbine
LT Low tension (415 V)
Max. Maximum
MCCB Moulded case circuit breaker
MCR Maximum continuous rating of the unit
Min. Minimum
MIS Management information system
MOD Merit order dispatch
MS Main steam
NDT Non-destructive test
NF Natural frequency
NRV Non return valve
O&M Operation and maintenance
OD Outer diameter
OEM Original equipment manufacturer
p Pressure (kPa or MPa)
P Power output (MW)
PADO Performance analysis, diagnostics and optimization
PAF Primary air fan
PC Personal computer
PLF Plant load factor (%)
PT Potential transformers
R&M Renovation and modernization
RH Reheat
RLA Remaining life assessment
RR Railway receipt
SAIDI System average interruption duration index
SAIFI System average interruption frequency index
SEC Specific energy consumption (kWh/t)
SFC Specific coal consumption (kg/kWh = t/MWh)
SH Superheater
SHR Station heat rate ((kcal/kWh)
SOC Secondary specific fuel oil consumption (ml/kWh)
SPM Suspended particulate matter
SR Steaming rate (t of steam /t of coal)
SSC Specific steam consumption (kcal/kWh=t/MWh)
ST Station transformer
T Temperature (0C)
TDBFP Turbine driven boiler feed pump
15
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
16
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
1.0 INTRODUCTION
The objective of the study is the independent assessment of achievable
performance parameters for Tata Powers thermal power station (Unit No. 3) and
suggestions for its improvements. The overall study report is in two volumes:
Volume 1 covers Boilers, turbines, heat exchangers, etc., and overall systems
Volume 2 covers Unit & station auxiliaries and generator.
In this Volume the fuel systems and overall systems are discussed.
This section introduces the power plant and defines the scope of work.
The Tata Power Jojobera had established coal fired thermal power station of 67.5
MW (Unit 1) and 4 units of 120 MW. The present station capacity is 547.5 MW. Unit
3 is presently under study.
Unit 3 of 120 MW has multi-fuel firing capability and consists of BHEL corner fired
boilers with BHEL turbines supplied by BHEL.
1: To assess through tests of individual equipment, the achievable unit heat rate,
loadability, capacity adequacy and improvements in auxiliary consumption and
specific oil consumption
1
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The energy audit covers the major equipment, auxiliaries and includes fact finding,
assessment of equipment and loss levels, performance measurement, analysis,
suggestions for improvement of performance parameters over a period of time,
maintenance improvements, operational improvements & strategic planning. The
detailed scope of work is as per the PO No. 5300076114 dt 16.04.2010.
Sl. Unit
No. Particulars No. 3
01 Fuel type Coal
02 Unit capacity MW 120
03 Steam to fuel ratio t/t 4.31
04 SSC t/MWh 2.960
05 DHR Kcal/kWh 2253.47
Figures 1-6 (see Annex 1) give the monthly variation of the KPI for Unit 3 for the
past 3 years.
2
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Figures 7-11 (Annex 1) give the sensitivity of the KPI to PLF. It can be seen that
there is reasonable correlation with the data (R2=around 0.6). However, there is
opportunity to improve the quality of the data acquisition and measurement.
At preset, the bare machine variables and KPI data are available but the majority of
data is not available for energy control. The important KPI are presently being
analyzed on a daily, weekly and monthly basis.
Recommendation: The daily, weekly, monthly and annual averaging of KPI (UHR,
SOC, SFC, AP,etc.) as well as machine related parameters must be made on EXCEL
available for sharing with the O & M and management. The same must be made
available on EXCEL sheet for analysis and in graphical form for trend analysis.
At present efficiency and performance tests are not being done in the units as a part
of the in-house energy efficiency program. This would give valuable data such as
3
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
effects of moisture and coal quality on the boiler efficiency, etc. Also efficiency tests
on boilers for different sources of coals are not presently available. Also efficiency
tests on boilers for different sources of coals are not available. Performance tests on
turbines, condenses, feed water heaters, generator, etc., and evaluation of AP are
not being practiced. Valuable information can be generated from these.
Detailed analysis of root causes for failures is being done to the extent required or
replacement and further operation. Detailed analysis of performance is done at a
macro level covering the KPI. At a micro level or parameter level, detailed root cause
analysis is not being done at present.
Failures
CPRI observations: The GCV of coal during the test is the representative coal
used by the TPS. The boiler has been tested in this coal condition.
4
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The results of the boiler efficiency are given in Table 11 (see Annex 2). The
measured boiler skin temperature is given in Table 12 (see Annex 2). The
performance of the tubular air pre-heaters are given in Table 13 (see Annex 2).
The observations and recommendations regarding the boiler performance are as
follows:
ii. O2 in flue gas is in the range of 3.72-4.96 % before APH and 5.15-8.98 %
after APH.
iii. The CO content measured in flue gas was 274-442 ppm. The measured CO is
on the higher side indicating incomplete combustion.
iv. Unburnt losses in bottom ash and fly ash are high. Unburnts in bottom ash is
5.6 % and 1.9 % in fly ash.
v. The wet flue gas loss is 4.81 % against the design value of 6.14 %.
vi. The maximum skin temperature is as high as 185 C which is high at certain
zones. Loss due to convection and radiation loss is 1.56 % compared to
design value of 1.21 %. The average overall surface temperature measured
is 72.7 C. The surface temperature should be 10 C above the ambient
temperature. Recommendation: The flexible insulation of the boiler needs
to be replaced at hot spots. Partial need based insulation replacement is
recommended.
5
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
05 Mill outlet
> 85 C while the operating values are in
temperature the range 88-96 C.
06 Secondary AirTo within 5 % of the mean value. SADC
balanced at
(secondary air damper control) must be on
wind boxes auto for the unit.
07 Furnace 2.5 % to 3.0 % and with less than 5 %
Oxygen leakage between Furnace Exit and
Economizer and less than 10 % leakage at
APH. O2 control in the furnace is in place.
The operating furnace O2 is 3.7-4.9 %.
08 Oxygen after < 4.2 % as per design and the operating
APH O2 is 5.6 %
09 Bottom ash < 4 % as per design and the operating
value is 0.1 to 0.2 %.
10 Fly ash < 1 % as per design and the operating
value is 1.9 %
11 Carbon < 100 ppm as per design and the operating
monoxide value is 272 ppm to 442 ppm.
Table 16 (Annex 2) gives the specific heating surfaces. The furnace volume is
undersized by 16 % for the present coal while the EPRS is OK. The SH is OK and
the RH is also OK. The ECO and APH are is also OK.
The performance of the economizer is given in Table 17 and the performance of the
water walls is given in Table 18.
6
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
ii. The performance of ECO is OK. The design flue gas velocity at ECO is
expected to be in the range of 8.5 to 9.5 m/s. Due to ash
accumulation and fouling, the velocities increase to nearly 12 m/s or
more resulting in enhanced erosion rates. To reduce erosion, close
monitoring of flue gas velocity is needed. Also suitably designed
cassette baffles of ceramic/steel with hard overlay may be introduced
for reduction of erosion. Recommendation: During a shut down,
before cleaning and clearing of the debris a clean air velocity test may
be conducted to confirm the velocity profile in the ECO in the running
condition. After clearing of all debris and fouling, the same may be
repeated and it may be ensured that the velocities are within 8.5 to 9.5
m/s. Gas velocity at the gap between the ECO coil bundle and the
boiler furnace wall must be minimized by frequent cleaning of debris.
Ceramic/hard coated steel cassette baffles may be introduced for
reduction of erosion. Material up gradation must also be considered.
Partial replacement of ECO coils is recommended.
iii. The APHs are tubular shell and tube type with two secondary APH and
one primary APH.
iv. Air leakage occurs in the APH because of the pressure difference
between the high pressure air and the low pressure exiting flue gases.
The air leaks into the flue gas stream and exits to the stack resulting in
energy loss of hot air, pressure loss of hot air and additional load on
the ID fan. The flue gas temperature at the APH outlet increases on
account of this besides resulting in reduced boiler efficiency and
increased auxiliary power to the fans. The LHS side leakage of
Secondary APH is 9.3 % and for RHS it is 21.3 % which is on the high
side, against the design value of 7.7 %. The leakage of primary APH is
19.8 % compared to the design value of 16.3 %. Air leakage in APH is
from two sources:
Punctured tubes at the centre of the nest
Punctured tubes at the sides (edge of the APH) and the boiler.
v. The erosive nature of Indian coals giving rise to wear and erosion of
high severity is also a cause for the tube punctures. Besides, the cold
end corrosion of heat exchanger materials leads to tubes being eaten
away due to the combined effects of wear and corrosion. APH leaks
reduce boiler efficiency by as much as 1 %. Recommendation: The
measures for the APH are as follows:
Clean air velocity tests to understand the air velocities in the
gap between the APH and boiler water wall surfaces.
Installation of ceramic cassette baffles for alteration of the flue
gas flow to avoid direct impingement on the tubes and
reduction of the flow velocities.
7
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
iii. Long term erosion is an effect for consideration in this boiler. The
main factors affecting erosion in the boiler are:
Flue gas velocity
Composition and percentage of mineral content
Changes in the flue gas direction
Arrangement of pressure parts
Flue gas temperatures
iv. The boiler efficiency is affected by some of the design parameters like:
Boiler volume
Gas temperature entering the first pendent at the goose neck
level.
Furnace exit gas temperature
Location and number of soot blowers
Burner input, clearance, mouth design and tilting mechanism
Heat input available at the primary combustion zone (burner
elevations).
In all the above design parameters, the boiler is satisfactory and
appropriate except for water wall under sizing for high ash coals.
8
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
vi. Flue gas temperature at boiler outlet (APH outlet) is dependent on:
Furnace heat absorption rate and slagging cum fouling
behavior
APH leakage (from air side to the flue gas side)
Excess air factor of the flue gas which is dependent on
gas tightness and air tightness in the boiler
APH effectiveness
Burner tilting mechanism and their response
Ambient air conditions
Fuel quality
vii. The high flue gas temperature at the boiler out can be controlled by:
Furnace cleaning through smart soot blower system
Water washing of APH during an outage
Optimizing of primary and secondary A/F ratios
viii. FEGT (furnace exit gas temperature) measurement and High quality
visible flame safe scanner system are already available and the
performance is good.
ix. The present soot blowing system is time based and open looped. This
can be converted into a closed loop system by installation of smart soot
blowing system or intelligent soot blowing system the heart of which is
the furnace cleanliness probe. This is nothing but a heat flux sensor
which gives a measure of the fouling through a deposition probe which
gives the degree of fouling or slagging and heat flux through a chordal
thermocouple which measures the furnace inner skin temperature.
Such heat flux sensors are incorporated in boiler water wall sections.
Based on the output of the sensors the soot blowing interval is decided
automatically through a logic based system incorporated into the plant
DCS. If the cleanliness value falls below a certain value it signals for a
soot blowing cycle. The benefits of the smart soot blowing system are
an increased level of furnace heat absorption (by around 10 %), a
lower exit flue gas temperature (around 10 C) and reduction in soot
blowing frequency and auxiliary steam (around 5 %) in the long term.
Recommendation: To maintain a high level of cleanliness in the
furnace, the present soot blower system needs to be converted into
smart soot blower system.
9
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Furnace and piping: Flow control and sealing: Ducts, dampers, valves,
wind box, etc.; supports and fixtures
ii. Recommendation: During overhaul all the gas flow guide vanes,
direction vanes, diversion baffles for flow diversions are to be inspected
and need to be replaced. Materials of diversion baffles must be alloy
steel with overlay of hard materials like silicon carbide or tungsten
carbide.
The observations regarding the coal and oil circuits are as follows:
ii. Recommendation: Retrofitting of fuel oil pump motor with VFD for
smooth control and invocation of oil guns.
10
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
ID fan capacity drop occurs due to wear and erosion of internals and results in
reduced efficiency as well. The damaged components are impeller, casing, scroll and
inlet damper. The options for improved performance are:
a. Brazed Tungsten Carbide cladding
b. Chrome Carbide weld overlay
c. Hard alloy steel
ii. The velocities of coal and flue gas also get altered due to high flow rates
which results in increased wear and erosion by 3 to 4 time (as erosion rate is
directly proportional to ~ v3). Change over to superior grade wear resistant
materials (medium alloy steels with hard weld overlays) is imminent. Control
of heat and air leaks is also equally important in system performance
restoration.
11
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Recommendations: For improving the mills, in the medium term, some additional
measures are:
Strain gauge under the bearing supports of the mill for on-line
weight of the mill to indicate the status of the loading of the mill. This
practice is used in International practices to know the level of loading rather
than other indirect parameters such as mill current and mill differential
pressure.
Monitoring of noise level inside the mill to assess the loading level
especially when the service air lines are choked. Sonic sound detection may
also be used for mills for mill condition monitoring.
12
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The condition assessment of steam generator components is given in Table 19. The
leakages in boilers are given in Table 20.
3.TURBINE- GENERATOR
The steam turbine is of the KWU (Siemens) design, three cylinder, throttle
governing, multi stage, reaction, tandem compound, single flow HP, double flow IP
and double flow LP with six uncontrolled extractions.
The results of the efficiency tests and heat rate of the turbines are presented in
Table 21. The loss of work in the turbines is given in Table 22.
ii. The turbine internal losses as indicated in Table 22 above are around 6.76
MWm. The total loss of work in the turbine is 7.12 MWm. These losses are
due to the turbine internals not converting the thermal energy in the
steam to mechanical work (turbine irreversibility) as per the design.
iii. Internal leaks in the turbine circuit result in loss of auxiliary power and
loss of work in steam. BFP recirculation valve passing of 10 t/h could lead
to loss of 75 kW. Similarly, SH, RH spray valves, HP vent valves passing
lead to losses.
iv. Sliding pressure operation: The provision is presently in use and may
be continued.
13
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
ii. The HRH temperatures are almost on par with the design. The HRH and
CRH pressures are lower the design by 0.8 MPa. The CRH temperature is
higher by 10 C.
iii. The LPT exit temperature is 55.7 C as compared to the design value of
46.4 C. The condenser vacuum is 12.0 kPa against the design value of 10.6
kPa. The cold end is optimized. However, the TTD across the condenser is
2.4 C against the design value of 3.4 C.
iv. Steam path audit: The deterioration in the operating heat rate is mainly
because of the steam turbine internal losses. The energy losses are in the
blading and steam paths of the turbine. Recommendation: During the
next capital overhaul steam path audit may be conducted to quantify
deterioration in heat rate at every stage of the turbine and for initiating
corrective action.
LPT and IPT retrofits: The earlier concept of R & M was generally thought of as
replacing highly stressed components and deformed members to increase the plant
availability and continue plant operation beyond the service life. In the light of the
above analysis, recommendations are given which are of replace philosophy. The
investment for this activity has its own justification that investment is relatively low
and keeps the system running in the present healthy and safe condition till a new
technology is infused enhancing the efficiency as well as health and life.
14
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Recommendation for turbines: Considering the above facts the present steam
turbine IP & LP cylinders may be replaced with standard 3-d stage specific bladed
turbines with 3-d modeled exhaust diffuser, improved tip to tip sealing, modified
exhaust hood spray and a turbine supervisory system. The standard added features
of the retrofitted turbines are as follows:
The expected life of the turbine is 15 years or 100,000 hours. The time for
replacement of the turbine is around 3 months. The efficiency is expected to
result in reduction in heat rate by around 10 kcal/kWh for IPT and 10 kcal/kWh
for the LPT for identical inlet conditions and exhaust condition.
Feed Heaters, turbine side lines, valves, pumps and heat exchangers
The performance of the feed water is indicated in Table 25 (see Annex 2).
ii. The TTD of HPH-5 is 11.7 C against the design value of 1.4 C. Higher TTD
indicates poor heat transfer. Recommendation: Cleaning of tube nest of HPH 6
to improve the performance.
iii. The TTD across LP heater 3 is -3.0 C against design value of 3.7 C. This gives
good performance of the heater but indicates that the energy conversion in the
steam turbine LP module is not as per the design.
iv. The TTD across LP heater 2 is -6.8 C against the design value of 12.2 C. This
indicates that the extraction steam is entering at a higher degree of superheat
than the design value. This again points out the poor performance of the turbine.
The reasons for the sub-optimal performance of HP feed water heaters are:
Air blanketing and improper venting in HP heaters due to isolation of vent air
line
Air blanketing and improper venting in LP heaters at sub-atmospheric
pressure
15
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Steam side contamination due to presence of oxygen above 100 ppb resulting
in exfoliation of tube material in the formation of scale layer.
iii. Deaerator: The deaerator temperature and pressure are below their design
values and boiling is affected because of feed being sub-cooled.
Recommendation: Oxygen measurement must be introduced in the
deaerator.
vi. BFP Lube oil cooler & BFP scoop oil cooler: These are shell and type
heat exchangers and operation is normal.
16
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Cooling tower - 3
Cooling tower is of counter flow with 4 cells. During study period all the 4 fans
were in service. Table 28 gives the performance of cooling towers.
Recommendation:
17
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The auxiliary steam is taken from the CRH line through auxiliary steam station after
pressure reduction and de-superheating.
The DM water consumption is normally designed at 1-3 % of the main steam flow
and the operating values are normally supposed to be in the range of 1-3 %. In this
unit the DM make up is well within limits.
18
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The capacity adequacy analysis was carried out for each of the major HT auxiliary
equipments. The Load factor of the auxiliary motor at 99.28 % MCR (test load) are
worked out and given in Table 29 (see Annex 2).
It can be seen from the Table that at the operating unit load of 100 % PL of the
unit, the auxiliaries CEPs pose capacity limitation as these are getting loaded to
almost 95 % of their power rating. At 100 % MCR , i.e., 120 MW, in the case of CE
pumps there is capacity limitation of 10 % and there are no margins. There is no
capacity limitation on any other auxiliaries.
The tripping reports for the Unit for the past 2 years is given in Annex 4:A4-1.
BTL: 0-1/year
19
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
No of trippings/year: 6/year
The number of forced outages are showing a decreasing trend from over 8
outages/year to 5/year over the years.
It is seen that the average time taken for hot warm and cold starts is as follows:
i. Run the unit as close to the design parameters as possible. The heat
rate will be minimum when the unit parameter deviation is minimum.
For every deviation of operating parameter there will be increase in
heat rate. Focus areas are O2 in flue gas and mill fineness.
ii. The operation criterion is based on running of the unit. The unit is
automated to a good extent to enable efficient operation. With the aid
of a few operator aids for start up and optimal operation the unit can
perform efficiently.
iii. The operation must consider the various inputs from Performance
optimization group and Chemists for process optimization.
20
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
vi. Maintaining 100 % availability of all feed water heaters and heat
recovery condensers.
vii. All OEM manuals must be thoroughly studied and donts must be
carefully understood and observed. This will avoid long term damage to
asset equipment and irreversible degradation of heat rate which will be
costly to reverse.
viii. Keep target parameters and maintain un-burnts in bottom ash and un-
burnts in fly ash, make up water %, etc., within limits. The combustion
limits are as follows:
o Bottom ash limits 4 %,
o Fly ash < 1 %.
o Optimal CO: 100 ppm
The TPC-G has installed SAP ERP package for their material management, preventive
maintenance, finance and HR activities.
Operational aids:
21
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
22
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
operational capture, documentation and transfer among the operators. The areas of
knowledge capture in operations are as follows:
23
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
ii. Valves: In-between two overhauls, boiler and turbine side valves some
times develop gland leaks or stem leaks.
8.2.2 Annual and capital overhauls
The Unit which has undergone 9 years of service has undergone 7 annual overhaul
(AOH) and 2 capital overhauls (COH) against their designated 7 AOH and 2 COH.
Overhauls are a part of the asset management process and their optimization is
required. The general practice is to go in for AOH every year for a period of 24-26
days and COH once in four years. Other patterns of overhauls are also being
followed such as a long AOH once bi-annually, or short AOH once every 8 moths,
etc. Normally, overhauls must be scheduled and done as per schedules and must
not be delayed by over 2 months. The maintenance planning must be oriented to
achieve the COH & AOH as per schedule. Recommendation: The overhaul pattern
may be reviewed and the optimal pattern may be established as there is scope for
further optimization. The overhauls must be so organized that the asset
management is optimized (asset value is preserved) and the TPS gets maximum
benefit in terms of restoration of UHR from the overhaul and also prevention of
leaks and damage in-between overhauls.
The major works undertaken during the COH are the overhauling of the turbine
modules and partial replacement of pressure parts like ECO, LTSH, water wall tubes,
etc.
24
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
25
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
26
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
27
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Step 3: Presently the condition monitoring group is entering the scene only when
high level of vibrations are sensed in any auxiliary such as ID fan, cooling water
pump, PA fan, etc. Recommendation: It is recommended to have a round the
clock condition monitoring group with the job responsibility of monitoring the
condition of equipment like vibrations, temperature rise, leakage levels, oil depletion,
loss of lubricant, leakage, etc., and recommend to the Maintenance Sections which
equipment needs to be attended to and give advance warning of the path to failure
well before it happens.
9. OVERALL SYSTEM
9.1 Test heat rate at 100 % load
The gross and net overall parameters are given in Tables 31 (Annex 2). The
deviation in efficiency and heat rate from design is given in Table 32 & 33.
28
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The basis for computing the difference in heat rate is by keeping all variables at their
design value and varying only the variable accounting for the increase in heat rate.
By this process simulation the difference in heat rate is arrived at.
Unit 3
Test UHR 2577.07 kcal/kWh
DHR 2253.7 kcal/kWh
Dev due to Boiler 48.1 kcal/kWh
Dev due to Turbine 274.8 kcal/kWh
Dev due to Generator 0.5 kcal/kWh
Test efficiency 33.4 %
Design efficiency 38.2 %
Overall difference 4.8 %
Overall difference 323.4 kcal/kWh
i. The overall design gross efficiency is 38.2 % and the overall operating
gross efficiency is 33.4 % at 100 % MCR.
ii. The design TG heat rate is 2253.71 kcal/kWh. The operating TG heat
rate (test) is 2577.10 kcal/kWh at the tested load of 100 % MCR.
iii. The deviation of the design TG heat rate from the operating Test TG heat
rate is 323.4 kcal/kWh which is attributed to 48.1 kcal/kWh due to boiler,
274.8 kcal/kWh due to turbine and 0.5 kcal/kWh due to the generator.
Thus, boiler is the equipment with maximum deviations.
This heat loss is represented by the DM water make up which represents the steam
lost from the process. Normal DM water make up is around 3 % of the main steam
flow.
The annual heat consumption for DM water make up (Q) in Mcal/h, is given by,
Q (Mcal/h) = {10-3[DM water make up (%) * Main steam flow at 100 % load
(kg/h)*(hsteam-hwater) (kcal/kg)/(boiler efficiency=0.86)] }
29
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The heat rate component due to cycling and abnormal operations is given by,
This heat consumption can be computed based on the number of hot, warm and
cold starts.
The heat consumption (Mcal) for any type of start as a function of the average
resource (coal, fuel oil and DM water) consumption (averaged over an year) for that
start is given by:
The annual heat consumption for cycling operations (Qc) in Mcal/year, is given by,
Q (Mcal/year) = {[Qhot start (Mcal) x number of hot starts/year]+ [Qwarm start (Mcal) x
number of warm starts/year]+ [Qcold start (Mcal) x number of cold starts/year]}
The annual energy generated (considering 100 % PLF) (E) in MWh is given by,
The heat rate component due to cycling and abnormal operations is given by,
This is the algebraic sum of the difference between the test heat rate of the station
in the month of CPRI test and the individual test heat rates or every month over the
year. In case, in the month of test, the heat rate is the highest or higher than the
standard deviation, seasonal variation is taken as zero.
30
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Test heat rate based on actual performance test under conditions of zero
make up and zero auxiliary steam consumption.
Energy components to account for reject coal at the mill. This is because the
coal entering the bunker is considered as entering coal and GCV of the
bunkered coal is taken. The component due to mill ejects is to be subtracted.
The unit heat consumption is computed considering all the above which portrays
the realistic heat consumption vis--vis the energy generated.
The heat rate credit is added algebraically to the unit heat rate in computing the
annual unit rate assessment.
31
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The annual heat rate therefore considers the seasonal variations, the cycling heat
requirements (due to hot/warm/cold starts), the energy components in rejects and
the heat lost in MS & RH piping. The basic data on DM water, rejects, resource
consumption in various types of starts, heat losses in piping between boiler and
turbine and calculations of the heat rate component based on these are given in
Annex 3 in the form or reproduction of the original EXCEL sheets.
Unit 3
Test UHR 2577.07 kcal/kWh
Test Efficiency 33.4 %
HR-Seasonal dev 0 kcal/kWh
HR-Cycling dev 26.00 kcal/kWh
HR-Dev DM 29.49 kcal/kWh
HR-Dev-rejects 8.04 kcal/kWh
HR-Dev-MS& RH pipe 2.7 kcal/kWh
Annual unit HR 2643.3 kcal/kWh
Annual Efficiency 32.5 %
ii. The loss due to rejects is also within limits as rejects are only 0.2 % of
the total coal and well within the 1 % limit. Hence no further
optimization is possible on this count.
iii. The loss due to DM make up is also well within limits. The DM make up
is 1.0 % of the MS flow and much lower than the limit of 3 % and
hence no further optimization is possible.
32
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
iv. Maintaining 100 % availability of all feed water heaters and heat recovery
condensers.
v. Cleaning of feed water heat tube nests and heat exchangers; and
replacement of self cleaning strainers.
vi. Modification of ID fan blading with aerodynamic profile and with hard weld
overlays.
The immediately achievable TG heat rate reduction for this unit is 10 kcal/kWh.
9.8.2 Medium term heat rate improvement (over 2-3 year period)
i. Furnace exit gas temperature and CCTVs for boiler firing elevation
viewing from the control room.
The TG heat rate reduction achievable under medium term scenario for this unit is
10 kcal/kWh.
9.8.3 Long term heat rate improvement (over 5 year period and further)
In the long term scenario of 5 years and over future the heat rate can be brought
down through extensive R & M of the units. The major replacements already done
and proposed are given above under the section on major replacements done and
proposed.
33
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
The major R & M works envisaged for long term improvement are as follows:
iii. Up gradation of the existing DCS with additional capacity of data storage,
engineering station, work station and data highway including FSSS, alarms
and MIS.
It is mentioned here that since long term measures are cost intensive, all easier
avenues of operational optimization, good housekeeping and wastage reduction
must be used to the optimal extent.
The TG heat rate reduction achievable under long term scenario for this unit is 25
kcal/kWh.
The comparative chart of the degradation of the UHR with the commercial heat rate
as declared by the TPS is as follows:
34
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Comparison of CPRI TG test HR as per std degradation rates and actual values
The degradation of the station commercially declared UHR is 17.50 % over design
UHR. The degradation rate is 1.75 %/year which works out to 39.43 kcal/kWh per
year.
35
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
Experimental test annual UHR (snap shot test UHR + factors to account for annual
effects) + [degradation rate based on 0.4 %/year of DHR] + [improvements due to
short term, medium term and long term measures]
2680
2650
Annual UHR
(kcal/kWh)
2620
-coal
2590
2560
TPC-G achieved
2530 Test UHR + degradation
Test UHR+ degradation+improvements
2500
2006 2008 2010 2012 2014 2016 2018
FY
36
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
10.CONCLUSIONS
The main conclusions of the study are as follows:
i. The gross overall efficiency of the Unit 3 TG set is 33.4 % against the
design efficiency of 38.2 %. The gross overall TG heat rate (TG HR) is
2577.1 kcal/kWh at the test load of 100 % as compared to the design
heat rate of 2253.7 kcal/kWh.
ii. The deviation in the test TG heat rate is 323.4 kcal/kWh which can be
attributed to 48.1 kcal/kWh due to the boiler, 274.8 due to the turbine and
0.5 kcal/kWh due to the generator. Hence the turbine is the component
leading to maximum losses.
iii. The annual unit heat rate (UHR) considering all factors such as PLF, DM
make up, rejects, energy consumption in starts, etc. is 2643.3 kcal/kWh for
Unit 3. This annual UHR represents the annual heat consumption of the unit
considering all annual realistic factors.
vi. Long term measures include waste heat recovery boiler, IP & LP turbine
retrofits with 3-d blading & up gradation of DCS.
vii. The investment in immediate, medium term and long term measures works
out to Rs. 562, 440 & 3600 lakhs respectively. The total cost is Rs. 0.38
crores/MW.
viii. The degradation of the station commercially declared UHR is 17.50 % over
design UHR. The degradation rate is 1.75 %/year which works out to 39.43
kcal/kWh per year.
ix. Trajectories of unit heat rate is provided on the basis of test snapshot heat
rate with factors for annual effects and annual degradation rate of 0.4% of
DHR. About 9 kcal/kWh/year degradation in UHR is predicted based on the
37
Vol. 1 Jojobera Unit No 3 CPRI Report TPC-G
test snap shot and improvements due to short, medium and long term
measures.
****************
38
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
Annex 1
(Figures, Graphs & Photographs)
1
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
100
90
80
70
60 2008
PLF (%)
50 2009
40 2010
30
20
10
0
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR
Months
120
100
Availabilty factor
80
2008
60 2009
2010
40
20
0
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR
Months
2
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
14
12
Auxiliary consumption (%)
10
8 2008
2009
6 2010
0
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR
Months
0.88
Specific coal consumption (kg/kWh)
0.86
0.84
0.82
0.8 2008
0.78 2009
0.76 2010
0.74
0.72
0.7
0.68
APR JUN AUG OCT DEC FEB
Months
3
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
12.0
10.0
8.0 2008
2009
6.0 2010
4.0
2.0
0.0
APR JUN AUG OCT DEC FEB
Months
3100
3000
2900
UHR (kcal/kWh)
2800
2008
2700
2009
2600
2010
2500
2400
2300
2200
APR JUN AUG OCT DEC FEB
Months
4
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
2
y = -0.0155x + 2.782x - 24.199
2
R = 0.9471
Availiablity factor v/s PLF
120.00
100.00
Avaliablity factor
80.00
60.00
40.00
20.00
0.00
0 10 20 30 40 50 60 70 80 90 100
PLF (% )
y = -0.004x + 10.674
2
Auxiliary consumption v/s PLF R = 0.0191
14
12
10
PLF(%)
0
0 10 20 30 40 50 60 70 80 90 100
Auxiliary consumption (% )
5
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
2
y = 3E-06x - 0.0011x + 0.8549
2
R = 0.2252
Specific coal consumption v/s PLF
0.88
Sp. coal consumoption (kg/kWh)
0.86
0.84
0.82
0.80
0.78
0.76
0.74
0 10 20 30 40 50 60 70 80 90 100
PLF (% )
2
y = 0.0029x - 0.4844x + 20.926
2
R = 0.9307
Specific fuel oil consumption v/s PLF
14
Sp. fuel oil consumption (ml/kWh)
12
10
0
0 10 20 30 40 50 60 70 80 90 100
PLF (% )
6
Vol. 1 Jojobera Unit No 3 Annex 1 CPRI Report TPC-G
2
y = 0.0368x - 8.1995x + 3054.1
2
UHR v/s PLF R = 0.3977
3000
2950
2900
2850
2800
PLF (%)
2750
2700
2650
2600
2550
2500
0 10 20 30 40 50 60 70 80 90 100
UHR (kcal/kWh)
7
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Annex 2
(Tables and Charts)
1
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
01 Boiler
Steaming rate t/h 352.2
Boiler efficiency % 87.03
02 Turbine
Electrical output rate MW 120
Specific steam consumption t/MWh 2.935
Turbine efficiency % 44.46
Turbine heat rate kcal/kWh 1934.53
03 Turbo Generator
Turbo generator efficiency % 43.85
Turbo generator heat rate kcal/kWh 1961.4
04 Generator
Electrical output rate MW 120
Generator efficiency at unity power factor % 98.63
2
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Sl.
Particulars Details
No.
01 Type Outdoor, two pass, pie type, radiant, Natural
circulation, balanced draft, dry bottom ash,
single drum, corner fired fusion welded water
walls.
02 No. of boilers per 1
turbine
03 Fuel used
Primary Coal / Oil
Secondary HFO
04 Fuel firing equipment
Type of fuel firing Direct corner firing
Type of coal mills XRP 783 Raymond Bowl mill, 36.5 t/h per mill,
442 kW motor
No. of coal mills 5/3 (total/ service)
Type of coal burners Coal Tilting Tangential Burners
Load per coal burner 8.33 % MCR per burner, 9.125 t/h
No. of coal burners 20/12 (total/service)
No. of coal elevations 5
Type of oil burners HFO, BHEL make
No. of oil elevations 3
No. of oil burners 12
05 Soot blowers Wall Blowers, Long Retractable Soot Blowers
Furnace zone 40 Nos., Wall blower, Medium used -
Steam
Platen, Convection and 20, Long retract, Medium used Steam
Reheater and ECO zone
06 Steaming capacity 352.2 t/h
07 Steam pressure
SH outlet 130.7
Drum pressure 140.8 kgf/cm2
Reheater outlet 28.78 kgf/cm2
08 Steam temperature
SH outlet 540 C
Reheater outlet 540 C
09 Heater types
3
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
4
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
5
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Heat Balance
100 % 100 % 60% 100 % TMCR
Losses unit BMCR TMCR TMCR with HPH out
6
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Fuel Burning
Equipment
Type Oil Burner
Make & Nos BHEL:12
Capacity 22.5 % SGMCR
Disposition Corner
7
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Predicted Performance
Description Unit 100% 100% 60% 100% TMCR
Flow BMCR TMCR TMCR with HPH out
Steam
Superheater Outlet t/h 390 352.2 212.6 333.7
Reheater Outlet t/h 320 301.8 185.1 316.7
Water
Feed Water t/h 401.7 352.2 212.6 343.7
SH Spray Stage-1 t/h 0 0 3.9 6.8
Stage-2 t/h 0 2.3 2.2 3.3
Air
Air Heater Outlet- Primary t/h 135 125.6 90.9 144.6
Air Heater Outlet- Secondary t/h 299.1 257.6 141.2 273
Tempering Air t/h 17 21.3 4.9 4.2
Total Combustion Air(including
Leak) t/h 491.4 448.4 277.3 462.1
Fuel
Coal(HHV-3350 kcal/kg) t/h 90.4 81.8 51.1 83.6
Gas
PAH Outlet t/h 167.2 158.9 117.1 173.3
SAH Inlet t/h 373.8 330.6 188.1 335.2
PAH Outlet t/h 167.2 158.9 117.1 173.3
SAH Outlet t/h 373.8 330.7 188.1 335.2
Temperature
Steam
Saturation Temp in Drum C 337 336 331 336
LTSH outlet C 424 426 419 438
Platen SH inlet C 424 426 407 423
Platen SH outlet C 522 528 535 530
Final SH inlet C 522 521 525 520
Final SH outlet C 540 540 540 540
RH inlet C 334 333 322 344
RH outlet C 540 540 540 540
Water
Economiser inlet C 235 234 212 188
Economiser outlet C 287 286 268 260
Air
Ambient C 33 33 33 33
AH outlet(Primary) C 277 274 244 250
AH outlet(Secondary) C 274 273 246 250
Gas
Leaving Furnace C 981 973 891 969
Entering Platen SH C 1082 1070 1012 1070
Leaving Platen SH C 981 973 891 969
Entering Reheater C 981 973 891 969
Leaving Reheater C 765 754 671 755
8
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
9
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Material
Boiler Drum SA270 GR70
Water Wall Tubes SA210 Gr.C
Inlet of All Super Heaters P11,T11 1.25 Cr,1Mo (Medium Alloys)
and Reheaters
Just Before the outlet of P22,T22 2.25 Cr,1 Mo (High Alloys)
Super Heaters & Reheater
Outlet of Super heaters P91, T91 12% Cr
and Reheaters
Soot Blowers
Wall Blowers 40 Nos
LRSB(For SHs, RH And
Eco) 20 Nos
10
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
MILLS
Type Bowl Mill - XRP 783
Make & Nos BHEL: 3
Capacity 36.5 t/h
Motor kW 300
System Pressurized Booster Cold PA
FD Fan 2 Nos
Make BHEL
Type AP1 17/11 - Axial Flow
Capacity 75.83 m/s
Specific Weight 1.04 kg/m
Total Head 487 mmWC
Speed 1480 rpm
Design Air Temp 50 C
Control Blade Pitch
Fan Reserve
Flow 34.90%
Pressure 64.88%
FDF MOTOR
Make BHEL
Rating 480 kW
Current 52 A
Insulation Class F
PA Fan 2 Nos
Make BHEL
Type AP2 17/12 Axial Flow
Capacity 44.26 m/s
Specific Weight 1.11 kg/m
Total Head 1179 mmWC
Speed 1480 rpm
Design Air Temp 50 C
Control Blade Pitch
Fan Reserve
Flow 47.60%
Pressure 97.40%
PAF MOTOR
Make BHEL
Rating 675 kW
Current 71 Amps
Insulation Class F
11
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
ID Fan 2 Nos
Make BHEL
Type NDZV 26 SIDOR
Orientation 45C Inclined Suction
Capacity 127.6 m/ s
Specific Weight 0.768 kg/m
Total Head 360 mmWC
Speed Variable
Design Air Temp 163 C
Control IGV and Scoop
Fan Reserve
Flow 42.30%
Pressure 81.80%
IDF MOTOR
Make BHEL
Rating 680 kW
Current 79 A
Speed 740 rpm
Insulation Class F
ID FAN HYDRAULIC COUPLING
Make Voith
Rotation CCW viewed in the direction of the power flow.
Scoop Tube Stoke 242 mm
Motor Speed 740 rpm
Sleep 3.10%
Turbo Coupling Speed 717 rpm
Regulating Range 05:01
Oil Tank Capacity 650 litre
12
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
No.
01 Type BHEL design, Three cylinder, throttle
governing, multi stage, reaction,
tandem compound, single flow with
six uncontrolled extractions
02 Electrical capacity 120 MW
03 Steam flow
Turbine inlet 355.6 t/h
04 Steam paths in the turbine
HP turbine Single flow, 25 reaction stages
IP turbine Single flow, 19 reaction stages/flow
LP turbine Double flow, 2x9 reaction
stages/flow
05 Steam temperature
HP turbine inlet 540 C
IP turbine inlet 540 C
LP turbine outlet 46.4 C
06 Steam pressure
HP turbine inlet 127.0 Kg/cm2
IP turbine inlet 28.80 Kg/cm2
IP turbine outlet 4.16 Kg/cm2
Turbine outlet 0.1060 Kg/cm2
07 Feed water heaters
HP 2
LP 3
Deaerator (open feed heater) 1
Heat recovery devices Yes
Gland steam condenser Yes
Stack steam condenser Yes
(condenser flash tank)
Vent steam condenser Yes
08 Turbine-generator Efficiency 44.46 %
09 Turbine-generator heat rate 1934.53 kcal/kWh
10 Turbine efficiency 43.85%
11 Turbine heat rate 1961.40 kcal/kWh
13
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
14
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
15
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
MATERIAL OF CONSTRUCTION
Turbine casing
HP outer casing/ barrel casing Cast Steel GS22 MO4
HP inner casing GS 17 CrMo V 511
IP casing Not Applicable
LP outer casing IS-2062 & IS 960
LP inner casing & LP blade carriers 4L, 4R GS 22 Mo4
LP blade carriers(1L, 1L, 3L, 1R, 2R, 3R) between blade IS 2062 & DIN 17155
carriers & diffusers HII
Turbine Shaft
HP/ IP rotor shaft 30 Cr MoNi V 511
LP rotor shaft 26 Ni Cr Mo V 115
Turbine disc (if shrunk on) Not applicable
Moving Blades
HP Turbine 1st stage X 22 Cr Mo V 121
HP Turbine other stages X 22 Cr Mo V 121
IP Turbine stages X 22 Cr Mo V 121
LP Turbine stages X 20 Cr 13
LP Turbine last stage X 5 Cr Ni 134/ X 7 Cr
Al 13
Fixed Blades
HP Turbine 1st stage X 22 Cr Mo V 121
HP Turbine other stages X 22 Cr Mo V 121
IP Turbine stages X 22 Cr Mo V 121
LP Turbine stages X 20 Cr 13
LP Turbine last stage X 20 Cr 13
Casing Joints Bolts
HP/ IP Turbine casing 21 Cr Mo V 57
LP Turbine casing Carbon steel (P8.8)
Shaft Coupling Rigid (integral), same
as rotor material
IP-LP cross around piping ASTM 533 GR 70
16
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Manufacturer BHEL,Hydrabad
Type Bottom Mounted
Orientation To Condenser Perpendicular to Turbine
Tube Axis Rotor Axis
Number 1
No of Pass 2
Hot well Divided
Water Box Divided
17
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
18
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Material of Construction
Shell SA516 Gr70
Condenser Neck SA516 Gr70
Water Box SA516 Gr70
Tube Sheet SA516 Gr70
Tube in Condensing Zone SB111UNS70600 (C-Ni 90/10)
Tube in Air Cooling Zone SA249TP304
Tube Support Plate SA516 Gr70
Vacuum Pump
GENERAL
Manufacturer Nash Korea Ltd.
Model no. AT 2006 E
Number 1+1
Stage of Pump 2
Standard condition for Air Suction HEI
Ejector Not provided
Coupling Flexible
DESIGN DATA
Guaranteed capacity of pump 15 scfm
Speed of Pump 490 rpm
Volume of Surface condenser, 450 m
turbine steam space and piping
Motor Rating 93 kW
Motor Current 191.6 A
Guaranteed Vibration Level 7 mm/sec
Guaranteed noise level at 1.0 m 85 dBA
COOLING WATER
Quality Passivated DM water
Design temperature 39 C
Design pressure 10 kgf/cm
MATERIAL OF CONSTRUCTION
Casing Cast Iron
Shaft JIS G4051 S45C (CS)
Impeller Nodular Iron
VACUUM PUMP RECIRCULATION PUMP
Quantity 13 m/h
Head 22 m
Motor Rating/ current 3.5 kW/ 7.5 Amps
19
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Cooling Tower
Supplier BDWT, Chennai
Induced Draft, Counter
Type Flow
No. of Cell 6
DESIGN DATA
Water Flow 18000 m/h/ tower
FAN
Manufacture Parag Fans, Indore
No. of Fans per Cell 1
No of Fans per Tower 6
No of Blades per Fan 4
Max. Discharge through Fan 1789369.2 m/h
Static Head at Max. Discharge 6.8 mWC
Speed 116 rpm
Motor Make ABB
Capacity/ Current/ Speed 45 kW/ 1500 rpm
BUTTERFLY VALVE
Purpose Hot water line isolation/ cell
Manufacturer Durga Engineering Co.
20
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Size 700 mm
No. of Valves per Tower 6
Method of operation Manual
Max. Flow m/h
Normal flow m/h
CONSTRUCTION FEATURE
Fills PVC Fills
Fills Height 1.5 m
Surface area per fills 412771.52 m2
Basin Size 16.8 x 16.8
Volume of water per basin 4572.3 m3
No of Heaters 6
HP Heaters 2
Deaerator 1
LP Heaters 3
HP Heater-6 Extraction Pressure 29.5
Ex. Temp 340
Drip Temp 192
FW inlet temp 185
FW outlet temp 233.6
FW Flow 355.6
FW pressure 156
Steam flow 33.32
HP Heater-5 Extraction Pressure 10.6
Ex. Temp 398
Drip Temp 158
FW inlet temp 152
FW outlet temp 185
FW Flow 355.6
FW pressure 156
Steam flow 17.873
Deaerator Extraction Pressure 3.8
Ex. Temp 281
FW inlet temp 119.5
FW outlet temp 149.6
FW Flow 355.6
FW pressure 3.8
Steam flow 14.687
LP Heater-3 Extraction Pressure 1.187
Ex. Temp 195
Drip Temp 98
Cond inlet temp 92
Cond outlet temp 119.5
Cond Flow 289.3
21
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Cond pressure 20
Steam flow 13.68
LP Heater-2 Extraction Pressure 0.17
Ex. Temp 105
Drip Temp 74
Cond inlet temp 68
Cond outlet temp 92
Cond Flow 289.3
Cond pressure 20
Steam flow 11.68
LP Heater-1
Ex Enthalpy kcal/kg 609.9
Drip Temp 71
Cond inlet temp 50
Cond outlet temp 68
Cond Flow 289.3
Cond pressure 20
Steam flow 9.5
H. P. HEATERS
H.P.- 5 H. P.- 6
GENERAL
Manufacturer BHEL BHEL
Tube Supplier Vallinox, France Vallinox, France
Type Shell/ removable Shell/removable
Number of closed feed water heater 1 1
per STG unit
Orientation Vertical Vertical
Tube Type U- Tube U-Tube
No. of Tube Passes 2 2
DESIGN DATA
Shell side data
Unit
Extraction Steam:
Flow t/h 19.201 36.633
Inlet temperature C 400.1 334.4
Shell inlet pressure kgf/cm 12.098 31.702
Drain Entering:
Source H.P.H.- 6
Flow t/h 36.633
Temperature C 193.5
Other drain entering NA NA
Drain Leaving:
Flow t/h 55.834 36.633
22
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
23
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Deaerater
Type of Deaerating Feed water Heater Spray Tray type
Manufacturer BHEL,Hyderabad
DESIGN DATA
Feed water flow 381.439 t/h
Temperature of Deaerated Water 150.7 C
Condensate Inflow 309.673 t/h
Temperature of Condensate Inflow 120.1 C
Heating Steam Quantity 15.931 t/h
Heating Steam Pressure 4.94 kgf/ cm
Heating Steam Temperature 284.1 C
Steam/ Flashed drains into Deaerator: Flow/ Temperature
From HP Heater 55.834 t/h / 159.9 C
From CBD 12.24 t/h / 170 C
Steam/ Flashed drains into Feed Water Storage Nil
Tank
Deaerating Heater Operating Pressure 4.94 kgf/ cm
Pegging Steam pressure at low load/ part load 3.0 kgf/ cm
Pegging Steam Temperature at low load/ part 200 to 330 C
load
Load Range as percent of TG MCR for pegging
steam < 60 %
Whether heating steam rakes are provided in Yes
deaerating feed water storage tank
Is a separate, initial heating steam rake provided Yes
6 kgf/ cm & FV/ 350
Deaerator Design Pressure/ Temperature C
Deaerator Feed water storage tank design 6 kgf/ cm & FV/ 230
Pressure/ Temperature C
Water storage capacity provided in feed water 60 m
storage tank upto normal water level
Sprayer Assembly Detail
Number of sprayer assembly 22
Spray assembly type Spring Loaded
Manufacturer of Sprayer assembly BHEL , Hyderabad
Condensate flow through each sprayer assembly 14.076 t/h
Pressure drop under design condensate flow 0.32 kgf/ cm
Tray Detail
Thickness 1.6 mm
No. of horizontal Trays in one Stack and no. of
Stacks 20 and 8
Total No. Trays 160
24
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
MATERIAL OF CONSTRUCTION
Deaerator shell Carbon Steel
Feed water storage tank shell & dished end SA 516 Gr 70
Sprayer SS TP 304
Tray SS 304
25
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Temperature C
26
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Heat transfer
surface m -- 25.5 16.7
Whether heater is
design for Yes
additional load
during abnormal
2.6 condition
3 CONSTRUCTIONAL FEATURE
Shell OD/ Thick/ 878/ 14/ 878/ 14/ 878/ 14/
3.1 L mm 8860 9700 9000
3.2 Tube
3.2.1 Number 350 350 350
15.875/ 15.875/ 15.875/
3.2.2 OD/ Length mm 7500 8600 7900
3.2.3 Gauge BWG 20
4 MATERIAL OF CONSTRUCTION
4.1 Shell SA 516 Gr 70
4.2 Shell cover SA 516 Gr 70
4.3 Tube SA 213 TP 304
27
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
28
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
1 DESCRIPTION
29
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
30
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
4 MATERIAL OF CONSTRUCTION
4.1 Inner Casing CA6NM CA6NM
ASTM A105/ SS
4.2 Outer Casing NA Cladding
4.3 Impeller CA6NM CA6NM
4.4 Diffuser CA6NM CA6NM
4.5 Casing Wearing Ring:
Chrome Chrome Hard
Material Hard 400 400
Hardness BHN Min. 350 Min. 350
Impeller Wearing Ring:
4.6 Material 1.4024.19 1.4024.19
Hardness BHN Man. 250 Man. 250
4.7 Shaft ASTM A276 ASTM A182
Type 410 Gr.F6NM
(Forged) (Forged)
CHR.PLATED CHR.PLATED
4.8 Shaft Sleeves AISI 316 AISI 316
4.9 Stuffing Box CA6NM CA6NM
ASTM A182
4.1 Balancing Device Gr.F6A
4.1 Pressure bolting studs EN24 V/ T EN24 V/ T
4.1 Nuts EN24 V/ T EN24 V/ T
5 LUBE OIL SYSTEM FOR BFP
Oil from lube oil system of
Hydraulic Coupling will be
5.1 Type of Pump supplied to Main Pump Bearing
5.2 Number of Pump 1 MOP + 1 AOP
MOP- 3847
5.3 Pump Speed rpm AOP- 1485
5.4 Motor Rating of Pumps kW AOP- 5.5 KW/ 11 A
5.5 Lube Oil Cooler type Shell & Tube type
6 TYPE OF COUPLING
6.1 Between Motor & Hydraulic Type : Flexible Membrane
Coupling Make : Triveni
Flexibox
Model : TLPW-1850- 0133-
x001
6.2 Between Hydraulic Coupling & Type : Flexible Membrane
BFP Make : Triveni
31
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Flexibox
32
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
De- Age
Unit Make
No of rated Date of (years)
Capacity
Units Capacity commissioning
(MW) Boiler Turbine
(MW)
1 2 3 4 5 6 7
Unit-3 120 120 27 Aug 2001 BHEL BHEL 9
Table 8: Results of proximate & ultimate analysis of raw coal samples collected
during Unit heat rate test
Table 9: Results of unburnts analysis of bottom ash and fly ash samples collected
during Unit heat rate test
33
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
34
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Drum level
104.5 63.1 77 324.4 197 50.1 67.6 43.1 50.7 45.1
59.9 60.4 330 195.1 120.7 127 235 329.8 331.1 97.3
73.1 65 64.3 64.9 70.3 305 329.4 280.6 138.5 139
Front
40.4 42.1 40.9 40.2 39.2 86.3 65.7 80.8 77.4 93.9 48.6
42.8 40.8 38.6 38.6 38.5 40.7 37.7 38.1 41
Rear
36.7 36.4 33.5 38 36 62.2 74.9 74.2 78.9 61.1 62.2
34.6 43 41.3 40.3 35.1 40.5 38.2 40.2 35.9 38.9 39.6
1 Level down
64.2 59.1 96 74.8 60.2 69.5 90 53.1 70.7 50.7
113.4 80 138 80.7 69.8 74.5 78.2 75.6 68.7 60.7
99.2 87.2 56.5 113.7 98.2 49.3 51.2 51.6 58.3 120.5
67 65.4 63.4 50.8 54.5 58.3 51.6 51.2 49.3 51.4
58.2 54.5 55.8 56.2 52.1 41.4 44.6 47.8 46.30 48.5
Rear
57.1 58.1 66 60.3 62.2 52.4 71.1 59.4 72.7 55.1 64.8
67.8 63.7 64.1 66.1 70.2 67 66.8 60.3 73.8 71.7 62.3
64.7 67.8
1 Level down
59.9 62.1 56.4 81.2 66.2 59.8 62.4 56.4 76 64.2
158.9 81 193 57.8 77.2 49.8 56.1 120 78.2 70.1
118.6 179 96.4 55.6 59.9 58.1 60.2 56.8 71.8 68.4
120.7 71.8 59.1 92 83.5 59.8 65.4 64.6 60.2 59.6
59.8 59.4 56.4 52.8 55 50.8 54.2 60.8 64.4
54.2
Rear
52 52.2 58.6 57.5 57.3 59.6 52.8 54.56 55.4 60.8 69
59 58.1 69.8 64.80 66.8 66.1 64.7 65 68.1 62.6 76.1
60.1
1 Level Down
60.8 61.5 58.1 53.9 59.6 57.1 57.9 57.4 56.4 52.5
66 68.4 62.8 77.9 73.6 60.7 44 62.8 61.1 53.4
96.8 73.8 90.7 70.4 119.2 60.5 61.2 185 197.2 122.1
72.8 68.7 77.8 68.3 106.3 111 99.6 66.1 107.1 48.5
68.5 83 70.4 84.2 54.5 54.2 70 70.5 68.5
62.5 61.9 67.1 62.8 62.3
Rear side
54.9 52.5 72.4 63.7 66 65.4 68.4 66.8 74.9 75.6 73.4
66.8 75 146 86.40 91.2 106 71.1 50.6 64.8 54.1 77
72.1 69.1 75.9 97.80
1 Level Down
35
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
60.4 66.4 61.2 69.3 60.5 67.8 67.4 57.9 60.5 61.2
68.4 67.5 63.4 62.4 65.7 113 75.1 66.9 70.4 64
69 87.8 72.7 141.9 131.00 178 110 107.6 87.3 53.3
53.7 54.4 55.6 57.3 101.4 55.9 49.5 48.3 48.6 49.7
57.3 55.6 54.4 53.7 62.6 58 59.4 56.6 49.3 67.3
60 61.2 61.9 58.4 57.3 47.5 58.9 62.1 61.1 58.1
76.6 75.1 60.1 60.5
Rear side
58.6 59.1 58.5 64.6 69.1 63.3 62.6 59.1 68.8 64.2 63.5
63.2 53.4 73.3 69.8 68.4 70.4 62.3 62.5
1 Level Down
(1st left 1st Right)
60.6 63.2 65.1 75 67.8 56.3 55.1 67.6 62.9 77.2
61.8 170 127 115.8 116.8 61.2 69.4 107.9 125.9 123.5
186.8 106 70.4 61.4 57.3 90.2 75.8 56.4 57.4 61.9
160.9 58.4 59.1 56.1 54.3 62 54.6 59.5 57.9 54.3
56.8 59 64.2
front side
64.7 73.7 62.9 70.7 77.3 64.8 65.9 114.1 113.6 94.2 110.2
67 63.8 64.3 65.2 70.9 73.2 63 72.5 73.6 85 95
Rear side
86.6 78.8 76.5 70.3 63.7 63.5 113 140.4 122.3 178.3 105.2
81.5 68.3 71.6 66.1 71 69.2 67.6 66.9 75.5 115.3 77.7
(2nd left 2nd Right)
74.8 67.5 58.7 55.5 56.7 65.3 68.1 57.8 87.8 65.6
193.6 191 193 100.8 58.2 65.2 55.25 127.1 123.4 143
170.6 108 165 94.4 71.2 58.6 146.3 168.8.2 85 98.5
65.8 61.3 61.8 64.1 69.4 56.1 54.2 62 49.5 68.5
68.5 71.1 64.2 60.7
Rear side
63.1 64.1 63.6 65.9 65.7 71.7 61.6 65.4 59.3 57.3 56.7
61.4 59.3 58.4 65.9 64.6 70.1 72.1 69.2
1 Level down
(1st left 1st Right)
64 57.3 71 73.8 61.4 55.3 57.3 76.3 68.5 54.3
122.6 77 75.6 74.5 64.7 136 140.5 90.2 57.8 56.1
106.8 101 125 162.3 132.2 120 98.5 155 152.7 146.8
82.7 67.5 64.8 67 70.3 52.1 55.6 70.5 52.4 160.8
60.7 73.2 62.9 64.2 86.8 58.6 70.6 75.9 68.9
front side
67.3 61.4 55.8 63.5 58.9 72.9 67.8 56.5 65.6 109.4 107.7
66.8 59.8 62.5 61.5 60.5 58.6 52.5 69.6 82.5 101.8 107.8
Rear side
56.1 56.1 67.8 61.3 56.9 67.3 53.2 117.2 104.1 96.9 98.8
85.4 57.2 61.9 61.4 67.5 64.5 56.2 62.3 61.6 64.2 68.5
(2nd left 2nd Right)
36
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
37
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
72.9 68.5 59.7 62.6 59.1 53.4 69.3 62.3 99.2 103.2 95.6
105.5 72.8 96.2 61.1 69.2 64.2 74.9 73.2 64.3 59.8 56.4
61.8 77.6 69.4 75.5 76.1 80.1 131 72.7
1 Level Down
51.5 55.5 50.9 54.3 49.7 51.7 62.9 111.9 64.1 46.4
55.1 53.5 53 46.3 71.8 59.4 48.3 47.5 41.9 43.7
67.9 44.7 73.8 44.6 75.6 44.3 50.9 51.2 48.4 60.5
68.9 72.3 66.2 68.9 54.3 52.2 55.4 56
Front side
122.4 41.6 84 92.60 79.3 113 85 62 51.3 58.4 61
61.4 45.1 46.6 48.6 42.8 53.8 42.5
Rear side
53.5 58.2 53.6 45.1 56 54.7 54.8 54.5 52.7 52.8 66.1
65.8 42.4 40.3 60.4 79.6 49.9 40.3 39.9
1 Level Down
70.3 62 58.7 56.3 61.3 61.7 70.4 60.1 77.6 59.9
55 54.2 77.3 83.6 118.1 60.6 62.9 46.7 53 58.3
57.8 115 124 96.2 108 109 110.6 105.9 86 120
100 112 63.2 60.8 64.5 46 61 102.7 100.8 92.8
46.4 45 75.6 56.4 86.4 55.6 69.1 70.7 67.3 72.3
44.3 81.3 49.4 54.2 54.2 56 57.1 64
Front side
62.4 56.8 55.8 78.1 66.1 66.7 67.5 74.8 87.1 90.3 90.6
101.9 88.8 72.5 153.6 129.7 117 128 72.8 55.3 47.4 46.3
62.5 55.3 57 60.9 55.8 64.5 56.8 60.6
Rear side
61.4 61.2 57.5 69.4 60.1 64.7 59.1 58.7 121.4 75.4 85.4
103.2 120 80.5 101.7 121.4 61.2 57.1 63 57.8 74.2 61.5
62.2 65.1 60.1 64 64.1 62.6 72.3 60.2
1 Level Down
51 46 40.5 40.7 38.9 48.8 46.1 42.1 47.3 40
53 49.2 45.6 54.5 43.4 38.9 41.3 48.1 45.6 46.4
109.4 112 93 147.6 43 42.4 40.8 48.2 128.3 130.3
47.3 48.2 59.4 96 85 105 103.8 108.9 105.4 92
43.1 50.1 41.8 46 47.2 55.4 44.6 55.8 44.3 46.1
41.5 50.1 52.2 46.4 44.5 48.3 38.9 40.4
Front side
47.5 46 43.8 47.3 53.4 42.5 52 47.7 48.9 43.9 50.2
50.1 41.5 46.1 44.3 55.8 44.6 48.2 56.1 84.1 49.9
Rear side
45.2 38.7 40.4 39.2 47.4 54.8 42.5 50.8 37.8 46.3 42.8
35.4 59.1 54.2 45.3 38.9 36.6 41.2 42.8 36.2 38.4 37.5
Average 72.7
38
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
39
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Sl. Operating
Particular Unit Design
No. PAPH
Oxygen in flue gas
1 Before APH % 3.6 4.0
2 After APH % 5.56 9.0
Flue gas temp
3 Before APH C 298.0 373.5
4 After APH C 139.0 152.8
5 T C 159.0 220.7
Air temperature
6 After APH C 274.0 308.4
7 Before APH C 33.0 35.6
8 T C 241.0 272.8
Air flow
9 Total t/h 125.6 179.2
Leakage
10 APH in-leakage t/h 20.5 35.5
11 APH in-leakage % 16.29 19.79
Thermal load
12 Thermal load MWt 8.7 14.2
T - Differential temperature
40
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
41
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
42
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
43
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
44
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
45
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
46
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
47
Table 25: Feed heater data for UNIT 3
48
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
49
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
50
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
01 Pre-operation procedures OK
Clean up OK
Chemical cleaning OK
02 Cold start up OK
Pre-light up OK
Initial firing OK
Light off OK
03 Hot start up OK
04 Warm start up OK
Normal operation OK
05
Increasing load OK
Decreasing load OK
07 Emergency procedures OK
Procedures adopted for operational
08 OK
optimization
51
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Table 31: Gross efficiency, heat rate and specific fuel consumption
52
Vol. 1 Jojobera Unit No 3 Annex 2 CPRI Report TPC-G
Table 33: Causes for deviation of gross heat rate from design
53
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Annex 3
(Procedures, Calculations &
Spread sheets)
1
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Q
Steam from boiler
=
Boiler Q
Fuel in to boiler
QSteam to turbine
Auxiliary steam =
QSteam from boiler
2
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
= P =
O (1)
o, g
Q I
B S T G
Boiler efficiency (
B) is the ratio of the rate of energy output of steam produced
at the boiler outlet to the rate of the energy input in raw coal at the mill inlet.
Q B,s
= (3)
B
Q I
Where QB,s is the rate of energy flow in steam produced by the boiler (in case of
steam generation) .
3
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
= P T
(4)
T
Q T ,s
Where QT,s is the rate of energy flow in steam drawn by the turbine (in case of
steam turbine). PT is the rate of mechanical energy output of the turbine.
= P O
(5)
G
P M
Where PM is the mechanical shaft output of the turbine (gas turbine or steam
turbine).
= P P
O A
(6)
A
P O
Q T ,s
= (7)
S
Q B ,s
This refers to the usage of auxiliary steam in between the boiler outlet and the
turbine inlet.
4
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
SFC =
3.6 m f
(8)
P O
3600
HR = (10)
T
=
m h s u (11)
is
m h s is
where his is the isentropic enthalpy change (flow weighted) across the turbine and
hu is the net useful enthalpy change (flow weighted) across the turbine (the
enthalpy change which has been converted into work plus the enthalpy change
which has led to heat transfer from the turbine skin). Isentropic efficiency refers to
the fraction of enthalpy difference that is convertible into work.
5
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
6
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Period of collection: to be collected after one hour from the start of the test.
2. Pulverized coal for sieve analysis- from each mill in service from all 4 corners
to constituting a total weight of about 200 gm sieve analysis of these samples
to be carried out.
Period of collection: to be collected after one hour from the start of the test.
3. Fly ash and bottom ash to be collected during the cycle followed by the test
and unburnt test to be carried out.
Period of collection: to be collected half an hour after the start of the test and the
7
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
second sample to be collected after one and half an hour from the start of the test.
8
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Data requirement:
Readings were taken from the control room instruments at regular interval of fifteen
minutes. The readings were taken half an hour before the start of the test followed
by every fifteen minutes till the completion of the test.
9
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Sl.
Particular Unit Unit # 3
No.
1 Gross calorific value of fuel (HCV) kcal/kg 4623
2 % of Carbon in fuel % 47.22
3 % of Sulphur in fuel % 0.60
4 % of moisture in fuel % 6.60
5 % of ash in fuel % 38.93
6 % of Hydrogen in fuel % 3.20
7 % of Oxygen in fuel % 6.55
8 % of UB in bottom ash % 5.60
9 % of UB in fly ash % 1.90
o
10 Bottom ash temp. C 900.00
o
11 Fly ash temp. C 153.67
12 Sp. Heat of bottom ash kJ/kgK 1.05
13 Sp. Heat of fly ash kJ/kgK 0.84
14 CO in flue gas ppm 350.00
15 % O2 in flue gas after APH % 6.76
o
16 FG temp. at APH outlet C 153.67
o
17 Ambient air temperature C 35.61
18 Humidity fraction of ambient air kg/kg 0.0206
19 Mill input shaft power kW 926.51
20 PA Fan input shaft power kW 601.82
21 FD Fan input shaft power kW 573.32
o
22 Avg. furnace skin temperature C 72.70
23 Furnace outer surface area m2 1629.50
24 Calorific value of CO kJ/kg 10092.40
25 % O2 in flue gas before APH % 4.14
26 % O2 in furnace % 4.14
o
27 Leaking FG temp. at first pass C 0.00
--
28 FG puffing factor in first pass 0.00
10
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Sl.
Particular Unit Unit # 3
No.
29 Gross calorific value of fuel (HCV) kJ/kg 19351.88
30 Net calorific value of fuel (LCV) kJ/kg 18648.63
CO2 in flue gas (Computed from
31 O2) % 12.58
32 Mass of air required for combustion kg/kg 6.84
33 Heat loss due to unburnt CO kJ/kg 33.62
34 Excess air factor at furnace -- 1.25
35 Excess air factor at APH inlet -- 1.25
Heat loss due to puffing in furnace
36 first pass kJ/kg 0.00
37 Loss due to bottom ash % 0.76
38 Loss due to fly ash % 1.03
Loss due to sens. Heat of bottom
39 ash % 0.37
40 Loss due to sens. Heat of fly ash % 0.16
41 Loss due to unburnt CO in flue gas % 0.17
42 Loss due to sens. Heat in dry FG % 5.77
43 Loss due to moisture in fuel % 0.90
44 Loss due to hydrogen in fuel % 3.91
45 Loss due to moisture in comb. Air % 0.16
46 Loss due to convection % 1.06
47 Loss due to radiation % 0.50
48 Heat equivalent of auxiliary power % -0.11
Heat loss due to puffing in furnace
49 first pass % 0.00
50 Total losses % 14.69
51 Thermal efficiency % 85.31
Correction factor to account for
52 annual average station GCV 0.00
53 Corrected test boiler efficiency % 85.31
11
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Sl.
Particular Unit Unit # 3
No.
1 MS flow into turbine t/h 387.35
2 HRH flow t/h 355.34
3 RH spray t/h 1.10
4 Plant load MW 119.14
5 Enthalpy of MS kJ/kg 3437.63
6 Enthalpy of HRH kJ/kg 3533.54
7 Enthalpy of CRH kJ/kg 3133.24
8 Enthalpy of RH spray kJ/kg 710.10
9 Enthalpy of FW at oulet of final feed heater kJ/kg 981.28
10 Generator efficiency % 98.61
11 Generator efficiency fraction 0.99
12 THR __ 2.52
13 Turbine heat rate kJ/kWh 9075.22
14 Turbine heat rate kcal/kWh 2167.97
15 Turbine efficiency % 39.67
16 Specific steam consumption t/MWh 3.25
12
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
13
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
14
Vol. 1 Jojobera Unit No 3 Annex 3 CPRI Report TPC-G
Saving in fuel
54 Saving in fuel t/h 8.16
55 Saving in fuel % 12.56
Deviation in gross overall efficiencies (%pts)
56 Boiler related loss % pts 0.71
57 Turbine related loss % pts 4.07
58 Generator related loss % pts 0.01
59 Aux. Power related loss % pts 0.00
60 Aux. Steam related loss % pts 0.00
61 Total dev. From design efficiency % pts 4.79
15
Vol. 1 Jojobera Unit No 3 Annex 4 CPRI Report TPC-G
Annex 4
(Documents Copied)
1
Vol. 1 Jojobera Unit No 3 Annex 4 CPRI Report TPC-G
Boiler
tripped on
1 23.05.08 10:01 23.05.08 11:41 1.67 Tripped 200.4
RH
protection
Boiler
tripped on
2 27.05.08 07:38 27.05.08 10:16 2.63 Tripped 315.6
RH
protection
Generator
tripped on
3 03.06.08 16:46 03.06.08 19:03 2.25 Tripped 270
reverse
power
Turbine
tripped on
4 15.06.08 10:57 15.06.08 13:26 1.5 Tripped condenser 180
vacuum very
low
Condenser
5 03.08.08 23:34 04.08.08 18:17 18.75 Planned water box 2250
cleaning
Generator
tripped on
6 22.08.08 09:50 22.08.08 13:02 3.2 Tripped 384
Class-A
protection
Flame
7 17.09.08 22:18 18.09.08 01:16 3 Tripped 360
Failure
Flame
8 28.09.08 16:35 28.09.08 18:12 1.63 Tripped 195.6
Failure
Condenser
9 30.09.08 13:31 30.09.08 15:04 1.55 Tripped Pressure 186
very high
2
Vol. 1 Jojobera Unit No 3 Annex 4 CPRI Report TPC-G
Human
error, during
change over
10 25.11.08 14:16 25.11.08 14:38 0.37 Tripped 44.4
of Bus
configuration
for export.
Boiler
tripped on
11 17.02.09 16:32 17.02.09 18:08 1.6 Tripped 192
Flame
failure
Boiler tripped
2 01.08.09 04:05 01.08.09 07:06 3 Tripped on Flame 360
Failure
Boiler tripped
3 11.08.09 07:51 11.08.09 10:24 2.55 Tripped on Flame 306
Failure
Turbine
Tripped on
4 09.09.09 03:03 09.09.09 07:05 4 Tripped Lub oil 480
Pressure Very
Low
Boiler tripped
5 03.12.09 05:22 03.12.09 07:50 2.5 Tripped on RH 300
Protection
6 23.12.09 18:09 Planned Desynchronised
Total Time 13.47 1616.4
3
%& & %& # !
%&' ( )&%
! " #
!
! $ ! * " !
%& & %& # !
" ! !
+ (,-%&. / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / ++
+ %&' ( ( 4 1 --/
//////////////////////////+
6+ 2 0 &2 3 %&' ( / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / #
=+ &0 2 10 0/ / / / / / / / / / / / / / / / / / / / / / / / / / / / / / ++6
>+ 5.% / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / / +6
+ B !
4 99 ) ! @ ! ! @
) - 9 $ ) $
! "# $ % % &' ( )
* ) +,- ) % .3 ), 2 %- 9$ /-$0 )
$ / $0 ) 1 2 3 :, 9 1 9
) 4 "5 1 ) !678 ) :
9 ) + ) , - 9 % 9 )
) 3 4 - ,
3 :, +,- 9( ) ) !67 2 4 )
1 % ) % 9 9 ) )
)9 % % 3 :, +,- * ) 9 ) %
;
:? ) 9 )% 9
:3 9 ) % / 99 0
:< ) ) (9
%& & %& # !
3<; ,; ' ; 99 ) ) 9 %
:@ ) % %
:$ ) % )4
+ ! !?
) 9 % 3<; ,; ' ; 3! 58 % 9 )4 9 ( 4
9
: C 3!
:* : /*3 0 C 38
( ) 9 ) 4
% ) ) % )( 4 ) ) % 9
: > 9 9
9 )4 % : ) :
= ) )) 9 ) %
) 9 ) )
) - 9 % % 4 9 ()
9 ) 4 : *3 4 /1 04
) )
) : 99 4 9 ) 9 =
9 " 9 % > ) %
9 )
9 ) > %9 ) ) 9 @ )
9 ) )% < 9 ( ) (4 (
9 ) ) ) ) ) * : /*3 0 1 % 9
> ! 9
6
%& & %& # !
+ ?A A A
7
%& & %& # !
!!
,' -
( )
B B $ % )* +
C C & '
P S
!!
3 % &
I I "# I I
O O O O
( " $$ /0 % %
+ ? ! " A A
;
%& & %& # !
+! A ?
3 :, +,- 9( ) ) !67 2 4 )
1 % ) % 9 9 ) )
)9 % %3 +,- * ) * ( 9
% ) %% %1 /#- 3; - 0 )% 99 4
/" " *0 ) +,- ) 9 ) %3 +,- 9
)9 9 ) 9 % % 3 :, 9 ) 3 :,
- 9 4 4 ) ) 4 ) ) 99 / " *0
% 4 @ 9 % 94
(4 9 9 % 9 : 4 9 9 9
) ) % ) > ) ; "
% # ) 4 ' ) 9
+ ! ! $ A "" ! A A
< ) ) ) 9 % ) % ) 99 5 9
> 9 9 ) ) %% % 9 %
9 % * 4 9 ) %% 9 %
)9 % 9 * 9 ) %
% % ) ) A % % 4
> 9
=
%& & %& # !
+ " ! A " !
4 ) ) ) 4 + 9 )
) 9 9 ) 9 % , * 9 )
9 5 ) +,- 9% > 9 = 8
) )
- % = D ) ) ( 9 5 )
/ - 9$ $ 0 / 9
= !65 3 0
-$ ) $ % ) ( )
> % 9 /; " 0 % 9 4
! 2%&9 ! " 10 9 & D ! 10 9 +
) > 9 ) 9 % 9 % =
) : )
1% % 4 9 ( 4 ) 1 /; + % 3 :,
- 90 1 9 4 %& & %& - 94 % %
> 9 # 1 4 ) 94 1 - ) 4
) 1 99 ) 9 )4 : )
) 9 %
! - : ) )3 @ 94 : )
" *- 9 : )
*3 = " <3 9 %, " ) " <3
>
%& & %& # !
+ ! ! ! ! ! ! !?
# B 7 8+; - )0
4 ) - % 9 ) ) ) *%
) 4 (4 ) 3! 58 , - 9
= 3< D )) 9 %
' % 9 % ( %
) 9 )% " )% 4 )
) 4 -& E @ 94 ) 9 % )
99 4 4
+ A !?
% 9 ) % "* %
% ) ) 9 ; "* 4 %
4 9 ) ) )
;) "* 9) 9 )
9 ) 4 F "*
- , 3, ) % > ) 3, )4 9G
, 9 )4 ) 9 ;) "*
# ) 4' ; 94 ) ) " % "
#-3; - 9 9 )4 % ) 4 " *( % )
9 ) ) 9 %
%& & %& # !
* % ) ( *3 4 )
& = 3/ 3 0 , "</ : ) ,
" ) < ) ) 0 "< 4 % ) %
& + % 9 "< 4 ) "* % 4 "<
) , 99 4 4 *3 * 9 )( % 4 9 ) "<
4 ) "* * 4 ) ) ) = ) *3 "< &
4 9 % 9 "< "* # 4 )
9 A * ) 4 ) 3 :, - 9
"< 9 *3
! " #
+ E $ " !! ! ?
# 1 4 ) ) 9 4 1 - ) 4 )
+ )3 - ) ) ) 4 1
+ ? E FA !!
%& & %& # !
+ #? E !
%& & %& # !
+ 6? E !!
#
%& & %& # !
+ 7? E #F ! "
6
%& & %& #
!
#+ !* D !$ ! ?
+ A ! "" !?
+ E E ?
; ) "* 9 4 ) ,* 9 #-3; - ) 9 #
9 )% 9 ) "* 9 1 9 7 =1 331 ) )
9 7 =1 /3 3 10( 9 9
4: 4 ) = 4 ) ) %4 %
%4 (7 =1 H I "* 9 ) ) ) 3, )4 )4
) ) ) %4 # ) 4 - 5J3 ) "-
= 5; + ,5++ 5; 3, 4 % "* 9 %
/@ F0 % ) /@ 70
+ ;? A ! ! !
7
%& & %& #
!
+ =? A ! ! !
' 4 "* 9 % % 4 ) ) )8 %
; # % 3,* ) 3*@ /3<; ,; ' <; 38
% 09 ) 4 4 /@ 60
( % ( 9 ) : " )
%9 ) ) )) )) ) : ) %
% ) % ) ) 9 * )) (
3*@ ) ) : ( > )%
) 99 ) % ) % - ) %) 9 )
% 3*@ 2 4 ))
+ >? "
=
%& & %& #
!
+ ? E D !! !
+ ! "" !
) ) % ) (
) ) > ) % )
% * ) ( % 4 ) 4 % 4 )
) )B
+ ) ) % = % )
" 9 ( ) ( ( 4 ) ) 9 ) ,
>
%& & %& #
!
) ?3, 99 ) G + 9 )
) ) 9 % 9 ) "* 9 1 4 ) ) 1
) 0- - % - &2 3 < A (, - ?
* (1 ) "* 9 % ) 3 4
99 9 > 9 , % )% 4 )
) ) % 4 4 =
) 9 % " 9 9 99
) 2 @1 /@ 1 0 1 ( 4
" 9 ( ) % ( ) % )
, % )9 % = ) %
) 4 )
1 % ( ) > 4 ) ) ) A )4 4
"*- %4 /7 =1 D -3 < :,0 4 ) 4
) 3! 58 *3 4 3*@ )
@1 = 1 % ( 99 4 ) %
)) *3 = ) 9 ) 4 ( 9 )
) ( 99 4 ) -
( ) = )) /- ! C 1)) - C 1))
0 * 9 ) 4 9 ( ) % 9 )
4 % ( 4 9 ) 9
%& & %& #
!
, 99 ) % ) % 4 " *( , 99 ) % 9 "*
4 % ) 4 4 ) 4 ) @& %
! ) @ , 99 ) % 9 47 =1 " * 4 % 4 % ))
*3 3 99 % 7 =1 99 ) 4 @& % 4
) ! ) @ @& 9 9 9 ) *3 !
) *3 & 9 ) ) 99 ) 9 9
9 ) F 3< D % ! ) @ ' ))
)) ) *3 ! ) *3 F @? ! /*3 %% ) 09 ) * 9 ) )
% @& % ! ) @ 9 ) , 99 )
% 9 ) ) +
9 )) % 99 ) ' 9 ) 4-
1 ) > ) 99 ) ) % )
) ) +
1 8 4 ) ) ) A)4 4 "*,
%4 /7 =1 D -3 < :,0 4 ) )
- 4 4 1 , 99
) 4 ) 1 8 4 ) % )
% 9- ) % , % ,
8 - ! ), ! - *% %
) 4 ( 4 4 4 4
9 4 )
) ) )
%& & %& #
!
)6 0 -?
- 94 + 9 4 % 9 )% )
% 4 "* 9 # ) )
$ 4 ) 9 ) 9 )% )
> 9 , ) ) 4 9 "* ) )
) ) ) ) % < % 9, *
.% 0 &2 3 < A 10 9 ?
< 1
* )% = % % % 9
- 9 ) 9 9 )
= K )< / ) ) ) ) % 0
@ ! 7 =! 8 = /@ :8 E0
3 % 9 % % %
1) ) 9 ) ) ( ) % %
%& & %& #
!
+ ? " A
%& & %& #
!
+ ?! A
#
%& & %& # !
%4 %$ &%, & (3 (
6
%& & %& # !
+ 4 %4 < ?
3<; $< -- % % ( 99 ( ) 9 ) 9 %
3<; ,; ' <; 3! 9 38 /@ ! 0 * ) )
( ) 9 % ) % 3 :,
3 : ( #*' ; ; -& E /; ) 99 : ) % ; %%: 99 0
@ ) % % 9 = 3<; " -( ) ) 9 % ) (
9 ) % 3 :, 3! 3 )
- 9 " % # ) 4 5 J3 3 % 3 , 9
' * ) 9 4 ) % :% )
% 4 ) 4 > ( 9 ) 3
) 9 ) 9 % ) % + 4 ) %
9 ( ) / : 9 0 ) % / 9 0 F 3< D
9 ) ( ) : :
99 %3 C 4 *3 & 4 <-
) ) /! ! !0 - *3 ) 3 C
: )) = ) ) )% ) * /* 0 =
, ) % 3! 9 ) * 4 * 3<; ,; ' <;
3! ) ) ) 9 )
) ) ) ) ) 3<; " % F 3< D %
7
%& & %& # !
3! % 9 3
% 9 ) ) )
+ ? A A !
3 : - 4 J ) % 3 :, 3! 538 4 99 )
% - !F 1 6 % 3<; " 99 )
% % 99 % 1- 8( @? !( & " ) 99
;
%& & %& # !
3 %) 9 % @ + 9 )% 4
+ ) % 9 = ) 9 ( ) %% 4 <
) @,+ ) 9 4 )) 4 @ ) 94 )% 9
= ) ) 9 , 9 ) % )
)4 = , % 9 % =, ) 9 )
9 )% ) 4 ) ) @ 9 % @,+
0 -?
3 % + ( ) 3 ( ) ,
4 ) 1 3 ) ) ) )% ) ;& #
99 % 3<; $< --: 4 @,+( % 4 % )) )
9
=
%& & %& # !
; 9 % *5; - 4 @ !8 !D
; 9 % , ) ) , 4 @
!E
; 9 %+ 9 ) 2
7C3 )/ ) 1 0 9 ) 9 - 4 @
!7
; -9 % 2 / % % 94 : ) 0 4
@ !F
; -9 % / + 1 0 4 @ !F
% )) 2 ))
) 4 % ) 5 ))
) 4 %" )) - 4 @ !6
" = ) )5 ) )
+ #? " E !A D
>
%& & %& # !
+ 6? " E !
+ 7? !" ! "
%& & %& # !
+ =? = ! !
%& & %& # !
+ >? !
%& & %& # !
+ 5 0& & 0?
*3 /* 3 0 , ' 4 3 :, 3! 9 *3
& / , 0 9 ) ( ) 4 % ) *3
& ( "*/ 9 " * % 0 ) 2 % 9 ) %%
*3 3*@ 9 ) + % 4 ) %%
% & 9 ) / , % - , 99 % + 0 4
) %%
* % /- 4 @ 80( ) ( *3 4 )
& = 3/ 3 0 , "</ )
, " ) < ) ) 0 "< 4 % )
% & + % 9 "< 4 ) "* %
4 "< ) , 99 4 4 *3 * 9 ) % 4
9 ) "< 4 ) "*
* 4 ) ) ) = ) *3 "< & 4
9 % 9 "< "* & "< 4 ) )
D % 4 4 )4 %
4 )) 2 D%
* , "< 4 ) % ) 9 % ( )4 9 )
& % 9 ) 9 ) 4
9 ) ) ) D %% ) 9 ) % & /1
4 @ !0
%& & %& # !
+ ? A " ! !
! < B
+ ? A ! ! !
* , "< F 1 9 ) 1 ) F 11 9 ) 1 D
9 ) ) % 9 9 ) &
F !9 ) 1 7 )F 1 !9 ) 1 F % ) 1 7
) 1 6 F & 9 ) % *3 = ) 1
#
%& & %& # !
+ ? " ! !
32 & . 0
+ ? ! ! !
6
%& & %& # !
+ #? ! " ! ! D ! !
7
%& & %& # !
+ 6? ! " ! ! D ! !
# 4 ) : 9 A * ) 4 : )3 :
, - 9 "< 9 *3
2 0 &2 5 0& ?
1 4 9 ) "
; 9 ) ) % 3 "< ) , "< 9 )
3
3 9 "<
;
%& & %& # !
+ 7? "
+ 6 !
3 99 ( 9 ) F 3< D ) ) % % )
9 ) * ; ) ) ) 4 9 )
) )
=
%& & %& # !
= 9 3< D )) 9 %
+ ;? ! E A " ; 6
>
%& & %& # !
4 %8- 3 4 ) 4 4@
" ?! # !
#
%& & %& # !
+ =? ! # !
#
%& & %& # !
6+ ! A
< ) ) - : 9 % % 4
- +*-,; "
#
%& & %& # !
7+ ! ! " " 8 :
" ? ! " !
%&' ( &0 0 9 2&% %& & %& 10 9 )-% & 8 0 & &9 9 %( %&)&0 % ( 4 2%&9 :
!& 9 0 @. 1 &0 $ %& '
! , %+ ( - 3 3! 9 9 %1 8 D
+ % = " *( + )
, %+ ( )- %
% ' 4 "* (
( 9 9 ( ( 99 !8E F
* %' 4 "* %4 (
) %3 - 9
99 % )
,1<+ F ! : E7 6 88
,1<+ F ,: - ! ED
, " ) ,1<+ F 1 !,: - E D
,1<+ F 1 : 8 E8
,1<+ F & ,: 5< !7 7!
- )+ 1
# )+ "*1
- <1"
# <1"
3*@
3<; D @ 94
8 * - 3< D 3 E! F6
!, " )
3<; " % & 1- 8/" ) F, 0
3<; " % & /" ) FE80
3<; " % 3< D /" ) J*,; < 7E80
" = < /! 3 0
3<; " % 3< D /" ) 7 DE0
D , )- ) - ! D ED
+ 9 %@ + 9
E 6 ! 7
,
+ 9 %@ + 9 +
F ! E
, " )
= & .)) 1 &0 ; +7=
6 + )4 / ) , --0 M 7 8N 77
! + - %4 ,+:<; " / ) , --0 M 7 8N 77
!! - =M N ! 8!
! - = /* ) , --0 M ! N !! 7
& 0 9 %&' ( &0 ;=+=
#
%& & %& # !
;+ A " B!
% 4 9 ) ) *9 $ %%
) , A %1 3 :, 3! - 9 : ) %
3 4 3 % 3 4 B
+ 00.9 ) & 0 (3 ( ?
!0 3 @ % % @O !!:! ) ) =6+ J O O
0 1 = 3 4 % ) ) % ) $
%% < !
!0 1 $ %% < ! ( + : > % , A ),
9 %F B
: 0) % 3 %0 < 3 < 3 * &< % 3 0 & ( 9 1 &
) G & 0 2&% 3 ) %& = + A ( * 3 &%9 0 &2
% & %22 -. & 0 3 4 C )) 2&% 3 (&9 ). & &2 %22
9 ) ( 2%&9 & 6 7+
0 1 , % 9 %) ) ) ) )
% H $ (3 %1I % : :$
3 ( ) + < - <, $ %%
< ! )
80 3 3 9 ) < %- %* ) /- * 3 <0 ) )%
9 %* ' 9 + ) % * # ,
##
%& & %& # !
D0 ; " = ) % 9 ) $
%% < 8% % %% *9 9
E0 < > / : =0 $ %% < !
;: A& KC &9 9 00 & 3 % & %2
%22
2 -. & 0 3 0 & 0) ( 2
(&9 ) & 9 &2 %&' ( 0 , . % & ) G & + A&< 4 %*
&< % 3 0 (&9 ) 3 )%&' ( < 3 4 %1 03&% 0) &2 9 &2 '.0 +6
& 30 3 ( L. 2 0 2&% 7J & 8 &0 5:+
70 < > /3 : =0 ) : < > /3 :
=0 4 "1 <
60 @ 9 %# , (< (; " = "
- $ %% < ) )
+ ) G & 3 0 -?
#6
%& & %& # !
" #? ! ! ! ! " !
#7
%& & %& # !
" 6? ! ! ! ! " !
#;
%& & %& # !
, ) 1 9 , 9 ( 3 4 )
A ) *9 $ %% 4 4 9 % +66
0 B 3
* 4 % % )% 9 , A % 1 ( 3 4 9
> 2 , 99 , A), %1 3 :, 3!
- 9 : )
#=
%& & %& # !
=+ ! ! "
" 7? E! ! + ++
4 -0 %&' ( &0 3 . - 0 9
% (. %0 0 " ,30
9 )3 , / 9 ) "5 1 0 ! F7 7
1 , A ), % 3 !!F 6
#>
#( ( #(& 3
23 *
! .
( ( "& ") *' ( " " ++& ' #,% ( -%+ ( +-%$ ( .( "# %/ 0 +
"# $%&"#' ( 0 /"$
45 2;1
! " # 2 ;<
! " # 0 <1
$ # $ =
% & # 4 0 *9
! ' . 67 * 12
( ) * ! ' . 67 2 =>
! . 67 1 **
( ( "& ") *' ( " " ++& ' "45' 316
2 !
! ( + , - 219 ::
6
$% % $% # !
>* !! D
!! D F ?
! "
6
$% % $% # !
6
$% % $% # !
>* !! D
!! D F ?
@ ! A " !) ! "
6#
$% % $% # !
>* !! D
!! D F ?
@ ! ) ! "
66
TATA POWER COMPANY LIMITED
JOJOBERA THERMAL POWER STATION
JOJOBERA, JHARKHAND
ABB LIMITED
PS POWER GENERATION
PLOT NO. 5 & 6, PHASE II,
PEENYA INDUSTRIAL AREA
BANGALORE 560 058
ABB
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
1.0 Preface
2 x 120 MW TPC, Jojobera Thermal Power Station has Procontrol P13 make control system of ABB
design with WSPose in units 2,3 as HMI. This system is utilized for realizing various functions
required for control; monitoring and operation of the FSSS and ATRS of 120 MW power generating
Unit # 2,3. The existing Procontrol system is provided with One Diagnostic station and Logic
development station for each unit. The existing system in each unit is using 2 IPBs.
Due to the age of the installed system and difficulty in maintenance and operation of the old
hardware, there is a requirement to upgrade the control system HMI. The requirement is for HMI
system that is Windows 2003/XP based compatible with the existing ABB make Procontrol System
with no loss/degradation in functionality/performance. ABB offers tailor made solutions for
upgrading/refurbishing the existing systems at minimum costs and without compromising on the
system performance. The interface for P13 is an original ABB design hardware developed for
Procontrol P13. This hardware is utilized as the interface for the HMI developed by ABB for its
Procontrol P13/42 and Advant series of DCS. The 800xA is a truly open HMI system based on
standard PC hardware, based on industry standard software like Windows 200X/XP and MS
Excel/ODBC/DDE/OPC etc.
The diagnostic station present at the plant is PRAUT microcomputer based SK06, which is used for
the logic development and monitoring of the system.
Due to shortcomings of SK06, the plant can face problem whenever there arises a need in
modification of the program or forcing of signals is to be done under the certain conditions, when
SK06 is connected to a particular 70PR03/70PR05. Also it is not possible with SK06 to do subsequent
operation w ith different participants.
This offer gives a detailed description of the upgrade for the existing Diagnostic Station to
Progress 3 and HMI to ABB latest state of the art solution -800xA. The offer is divided into two
phases, in the first phase we propose to upgrade the Engineering Station and in the second Phase, the
existing HMI to 800xA. Both the activities will be carried out in parallel.
2.0 Procontrol P13 Upgradation of Engineering cum Diagnostic Station:
2.1Technical Proposal:
Progress 3, is based on Windows XP Operating station platform and compatible with the existing
Procontrol P13 system with no loss/degradation in functionality/performance.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 2 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Based on the initial discussions at ABB Bangalore, ABB had proposed to introduce 6 number of
70BK03 modules to access data from the TMR local panels into Progress3. However, based on site
visit and discussions at site, it is proposed to extend the existing IPB (One Number) to all the TMR
panels. This will have the following advantages.
Access of Trend Data from the signals.
Separate FKB signals will not be required.
Trip Conditions (22 signals) from each of the TMR channels shall be connected to the new HMI
System to help trip analysis. This will help in root cause analysis for the trip conditions.
Internal Signals of BK and PR modules will also be available for analysis into Progress3.
However, the existing TMR Configuration, its functionality and the communication from TMR panels
to common panel will be retained as existing.
The existing TMR panels communicate with the IPB by means of communication through 70BK03
modules. The schematic below shows the existing configuration.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 3 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
For the TMR configuration of EHTC and Turbine Protection, it is proposed to extend the IPB to the
se local Buses for better data aquisison.
In order to extend the IPB, ABB will introduce 2 BK02 (One for Turbine Protection and One for
EHTC) and One 70FA01 box with FK coupler cards for each TMR panel. Please refer below schematic.
Progress 3 Computer will placed near the diagnostic panels within a distance of 2mtrs.
The Procontrol P13 Progress 3 is connected to the platform via one or more 70BK03 modules.
The process of up gradation will include the replacement of existing PC for diagnostic Station. The
connection to IPB will be through 70BK03C module installed in the existing diagnostic panel. The
Progress 3 computer will be connected to the 70BK03C module over serial (RS232) communication.
The Progress 3 computer will be communicating through 70BK03C in the diagnostic panel to the IPBs
and hence to the different stations on the IPBs.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 4 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
The Proposed configuration is shown in the above drawing.
In the present case in a 70BK03 will be placed in the existing diagnostic station where the progress 3
computer will be connected to the 70BK03. The system will be communicating through the 70 BK02
modules in the diagnostic station to the IPBs and to the local stations.
Procontrol Progress 3 is a Programming documentation and service tool. It has been specifically
designed to enable upgrade or replacement of older generation of Procontrol Engineering. The
system runs on Microsoft Windows 2000/XP Professional Personal Computers or Notebooks. It is
controlled interactively on monitor with aid of state of the art user-friendly graphical interface
windows techniques.
1) Single Point Uploading: The instruction codes can be read and loaded to the EEPROMs of the
70PR05 processors of all the P13 stations from single point i.e Progress 3 engineering station. This
eases the conventional process of program loading by connecting to the processors individually.
2) Easy Code Transfer: The ease of code transfer from existing EPROMs and graphical
documentation of the codes makes it an ideal choice for Procontrol Processor Upgrades. Additional
import functions allow the as built documentation of existing application programs generated by
older Procontrol P13 tool generations.
3) Over all Administration and Addressing: Progress 3 provides all the facilities the user needs to
Engineer, Commission and service the Procontrol P13 Platform. This includes the administration of:
Techno-Commercial Proposal
Techno-Commercial Proposal Page 5 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Projects
Intra Plant busses
Local busses
Bus Couplers
Stations, racks, devices
Signals
Documentation Structure
Load Modules
Parameters
Test sets
Also the addressing includes of:
Devices
Signals
Parameters
Service RAM
Techno-Commercial Proposal
Techno-Commercial Proposal Page 6 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
With the implementation of PC based Progress 3, Procontrol modules like 70SK30, 70SK31, 70SK32,
70SK33, 70SK34, 70SK35, 70SK36, 70SK37 modules are not required and hence bringing down the
Note: The above features are the software features of Progress 3 software. The complete use of the
functionality and the features will depend on the existing Procontrol P13 system, its interface to the
existing P13 and available engineering backups.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 7 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
2.3 Development of Functional Block Diagram
As the logic back-up available with M/s Tata Power is in the form of hex -code, the logic for each
controller will be developed in the form of functional block diagram from the existing hardcopy
From the available document we find that there is 28 redundant pair of controllers and 18 non
redundant Controllers. There is approximately 85 drive control modules (AS04 modules) installed in
the Plant.
The Process of development of a Function Block diagram will involve the following steps.
Creation of Function Block diagram from the existing documents in the Function Block editor of
Progress 3.
Comparison of the target code generated with the one existing in the Controller in the form of
As per ABBs standard policy and in order to bring your plant to the current technology level from time
to time and market trends, ABB is committed towards providing you with the best solutions based on
the technological upgrades and continuous enhancements, globally over the years.
It is our endeavor to inform and provide you the opportunities for implementing state of the art
technology as a step towards protection of your investment and prolonging plant & system life.
Upgrades of the Procontrol P13/42 system with the latest HMI Operator system have been carried out
at a number of other installations by ABB.
ABBs latest generation of Human System Interface, the 800xA (Process Portal A), combines the
comprehensive process know-how and installation experience with advanced software functionality.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 8 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Based on Windows 2003/XP platform, the 800xA unified user interface provides a consistent method
for accessing enterprise wide data in real-time for managerial decisions as well as for launching multiple
applications from any connected workstation in your plant or office. The software, 800xA is a truly
open HMI system based on standard PC hardware and works on industry standard software like
Windows 200X/XP and MS Excel/ODBC/DDE/OPC etc.
The seamless integration of ABBs Procontrol P13 Platform in to the world of Industrial IT allows you
to increase your overall efficiency and to achieve greater asset optimization by making real-time data
available across the entire enterprise. 800xA Process Portal provides flexible opera tion with a high
level of scalability in order to respond to changing operation and production needs.
3.1 Proposal
It is proposed an two 800xA servers with 100% data handling capacity will be installed to achieve data
concentration from the local P13/42 IPB for the HMI system.
With our 800xA and P13 Connect solution, we provide the possibility for step wise, continuous
migration solutions to the latest automation technology. This unique ABB approach ensures investment
protection by preventing equipment obsolescence through out the plants life.
The modifications in the 800xA application program are limited to the interconnection functionality
to the new 800xA.
A modification of the Procontrol P13 application programming to change the functionality of the plant
control is neither envisaged nor required.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 9 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
The installation process is a detailed operation involving a high level of design, engineering and
planning in order to achieve the required level of reliability and functionality. In order to achieve this,
the following procedure is followed as a standard:
1. Data collection of existing HMI : This step involves the process of collecting data and details of
the existing configuration and various other aspects like the Mimics, trends, logs, reports etc. This
step also involves the handover of critical data like the VPC command structures; partitioning
diagrams and the engineering database dump from the EDS/ OWS, Performance calculation details
etc by the customer to ABB.
2. Design and Engineering of the New HMI package: In this step, the New HMI package
configuration and functionalities are built in line with the existing plant operation philosophy and
system configuration. Many improvements in the mimic layout and look and feel can be integrated
during this procedure with the involvement of the plant engineers with ABB engineers during this
stage. The new Mimic layouts, trend configurations, log and report configurations are carried out in
this step. Configuration and migration of the existing engineering and configuration data is also
carried out.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 10 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Fig:02
3. Installation of New HMI software server: As the first step, the data acquisition server is loaded and
initialized with the new HMI software. The newly installed server is then connected to the P13/42 IPB
using the spare set of tapping from the FA coupler box. This server is assigned the last available address
on the IPB. Please refer figure below for details of the retrofit. This step is carried out online during
plant operation with out any hindrance to normal control and operations of the plant.
Once the parallel data acquisition server is put online, the acquisition of data on this server and its
associated client is monitored. Commands are given from this operator station and checked on the
Diagnostic station by calling the telegram address for that command. These commands will not have any
effect on the normal plant operation or DCS functioning as the addresses used will be un-used in the P13
logics. Hence these commands can only be read by the Diagnostic station and will not be read by the P13
controllers. This monitoring process is carried on till each of the tags configured have been physically
verified for correctness of configurations. Refer fig:03
Techno-Commercial Proposal
Techno-Commercial Proposal Page 11 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
4. Hot commissioning of the installed server: This step is carried out during any available plant
shutdown, which could be of a very small duration to enable on-line HOT testing of the commands from the
new HMI stations. In this step, one of the existing servers is shutdown and brought offline. Now, the new
HMI server is assigned the address of this existing server, which has been brought offline, and normal
operation is resorted to from this new Server client setup. As all the data acquisition tags and command
tags including feedbacks have already been tested using parallel server and the Diagnostic station, in step
# 3, this step will involve actual operation of only the required drives and valves etc in order to HOT
commission the new HMI system.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 12 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
The P13 interface represents the linking element between the process visualization software and the
P13 bus through PIF Board. The PIF board serves to connect to the P13 bus directly. In turn, the P13
interface accesses the PIF board, which is mounted directly in the PCI slots instead of the conventional
ISA slots that are obsolete. Interfacing of Operate IT with ABB make Procontrol P13 system is done
by the PIF card, which communicates directly with the P13 without any third party communication
device in between. Hence the hardware reliability is maintained. Following are some of the advantages
of the PIF card:
Techno-Commercial Proposal
Techno-Commercial Proposal Page 13 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Advantages:
Interface 800xA directly with P13 without any third party interface between P13 & 800xA.
Interface mounts directly in PCI slots, which eliminates the hardware obsolesce problem as in
traditional ISA slots.
Control program to watch several Statistical values concerning P13 Interface
Interface device driver diagnosis tool in Windows NT to check the status, interrupt used and I/O
port address area reserved by the device driver.
The control functions can be easily and efficiently designed using the Functional Unit libraries included
in 800xA, which reflect power plant standards and practice. These libraries include standard basic
function blocks for analog and binary functions. Furthermore, proven solutions for handling drives,
pumps, controllers etc. have also been programmed into function blocks and are offered with the
800xA shown in table 1. Furthermore, to increase engineering efficiency and quality on a functional
level, a library of Functional Units is offered with the 800xA. A Functional Unit serves as an entity,
keeping all the components for a specific solution such as a drive, across the control system.
Accordingly, and as shown in figure 1, each Functional Unit consists of: 1) process I/O functions 2)
application macro communication over the Control Bus, HMI presentation data (faceplate and object
display attributes)
Techno-Commercial Proposal
Techno-Commercial Proposal Page 14 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
ProcontrolP13
Examples of Functional Units
Note: The above features are the software features of P13 connect software. The complete use of
the functionality and the features will depend on the existing Procontrol P13 system, its limitations
and available engineering backups.
Data Integration:
Using the 800xA Servers and through Fiber Optic Communication all real time data including process
graphic, trends, logs, alarms etc for individual, multiple units can be made available at a single place.
Ease of use
800xA and P13 Connect, is a dedicated power plant operator station solution designed to increase power
plant operation efficiency and reduce engineering effort.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 15 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Information transmission security
Redundant Interface design and high coupler performance allow safe bi-directional transmission of any
signal without loss of information.
Full compatibility
As the original Procontrol P13 equipment supplier, and based on our large experience and reference in
hundreds of power plants world wide, we guarantee the full compatibility of the new 800xA with the
Procontrol P13 automation solution.
On-line retrofit
As the original Procontrol P13 equipment designers, and based on our large experience a high degree of
Design and Engineering reliability has been built into the retrofit solution for P13/42 systems. Due to
this, it is possible to perform a really On-line retrofit solution even in a critical application such as a
power plant control system. This provides an opportunity to upgrade/retrofit the P13 systems without
the requirement of an actual plant shutdown. A plant shutdown would be required only for a few days
for the purpose of HOT testing of the critical drives etc.
Investment protection
With our OperateIT and P13 Connect solution, we provide the possibility for stepwise, continuous
migration solutions to the latest automation technology. This unique ABB approach ensures investment
protection by preventing equipment obsolescence through out the plant life.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 16 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Aspect Object
...one integrated thing that Aspects
hides all the differences"
Process
IFS Graphics
Real ABB Operator Interaction
Object Object
Maintenance record
Operator interaction
Control
Control
MS Word
Builder
Control
Data sheet
Simulation
iGES
ElMaster Model
Simulation
Electrical Model
diagram
AutoCad
MS
P&IExcel
Diagram
P&ILoop
Diagram
spec
Aspect
Systems
ABB Automation
OIT Overview 000907
Page 10
The enabling technology for this data access, storage, and management is ABBs patented Aspect
Object framework. Aspect Objects relate all of your plant data, the Aspects, to specific plant assets,
the Objects. The headache of locating information spread between different people, locations,
computers, and applications is over. Aspect Object navigation presents the entire production facility in
a consistent, easy to view fashion. This allows a single window environment to include smart field
devices, asset optimization functions, information management, batch management, safety systems, and
MES (Manufacturing Execution Systems) applications.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 17 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
The 800xA OPC Client Connection is intended for use with third party clients. In an ABB Industrial
IT installation, the connectivity packages are used to integrate the operator workplaces, etc. with
the Industrial IT controllers.
All run-time data, and some configuration data in the system is available for other clients via OPC.
The 800xA System acts as an OPC-Server for OPC-DA and OPCHDA. The 800xA System acts as an
OPC-Server for OPC-DA (1.0, 2.0), OPC-HDA (1.20), and OPC -AE (1.1). Several OPC-Clients can be
connected simultaneously to the system to exchange data.
Operations
The Operator Workplace is built on Operate IT process portal technology and it is the 800xA
System Operator Interface.
The key functions provided are: presentation of process graphics, execution of process faceplates,
presentation of trends, and presentation of alarms.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 18 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Operator Workplace - Remote Client.
Features:
Personalized workplaces for focused information access
The Operator Workplace provides efficient control and supervision of different kinds of processes in
integrated systems.
The Operator Workplace uses client/server capabilities allowing both client and server applications to
run in one PC for a small configuration, or to run in a configuration with one server and up to thirty
client workplaces.
Functional overview:
Graphics displays, with support for ActiveX components to include any third
party graphical component.
Operator History, including trend presentation and Alarm and Event history.
Excel based reporting (scheduled and on demand).
Faceplates
Faceplates are designed mainly for operator use, to monitor and effect control of a process. Each
object can have up to three different sized faceplates, depending on the needs of the object and the
user (see Figure 2 Faceplates.)
The Operator Workplace provides a flexible faceplate framework, making the creation and the
customization of the product-supplied faceplates straightforward and intuitive. The faceplate
framework is composed of five main areas.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 19 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
1. At the top of the faceplate is the header area. This includes the object name and description,
as well as alarm state indication, acknowledgement button, and object in-use (or locked)
indication.
2. Below the header area is the status area. This includes object state indication (e.g., manual
mode) and link buttons to other aspects (e.g., operator note).
3. At the bottom of the faceplate are the faceplate size selection buttons (for reduced, normal,
and expanded size faceplates).
4. Above the faceplate size selection buttons is the control button area. The configuration of the
status and button areas is done through simple fill-in-the blanks configuration and provides the
ability to link in button and status indicators.
5. Between the status and button area is a faceplate element area. This is a free-form graphic
that is configured in the same way as any process graphic.
Figure 2 Faceplates
Quad Display
It is possible to divide the display area in four smaller areas where each area can hold an individual
display to get a better overview of a process. The content of each mall area can be maximized to
Techno-Commercial Proposal
Techno-Commercial Proposal Page 20 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
cover the whole display area and will return to the original quarter area again when minimized. See
Figure 7A.
Navigation
The Operator Workplace supports the ability to right click on any object to view and select available
actions or display call-ups from a context menu. For a given user, the context menu is the same, no
matter where the object is displayed. The configuration of an object in and of itself automatically
defines the possible selections available within the context menu. The context menu is filterable
based upon the user log-in, such that an engineer might have access to certain actions that are
configuration-related, while an operator would not have access to them. The context menu also
contains a reference list of other graphics or displays in which the same object is used, allowing the
Techno-Commercial Proposal
Techno-Commercial Proposal Page 21 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
user to quickly navigate to them. This reference list is provided automatically without requiring the
user to do any manual mapping.
Within the tool collection of the application bar, a number of navigational buttons and pull down menus
are available to provide quick access to displays and information. Object and aspect history lists as
well as back and forward buttons allow an operator to view and recall past selections quickly.
Associated displays of a selected object or aspect can be quickly called up using short cut buttons
that are automatically enabled when the object or aspect is selected.
Alarm List
The Alarm List displays all events matching the configured alarm filter. All, or a subset of an events
attributes, along with the current value for that objects can be displayed. Viewing the alarms is very
flexible. Use the default sort order or adjust the sorting by double clicking on the headers. Adjust
the layout by drag & drop columns to suit your needs. Return to the default layout by just clicking on
the reset button.
The colors and blinking of alarms are configurable. It is also possible to define what columns to
present, the time format, and the sorting order of the list.
Event List
The Event List displays all events matching the configured event filter. The event list functionality is
the same as for alarm list, except acknowledge.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 22 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Trend Display
Trend displays are some of the most important tools associated with operating and analyzing
industrial process. The Operator Workplace addresses this need by presenting the operator wing an
extensive set of trending features and functions.
The Remote Clients adhere to the access control concept generally supported by Operator Workplace
Clients.
Operation graphics, alarm&event, trend, history logging, system status, and faceplates
Information Manager
Techno-Commercial Proposal
Techno-Commercial Proposal Page 23 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Batch client
A third party solution from Citrix is used to implement remote clients. Ci trix Metaframe Presentation
Server software must be installed on an Application Server running an Operator Workplace rich
client to enable access from remote clients.
Audit Trail
The Security and Access Control System allows audit of operator actions and security. The system
supports logging of security violations, configuration changes, and operator actions to the process.
The audit logs can be viewed in the alarm and event list. This makes it possible to see the effect of
an operation. The audit log contains the following information:
Date and time for the operation
Type of operation
Platform for process and information management software with easy access to process data.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 24 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Replacement /Up gradation needs minimal Engineering.
Process operation from any of the operator stations using face plates for interaction
Advanced alarm and event handling, using priorities and configurable filters
Techno-Commercial Proposal
Techno-Commercial Proposal Page 25 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
5.0 Replacement of Critical Modules.
Based on the site visit and discussion, it is proposed that the following critical modules whose
malfunctioning may cause Unit Tripping will be replaced with imported modules of ABB. This
replacement is to be done in each of the TMR Channels
It is also proposed to replace some of the existing modules of the Turbine Protection Panel (CJJ32)
and EHTC Common (CJJ31) with ABB manufactured modules. The list of these modules is enclosed
below.
Sl No Modules CJJ31 CJJ32 CJJ21 CJJ22 CJJ23
1 70EB01 10 8 8 8
2 70EB02 5
3 70AB01 30
4 70AB02 4 4 4
5 70BK03 3 3 3
In TMR panels EB01 will be replaced at locations, EA10, EA11, FA01, FA02, FA10, FA11, GA10 and GA11.
Similarly, AB02 will be replaced at locations FA34, FA35, GA34 and GA35.
1. The offer covers only signals available in the present system and available in the IPB.
2. Availability of existing documentation with logics for P13 system with M/s Tata Power
3. The specification of the server will be strictly in accordance with the ABBs recommended
hardware for 800xA systems.
4. The modifications in the 800xA application program are limited to the interconnection functionality
to the new 800xA.
5. There is space in the TMR Panels to keep BK03 modules.
6. A modification of the Procontrol P13 application programming to change the functionality of the
plant control is not included and not required .
Techno-Commercial Proposal
Techno-Commercial Proposal Page 26 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
7.0 Duration of the Project
Commissioning of Engineering Station will require at most 15 days for commissioning at site. The system
can be commissioned online, however for downloading to the controller, it is recommended to have
shutdown. That limits the actual Plant outage required to be maximum 4 days. A detailed Activity
schedule will be submitted after the award of Offer.
The 800xA HMI system will need a max. Of 15 days for installation, testing and commissioning at site,
after the material has reached the site and design and engineering has been done in our office. Please
also refer to the upgradation procedure mentioned in the beginning of the proposal. This limits the
Commissioning time by checking the input signals in the IPB during online running of the Plant.
Commissioning is only limited to the outputs from the system.
The scope of this offer for one unit is as detailed in sections below.
8.1 Scope of supply:
Techno-Commercial Proposal
Techno-Commercial Proposal Page 27 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
HMI Upgrade
Qty/ Total
Item description UOM
No. Unit Qty
A Procontrol P13/42 Upgradation
Server Workstation for 800xA :
Xeon Dual/Quad core 1.6GHz, 1x 73GB SAS /80GB SATA HDD,
2 4 Nos.
2 GB RAM,20" TFT Monitor, Std Keyboard, Mouse,
Win 2003 Server. (Make: DELL/HP/IBM/Equiv)
2. Operator Workstation for 800xA
P4 Dual/Quad core 1.6GHz, 1x 73GB SAS /80GB SATA HDD,
4 8 Nos.
1GB RAM,20" TFT Monitor, Std Keyboard, Mouse, Win XP.
(Make: DELL/HP/ IBM/Equiv)
4 P13 interface cards (PIF03) for HMI server
4 8 Nos.
(PCI slot compatible) with connecting cable
7 800xA software for Server Workstation with license for
1 2 Lot
2000 tags and 300 history points, license dongle and media box
6 Communication Setup
Switch, LAN cable, redundant Networking within the distance of 1 2 Lot
100 mtrs.
7 A4 Color Laser printer for Reports 1 2 No
8 Dot matrix printer for Alarms 1 2 No
9 Rev Drive for external data storage. 1 2 No
Note:
This offer quantity is for two units only
1) Power Cables.
3) Furniture
Techno-Commercial Proposal
Techno-Commercial Proposal Page 28 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
8.3 Scope of Work:
Progress 3:
Uploading the 70PR02, 70PR03 data through EPROM Programmer and uploading the BK02
and FV01 data in the Progress 3. Modification in Hex Editor and downloading.
Uploading the 70PR05b data in the Progress 3. Modification in Hex Editor and downloading
Taking back up, Design, Engineering and Up gradation of the existing database to ABBs
make Progress 3.
Preparation of Function Block Diagram based on the latest Hardcopy available in the Plant
ABBs scope is limited to the data and tags available in the present system. Any modification
Changes and Modification in Cabinets, dismantling and mounting of racks, IO cards etc.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 29 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Any logics or schemes that is non existent and not operational in the present system as on
date.
Notes:
1. One 230VAC/110VAC UPS Power Supply is to be provided by M/s Tata Power for the 800xA
server and operator work stations and Progress 3 PC.
2. Furniture for the computers to be provided by M/s Tata Power .
3. FBD Hard Copy and updated documentation must be provided by M/s Tata Power
Techno-Commercial Proposal
Techno-Commercial Proposal Page 30 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
9.0 COMMERCIAL PROPOSAL
Price Schedule:
Rs 150,000/-
1 Development of Function Block Diagram per Controller 1 Num (Rupees One Hundred and
Fifty Thousand Only)
Development of Function Block Diagram per Drive Rs. 50,000/-
2 1 Num
Control Module (Rupees Fifty Thousand Only)
Note: for number of Controllers, see their relevant technical section. The Quantity is based on site feedback.
For Critical Modules , please check the relevant portion.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 31 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
9.3 Unit price for Critical Modules
Your Acceptance of our offer should be communicated through a written purchase order
specifying the following terms and conditions as an explicit acceptance of it.
IMPORTANT NOTICE
This Budgetary offer No E.UAPS.RE.8.00 52.R1 dated 04.05.200 9 is preliminary and not final and
as such non binding. It is tendered for discussion only, does not constitute a term to contract and
ABB can, without notice, mak e any changes in ABBs own discussion.
Prices The quoted prices are net & firm and on DELIVERY, EX WORKS PEENYA
BANGALORE. Our scope is based on the above mentioned items in scope of
supply and services only.
Excise Duty The offered prices are exclusive of all taxes and excise duties,
Sales Tax levies, cess & octroi, Service Tax etc. which have to be borne by you
And Other at actual as per the prevailing rates at the time of delivery and
Levies service. Present prevailing rate, ED on hardware (including CESS) is
8.24%, ED on Software in CD-ROM (including CESS) is 8.24%, Sale
Tax is 2% and Service Tax (Including CESS) 10.3%. You shall furnish
necessary declaration forms wherever applicable.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 32 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
reimbursed at actual on demand by concerned authorities at
applicable rates at the time of dispatch / levy within the contractual
delivery period.
Delivery All items as per the B.O.M shall be supplied within 20 weeks on receipt
of technically and commercially clear order. The above delivery reckons
the availability of frozen engineering information within 30 days of
receipt of technically / commercially clears order.
Freight and The prices quoted do not include cost towards freight and transit insurance.
Insurance Freight charges and insurance will be in your scope.
Note We shall intimate you the dispatch details to enable you to arrange
insurance. If you do not arrange the insurance, goods will be dispatched to
you at your risk.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 33 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
commissioning, whichever is earlier.
Validity of offer Unless otherwise specified in writing, this quotation will expire thirty (30)
days from the date of offer.
Change in Scope This quotation is based on our understanding of the enquiry. If subsequent to
of Supply. the tender evaluation and placement of order, changes in the specification
alter the quoted scope of supply and services, we reserve the right to re-
negotiate the contract price. In case the quantities would increase or
decrease during the execution of the Works, the Contract price will be
adjusted on the basis of the prices valid at that time.
Routine Progress, Visits for the above by customer's engineers will not be subject to an
Witness Testing additional charge provided such visits do not affect the agreed production
& Inspection. program. Also the charges for travel, lodging, boarding of customers /
Purchasers persons shall not be in ABB scope.
Test Certificates Internal Testing Certificates will be provided.
Exclusion of Exclusion of Consequential Losses and Limitation of Liability:
Consequential Notwithstanding anything contained in the conditions to the contrary, the
damages & Supplier shall not be liable for any special, indirect or consequential damages
Limitation of or losses, such as, but not limited to, loss of revenue, loss of use, loss of
liability production, loss of data, loss of con tracts, costs of capital or costs
connected with interruption of opera tion.
The total liability of the supplier, irrespective of whatever legal reason,
shall be limited to the 1% value of the contract price.
Erection and Our scope of job will be completed in all respects within 15 days from
Commissioning: the clearance and availability of the control room and Shutdown.
Service Charge Extra Man day @ Rs. 25,000/- for Commissioning and Service, in case the
reason of delay of commissioning is not attributed to ABB.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 34 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Force Majeure Force Majeure is herein defines as any cause which is beyond the
control of the contractor or owner as the case may be, which they could
not foresee, or with a reasonable amount of diligence could not be
foreseen, and which substantially affects the performance of the
contract such as:
Scope of Supply & The scope of our supply shall be limited to the items mentioned in the
Works Bill of Material. The scope of our works shall be limited to the
Supervision of installation and commissioning of the items mentioned in
the Bill of Material.
End User ABB Will provide an end user statement once the order is finalized.
Statement The same needs to be signed and attached along with the Purchase
Order.
ARBITRATION & All disputes and differences arising out of or connected with the
JURISDICTION execution of the contract/ order, failing amicable settlement on mutual
terms shall be referred to arbitration in line with the provision of the
Indian arbitration act in force. In the event of dispute the jurisdiction
for settlement of the same.
Techno-Commercial Proposal
Techno-Commercial Proposal Page 35 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
Customer TPC Ltd, Jojobera Thermal Power Station
Project
Offer No
Enquiry ref
Proposal for Progress3, and 800xA HMI
E.UAPS.RE.8.0052. R1 dated 04.5.200 9
Site Visit of our Representative ABB
Procontrol P13 HMI/EWS
Power
Year End User Plant Country Retrofit Existing Technology
MW
Ref.
1 IPGCL IPGCL INDIA R Pose90 AS160 OS
Desk
7 2008 APGENCO Pochampadu INDIA 3x9 R Operation 800xA/Progress 3
2008/
8 UE AGBP NEEPCO INDIA R Pose90 800xA
2008/
10 UE RRVUNL KTPS INDIA 210 R Pose90 800xA/Progress 3
Techno-Commercial Proposal
Techno-Commercial Proposal Page 36 of 36
Preliminary Draft- For Discussion Only-Confidential
We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without express
authority is strictly forbidden. Copyright 2008 ABB. All rights reserved.
TATA POWER COMPANY LIMITED
JOJOBERA THERMAL POWER STATION
JOJOBERA, JHARKHAND
COMMERCIAL PROPOSAL
ABB LIMITED
PS POWER GENERATION
PLOT NO. 5 & 6, PHASE II,
PEENYA INDUSTRIAL AREA
BANGALORE 560 058
ABB
Customer Tata Power Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P13 Spare
E.UAPS.RE.10.024.R0 Dated 8.2.2010
Your Discussion with our Representative
ABB
Commercial Offer
Price Offer:
Total in INR: Rupees Five Million Three Hundred and Sixty Five Thousand Only 5,365,000 /-
* The price quoted includes the services required for installation of cold standby server. No software or
licenses have been considered.
Commercial Proposal
Page 2 of 4
Commercial Proposal
Customer Tata Power Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P13 Spare
E.UAPS.RE.10.024.R0 Dated 8.2.2010
Your Discussion with our Representative
ABB
GENERAL TERMS AND CONDITIONS
Your Acceptance of our offer should be communicated through a written purchase order specifying the
following terms and conditions as an explicit acceptance of same.
Prices The quoted prices are net & firm and on DELIVERY, EX WORKS PEENYA
BANGALORE.
Excise Duty The offered prices are exclusive of all taxes and excise duties, levies, cess & octroi,
Sales Tax Service Tax etc. which have to be borne by you at actual as per the prevailing rates
And Other at the time of delivery and service. Present prevailing rate, ED is 8.24%, Sales Tax is
Levies 2%. You shall furnish necessary declaration forms wherever applicable.
Delivery Delivery time for supply of the modules is about 16 weeks from the date of receipt of
the technically and commercially clear/firm order.
Packaging Included.
and Handling
Freight The prices quoted do not include cost towards freight and transit insurance. The
material will be dispatched on Freight at actual shall be applicable and insurance
will be in your scope.
Note We shall intimate you the dispatch details to enable you to arrange insurance.
If you do not arrange the insurance, goods will be dispatched to you at your risk.
Warranty 12 months from the date of dispatch.
The warranty period shall expire prematurely if the customer or a third party
undertakes inappropriate modifications or repairs to the Supply or if the customer, in
the event of a defect, does not immediately take all appropriate steps to mitigate the
damage and give ABB the opportunity to remedy such defect.
The above prices are valid for a period of 30 days from the date of offer.
Validity
LD Clause Not Applicable.
Exclusion of Exclusion of Consequential Losses and Limitation of Liability:
Consequenti Notwithstanding anything contained in the conditions to the contrary, the
al damages & Supplier shall not be liable for any special, indirect or consequential damages
Limitation of or losses, such as, but not limited to, loss of revenue, loss of use, loss of
liability production, loss of data, loss of contracts, costs of capital or costs connected
with interruption of operation.
Commercial Proposal
Page 3 of 4
Commercial Proposal
Customer Tata Power Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P13 Spare
E.UAPS.RE.10.024.R0 Dated 8.2.2010
Your Discussion with our Representative
ABB
Force
Majeure Force Majeure is herein defines as any cause which is beyond the control of the
contractor or owner as the case may be, which they could not foresee, or with a
reasonable amount of diligence could not be foreseen, and which substantially
affects the performance of the contract such as:
a) Natural phenomena including but not limited to floods, droughts, earthquakes
and epidemics.
b) Act of Government, domestic or foreign including but not limited to war, declared
or undeclared priorities, quarantines, embargoes.
c) Riots and Civil commotion.
Transportation delay due to above force Majeure clause (a), (b) and (c) of above
Commercial Proposal
Page 4 of 4
Commercial Proposal
TATA POWER COMPANY LIMITED
JOJOBERA THERMAL POWER STATION
JOJOBERA, JHARKHAND
TECHNO-COMMERCIAL PROPOSAL
ABB LIMITED
PS POWER GENERATION
PLOT NO. 5 & 6, PHASE II,
PEENYA INDUSTRIAL AREA
BANGALORE 560 058
ABB
Customer Tata Power , Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P 13 Spare
E.UAPS.RE.9.0257.R1 dated 25/11/2009
Email dated 23/11/2009
ABB
Commercial Offer
Price Offer:
* We will require 2 days service for the same considering plant is under shutdown.
Techno-Commercial Proposal
Page 2 of 4
Commercial Proposal
Customer Tata Power , Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P 13 Spare
E.UAPS.RE.9.0257.R1 dated 25/11/2009
Email dated 23/11/2009
ABB
GENERAL TERMS AND CONDITIONS
Your Acceptance of our offer should be communicated through a written purchase order specifying the
following terms and conditions as an explicit acceptance of same.
Prices The quoted prices are net & firm and on DELIVERY, EX WORKS PEENYA
BANGALORE.
Excise Duty The offered prices are exclusive of all taxes and excise duties, levies, cess & octroi,
Sales Tax Service Tax etc. which have to be borne by you at actual as per the prevailing rates
And Other at the time of delivery and service. Present prevailing rate, ED is 8.24%, Sales Tax is
Levies 2%. You shall furnish necessary declaration forms wherever applicable.
Delivery Delivery time for supply of the modules is about 16 weeks from the date of receipt of
the technically and commercially clear/firm order.
Packaging Included.
and Handling
Freight The prices quoted do not include cost towards freight and transit insurance. The
material will be dispatched on Freight at actual shall be applicable and insurance
will be in your scope.
Note We shall intimate you the dispatch details to enable you to arrange insurance.
If you do not arrange the insurance, goods will be dispatched to you at your risk.
Warranty The warranty of the supplied system is limited against manufacturing defects for the
hardware items supplied as per the bill of material for a period of 12 months from
date of dispatch.
The warranty period shall expire prematurely if the customer or a third party
undertakes inappropriate modifications or repairs to the Supply or if the customer, in
the event of a defect, does not immediately take all appropriate steps to mitigate the
damage and give ABB the opportunity to remedy such defect.
Validity The above prices are valid till 11.12.2009. Prices will be having upward price
revision in the next financial year.
LD Clause Not Applicable as this is a spare offer.
Exclusion of Exclusion of Consequential Losses and Limitation of Liability:
Consequenti Notwithstanding anything contained in the conditions to the contrary, the
al damages & Supplier shall not be liable for any special, indirect or consequential damages
Limitation of or losses, such as, but not limited to, loss of revenue, loss of use, loss of
liability production, loss of data, loss of contracts, costs of capital or costs connected
with interruption of operation.
Techno-Commercial Proposal
Page 3 of 4
Commercial Proposal
Customer Tata Power , Jojobera
Project
Offer No
Enquiry ref
Quotation for Procontrol P 13 Spare
E.UAPS.RE.9.0257.R1 dated 25/11/2009
Email dated 23/11/2009
ABB
Force
Majeure Force Majeure is herein defines as any cause which is beyond the control of the
contractor or owner as the case may be, which they could not foresee, or with a
reasonable amount of diligence could not be foreseen, and which substantially
affects the performance of the contract such as:
a) Natural phenomena including but not limited to floods, droughts, earthquakes
and epidemics.
b) Act of Government, domestic or foreign including but not limited to war, declared
or undeclared priorities, quarantines, embargoes.
c) Riots and Civil commotion.
Transportation delay due to above force Majeure clause (a), (b) and (c) of above
Techno-Commercial Proposal
Page 4 of 4
Commercial Proposal
$% % $% # !
>* !! D
!! D F #?
" 5 ! !
67
ABB wins Best Power Plant Upgrade award at Asian Power Awards 2010 Page 1 of 1
ABB upgraded the control system for a 2 X 120 MW coal based thermal
power plant of Tata Power. Tata Power, erstwhile known as Tata Electric,
pioneered the generation of electricity in India nine decades ago. Today, it is
the country'
s largest private power utility.
The power plant feeds the steel plant at Tisco Jamshedpur, Jharkhand and Rekha Subramaniam, the local
is very critical to the operations of the large steel plant. The plant was facing Business Unit manager for Power
a problem of availability of the control system affecting the availability of Generation in India receiving the
power supply to steel plant. ABB conducted a survey and analyzed that award on behalf of ABB.
upgrading the system would significantly improve the reliability and
availability of the control system. Thus the customer will be able to achieve Contact us
the objective at a fraction of the cost of a new system.
Page information:
ABBs scope included upgrade of Procontrol P13 control and existing HMI
(Human Machine Interface) system, supply of new engineering and Rajeev Kishore
diagnostic tool - Progress3 for the Procontrol P13 system and supply of Anshuman N
critical spare parts. The State of the Art HMI system improves the plant
operations and the Function Chart Builder facility of the Progress3 will Contact us
facilitate on-line functional logic monitoring and simulation features for the
Procontrol P13 System. The upgrade was completed within a short plant General information:
maintenance period. Contact ABB
http://preview.inside.abb.com/cawp/seitp202/B24909EAC16B6A7F482577DC0029AA2... 12/13/2010