Unlike selected activities, Use the Progress Spotlight feature Choose View, Progress
when Progress Spotlight is Spotlight, or click the Progress Spotlight icon to highlight a timeperiod
active, activities remain equal to the smallest increment of the displayed timescale from the
spotlighted even when you previous data date. To increase/decrease the highlighted area between
click in another area of the the previous data date and the new date by one or more timescale
workspace.
increments, drag the data date line to the right or the left.
Update activities as described later in this chapter, or reschedule the
project immediately according to the new data date by pressing F9.
Drag the data date line Click the data-date line; when it changes to
an arrow, drag the line to the right until you reach the new data date. The
Project Management module spotlights the activities between the last
data date and the new data date. Update activities as described later in
this chapter, or reschedule the project immediately according to the new
data date by pressing F9.
For more information Depending on the density of the timescale above the activity bars, you
about the Update Progress
dialog box, see Estimating
may not be able to position the data date line on the exact date and time
Progress Automatically on you want to use. In this case, enter the data date in the Update Progress
page 306. dialog box and have the Project Management module estimate progress
as of that date before you update individual activities.
You can not drag the new data date line to a date that is
before the old data date line.
Click Apply. For each activity in the update, Project Management module
estimates percent complete amounts as of the data date, sets dates to actual
dates if they fall before the new data date, and estimates remaining
durations for activities that are not finished as of the data date. The Project
Management module also updates resource assignments based on each
activitys revised percent complete and remaining duration while adhering
to Autocost Rules. In addition, the Project Management module takes into
account only the first price per unit in the Resource Dictionary, if more
than one price per unit for varying through dates exists, when updating
resource assignments.
Mark the Auto Compute Actuals The Auto Compute Actuals option is
checkbox for each activity you listed in the General section of Available
want to update automatically. Options in the Columns dialog box.
For more information on Update progress automatically Once you set the appropriate Auto
applying actuals, see
Compute Actuals options, you can update progress automatically.
Interrupting Activity
Progress on page 320. Choose Tools, Apply Actuals.
For information on Approve timesheets Choose Tools, Time Approval. From the
configuring resources to
use timesheets, see the
Approving As drop-down list, if necessary, choose your designated time
Administrators Guide. approval role, which is determined by your security profile.
A notification message Select the timesheet period you want to review. In the top half of the
appears at the top right of window, select the timesheet you want to review; the window refreshes
the window when you have to display the timesheet details in the bottom half of the window. Right-
resubmitted timesheets to click the selected timesheet and select Approve to update the project
review. with activity progress, or select Reject to return a timesheet to a
Timesheets user.
Select a
timesheet
period.
Click to filter
timesheets by status,
such as Action
Required, Approved,
Rejected, or Not
Submitted.
Displays activity
information for the
selected timesheet.
Icon Description
Above the appropriate table, click to customize the columns you want
to display.
Icon Description
When you run a report as a resource manager, the report displays data
for all resources whose timesheets you are responsible for processing.
When you run a report as a project manager, the report displays data
for those projects to which you have OBS access.
Next to the appropriate timesheet, click to add or view notes for the
timesheet. To quickly view the last note added for a timesheet, hover
over the icon. This icon does not appear for Not Started timesheets.
For more information on Set percent complete type An activitys percent complete can be
defining activity and
duration types, see
calculated according to activity duration, activity units, or a physical
Working with Activities percent complete that you enter for each activity. Choose Project,
on page 211. Activities, and display the Activity Details General tab or add a column
for Percent Complete Type in the Activity Table.
Select the percent complete type based on how you report progress for
the activity.
Select Physical Percent Complete when activity progress can most
easily be reported based on personal judgment. Enter the activity
percent complete.
Select Duration when activity progress can be easily reported in
terms of actual calendar days of work remaining.
Duration% Cmp = [(Planned Duration Rem Duration) / Planned Duration]
x 100
Select Units when progress is best reported based on the work effort
that has been accomplished and how much effort remains. Enter the
actual and remaining units.
Units % Cmp = [Actual Units / At Completion Units] x 100
Update actual dates Once an activity is underway, update its start
and finish dates and other status information. Choose Project, Activities
and display the Activity Details Status tab. If the activity has actually
started, mark the Started checkbox, then specify the actual start date in
the Started field. If the activity is complete, mark the Finished
checkbox, then specify the actual finish date in the Finished field.
To update any other Update activities with Duration percent complete type In the
activity data, such as Activities window, select the activity to update and display the Activity
remaining duration or Details Status tab. In the Remaining field, type the remaining number of
actual units, you must first workperiods needed to complete the selected activity. When you
enter an actual start date schedule or apply actuals, the actual duration is calculated as the total
for the activity.
working time from the actual start date to the current data date (for in-
progress activities) or to the actual finish date (for completed activities),
using the activitys calendar.
The module calculates the actual Type a new remaining duration for the activity.
duration for the activity when you apply
actuals or schedule the project.
Actual Regular Units for a When you update activities manually, you should turn off Auto
resource indicate the Compute Actuals settings; otherwise, your changes are
actual amounts without overwritten when you apply actuals or calculate the schedule.
considering overtime units.
Actual Units include Actual
Regular Units plus Actual
Overtime Units.
When you update units in the The Labor Units amounts in the Status
Resources tab, the Started tab total the amounts for all resources
checkbox in the Status tab is assigned in the Resources tab.
automatically marked.
The Duration Type setting for an activity allows you to control how the
module synchronizes these variables when any one of the equations
variables are changed.
When you When you When you When you add When you add
Activity change units, change the change units/ the first additional
duration type this value duration, this time, this value resource, this resources, this
changes... value changes... changes... value changes... value changes...
The module calculates an actual duration for all activities based on the
amount of time actually worked. The amount of time an activitys
progress is suspended is considered nonworktime based on activity and
resource calendar definitions. You can use bar necking to graphically
display the suspended activitys nonworktime. In the Bars dialog, Bar
Settings tab, select the Calendar nonwork time option under Bar
Necking Settings. You can also show suspend and resume dates as
columns.
Applying Actuals
Once progress is recorded by approving timesheets, entering actual data,
and/or setting Auto Compute Actuals options, you must apply actuals.
Applying actuals schedules activities with progress and/or that have the
Auto Compute Actuals option set. When you apply actuals, you move
the data date or time now. The module schedules activities only within
the specified timescale (between the current data date and new data
date) and calculates progress for those activities that are set to
automatically calculate actuals.
Apply actuals Open the project or EPS node that contains the
projects to schedule. Choose Tools, Apply Actuals. If you opened an
EPS node that contains multiple projects, you can choose to use the
same data date for all projects and then specify the date, or you can
choose to use a different data date for each project and then select the
dates.
Choose to use a
different data date
for each project.
Link actual and actual this period units and cost To store
period performance on a project, the actual and actual this period units
and cost must be linked. Choose Enterprise, Projects. Click the Layout
Options bar and choose Show On Bottom, Project Details. In the Project
Details, Calculations tab, mark the Link Actual and Actual This Period
Units and Cost option.
For details on defining Post actual amounts for the period Choose Tools, Store Period
financial periods in the
Financial Periods
Performance. The Store Period Performance dialog box lists all open
dictionary, refer to the projects. For each project you want to store period performance for,
Primavera Administrators double-click in the Financial Period column to select a financial period.
Guide.
The Select Financial Period dialog box lists all financial periods
predefined in the Financial Periods dictionary. If you do not want to
store period performance for a project, remove the mark from the
corresponding checkbox in the Selected column.
Double-click in the
Financial Period
column to select a
financial period.
Click Store Now. The Project Management module stores the actual this
period values in the selected financial period for each project (regardless
of the data date or actual start dates), then sets actual this period values
to zero in anticipation of the next schedule update period.