The applicants must establish, implement and document the processes and
procedures required to achieve BIM objectives in the BIM Execution Plan
(BEP), including the following:
3. Inter-discipline collaboration
3.1 Data sharing process, framework and protocol, including the
data information and models to be shared, file formats and
frequency of data sharing
3.2 Coordination review process and plan, including use of BIM in
coordination meetings
3.3 Clash detection procedure, methodology and plan
Besides Items 1 3 above, BIM Fund applicants must fill up Items 4 9 below,
which will be reviewed for BIM Fund assessment purposes. Applicants may
use other templates, as long as the equivalent content of all Items 1 9 are
included and any other relevant information.
1
4. PROJECT INFORMATION
Project Owner
Project Title
Project Description
Contract Type
5. PROJECT MEMBERS
2
6. KEY PERFORMANCE INDICATORS
Key Performance Indicators are used to quantify the productive performance of the BIM project delivery.
3
7. MODEL CHECKLIST FOR BIM COLLABORATION
Notes
Applicants must fulfil at minimum the list below, in at least one of the following stages:
- Design stage before tender
- Before substructure construction
- Before superstructure construction.
4
7.2 INTER-DISCIPLINE 7.3 INTRA-DISCIPLINE
5
COORDINATION CLASHES: 1. OVERLAPS AND DUPLICATES:
Perform interference checks for all coloured boxes below Perform automated interference checks for the same element.
- The GREEN boxes are compulsory to be checked, if applicable. There must be zero interferences
There must be zero interferences 2. USE OF CORRECT OBJECTS:
Turn off visibility of all categories except for category to check.
There must be no instance of any model element not belonging to this category.
3. INFORMATION
Open prepared schedule
There must be no instance of any model type using "Generic", Typical,
"Default", or any ambiguous type
4. NAMING CONSISTENCY
In same schedule, all model types must be named consistently
ARCHITECTURAL STRUCTURAL
FoundationStructural
Structural Framing
ColumnStructural
Structural Wall
NAMING
Window
1 2 3 4
(others)
(others)
REMARKS
Ceiling
Floor
Door
Slab
Wall
CONVENTION
STRUCTURAL LARCHITECTURA
Floor 00
Wall
Ceiling
Door
Window
Generic Models
Structural Column
Structural
Foundation
Structural Framing
Structural Wall
Slab
Generic Models
MEP
Mechanical
Equipment
Ducts
Air Terminals
Pipe
6
Plumbing Fixtures
Cable Tray
Generic Models
Grids are aligned No clashes for pile cap Pipe clashing with pile cap
Grids are not aligned Single plumbing fixture Duplicate plumbing fixture
8. BIM Objective and Responsibility Matrix (Refer to Singapore BIM Guide Appendix B)
9. Model elements within each deliverable (Refer to Singapore BIM Guide Appendix A)