This document provides details for calculating the volume needed to create a balanced cement plug in a 9.5 inch casing with a 4 inch stinger at a depth of 7,600 feet. It determines that pumping 30 barrels of cement and displacing with an additional 78.4 barrels will result in a balanced plug with the top of cement at 7,238 feet below the surface.
This document provides details for calculating the volume needed to create a balanced cement plug in a 9.5 inch casing with a 4 inch stinger at a depth of 7,600 feet. It determines that pumping 30 barrels of cement and displacing with an additional 78.4 barrels will result in a balanced plug with the top of cement at 7,238 feet below the surface.
This document provides details for calculating the volume needed to create a balanced cement plug in a 9.5 inch casing with a 4 inch stinger at a depth of 7,600 feet. It determines that pumping 30 barrels of cement and displacing with an additional 78.4 barrels will result in a balanced plug with the top of cement at 7,238 feet below the surface.