Você está na página 1de 6

PROJECT:

Construction of 2Nos of 33KV Line for Construction Power


With
33/11KV SUB STATION WITH RMU

2 17.1.17 Revised as per comments SA IK


1 07.4.16 Revised as built at site SA IK
0 9/17/2014 SUBMITTED FOR APPROVAL SA IK
REV DATE DESCRIPTION CHKD APPD

NTPC LTD.
OWNER
ENGINEERING DIVISION

CONTRACTOR C & S Eectric Ltd. New Delhi


CONSTRUCTION OF 2NOS OF 33KV LINE FOR
PROJECT: CONSTRUCTION POWER WITH 33/11KV S/S WITH RMU FOR
DARLIPALI
DRN. NAME SIGN DATE
ALIF ENGINEERS & PLANNERS PRPD A.K. 07.4.16
MUMBAI CHKD S.A 07.4.16
APPD S.A 07.4.16

High Mast Foundation - DESIGN DOC NO: REV. NO.


TITLE :-
CALCULATIONS NESCL/NTPC/CS-DA-EE-101 R2

1
DOC.NO:
ALIF ENGINEERS AND
PLANNERS
Design calculation Mast Foundation
REV - R2

1.20

1.20 3.20

3.20
As per Mast design Page 8 1002-1-PVE-A-020-R3
Maximum vertical load at PL = 20.100 KN 2.049 T

Maximum shear at PL = 15.300 KN 1.560 T

Maximum moment at PL = 233.400 KN 23.792 T

Design Data:
Depth of Foundation = 2.0 m
Depth of filling 0 m
Safe Bearing capacity of soil = 10.0 t/m2
Density of soil = 1.6 t/m3
No of columns per foundation = 1
Gross Bearing capacity of soil = 10.0 x 1.25 + 1.6 x 2
= 15.70 t/m2

Grade of concrete = 25 N/mm2


Density of concrete = 2.5 t/m3
Reinforcement yield stress = 415 N/mm2
FOS = 1.5
Coefficient of friction between soil&conc = 0.2
Angle ofrepose = 10 degrees

0.3

2.0

0.3

3.20

C S ELECTRIC 2
DOC.NO:
ALIF ENGINEERS AND
PLANNERS
Design calculation Mast Foundation
REV - R2

Assume size of raft as follows


L = 3.20 m
B = 3.20 m A = 10.24 Sqm
t = 0.30 m Z = 5.461 m3

Depth of foundation from FGL = 2.0 m

Pedestal size pxp = 1.200 m x 1.200

Plinth level from FGL = 0.30 m


Height of pedestal = 2 m
SCF
Moment at base M = ( 23.792 + 1.560 x 2.30 )
= 27.38 tm Normal Cond
Factored Moment = 27.38 x 1.5 = 41.07 Tm

Height of soil = 1.70 m

Calculation of down thrust


Weight of raft w1 = 3.2 x 3.2 x 0.3 x 2.5
= 7.68 t

Weight of pedestal w2 = 1.2 x 1.2 x 2 x 2.5 x 1


= 7.20 t

Total wr = 7.68 + 7.20 = 14.88 t

Weight of soil ws = ( 3.20 x 3.20 )-(1x 1.2 x 1.2 ) x 1.70 x 1.7

ws = 25.43 t
Vertical
Equip load
+ str = 2.05 t

Total vertical load P = 14.88 + 25.43 + 2.05


= 42.36 t
Check for eccentricity, Bearing pressure & Overturning

Ecccn e = M/P 27.38 / 42.36 = 0.65 L/6 = 3.20 / 6 = 0.53

2
Therefore e > L/6 Pmax = 2P /( 3 B ( 0.5 L - e) = 9.254 t/m

Maxm soil press p1 (P/A + M/Z) = 42.36 / 10.24 + 27.38 / 5.461


= 4.14 + 5.01 = 9.15 t/m2

= 9.25 t/m2< 15.70 SAFE

Pmin = -0.88 t/m2 Less than 10% hence Ok. Take modified pressure

F.O.S against overturning = 42.36 x 3.2 / 2


= 27.38

= 2.48 > 1.5 SAFE

F.O.S against sliding = 42.36 x 0.2


1.560
= 5.43 > 1.5 SAFE
C S ELECTRIC 3
DOC.NO:
ALIF ENGINEERS AND
PLANNERS
Design calculation Mast Foundation
REV - R2

Design of bottom pad


Downward pressure to concrete = 0.3 x 2.5
2
= 0.75 t/m
Downward pressure due to earth = 1.7 x 1.6
= 2.72 T/m2

Net upward pressure on pad = 9.25 - 3.47


= 5.78 t/m2

Maximum overhang = 3.2 - 1.20


2.00
= 1.00 m

2
Maximum bending moment = 5.78 x 1.00 = 2.89 tm
2
Factored maximum moment = 2.89 x 1.5
= 4.34 tm
Effective depth d = 235 mm

Mu/bd2 = 42555361 = 0.77 N/mm2


2
1000 x 235
% steel = 0.221 %
Minimum % steel = 0.12 %
2
Ast required = 518.26 mm

Diameter of bars = 10 mm
Centre to Centre spacing provided = 81.58 mm (38 Nos in 3100mm)
2 2
Ast provided = 962.6 mm > 518.26 mm OK
Hence provided 10 mm @ 82 mm c/c at Bottom
10 mm @ 190 mm c/c at Top is safe
Check for shear:-
one way shear
Maximum shear at a distance "d" from the face of the column

Overhang from the face of the column = 1 - 0.235


= 0.765 m
Shear force = 5.78 x 0.765
= 4.42 t/m

Factored Shear force Vu = 4.42 x 1.5 = 6.637 t

Maximum shear stress Tv = 66371 = 0.28 N/mm2


1000 x 235
For pt '= 0.41
factor = 7.09
Permissible shear stress = c = 0.45 N/mm2 SAFE

C S ELECTRIC 4
DOC.NO:
ALIF ENGINEERS AND
PLANNERS
Design calculation Mast Foundation
REV - R2

Two way shear


Critrical section at d/2 from face of pedestal = 117.5 mm
Perimeter for fractured pyramid = 2 * (B1+d+L1+d) = 5270 mm
Area of fractured pyramid = (B1+d) * (L1+d) = 2.05923 m2

Punching shear = V = (A-Pyramid Area) * P Max = ( 10.24 - 2.06 ) x 5.78


= 47.317 Ton
Eff depth at critical section = 235 mm

Shear stress = Vu / (Perimeter * Min Depth) = 0.57 N/MM2

Allowable shear stress = 0.25 * SQRT(Fck) = 1.25 N/MM2 HENCE SAFE

Design of Pedestal
Pedestal size = 1.2 x 1.20 m
Vertical load on pedestal = 20.100 t

self weight of pedestal = 2 x 1.2 x 1.2 x 2.5


= 7.20 t

Total vertical load = 20.100 + 7.20 = 27.30 t

shear at plinth level = 1.56 t

Moment at the base of the pedestal = 1.56 x( 2.3 - 0.3 )


= 3.12 tm

0.3

2.0

0.3

3.20
Factored Total vertical load = 27.30 x 1.5 = 40.95 T
Factored Moment at the base of the pedestal =( 23.79 + 3.12 ) x 1.5 = 40.37 Tm

COMPRESSION WITH BENDING

lef = 2.0 x 2 = 4.00 m


lef / D = 3.33 < 12 Short Column

Total Moment = 40.37 + 0.00 = 40.37 Tm

Pu/fck bd = 0.01138 Mu/fck bd2 = 6.54E-09

Since Load is is very less only minimum reinforcement as per cl. 26.5.3(b) of IS 456 will be required.

Concrete area required to resist direct vertical load= 40.95 x 10000


0.36 x 25.00
= 45500.00 mm2

C S ELECTRIC 5
DOC.NO:
ALIF ENGINEERS AND
PLANNERS
Design calculation Mast Foundation
REV - R2

Minimum Ast required = 0.8 % of the concrete area required to resist direct vertical load

= 0.80 x ####### = 364.00 mm2


100.00
Provide longitudinal reinforcement of 36 nos 12 dia

Ast Provided = 4069.44 mm2


Spacing between reinforcement = 140.00 < 300 OK

Design for lateral ties :


Spacing of lateral ties shall be least of the following :-

I) Least lateral dimn of column = 1200.00 mm


ii) 16 x dia of longitudinal reinf = 16.00 x 12 = 192.00 mm
iii) 48 x dia of transverse reinforcement= 48.00 x 8 = 384.00 mm

Provide 8 Dia Links at 200 c/c


XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX