By: CEOoftheSOFA
July 4, 2010
This history of the Macondo well blowout has been assembled using information from
the Oil & Gas Journal and the Houston Chronicle, two of the more reliable sources of
information on the oil and gas industry.
The information released to the public on the cause of the blowout has been insufficient.
BP is unwilling to release information due to the liability issues. The federal government
has much information that it is not releasing. I have assembled as much reliable
information as I could and tried to make a reasonable guess as to the cause of the
blowout. My opinion on the cause differs from the views of the popular press.
The Macondo well is an exploratory well, in search of a new oil field at a water depth of
4992 ft. The well was estimated to require 51 days to drill at a cost of $96 million.
The well was spudded on October 7, 2009 by the Transocean Marianas. The drilling rig
was damaged in Hurricane Ida on Nov. 8-9 and was towed to a shipyard on November
26 for repairs. The Transocean Horizon rig resumed drilling when they landed the BOP
stack on February 8, 2010.
The well experienced four well control events. A well control event is when formation
fluids (oil, gas, water) enter the wellbore, also known as a “kick”. These events occurred
on Feb. 17-23, March 2-5, March 8-14, and April 4-7. The primary method of detecting
a kick is to measure increases of drilling mud volume in the mud tanks. Typically, when
this is observed, the pipe rams on the blow-out preventer are closed. The pipe rams
seal around the drill pipe. The mud flow exiting the well is directed through a choke
valve which is partially closed to increase the surface pressure. This increases the
bottom hole pressure and prevents further influx of formation fluids into the wellbore.
The formation fluids are then circulated out of the well while increasing the mud weight
by adding barite to the drilling mud. When the mud weight is increased, it is no longer
necessary to hold back pressure with the choke valve. At this point, drilling can resume.
A synthetic, oil based drilling mud was used. At the completion of the drilling, the mud
weight was 14 pounds per gallon (ppg). This equates to a formation pressure of 13,366
pounds per square inch (psi).
The well was drilled to a total depth of 18,360 ft. A tapered string of production casing
consisting of 7” and 9-5/8” casing was run from the total depth of the well to the surface.
The casing was cemented by Halliburton. The purpose of the cement is to seal out
formation fluids. When the well is ready to be put on production, holes will be perforated
into the casing to allow oil and gas to enter the wellbore.
This represents a very aggressive casing program and is the primary reason the well
drilling was behind schedule. The casing program was increased in response to the four
well control events. The well is encased in steel down to a depth of 17,168 ft. The well
is currently flowing behind the 7” production casing, so the three lower liners and the 16”
casing are exposed to the oil flow. The 9-5/8” liner is the weak point with a yield strength
of 22,000 psi which is 9,000 psi greater than the shut-in reservoir pressure. The well is
therefore capable of withstanding the shut-in reservoir pressure if the well were shut in.
After the cement job of the production casing, the next task was to temporarily plug the
well by setting several cement plugs in the well. This is done by running drillpipe and
tubing to several different depths and spotting cement plugs. Prior to doing this, it was
necessary to replace the oil based drilling mud with sea water, since the drilling mud
would contaminate the cement. Seawater weighs about 5 ppg less than the drilling mud,
and would not exert sufficient hydrostatic pressure on the oil formation to prevent fluid
flow into the wellbore. If the cement were holding properly, it would not matter if the
hydrostatic pressure were high enough since the cement should have sealed the well.
There was a difference of opinion on the rig concerning the results of the pressure tests
that were run to evaluate the cement job. A meeting was held at 1:00 PM on April 20,
between the BP head drilling engineer and the lead Transocean engineer. It is not
known what they were arguing about, but it is likely they were arguing over the results of
the pressure tests. Apparently, the Transocean engineers thought the results showed
that formation fluids were entering the wellbore due to a failed cement job, but they were
overruled by the head BP drilling engineer who made the decision to continue. (One of
the Transocean people was heard saying “well at least we have the BOP’s”, after leaving
the meeting.) At 7:50 PM a pressure test was performed after which BP incorrectly
concluded that formation fluids were not entering the wellbore. However, right after
that, personnel on the rig floor reported that the fluid rate exiting the well was greater
than the fluid rate entering the well. At 9:00, gas began coming out of the riser. Despite
this, the pumping of seawater did not stop until 9:31. The gas ignited at 9:49 and the
entire rig was engulfed in flames. The blind shear rams on the blowout preventers were
not closed until after this. These rams should shear the drill pipe and completely seal
the well. 8,300 feet of drill pipe was then dropped into the 18,360 ft well. The blind
shear rams only partially sealed the well. Because of the bad cement job, the well is
now flowing outside the 7 inch production casing. The well pressure is now being
exerted on the three lower liner strings and the 16” casing which was set at a depth of
11,585 ft.
Shortcuts
BP took several shortcuts which may have compromised the integrity of the well.
1. A cement bond log was not run. The usual practice is to run a cement bond log
to evaluate the effectiveness of the cement job. Schlumberger was on site to run
the cement bond log, but BP decided not to run one, presumably to save the 12
hours it would take to run it. Pressure tests were run instead, but were
inconclusive.
2. A lockdown sleeve was not used in the wellhead seal assembly for the
production casing. This could cause the seal to unseat if there is upward
movement of the casing, allowing fluid to enter the riser. Upward movement is
normal as the casing expands when the temperature increases during the
production of formation fluids.
3. Only 261 bbl of mud was circulated prior to the cement job, which is far short of
the usual 1.5 times the hole volume that is recommended by the API. The
purpose of this is to clean the hole of debris and formation fluids, to improve the
integrity of the cement job. This also saved 12 hours of time.
4. BP has been criticized for running production casing instead of a liner. The liner
would have been sealed inside the next higher liner which would have given an
additional seal to prevent migration of formation fluids. The liner could have then
been tied back to the surface. As it is now, the well is producing oil and gas from
behind the production casing.
5. There was testimony that BP only used 6 centralizers instead of the
recommended 21 on the production casing. Centralizers cost about $100 each
and take about 2 minutes to install. Centralizers keep the casing in the middle of
the hole to improve the cement bond.
The popular press has focused on these shortcuts as the ultimate cause of the blowout,
and that these shortcuts were taken just to save money. These 5 items together only
saved one or two days of rig time, or about a million dollars. The press has charged that
BP ordered these short cuts because the well was behind schedule and over budget. I
don’t buy it. It is not uncommon for exploratory wells to be over budget. They should
have been happy that they had a discovery.
I don’t think the fault should be focused only on the failed blowout preventer or the bad
cement job. Bad cement jobs happen occasionally without resulting in burned rigs.
Blowout preventers are supposed to be activated before the rig is engulfed in flames. I
think the key cause of the blowout is simple human error (SHE) on the part of the BP
head drilling engineer, who did not notice that the well was kicking. The well was likely
kicking all afternoon and evening, and no one noticed until gas was coming out of the
riser. It is inexcusable to allow this to go unnoticed for such a long time. All drilling
engineers must be certified in well control. An annual class must be taken, with a written
test and a test on a rig simulator. The primary thrust of the class is to determine when a
well is kicking.
For this reason, I believe the primary cause of the blowout is simple human error on the
part of BP. If the BP employees noticed that the well was kicking, the shortcuts would
never have come into play. An undetected kick could have caused a blowout during any
of the four well control events, where the failed cement job would not have been a factor.
For this reason, I believe BP will be found to be almost completely at fault. Transocean
had the right to stop the operation, and for this reason they may bear a small amount of
responsibility. The only way I can see Halliburton taking a small part of the blame is if it
is shown that the cement was improperly mixed or displaced.
I don’t fault the Transocean blowout preventers because the rig was already on fire
when they were activated. Blowout preventers are supposed to be activated before the
rig is on fire. It is possible that the rig may have moved during the explosion and may
have put the riser at an angle and prevented the proper closing of the BOP. Subsequent
investigations will reveal if this was the case.
The above indicates how easy it is for a blowout to occur. I’m surprised it doesn’t
happen more often. Since it is so easy for this to happen, it is inexcusable that BP
should have been so completely unprepared for the aftermath. BP should have had the
containment system built and tested ahead of time. (Shell had one on standby) And
there should have been much more surface cleaning assets on standby, such as booms
and skimmers. BP was so unprepared, that I believe they should have their drilling bond
revoked in the Gulf of Mexico and they should be made to pay for each individual’s loss
due to the spill, even if it causes BP to go bankrupt. Politicians that are paid off by the
petroleum industry have indicated that this liability will prevent smaller companies from
drilling in deep water. That’s too bad. I also believe that the 6 month drilling moratorium
is necessary because all available oil containment assets are already in use and there
would be nothing available if there were another blowout on another well.