ID Task Task Name Duration PredecessorsStart 28 Jun '15 05 Jul '15 12 Jul '15 19 Jul '15 26 Jul '15

05 Jul '15 12 Jul '15 19 Jul '15 26 Jul '15 02 Aug '15 09 Aug '15 16 Aug '15 23 Aug '15 30 Aug '15 06 Sep '15 13 Sep '15 20 Sep '15 27 Sep '15
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
1 Proyek Rumah Hantu 64 days Wed 01/07/15
2 Pek.Persiapan 6 days Wed 01/07/15
3 Pembersihan.Lahan 4 days Wed 01/07/15
4 Pemasangan Bowlank 2 days 3 Tue 07/07/15
5 Pek.Lantai 1 64 days Wed 01/07/15
6 A.Pek.Pondasi 18 days Thu 09/07/15
7 Galian Tanah 4 days 4 Thu 09/07/15
8 Urugan Pasir 2 days 7 Wed 15/07/15
9 Aanstampeng 2 days 8 Fri 17/07/15
10 Pond Batu Kali 1pc:4ps 10 days 9 Tue 21/07/15
11 Urugan kembali 4 days 10SF Wed 15/07/15
12 B.Pek.Beton Lt.1 62 days Wed 01/07/15
13 Pek.Strous 6-15 6 days Tue 14/07/15
14 Pek.Bekesting 0 days 7 Tue 14/07/15 14/07
15 Pek.Pembesian polos 5 days 14SS Wed 15/07/15
16 Pek.Pembesian ulir 5 days 14SS Wed 15/07/15
17 Pek.Beton 1 day 15;16;14 Wed 22/07/15
18 Pek.Sloof 20/25 2-12 3 days Wed 15/07/15
19 Pek.Bekesting 2 days 7 Wed 15/07/15
20 Pek.Pembesian polos 2 days 19SS Wed 15/07/15
21 Pek.Pembesian ulir 2 days 19SS Wed 15/07/15
22 Pek.Beton 1 day 19;20;21 Fri 17/07/15
23 Pek.Kolom 15/15 4 days Wed 15/07/15
24 Pek.Bekesting 2 days 19 Fri 17/07/15
25 Pek.Pembesian polos 2 days 19SS Wed 15/07/15
26 Pek.Pembesian ulir 2 days 19SS Wed 15/07/15
27 Pek.Beton 1 day 22 Mon 20/07/15
28 Pek.kolom 20/20 6 days Wed 15/07/15
29 Pek.Bekesting 2 days 24 Tue 21/07/15
30 Pek.Pembesian polos 2 days 25SS Wed 15/07/15
31 Pek.Pembesian ulir 2 days 25SS Wed 15/07/15
32 Pek.Beton 1 day 22SS Fri 17/07/15
33 Pek.Balok B1 (17,5 x 35) 7 days Mon 20/07/15
34 Pek.Bekesting 5 days 32 Mon 20/07/15
35 Pek.Pembesian polos 5 days 34SS Mon 20/07/15
36 Pek.Pembesian ulir 5 days 34SS Mon 20/07/15
37 Pek.Beton 1 day 40 Tue 28/07/15
38 Pek.Balok B2 (15 x30) 6 days Mon 27/07/15
39 Pek.Bekesting 1 day 36 Mon 27/07/15
40 Pek.Pembesian polos 1 day 39SS Mon 27/07/15
41 Pek.Pembesian ulir 1 day 39SS Mon 27/07/15
42 Pek.Beton 1 day 37FF+4 daysMon 03/08/15
43 Pek.Tangga Beton 1 7 days Mon 27/07/15
44 Pek.Bekesting 3 days 39SS Mon 27/07/15
45 Pek.Pembesian polos 3 days 39SS Mon 27/07/15
46 Pek.Beton 1 day 42 Tue 04/08/15
47 C.Pekerjaan Pasangan 30 days Wed 05/08/15
48 Pek.Pas dding bata (1pc:5ps) 30 days 46 Wed 05/08/15
49 Pek.Pasbata trasram (1pc:3ps) 5 days 48SS Wed 05/08/15
50 Pek.Plesteran Trasram (1pc:2ps)3 days 49 Wed 12/08/15
51 Pek.Plesteran (1pc:2ps) 6 days 50 Mon 17/08/15
52 Pek.Ancian 7 days 51 Tue 25/08/15
53 D.Pekerjaan Lantai 32,5 days Fri 24/07/15
54 Pas.Keramik 40x40 5 days 134SF+5 days
Fri 24/07/15
55 Pas.Keramik 30x30 5 days 54SS Fri 24/07/15
56 Rabat beton 1pc:3ps 1 day 51 Tue 25/08/15
57 Urugan pasir bawah keramik 4 days 52 Thu 03/09/15
58 Pek.keramik Tangga 6 days Fri 24/07/15
59 keramik 30x30cm 4 days 55SS Fri 24/07/15
60 keramik artistik 5x 20cm 2 days 59 Thu 30/07/15
61 keramik 20 x 20 cm 2 days 60SS Thu 30/07/15
62 E.Pekerjaan Kusen 4 days Wed 16/09/15
63 Pek.Kusen Pintu 1 2 days 48 Wed 16/09/15
64 Pek.Kusen Pintu 2 2 days 63SS Wed 16/09/15
65 Pek.Kusen Pintu 3 2 days 63SS Wed 16/09/15
66 Pek.Kusen Pintu 4 (alum) 0,5 days 63SS Wed 16/09/15
67 Pek.Kusen Jendela 2 4 days 63SS Wed 16/09/15
68 Pek.Kusen Jendela 3 1 day 63SS Wed 16/09/15
69 Pek.Kusen Jendela 4 0,5 days 63SS Wed 16/09/15
70 Pek.Kusen Jendela 6 2 days 63SS Wed 16/09/15
71 Pek.Kaca Jendela 2 (5cm) 0,5 days 70 Fri 18/09/15
72 Pek.Kaca Jendela 3(5cm) 0,5 days 70SS Wed 16/09/15
73 Pek.Kaca Jendela 4 (5cm) 0,5 days 70SS Wed 16/09/15
74 Pek.Kaca Jendela 6 (5cm) 0,5 days 70SS Wed 16/09/15
75 Pek.Kaca Daunpintu 1(5mm) 0,5 days 70SS Wed 16/09/15
76 Pek.Relling Tangga 3 days 80 Thu 17/09/15
77 Pek.Daun pintu 1 0,25 days 63SS Wed 16/09/15
78 Pek.Daun pintu 2 2 days 63SS Wed 16/09/15
79 Pek.Daun Pintu 3 1 day 63SS Wed 16/09/15
80 Pek.Daun Pintu 4 1 day 63SS Wed 16/09/15
81 Pas.Handle pintu & jendela 2 days 80 Thu 17/09/15
82 Pas.Engsel pintu & Jendela 2 days 80SS Wed 16/09/15
83 Pas.Pengunci Pintu & Jdl 1 day 80SS Wed 16/09/15
84 F.Pekerjaan Pengecatan 5 days Thu 17/09/15
85 Pek.plamir 5 days 83 Thu 17/09/15
86 Pek.Cat dinding,kolom,balok dll 5 days 85SF+5 daysThu 17/09/15
87 Pek.Cat Kusen 2 days 85SF+2 daysThu 17/09/15
88 Pek.Cat daun pintu 1 day 85SF+1 dayThu 17/09/15
89 Pek.pengecatan lisplank 2 days 85SF+2 daysThu 17/09/15
90 Pek.Pengecatan plafon 2 days 85SF+2 daysThu 17/09/15
91 G.Pekerjaan Instalasi Listrik 1 day Fri 31/07/15
92 Pek.Pemasangan Kabel 1 day 54 Fri 31/07/15
93 Pek.Pas saklar tunggal 1 day 92SS Fri 31/07/15
94 Pek.Pas saklar Ganda 1 day 92SS Fri 31/07/15
95 Pek.Pas sekering dan MCB 1 day 92SS Fri 31/07/15
96 Pek.Pemasangan Titik lampu 1 day 92SS Fri 31/07/15
97 H.Pekerjaan Sanitasi Air 1,5 days Mon 20/07/15
98 Pekerjaan Sanitasi Air bersih 1 day Mon 20/07/15
99 Pek.Kran Air 1 day 22 Mon 20/07/15
100 Pek.Pipa PVC 1 day 99SS Mon 20/07/15
101 Pek.Wastafel 1 day 99SS Mon 20/07/15
102 Meteran PDAM 1 day 99SS Mon 20/07/15
103 Tandon Air 0,5 days 99SS Mon 20/07/15
104 Pekerjaan Sanitasi Air Kotor 1 day Mon 20/07/15

Project: ADI 125724244 PROJRCT Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Wed 01/06/16 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 1
ID Task Task Name Duration PredecessorsStart 28 Jun '15 05 Jul '15 12 Jul '15 19 Jul '15 26 Jul '15 02 Aug '15 09 Aug '15 16 Aug '15 23 Aug '15 30 Aug '15 06 Sep '15 13 Sep '15 20 Sep '15 27 Sep '15
Mode M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T
105 Pek.Pipa PVC 3'' 1 day 103 Mon 20/07/15
106 Pas.Closet Jongkok 1 day 105SS Mon 20/07/15
107 Pas.Closet Duduk 1 day 105SS Mon 20/07/15
108 Pek.flour drain 0,5 days 105SS Mon 20/07/15
109 Pek.Septick Tank 1 day 105SS Mon 20/07/15
110 Pek.Resapan 1 day 105SS Mon 20/07/15
111 I.Pekerjaan Plafon 64 days Wed 01/07/15
112 Rangka plafon dalam 5/7 5 days 76 Tue 22/09/15
113 Plafond 100X100cm 5 days 112SF+5 days
Tue 22/09/15
114 Lis plafond 4 days 12SF+4 daysWed 01/07/15
115 Pekerjaan Lt. 2 48 days Tue 21/07/15
116 A.Pekerjaan Beton LT 2 8 days Tue 21/07/15
117 Pek.kolom K1 20/20 2 days Tue 21/07/15
118 Pek.Bekesting 2 days 110 Tue 21/07/15
119 Pek.Pembesian polos 2 days 118SS Tue 21/07/15
120 Pek.Pembesian ulir 2 days 118SS Tue 21/07/15
121 Pek.Beton 1 day 118SS Tue 21/07/15
122 Pek. Kolom Praktis KP 15/15 4 days Tue 21/07/15
123 Pek.Bekesting 2 days 118 Thu 23/07/15
124 Pek.Pembesian polos 2 days 123SS Thu 23/07/15
125 Pek.Pembesian ulir 2 days 123SS Thu 23/07/15
126 Pek.Beton 1 day 121SF+1 dayTue 21/07/15
127 Pek.Balok B2 (15 x30) 2 days Wed 22/07/15
128 Pek.Bekesting 2 days 126 Wed 22/07/15
129 Pek.Pembesian polos 2 days 128SS Wed 22/07/15
130 Pek.Pembesian ulir 2 days 128SS Wed 22/07/15
131 Pek.Beton 1 day 126 Wed 22/07/15
132 Pek.Balok B3 (15 X 25) 3 days Thu 23/07/15
133 Pek.Bekesting 2 days 128 Fri 24/07/15
134 Pek.Pembesian polos 2 days 133SS Fri 24/07/15
135 Pek.Pembesian ulir 2 days 133SS Fri 24/07/15
136 Pek.Beton 1 day 131 Thu 23/07/15
137 Pek.Plat Lantai 2 (tebal 12 cm) 5 days Fri 24/07/15
138 Pek.Bekesting 4 days 136 Fri 24/07/15
139 Pek.Pembesian polos 4 days 136 Fri 24/07/15
140 Pek.Beton 1 day 138;139 Thu 30/07/15
141 Pek.Ring Balok 20/40 3 days Fri 24/07/15
142 Pek.Bekesting 2 days 128 Fri 24/07/15
143 Pek.Pembesian polos 2 days 142SS Fri 24/07/15
144 Pek.Pembesian ulir 2 days 142SS Fri 24/07/15
145 Pek.Beton 1 day 143;144 Tue 28/07/15
146 B.Pekerjaan Pasangan 31 days Wed 29/07/15
147 Pek.Pas bata merah (1pc:5ps) 15 days 145 Wed 29/07/15
148 Pek.Pas bata trasram (1pc:3ps) 1 day 147 Wed 19/08/15
149 Pek.Plesteran Trasram (1pc:2ps)2 days 148 Thu 20/08/15
150 Pek.Plesteran (1pc:2ps) 7 days 148 Thu 20/08/15
151 Pek.Ancian 8 days 150 Mon 31/08/15
152 C.Pekerjaan Lantai 2 days Thu 10/09/15
153 Pas.Kramik 40x40 2 days 151 Thu 10/09/15
154 Pas.Kramik 30x30 1 day 153SS Thu 10/09/15
155 Rabat beton 1pc:3ps 1 day 154SS Thu 10/09/15
156 D.Pekerjaan Kusen 6 days Fri 11/09/15
157 Pek.Kusen Pintu 2 1 day 155 Fri 11/09/15
158 Pek.Kusen Pintu 3 1 day 157SS Fri 11/09/15
159 Pek.Kusen Pintu 4 (alumunium) 0,5 days 157SS Fri 11/09/15
160 Pek.Kusen Pintu 5 0,5 days 157SS Fri 11/09/15
161 Pek.Kusen Jendela 1 0,5 days 157SS Fri 11/09/15
162 Pek.Kusen Jendela 2 4 days 157SS Fri 11/09/15
163 Pek.Kusen Jendela 6 1 day 157SS Fri 11/09/15
164 Pek.Kaca Jendela 1 (5mm) 1 day 163 Mon 14/09/15
165 Pek.Kaca Jendela 2 (5mm) 1 day 164SS Mon 14/09/15
166 Pek.Kaca Jendela 6 (5mm) 1 day 164SS Mon 14/09/15
167 Pek.Daun pintu 2 1 day 164SS Mon 14/09/15
168 Pek.Daun Pintu 3 1 day 164SS Mon 14/09/15
169 Pek.DaunPintu 4 1 day 164SS Mon 14/09/15
170 Pek.Daun Pintu 5 1 day 164SS Mon 14/09/15
171 Pas.Handle pintu & jendela 4 days 170 Tue 15/09/15
172 Pas.Engsel pintu & Jendela 1 day 171SS Tue 15/09/15
173 Pas.Pengunci Pintu & Jendela 0,5 days 171SS Tue 15/09/15
174 E.Pekerjaan Pengecatan 4 days Wed 16/09/15
175 Pek.Plamir 4 days 173 Wed 16/09/15
176 Pek.Cat Dinding,kolom,balok dll 4 days 175SS Wed 16/09/15
177 Pek.Cat Kusen 1 day 175SS Wed 16/09/15
178 Pek.Cat daun pintu 4 days 175SS Wed 16/09/15
179 Pek.pengecatan lisplank 1 day 175SS Wed 16/09/15
180 Pek.cat plafond 1 day 198 Fri 18/09/15
181 F.Pekerjaan Instalasi Listrik 45,5 days Wed 22/07/15
182 Pek.Pemasangan Kabel 2 days 180 Mon 21/09/15
183 Pek.Pas saklar tunggal 1 day 192FS+3 days
Tue 28/07/15
184 Pek.Pas saklar Ganda 0,5 days 192SS Wed 22/07/15
185 Pek.Pas sekering dan MCB 0,5 days 192SS Wed 22/07/15
186 Pek.Pemasangan Titik lampu 1 day 192SS Wed 22/07/15
187 G.Pekerjaan Sanitasi Air 2 days Tue 21/07/15
188 Pekerjaan Sanitasi Air bersih 1 day Tue 21/07/15
189 Pek.Kran Air 0,5 days 99 Tue 21/07/15
190 Pek.Pipa PVC 1 day 189SS Tue 21/07/15
191 Tandon Air 1 day 189SS Tue 21/07/15
192 Pekerjaan Sanitasi Air Kotor 1 day Wed 22/07/15
193 Pas.Closet Duduk 1 day 191 Wed 22/07/15
194 Pek.flour drain 1 day 193SS Wed 22/07/15
195 Pek.PVC 3'' 1 day 193SS Wed 22/07/15
196 H.Pekerjaan Plafon 4 days Mon 14/09/15
197 Rangka plafon dalam 5/7 4 days 153 Mon 14/09/15
198 Plafond 100X100cm 4 days 197SS Mon 14/09/15
199 Lis plafond 3 days 197SS Mon 14/09/15
200 I.Pekerjaan Atap 5,5 days Thu 17/09/15
201 Pek.Kuda-kuda 3 days 199 Thu 17/09/15
202 Pek.Pengapit 6/12 0,5 days 201SS Thu 17/09/15
203 Pek.Gording 8/12 1 day 202 Fri 18/09/15
204 Pek.Kasau 5/7 4 days 203 Mon 21/09/15
205 Pek.Nok 8/12 1 day 204SS Mon 21/09/15
206 Pek.lisplank 2/20 1 day 204SS Mon 21/09/15
207 Pek.Bubungan 3 days 204SS Mon 21/09/15
208 Pas.Genteng 3 days 205SS Mon 21/09/15

Project: ADI 125724244 PROJRCT Task Milestone Project Summary External Milestone Inactive Milestone Manual Task Manual Summary Rollup Start-only Deadline
Date: Wed 01/06/16 Split Summary External Tasks Inactive Task Inactive Summary Duration-only Manual Summary Finish-only Progress

Page 2

Você também pode gostar