Escolar Documentos
Profissional Documentos
Cultura Documentos
CONSTRUCTION METHODOLOGY
1
POLE ERECTION
1. Coordination with UPLB Project Engineer prior to proceeding to any work &
securing necessary work permit.
2. Request for a schedule of Temporary Power Interruption on areas affected by the
erection of concrete poles. The specific areas are:
For 13.2 kV To be discuss on coordination meeting.
Note:
a) Schedule of shutdown for 13.2 kV must be within one single day as much as
possible during Saturdays and Sundays as discussed in the pre-bid
conference.
3. Prior to erection, install ground wire inside the concrete poles.
4. Assist UPLB Engineering personnel in de-energization of power supply on affected
areas.
5. Isolate power from energy source, Install lock-out and tag-out, discharging stored
energy and installing cluster grounding prior to proceeding with the activity.
6. Install warning signs and caution tape around the work area.
7. Assign personnel to man the traffic flow.
8. Erection of each pole using crane and telescopic man-lift equipment, to ensure fast
and accurate movement and avoid delay in the schedule of temporary power
interruption.
9. The back fill is thoroughly tamped the full depth.
2
POLE DRESSING AND STRINGING OF WIRE
1. Install a High Voltage Barrier on High Voltage line if any on opposite the
proposed location of stringing during scheduled shutdown in preparation for the
preceding works. In case the proposed work activities on potentially energized
area are restricted. For safety considerations, longer schedule from 6 AM to 5 PM
of temporary interruption shall be requested or a second schedule shall then be
considered.
2. The minimum line to line clearance from potentially energized 69 kV and 13.2 kV
respectively must be 1.8 meters away. The minimum line to line clearance for
13.2 kV must be 1.2 meters.
3. Installation of cross arms and its braces, insulators and other pole line accessories
using telescopic man-lift equipment particularly when working near the High
Voltage line. Clearance of workers from potentially energized line must be 1.8
meters away for safety consideration.
4. Installation of cross arms and its braces, insulators and other pole line accessories
by pulling-up manually using single pulley attached on the upper tip hole of the
pole. This procedure is applicable for non potentially energized power lines area.
5. In preparation for stringing of ACSR wire, a 1 diameter nylon rope are stringed
first to serve as pulling aid. Pulleys and rollers are installed in every pole to serve
as guide and protection of the ACSR wire.
6. ACSR wires are placed on a stand spool that will serve as dispenser during
stringing. The ACSR wires are to be tied to the end individually by a 1 diameter
nylon rope.
7. Hand held radios will to be used during stringing to man the puller and the
dispenser teams to synchronizing with each other.
8. Self-loading truck is to be used to pull the nylon rope.
9. Tensioning of ACSR wires are by fixing to one end using suspension insulators
and strain clamps, and pulling to the other end using ratchet type chain block to
the desired sagging level.
10. Wire sagging will be observed depending on the spanning distance and size of
wire.
3
2. Installation of fuse cut-outs and lightning arresters are to be mounted on steel
cross arm using L& I bracket. Clearance, accessibility, ampere rating of fuse link
and rating of lightning arrester must be properly observed.
3. Ground terminal of lightning arrester must be connected to system / equipment
grounding and or on grounding rod.
TURNOVER
1. Conduct proper coordination to UPLB project-in-charge to formalize the final
turn-over of the project.
2. Rectify punch lists if any.