Você está na página 1de 59

ISPE Central Canada Chapter

BAS Lifecycle Overview using GaMP

January 24, 2006 Toronto


January 25, 2006 Montreal

Irene Miess Sr Manager Regulated Industries


Siemens Building Technologies

Company Confidential
BAS Lifecycle Overview using GaMP

GaMP Model

System Impact Assessment

Direct Impact Systems


Indirect Impact Systems

Good Engineering Practice


Commissioning
Qualification Practices
Installation and Operational Qualification

Documentation Requirements
Ongoing Operation

Company Confidential
Good Automated Manufacturing Practice (GaMP)

As a regulated site supplier, what guidance do we have in


delivering a validated and compliant system?

Design & Commissioning Ongoing


Planning Installation
Development & Qualification Operation

FAT
NO
Required? Good Automated Manufacturing
Practice (GaMP)
GaMP provides a method to relate
YES
development activities to validation
Factory activities on automated systems using a
Acceptance life cycle approach
Testing

Company Confidential
Good Automated Manufacturing Practice (GaMP)

GaMP was created due to:


the increased use and complexity of automated systems in FDA regulated
manufacturing areas

the less mature interpretation of regulations in automated applications


than in more conventional, non-automated areas

GaMP benefits FDA regulated companies by:


Improving the understanding & interpretation of regulations
Providing established guidelines for
suppliers of automated systems

Clarifying the division of responsibility


between user and supplier

Reducing the cost and time taken to


achieve compliant systems
A GaMP Industry Board establishes
GaMP principles and recommendations
Company Confidential
Project Lifecycle (GaMP)

Design & Commissioning Ongoing


Planning Installation
Development & Qualification Operation

FAT
NO
Required?

YES

Factory
Acceptance
Testing

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional and Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
Master Validation Plan

The Validation Master Plan (VMP) is the key document in the overall
validation process, and is critical to the success of the project. It is an
important project document and a living document that must be
maintained throughout the project life cycle.
The validation master plan typically defines:

Validation Strategy
Validation Deliverables
Acceptance Criteria
Change Control Management
Standard Operating Procedures
Training
Documentation Management
Maintaining a Validated State

Company Confidential
Master Validation Plan

BAS needs to be addressed

Monitor & Alarm only

Direct Impact only

If you want tomatoes,

dont plant turnips!

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional and Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
User Requirements

The User Requirement Specification (URS) specifies the


requirements of the user for individual aspects of the facility,
equipment, and systems in terms of function, throughput,
operability, and applicable standards
Defines what the user wants the system to do. What functions
will be carried out, the data on which the system will operate,
and the operating environment. Non-functional requirements,
such as constraints (that is, time) and what deliverables will be
provided by the system (that is, Training, Testing, Tools), are
also documented
The User Requirement Specification (URS) and Performance
Testing are linked. The URS provides the performance
benchmark criteria upon which the performance qualification
(PQ) is based

Company Confidential
BAS User Requirement Spec

Do you want
to follow GaMP
traceability matrix
functional specs
testing

calibratable sensors
commissioning documents
remote notification
horn/bell
paging

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
Impact Assessment

A process which allows a complex situation of interdependent


engineering systems and components to be reviewed,
understood and systematically evaluated for their effect on
product quality (Commissioning vs. Qualification).

Company Confidential
Relationship Between Systems and Components

Components

Critical Non-Critical

Direct
Good
Impact Engineering
Practices +
Systems Qualification
Practices
Indirect/
No Impact 8 Good
Engineering
Practices +
Commissioning

Company Confidential
System Level Assessment

System: An organization of engineering components


which have defined operational function (e.g., piping,
instrumentation, equipment, facilities, computer hardware,
computer software, etc.)

System Boundary: A limit drawn around a system to


logically define what is and is not included in the system.

Company Confidential
System Level Assessment

Direct Impact System: An engineering system that is


expected to have a direct impact on product quality.

Indirect Impact System: An engineering system that is


not expected to have a direct impact on product quality,
but is linked to a direct impact system.

No Impact System: An engineering system that is not


expected to have an impact on product quality.

Company Confidential
System Level Assessment

System Impact Assessment: The process of evaluating


the impact of the operating, controlling, alarming and
failure conditions of a system on the quality of a product.
The quality of the product can be impacted by a system
or systems which meets any of the following criteria:
In contact with the product
Used as an excipient
Controls the process or
Provides information relative to product acceptance or
rejection

Company Confidential
Component Level Assessment

Critical Component: A component within a system


where the operation, contact, data, control, alarm or
failure will have a direct impact on the quality of the
product.
Non-Critical Component: A component within a system
where the operation, contact, data control, alarm or
failure will have an indirect or no impact on the quality of
the product.

Company Confidential
Relationship Between Systems and Components

Components

Critical Non-Critical

Direct
Good
Impact Engineering
Practices +
Systems Qualification
Practices
Indirect/
No Impact 8 Good
Engineering
Practices +
Commissioning

Company Confidential
BAS Draw Boundaries
HVAC

BAS only

AHU controls

zone controls

monitor & alarm

Design system accordingly


Separation by panels

Separate GMP from non GMP

Company Confidential
Where are YOUR Boundaries

Sample P&ID of HVAC and BAS Equipment


Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional and Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
Quality System Program and Implementation Plan

The Quality System Program and Implementation Plan is


a contractual document between the Client and BAS
supplier.

Defines actions, deliverables, responsibilities, and


procedures satisfying the user quality and validation
requirements.

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional and Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
Functional Requirements Specification

The Functional Requirements Specification (FRS) describes the


detailed functions of the facility, equipment, and system (i.e.,
what the system will do).

The Functional Specification is normally written by the Supplier


and then reviewed and approved by the Customer.

The FRS is used to develop the Acceptance Test Specification


that outlines those items to be tested as part of the Factory
Acceptance Test (FAT) and/or Site Assessment Test (SAT).

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Hardware Software Phase

Customer Approval of
Functional and Design

Factory
Acceptance Test
(FAT) Phase

Company Confidential
Design Specification

The Design Specification (DS) document developed by Supplier


describes how to build the facility, equipment, and system (that
is, how to design or construct the system).

It is recommended that the Design Specification is illustrated by


the use of diagrams wherever possible.

The Design Specification is normally written by the Supplier


and then reviewed and approved by the Customer.

In most cases the DS may be included in the FS

Company Confidential
Planning and Design/Development Phases

Master Validation Plan


(MVP)
Planning
Phase
User Requirement Impact
Specification (URS) Assessment

Quality System Program Functional Specification


and Implementation Plan Hardware Software

Engineering Submittal Design &


Development
Linked to Hardware Software Phase
Installation
Qualification (IQ) Customer Approval of
Functional and Design
Linked to
Operational
Qualification (OQ)
Factory
Linked to Acceptance Test
Performance (FAT) Phase
Qualification (PQ)
Company Confidential
Project Lifecycle (GaMP)

Design & Commissioning Ongoing


Planning Installation
Development & Qualification Operation

FAT
NO
Required?

YES

Factory
Acceptance
Testing

Company Confidential
Project Lifecycle (GaMP)

Design & Commissioning Ongoing


Planning Installation
Development & Qualification Operation

FAT
NO
Required?

YES

Factory
Acceptance
Testing

Company Confidential
FAT and Installation Phases

Factory
NO Acceptance
Test (FAT)
Required? Factory Acceptance
Test (FAT) Phase

YES

BUILD SYSTEM

Factory Acceptance Test


(FAT)

BUILD SYSTEM Installation at Job Site Develop Installation Phase


IQ/OQ/PQ Tests
Develop
Commissioning Plan

Commissioning& Qualification Phase

Company Confidential
FAT and Installation Phases

Factory
NO Acceptance
Test (FAT)
Required? Factory Acceptance
Test (FAT) Phase

YES

BUILD SYSTEM

Factory Acceptance Test


(FAT)

BUILD SYSTEM Installation at Job Site Develop Installation Phase


IQ/OQ/PQ Tests
Develop
Commissioning Plan

Commissioning& Qualification Phase

Company Confidential
Factory Acceptance Test (FAT)

A FAT is recommended when the project deadline is critical


and construction schedule does not allow enough time for
commissioning and validation after installation.
Combining the commissioning findings with the FAT as part of
the validation process helps avoid collecting data twice, making
better use of time and project resources.
Other tests used during the FAT and SAT may be used to support
the validation effort.
The request for the FAT occurs during the planning stage of a
project and usually is included in the Validation Master Plan and
the Request for Quote (RFQ).

Company Confidential
Project Lifecycle (GaMP)

Design & Commissioning Ongoing


Planning Installation
Development & Qualification Operation

FAT
NO
Required?

YES

Factory
Acceptance
Testing

Company Confidential
Commissioning/Qualification Phase & Ongoing Ops

Start-up & Commissioning

Site Acceptance Test (SAT) Commissioning &


Qualification Phase

DIRECT IMPACT INDIRECT & NO


SYSTEMS IMPACT SYSTEMS

Installation Trending to verify


Qualification (IQ) operational changes

Operational
Qualification (OQ)

Performance
Qualification (PQ)

Change Control Document Control


Ongoing
Standard Operations (SOPs) Training Operations

Maintenance Operations Business Continuity


Company Confidential
Impact Assessment

GEP Only
Parking Facilities No Impact

Office Terminal Devices

Office HVAC Systems

Chilled Water Systems Indirect Impact?


cGMP HVAC Systems

Building Management System

cGMP Terminal Devices Direct Impact


GEP and
Qualification
Company Confidential
Commissioning Plan
IMPACT ASSESSMENT GEP COMMISSIONING GEP / QUALIFICATION IQ / OQ
DOCUMENTATION

Parking Facility Vendor Standard X

Office Terminal HVAC Vendor Standard X


Equipment

Office Central HVAC Vendor Standard X


Equipment

Chilled / Hot Water Vendor Standard X


Systems

Building Automation Vendor Standard X Enhanced Documentation X


System / FAT?

cGMP Central HVAC X Enhanced Documentation X


Critical Systems

cGMP Terminal HVAC X Enhanced Documentation X


Critical Systems

Other Validated Ancillary X Enhanced Documentation X


Systems

Company Confidential
Commissioning

A well planned, documented and managed engineering


approach to the start-up and turnover of facilities, systems
and equipment to the end-user that results in a safe and
functional environment that meets established design
requirements and stakeholders expectations.

Company Confidential
Commissioning

Concepts:

Requires close cooperation of a multi-disciplined team

Builds on concepts and activities such as Impact Assessment


and Good Engineering Practices

Execution typically occurs after the installation of equipment,


piping and instrumentation is complete and operational

Systems, equipment and instrumentation need to be physically


complete and operational

Company Confidential
Commissioning Plan

Agree on the Commissioning Plan early in the project


Plan should identify systems to be commissioned, activities and
sequences, deliverables, personnel and organizations involved
and their roles/responsibilities
Provide list of facilities, utilities and equipment to be commissioned
Approvers should include Design, Construction and the End-User
representatives; include Validation and QA for direct impact
systems
Commissioning should be integrated with qualification activities for
direct impact systems
Commissioning may be the final activity prior to use/operation by
the end-user
Plan for either phased or one-time turnover

Company Confidential
Commissioning Process

Levels of commissioning for building automation systems:


Standard Commissioning
Enhanced Commissioning

The level of commissioning is defined in the VMP and Quality


Plan.
Direct Impact systems require enhanced documentation, which
may involve additional tests, documentation, QA change control,
and QA review/approval. Enhance documentation should
complement (not repeat) the documentation that is created
through GEP.

Company Confidential
Commissioning/Qualification Phase & Ongoing Ops

Start-up & Commissioning

Site Acceptance Test (SAT) Commissioning &


Qualification Phase

DIRECT IMPACT INDIRECT & NO


SYSTEMS IMPACT SYSTEMS

Installation Trending to verify


Qualification (IQ) operational changes

Operational
Qualification (OQ)

Performance
Qualification (PQ)

Change Control Document Control


Ongoing
Standard Operations (SOPs) Training Operations

Maintenance Operations Business Continuity


Company Confidential
Site Acceptance Test

Tests that are completed On-site with installed


equipment to prove the correct operation of the
software, hardware, and instrumentation as defined
by the URS

Company Confidential
Site Acceptance Test

The Site Acceptance Test (SAT) is performed to determine that the


system and any associated equipment has not been damaged and
functions correctly in its operating environment.

The SAT normally constitutes a repeat of the FAT (or portions of the
FAT) in the users environment plus those test made possible with all
process, field instrumentation, interfaces, and service connections
established.

The SAT may be combined with equipment and plant


commissioning, and this will provide a basis for the IQ and OQ.

The incorporation of SAT into qualification testing is acceptable


where the level of detail and documentation of the tests meet the
requirement of user company policies and procedures, and are
acceptable to user company QA.

Company Confidential
Commissioning/Qualification Phase & Ongoing Ops

Start-up & Commissioning

Site Acceptance Test (SAT) Commissioning &


Qualification Phase

DIRECT IMPACT INDIRECT & NO


SYSTEMS IMPACT SYSTEMS
Installation Trending to verify
Qualification (IQ) operational changes

Operational
Qualification (OQ)

Performance
Qualification (PQ)

Change Control Document Control


Ongoing
Standard Operations (SOPs) Training Operations

Maintenance Operations Business Continuity


Company Confidential
BAS Installation Qualification Table of Contents

Documentation Verification

SOP Verification

Hardware and Software Verification

Field Panel

Hardware and Firmware Verification

Utility Verification

Application Code Version Verification

Company Confidential
Installation Qualification Table of Contents

Database Configuration Verification

Trend Configuration Verification

Trend Collection Schedule Verification

Alarm Configuration Verification

Point Configuration Verification

Alarm Management Configuration Verification


Remote Notification Configuration Verification

Alarm Paging Notification Verification


Point List Verification

Company Confidential
Installation Qualification Table of Contents

Archive Database Configuration Verification

Data Base Verification

Data Server Configuration Verification

Archive Schedule Verification

Data Purge Configuration Verification

Summary Point Configuration Verification

Uninterruptible Power Supply Installation Verification

Field Device Calibration Verification

Field Equipment Installation Verification

Company Confidential
Commissioning/Qualification Phase & Ongoing Ops

Start-up & Commissioning

Site Acceptance Test (SAT) Commissioning &


Qualification Phase

DIRECT IMPACT INDIRECT & NO


SYSTEMS IMPACT SYSTEMS
Installation Trending to verify
Qualification (IQ) operational changes

Operational
Qualification (OQ)

Performance
Qualification (PQ)

Change Control Document Control


Ongoing
Standard Operations (SOPs) Training Operations

Maintenance Operations Business Continuity


Company Confidential
Operational Qualification Table of Contents

System Security Qualification Test Cases


User Account Security
Access Groups
Audit Trail Qualification Test Cases
Audit Trail Verification
Long Term Storage of Audit Trails
Field Panel Qualification Test Cases
Field Panel Loss of Communication
Field Panel Battery Check
Field Panel Power Failure Alarming and Recovery
Electric Field Instrument (EFI) Interference

Company Confidential
Operational Qualification Table of Contents

Uninterrupted Power Supply

Custom Code Testing

Scheduled Functions Qualification Test Cases

Trend Collection Report Verification

Data Server Verification

Archive Schedule Verification


System Alarms Qualification Test Cases
Standard Alarm Notification Test
Enhanced Alarms Notification Test

Company Confidential
Operational Qualification Table of Contents

Remote Notification Qualification Test Cases

Building Level Network Event

Escalation Test

Alarm Management Qualification Test Cases

Alarm Management Operational Test Case

Alarm Management Archival Test Case

Data Integrity Qualification Test Cases

Transmitter Failure Test

72 Hour Trend Analysis

Company Confidential
Commissioning/Qualification Phase & Ongoing Ops
Linked to User
Requirements Spec Start-up & Commissioning
Linked to Functional
Requirements Spec
Site Acceptance Test (SAT) Commissioning &
Linked to Design
Qualification Phase
Spec

DIRECT IMPACT INDIRECT & NO


SYSTEMS IMPACT SYSTEMS

Installation Trending to verify


Qualification (IQ) operational changes

Operational
Qualification (OQ)

Performance
Qualification (PQ)

Change Control Document Control


Ongoing
Standard Operations (SOPs) Training Operations

Maintenance Operations Business Continuity


Company Confidential
Standard Operating Procedures (SOPs)

System Operation
Change Control/ Upgrade Procedures
Hardware Maintenance Procedures
Software Maintenance Procedures
Electronic Records/Data Management Procedures
Incident Management Procedures
System Security Procedures
Training Procedures
Disaster Recovery Procedures
Source Code Handling

Company Confidential
The V-Model:
A Basic Framework for Specification, Design and Testing

User Requirements PQ Test Plan Performance


Specification Qualification

Functional OQ Test Plan Operational


Specification Qualification

IQ Test Plan Installation


Design Specification
Qualification

System Build

Company Confidential
IQ/OQ
Pre-Approved Protocol

Installation Operation Performance


Direct Impact
Systems
Critical Devices Calibration
<
< Change
< Control

Indirect/
No Impact
Systems
Point to Point Start Up Trending
Non-Critical
Devices
Forms with Signatures & Dates
Related
Specifications
Design Functional User Requirement
Specification Specification Specification

Company Confidential
Questions??

If you want tomatoes



Dont plant turnips!

Company Confidential
Company Confidential
Siemens Building Technologies

Irene Miess
847-941-5840
irene.miess@siemens.com

Dave Barrett
905-799-9937
david.barrett@siemens.com

Company Confidential

Você também pode gostar