MONITORING CONCRETING PLAN

TASK NAME Date OCT '16 NOV '16 DEC '16 JAN '17
QTY
14-Jan-17 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31
ADDITIONAL OF MAIN TRANSFORMER 230MVA - INALUM Check
FOUNDATION 275 KV AREA
AREA PRIORITY 1
Oil Tank
Concreting Pile (PA) 31-Oct-16 Plan 14 13,56
Act 7 7 13,56
Concreting K225 16-Nov-16 Plan 42 42,38
Act 42 42,38
Main Transformer 230 MVA 0,00
Concreting Pile (PA) 29-Nov-16 Plan 27 27,12
Act 7 2 5 13,56
Concreting K225 16-Dec-16 Plan 46 46,29
Act 0,00
Landing Gantry mPA6 axis A-4 0,00
Concreting Pile (PA) 4-Nov-16 Plan 9 9,04
Act 7 2 9,04
Concreting K225 for Footing 18-Nov-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 21-Nov-16 Plan 6 5,60
Act 0,00
Landing Gantry mPA6 axis B-4 0,00
Concreting Pile (PA) 6-Nov-16 Plan 9 9,04
Act 2 7 9,04
Concreting K225 for Footing 22-Nov-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 25-Nov-16 Plan 6 5,60
Act 0,00
Gantry Foundation mPA3 axis A-3 0,00
Concreting Pile (PA) 11-Nov-16 Plan 9 9,04
Act 7 2 9,04
Concreting K225 for Footing 26-Nov-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 29-Nov-16 Plan 6 5,60
Act 0,00
Gantry Foundation mPA2 axis A-2 0,00
Concreting Pile (PA) 14-Nov-16 Plan 9 9,04
Act 0,00
Concreting K225 for Footing 30-Nov-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 3-Dec-16 Plan 6 5,60
Act 0,00
Gantry Foundation mPA1 axis A-1 0,00
Concreting Pile (PA) 17-Nov-16 Plan 9 9,04
Act 0,00
Concreting K225 for Footing 4-Dec-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 7-Dec-16 Plan 6 5,60
Act 0,00
Gantry Foundation mPA4 axis B-2 0,00
Concreting Pile (PA) 20-Nov-16 Plan 9 9,04
Act 0,00
Concreting K225 for Footing 8-Dec-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 11-Dec-16 Plan 6 5,60
Act 0,00
Gantry Foundation mPA5 axis B-3 0,00
Concreting Pile (PA) 23-Nov-16 Plan 9 9,04
Act 0,00
Concreting K225 for Footing 12-Dec-16 Plan 8 7,97
Act 0,00
Concreting K225 for Pedestal 15-Dec-16 Plan 6 5,60
Act 0,00
Disconnecting Switch m24 (3 units) 0,00
Concreting K225 for Footing 20-Nov-16 Plan 24 24,00
Act 0,00
Concreting K225 for Pedestal 26-Nov-16 Plan 11 11,48
Act 0,00
Circuit Breaker Dead Tank m27A (1 unit) 0,00
Concreting K225 for Footing 23-Nov-16 Plan 10 10,14
Act 0,00
Concreting K225 for Pedestal 27-Nov-16 Plan 7 6,55
Act 0,00
Post Insulator m28 (2 units) 0,00
Concreting K225 for Footing 27-Nov-16 Plan 3 3,20
Act 0,00
Concreting K225 for Pedestal 30-Nov-16 Plan 2 1,66
Act 0,00
Surge Arrester m20 (1 unit) 0,00
Concreting K225 for Footing 29-Nov-16 Plan 2 1,60
Act 0,00
Concreting K225 for Pedestal 2-Dec-16 Plan 1 1,38
Act 0,00
Cable Trench CT3 22-Dec-16 Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 27,60
Act 0,00
Cable Trench CT4 5-Jan-17 Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 32,44
Act 0,00
FOUNDATION 33 KV AREA 0,00
AREA PRIORITY 2 0,00
Capacitor Bank 1 units axis B-6 0,00
Concreting Pile (PB) 12-Nov-16 Plan 5 5,08
Act 5 5,08
Concreting K225 20-Nov-16 Plan 14 13,88
Act 0,00
Capacitor Bank 1 units axis B-6' 0,00
Concreting Pile (PB) 15-Nov-16 Plan 5 5,08
Act 1 1,27
Concreting K225 23-Nov-16 Plan 14 13,88
Act 0,00
Capacitor Bank 1 units axis B-7 0,00
Concreting Pile (PB) 18-Nov-16 Plan 5 5,08
Act 4 3,81
Concreting K225 26-Nov-16 Plan 14 13,88
Act 0,00
Gantry MP1 2 units axis AB-5 0,00
Concreting Pile (PB) 20-Nov-16 Plan 5 5,08
Act 4 1 5,08
Concreting K225 for Footing 28-Nov-16 Plan 3 3,46
Act 0,00
Concreting K225 for Pedestal 1-Dec-16 Plan 3 2,88
Act 0,00
Gantry MP1 2 units axis AB-6 0,00
Concreting Pile (PB) 20-Nov-16 Plan 5 5,08
Act 5 5,08
Concreting K225 for Footing 28-Nov-16 Plan 3 3,46
Act 0,00
Concreting K225 for Pedestal 1-Dec-16 Plan 3 2,88
Act 0,00
Gantry MP1 2 units axis AB-7 0,00
Concreting Pile (PB) 22-Nov-16 Plan 5 5,08
Act 5 5,08
Concreting K225 for Footing 1-Dec-16 Plan 3 3,46
Act 0,00
Concreting K225 for Pedestal 4-Dec-16 Plan 3 2,88
Act 0,00
Potential Transformer m23 (2 unit) 0,00
Concreting K225 for Footing 1-Dec-16 Plan 5 5,48
Act 0,00
Concreting K225 for Pedestal 4-Dec-16 Plan 4 3,58
Act 0,00
Current Transformer m12 (2 unit) 0,00
Concreting K225 for Footing 2-Dec-16 Plan 3 3,04
Act 0,00
Concreting K225 for Pedestal 5-Dec-16 Plan 2 1,79
Act 0,00
Post Insulator m18 (3 units) 0,00
Concreting K225 for Footing 7-Dec-16 Plan 5 4,80
Act 0,00
Concreting K225 for Pedestal 13-Dec-16 Plan 2 2,50
Act 0,00
Circuit Breaker+Current Transformer (m16+m12) 3 units 0,00
Concreting K225 for Footing 11-Dec-16 Plan 9 8,61
Act 0,00
Concreting K225 for Pedestal 17-Dec-16 Plan 18 18,25
Act 0,00
Disconnecting Switch m13-A (3 units) 0,00
Concreting K225 for Footing 15-Dec-16 Plan 6 6,48
Act 0,00
Concreting K225 for Pedestal 20-Dec-16 Plan 5 5,37
Act 0,00
Cable Trench CT1 22-Dec-16 Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 17,66
Act 0,00
Cable Trench CT2 5-Jan-17 Plan 0 0 0 0 0 0 0 0 0 0 1,43
Act 0,00
AREA PRIORITY 3 0,00
Capacitor Bank axis C-7 0,00
Concreting Pile (PB) 25-Nov-16 Plan 5 5,08
Act 0,00
Concreting K225 3-Dec-16 Plan 13 13,44
Act 0,00
Capacitor Bank axis D-7 0,00
Concreting Pile (PB) 28-Nov-16 Plan 5 5,08
Act 0,00
Concreting K225 6-Dec-16 Plan 11 11,20
Act 0,00
Capacitor Bank axis E-7 0,00
Concreting Pile (PB) 1-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 9-Dec-16 Plan 13 13,44
Act 0,00
Capacitor Bank axis F-7 0,00
Concreting Pile (PB) 4-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 12-Dec-16 Plan 11 11,20
Act 0,00
Capacitor Bank axis G-7 0,00
Concreting Pile (PB) 7-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 15-Dec-16 Plan 13 13,44
Act 0,00
Capacitor Bank axis H-7 0,00
Concreting Pile (PB) 10-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 18-Dec-16 Plan 11 11,20
Act 0,00
Circuit Breaker+Current Transformer (m16+m12) 6 units 0,00
Concreting K225 for Footing 21-Dec-16 Plan 17 17,23
Act 0,00
Concreting K225 for Pedestal 28-Dec-16 Plan 37 36,50
Act 0,00
Disconnecting Switch m13 (6 units) 0,00
Concreting K225 for Footing 25-Dec-16 Plan 13 12,96
Act 0,00
Concreting K225 for Pedestal 31-Dec-16 Plan 11 10,74
Act 0,00
Post Insulator m18 (6 units) 0,00
Concreting K225 for Footing 29-Dec-16 Plan 10 9,60
Act 0,00
Concreting K225 for Pedestal 4-Jan-17 Plan 5 4,99
Act 0,00
AREA PRIORITY 4 0,00
Capacitor Bank axis K-7 0,00
Concreting Pile (PB) 13-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 21-Dec-16 Plan 13 13,44
Act 0,00
Capacitor Bank axis L-7 0,00
Concreting Pile (PB) 16-Dec-16 Plan 5 5,08
Act 0,00
Concreting K225 24-Dec-16 Plan 11 11,20
Act 0,00
Disconnecting Switch m13 (2 units) 0,00
Concreting K225 for Footing 24-Dec-16 Plan 4 4,32
Act 0,00
Concreting K225 for Pedestal 27-Dec-16 Plan 4 3,58
Act 0,00
Circuit Breaker+Current Transformer (m16+m12) 2 units 0,00
Concreting K225 for Footing 26-Dec-16 Plan 6 5,74
Act 0,00
Concreting K225 for Pedestal 29-Dec-16 Plan 12 12,17
Act 0,00
Post Insulator m18 (2 units) 0,00
Concreting K225 for Footing 28-Dec-16 Plan 3 3,20
Act 0,00
Concreting K225 for Pedestal 31-Dec-16 Plan 5 4,99
Act 0,00
AREA PRIORITY 5 0,00
Gantry mP3 axis A-8 ( 2 units) 0,00
Concreting Pile (PB) 18-Dec-16 Plan 5 5,08
Act 3 2,54
Concreting K225 for Footing 26-Dec-16 Plan 5 4,61
Act 0,00
Concreting K225 for Pedestal 29-Dec-16 Plan 5 5,12
Act 0,00
Gantry mP2 axis A-9 ( 3 units) 0,00
Concreting Pile (PB) 20-Dec-16 Plan 8 7,62
Act 1 1 2,54
Concreting K225 for Footing 28-Dec-16 Plan 5 5,34
Act 0,00
Concreting K225 for Pedestal 31-Dec-16 Plan 4 4,32
Act 0,00
DS+CT+CB (m13B+m12+m16) 2 units 0,00
Concreting K225 for Footing 28-Dec-16 Plan 26 25,97
Act 0,00
Concreting K225 for Pedestal 31-Dec-16 Plan 0 0,17
Act 0,00
Disconnecting Switch m13-B (1 unit) 0,00
Concreting K225 for Footing 30-Dec-16 Plan 2 2,16
Act 0,00
Concreting K225 for Pedestal 2-Jan-17 Plan 2 1,79
Act 0,00
Cable Sealing End mCSE (1 unit) 0,00
Concreting K225 for Footing 1-Jan-17 Plan 2 1,60
Act 0,00
Concreting K225 for Pedestal 4-Jan-17 Plan 1 0,83
Act 0,00
CSE+CT+CB (mCSE+m12+m16) 1 unit 0,00
Concreting K225 for Footing 2-Jan-17 Plan 13 12,99
Act 0,00
Concreting K225 for Pedestal 5-Jan-17 Plan 0 0,07
Act 0,00
Post Insulator m18 (2 units) 0,00
Concreting K225 for Footing 3-Jan-17 Plan 3 3,20
Act 0,00
Concreting K225 for Pedestal 6-Jan-17 Plan 5 4,99
Act 0,00
Cable Trench CT5 8-Jan-17 Plan 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 41,94
Act 0,00
AREA PRIORITY 6 0,00
Auxiliary Transformer Foundation 0,00
Concreting K225 13-Jan-17 Plan 1 1,20
Act 0,00
Concreting Plan Daily 0 0 0 0 0 14 0 0 0 9 0 9 0 0 0 0 9 5 0 9 5 42 9 13 0 52 7 14 34 10 12 37 11 10 35 11 18 6 20 21 3 12 18 12 17 9 18 24 13 5 31 55 22 20 4 17 17 4 3 19 3 13 7 38 30 5 12 3 16 5 7 2 6 1 1 0 0 0 0 1 0 0 0 0 0 0 0 17 0 0 0 13 0 0 37 0 0 11 971,97
Concreting Plan Commulative 0 0 0 0 0 14 14 14 14 23 23 32 32 32 32 32 41 46 46 55 60 102 111 124 124 176 183 197 231 241 253 290 301 311 346 357 375 380 400 421 424 436 454 465 482 491 509 533 546 551 581 637 659 679 683 700 717 721 724 743 746 759 766 803 833 838 851 854 870 875 882 884 890 892 893 893 893 893 893 895 895 895 895 895 895 895 895 912 912 912 912 925 925 925 961 961 961 972
Concreting Actual Daily 7 0 0 0 0 7 0 0 0 14 0 0 0 14 0 0 11 0 0 2 0 5 56 8 4 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 127,10
Concreting Actual Commulative 7 7 7 7 7 14 14 14 14 27 27 27 27 41 41 41 52 52 52 54 54 59 116 123 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127 127
Achievement up to Date (%) 13,08%