Escolar Documentos
Profissional Documentos
Cultura Documentos
Denis Mollica, Alexandre Dominice, Lucca Zamboni, Gabriel H. Batista, Joo P. Silva, Luiz A.
Costa, Marco A. P. Fredes - EDP Brasil
879
2
CSO1307, as it involves feeder BIR1301, from Biritiba network. The last module used in the studies described in this
substation, and feeder CSO1307, from Cesar de Sousa paper is the SCADA, which is composed by a software system
substation. typically used by power distribution systems to communicate
A. Laboratory with the IEDs installed in the field and measure/control the
The Smart Grid laboratory is an environment where the values for the digital and analogic variables of the power
behavior between the different systems present in a power distribution network.
distribution company may be reproduced. It is composed by 1) Electric network simulator
different software systems, such as Supervisory Control and In the laboratorys environment, SINAP software, provided
Data Acquisition (SCADA) system, Distribution Management by Sinapsis company [6], is used for simulating the power
System (DMS), Meter Data Management (MDM) system, distribution network. The software uses the topology data of
the actual power network and typical load curves. Through the
Outage Management System (OMS), among others, integrated
software, it is possible to carry out power flow and short-
with different hardware systems or Intelligent Electronic
circuit analysis, verifying the values for electric variables
Devices (IEDs), such as controllers for HV/MV transformers
involved and the status of the equipment under different load
On-Load Tap Changers (OLTCs), controllers for MV conditions over the day and over different contingencies along
capacitor banks, controllers for MV voltage regulators, the network. The values for the monitored variables of the
controllers for reclosers and regular switches, among others. power network are transmitted to the signal transducer module
Thus, in the Smart Grid laboratory the systemic behavior of by a TCP/IP server sub-module developed in SINAPs
the power distribution systems may be simulated in a environment.
controlled environment, considering conditions similar to 2) Signal Transducer
those found on the real distribution systems. This structure This module is composed by PXI equipment, manufactured
provides conditions to analyze the impact of new technologies by National Instruments [7] and by voltage and current
or to evaluate the performance of changes in the regular amplifiers. The TCP/IP packages from the Electric Network
activities of the power distribution system without Simulator are received by PXI, which generates actual
compromising the real power distribution system operation. analogic and digital signals according to the routines
For the FLISR studies described in this paper only part of implemented using LabVIEW. Then, these signals are
the Smart Grid laboratorys structure was considered. The amplified to voltage/current ranges expected by the real IEDs.
portion of the laboratory used was composed, in a simplified 3) IEDs
way, by only four autonomous modules that communicate and The devices used in the studies described in this paper are
interact in a bidirectional manner, as presented in Figure 1. circuit breaker controllers and recloser controllers. IEDs
typically used by the power distribution companies and that
Network Emulator can be remotely controlled were used in the laboratory. The
Electric network IEDs chosen for the studies were three units of the Form6
simulator recloser controller from Cooper, one unit of SEL-751A bay
controller from Schweitzer Engineering Laboratories [10], and
one unit of the TPU-S220 bay controller from EFACEC [11].
Thus, the signals generated by the signal transducer module
Signal Transducer are adequately provided to the TPs and TCs of these IEDs,
following their typical operation range.
4) SCADA
The SCADA system used in the studies described in this
paper was the Action.NET system from SPIN company [8].
IEDs Action.NET is responsible for monitoring the IEDs, receiving
analogic and digital data, and sending command actions
through the same communication protocols used in the field.
The communication link between the IEDs installed in the
laboratory and the Acion.NET system used DNP3 protocol.
SCADA The data received from the IEDs are used in the TARST
Fig. 1. Smart Grid laboratory's structure routine programmed in its environment in a way to generate
control decisions and send it as commands to the IEDs.
The Electric Network Simulator module and the Signal
B. TARST
Transducer module are parts of the Network Emulator, whose
role is to reproduce the operation of real power distribution As stated before, the TARST routine used by EDP
Bandeirante and EDP Escelsa is intended to transfer loads
networks. These two first modules provide the values for
between feeders from the same substation (SE) or from
digital and analogic variables from the power distribution
different substations in an automatic way. The routine is used
network that will be transmitted to real IEDs, which are
to transfer loads in bidirectional way, which means that there is
normally used to monitor and control power equipment the possibility of load restoration for any of the two feeders
installed in the HV and MV portions of the power distribution involved. Such transfer occurs when there is an occurrence at
880
3
the first portion of one of the feeders, causing the interruption related to the measurements, there are also local variables,
of supply for all the customers. Therefore, the customers at the related to counters, flags and the TARST state.
second part of the feeders may be transferred to the other TARST routine can assume six state types. An integer
feeder involved in the routine, by opening a Normally Closed number represents each state, from zero to five, and is stored
(NC) recloser and closing a Normally Opened (NO) recloser. at local variable in the TARST routine, as stated before. This
Such transference is maintained throughout the complete variable is associated with the NO recloser present between the
period in which the network will be under maintenance and involved feeders. The values and respective states that the
mitigates the impact of the fault reducing the number of TARST routine can assume are :
interrupted customers. After the repair, the load transferred is 0 State: SUCCESS;
undone and both feeders are configured according to their 1 State: OPERATIONAL BLOCKING;
regular operational conditions. A step-by-step operation 2 State: LOAD RESTRICTION BLOCKING;
sequence is illustrated in Figure 2. 3 State: COMUNICATION FAILURE;
4 State: ACTIVE;
5 State: BLOCKED.
Figure 3 presents a flowchart of TARST routine. The
structure based on successive conditional commands
mentioned before can be observed in the diagram. Each cycle
of the routine occurs within a 10 seconds time window, which
is determined in the SCADA system.
The routine begins with creation of the variables that will
store the values for the digital and analogic measurements
obtained from the IEDs involved. It also is necessary that the
operator has defined the TARST routine execution variable as
ACTIVE in SCADA system, in order to ensure its automatic
execution.
For each TARST routine, there are local variables that
work as counters. These counters help to build up the
automatic load transference logic and are incremented at each
cycle of the SCADA system. In the TARST routine used for
this study, there are two counters: one for each available
direction of load flow. These variables are associated with the
NC reclosers that can be opened in order to allow the load
transference. For example, variable ABRIR071657 of the
BIR1301-CSO1307 TARST routine studied in this paper is the
Fig. 2. TARST routine execution counter variable used to verify the procedure of transferring
load from the feeder BIR1301, where the NC Recloser
TARST routines are implemented in the SCADA system, BIR071657 is installed, to the feeder CSO1307. In a similar
localized at the COD of the company power distribution way, there is the ACSO071578 counter referring to feeder
systems. As the SCADA system is important in many aspects CSO1307, since the BIR1301-CSO1307 TARST routine is
of the operation of distribution systems, one of the major bidirectional.
concerns is that the implemented routines should not affect the When a TARST routine is active and the counters have
SCADA operation or cause system breakdowns. Thus, the null values, the cycle of logic tests starts monitoring the need
TARST routines use only conditional commands (if-else- for load transference in both directions. One may summarize
then commands) in a sequential way and loop commands are the TARST routine from the NC Recloser #1 point of view,
not considered. located at the defective feeder, as follows:
After a TARST routine is automatically performed, the 1) NC Recloser #1 Normal Operation
feeders involved may only have their original configuration One verifies if there is voltage at the downstream side of NC
reestablished through specific commands performed by the Recloser #1. The minimum voltage level is set to at least 75%
operators at COD. This condition guarantees safety for that the of the nominal phase voltage. In the routine one also checks if
maintenance staff, ensuring that the distribution network will the protection function from NC Recloser #1 has not been
assume its original configuration only after the repairs are executed and it is with a closed status. If these conditionals are
completed and there is no risk to endanger human lives. Thus, satisfied, the NC Recloser #1 should operate normally, a load
a member of the maintenance team has to inform the COD transference is not necessary and the counter is set to zero. On
operator that the repair has already been concluded and that the other hand, if one of these conditions are not satisfied, the
the distribution network may be powered up again. routine starts to verify if it is possible to proceed with the load
In the TARST routine, there are variables related to the transference.
real time measurements obtained from the circuit breakers and 2) Both Feeders with No Voltage
from the reclosers involved in the logic. Besides the variables One verifies if there are no voltage at both sides of the NO
Recloser. No voltage level is set to less than 25% of the
881
4
nominal phase voltage. If this condition is satisfied, it means command to NO Recloser. Then, one verifies if the NC
that the feeder to which the load should be transferred is also Recloser #1 followed the command and is opened, as well as,
under a fault. In this case, the TARST routine should not if the protection adjustments of the NO Recloser has been
proceed with the load transference and the counter should be altered. Upon its confirmation, a closing command will be sent
set to zero. to the NO Recloser and the TARST routine status will be
3) NC Recloser #2 with Operated Protection altered to SUCCESS.
One verifies if there is voltage at the NC Recloser #2, at
the feeder to which the load should be transferred. One also ACTIVE
checks if its protection function has been executed, and it is
with an opened status. If any of these conditions is satisfied, it
Counter = 0
means that there was fault downstream the other feeder, to
which one intended to transfer the load from the defective
feeder. As a result, one cannot perform the load transference NC Recloser #1
and TARST routine assumes the OPERATIONAL Normal Operation
True
BLOCKING status. Due to safety issues, its reactivation can
False
only be performed by the operator.
4) Counter
If one does not satisfy any of previous three tests, the Both Feeders with
No Voltage
TARST routine verifies if there is voltage on at least one side
of the NO Recloser. Confirming the absence of voltage leads False
to conclude that there is a fault upstream of NC Recloser #1
and the TARST routine may proceed with the load NC Recloser #2 with TARST in
transference. If that is the case, the TARST routine counter Operated Protection
True
Operational Blocking
will be increased by one. It is necessary that the test results
False
remain the same for four cycles of the SCADA system, which
is equivalent to 40 seconds, so that the next stages will be Counter +1
executed.
5) Communication Failure False
One verifies if there was a communication failure with any Counter > 3
of the reclosers involved in the TARST routine. If there is a
communication failure, the TARST routine assumes True
COMMUNICATION FAILURE status and may only be
reactivated by the operator, due to safety issues. Communication TARST blocked by
6) Load Restriction Failure
True
Communication Failure
882
5
The reconfiguring of the feeders to their original topologies Using SINAP, one notices that, under regular operation
will only happen through commands sent by the operator at the conditions, the peak of the demand in both feeders happen at
distribution operation center. 6:00 PM. At the peak, a current of 201A was measured at the
circuit breaker of feeder BIR1301 and a current of 221A was
III. APPLICATION EXAMPLES measured at the circuit breaker of feeder CSO1307.
A bidirectional TARST routine of load transference In the tests performed in the Smart Grid laboratory, the
between feeders BIR-1301 and CSO-1307 has been used in current values and reclosers statuses are generated by the
this study. The control of following reclosers were involved: SINAP and transmited to the IEDs. Their values can be
BIR071657 (NC); verified directly throught SCADA system. Thus, the tests
simulates the exactly situation faced by the operators located at
BIR071658 (NO);
the distritubution operation center.
CSO071578 (NC).
Figure 6 shows the laboratorys SCADA system display of
Figure 4 presents the georeferenced topology of the feeders
the studied TARST routine with the network operating in the
BIR1301 and CSO1307 in the SINAP software. The BIR1301
conditions of 6:00 PM. It is the same display shown to the
feeder from Biritiba substation is represented in red. The
operators at the distribution operation center. The elements
CSO1307 feeder from Cesar de Sousa substation is
that compose the TARST routine are represented at the
represented in blue. Both feeders supply a total of 13,110
display, making it possible to observe the circuit breakers,
customers. 7,182 customers are supplied by the feeder
represented by squares, reclosers, represented by rectangles,
BIR1301 and 5,928 customers are supplied by the feeder
and voltage regulators, represented by circles. The state of the
CSO1307.
reclosers and circuit breakers are represented by colors: red
means a closed status and green means opened status. The
current in each recloser and circuit breaker is shown below its
representative blocks. A time period simulation may be carried
out by automatically varying the time frame in SINAP. Then,
one may notice the current values changing as it was in a
regular situation observed by the regular operator at the
distribution operation center.
TARST routine status is informed to the operator through
the rectangle below the representation of the NO Recloser.
There is also a button for manual blocking command of the
TARST routine. It is possible to observe that the TARST
routine status is ACTIVE in the display.
883
6
After the sucessful tranference using real IEDs in the IV. CONCLUSION
laboratory, the TARST routine display presents a SUCCESS This paper presented the simulation of a real load
status, as seen in Figure 8. New values for the current transference used in power distribution utilities in a controlled
measurements and reclosers statuses are also shown in the environment. It was possible to represent the integration
SCADA display for this TARST routine. between real software systems typically used in distribution
operation centers, such as SCADA systems, with real hardware
systems typically installed in the field, such as IEDs used to
controle circuit breaker and reclosers. The power network was
virtully represented through a software system and a
infrastruture was developed to synthesyse digital and analogic
signals to the expected levels of power instrumentation present
in the field.
Through this approach one may simulate the operation of
power distribution networks. Such approach was illustrated
through the simulation of the TARST routine, allowing
operator training under several different occurrences in the
network in a controlled and risk free environment. Therefore,
laboratorys structure also provides a favorable environment
for equipment testing, aiming the improvement of the
parametrizations of IEDs used by the company.
Fig. 7. Network under a contigency condition on the feeder CSO1307
TARST routine presented promising results in terms of
quality of service. However, it is possible to observe the
possibility of improvements. The Smart Grid laboratory is the
ideal environment to test and modify the TARST routine
without offering risks to the companys operation. Examples of
the possible improvements are: inclusion of load transference
to relief, considering more than three reclosers, minimizing
Fig. 8. TARST display after the operation prioritary loads interruption.
The network topology after the load transference is V. REFERENCES
presented in Figure 9. The network will remain in this setting
[1]. J. R. Aguero, Applying Self-Healing Schemes to Modern Power
until the restablishment of the supply and the operator at the
Distribution Systems, em IEEE Power and Energy Society
distribution operation center manually undo the transference. General Meeting, San Diego, 2012.
The simulation of the TARST routine for automatic load [2]. X. Bai, D. Strickland e C. Harrap, Application of Automatic
transference under a contingency situation avoided the Load Transfer on Feeder Utilisation Balance, em IET
interruption of supply of over 56% of customers at the International Conference on Resilience of Transmission and
CSO1307 feeder. At the time of the peak demand, this amount Distribution Networks, Birmingham, 2015.
of customers is equivalent to 2.5MVA of power which was [3]. L. Liu e X. Zhao, Study on Self-healing Control Strategy of
reestablished within 50 seconds. Thus, this major occurrence is Smart Distribution Network, em IEEE PES Innovative Smart
not considered for calculating quality of service performance Grid Technologies, Tianjin, 2012.
[4]. S. Toune, H. Fudo, T. Genji, Y. Fukuyama e Y. Nakanishi,
indexes such as SAIFI and SAIDI. Comparative Study of Modern Heuristic Algorithms to Service
Restoration in Distribution Systems, IEEE Transactions on
Power Delivery, vol. 17, n 1, pp. 173 - 181, 2002.
[5]. J. M. Solanki, S. Khushalani e N. N. Schulz, A Multi-Agent
Solution to Distribution Systems Restoration, IEEE Transactions
on Power Systems, vol. 22, n 3, pp. 1026 - 1034, 2007.
[6]. Sinapsis, Sinapsis Inovao em Energia, [Online]. Available at:
http://www.sinapsisenergia.com/portal/
[7]. National Instruments [Online]. Available at:
http://www.ni.com/pt-br.html.
[8]. SPIN Engenharia [Online]. Available at:
http://www.spinengenharia.com.br.
[9]. EATON, Cooper Power Systems. Available at:
http://www.cooperindustries.com/content/public/en/power_syste
ms/products/controls_and_relays/recloser_controls/form_6.html
[10]. Schweitzer Engineering Laboratories. Available at:
https://selinc.com/products/751A/
Fig. 9. Grid's settings after the TARST operation
[11]. EFACEC. Available at:
http://www.efacec.pt/presentationLayer/efacec_press_01.aspx?tip
o=0&id=432&area=2&idioma=2
884