Escolar Documentos
Profissional Documentos
Cultura Documentos
Full-scale specimens representing actual high quality riser girth welds will have the same distribution of
defects as the actual girth welds, which tend to be free from conventional defects but do contain inherent
flaws that are not detectable by conventional automated ultrasonic testing (AUT). To illustrate the implications
of this, typically a 3 mm high surface breaking flaw will with 90% probability of detection (PoD) and 95%
confidence be detected by AUT. However, a slightly smaller undetectable surface breaking planar defect 2.9
mm high and 12 mm long could by standardized crack growth analysis (BS7910) have a fatigue life only 20-
40% of the endurance test (D-curve).
It is well known that fatigue crack growth analysis carried out as part of an engineering critical assessment
(ECA) that is based on the actual initial defect size is conservative when compared to endurance tests, but
guidance for ECA-based design fatigue factor (DFF) is not provided in design codes. One half of the
endurance DFF has been informally adopted by the industry for ECA based assessments. The industry is
pursuing riser girth welds with increased fatigue properties, even beyond the D-curve, proven by endurance
testing. Hence, either the standardized PoD of AUT and conservative crack growth analysis will limit the
fatigue utilization of these high fatigue performance riser girth welds, or the girth weld acceptance criteria will
not be supported by existing scientific methods.
This is viewed as an enhancing technology as the fatigue resistance of riser girth welds in many
circumstances will limit available field development concepts.
OBJECTIVE:
The purpose of the CTR is to develop a less conservative crack growth analysis model which will be valid for
high fatigue performance riser girth welds and would lead to more accurate acceptance criteria related to
defects that are detectable with sufficient PoD. This will allow better utilization of the high fatigue performance
riser girth welds existing and pursued by the industry, and be based on rational theoretically based
acceptance criteria.
DELIVERABLES:
Extensive data from the mapping of the defects and other characteristics of riser girth welds that
control their fatigue performance.
A validated crack initiation/short crack growth model of the fatigue behaviour of high performance
riser girth welds in either the as-welded or improved (e.g. ground or peened) condition.
Recommendations for complementary inspection methods for use during and after welding with
estimated associated PoDs.
Statistical distributions of the types and maximum sizes of defects for welding processes and
process parameters used in riser girth welding.
Risk based calibrated DFF for ECAs based on fatigue crack growth analysis.
Overall report and practical Guidelines.
SCOPE OF WORK (Work plan & schedule):
Project management
Welding, Inspection and Defect Distributions
Review of fatigue controlling defects from representative fatigue tests, 01.08-05.08
Review and analysis of representative NDT records, 01.08-05.08
Evaluation of welding methods and appurtenant defect distributions, 06.08-12.08
Statistical analysis and prediction of defect distribution, 01.09-05.09
Fatigue crack initiation and initial growth from defects
Development of models for crack initiation and initial growth from defects, 01.09-05.10
Fatigue testing, 06.09-05.10
Probabilistic analysis and determination of design fatigue factors (DFF), 01.09-05.09
Development of Design Guidelines and Recommended Practice, 07.10-12.10
Completion Date:
December 2010
VALUE:
Based on cost saving of 5% CAPEX of approximately ten fields the benefit could be expected to be several
100 million USD.
CONTRACTING PLAN:
The management for the work will be by a primary contractor (possible candidates include DNV, TWI, SWRI,
EWI) in close contact with the steering committee. All the sponsors will have a seat in the JIP steering
committee, with representatives from the major contractors as consultants/experts. Some of the different work
packages will be subcontracted to experienced research institutes with the best qualifications (relevant data
basis, previous experience, testing facilities, human resources) to complete the scope of work. The primary
contractor will be responsible for subcontracting, however, the steering committee may be asked to help
evaluate and rank the candidates. Separate subcontracts, to be managed by the main contractor, will be
issued to experienced welding- and AUT contractors.
OBJECTIVE:
Use full scale rope tests and subrope tests to develop and validate a method to predict remaining life of
mooring systems, so that we have proof that insert recovery is not necessary. Use risk and reliability
methods to determine the relative risk of insert removal/recovery vs. not recovering inserts. Develop
alternative methods (to insert recovery) to demonstrate that installed mooring systems are safe.
DELIVERABLES:
Deliverables willl be a fully verified polyester rope remaining-life prediction model. Results from a industry-
validated risk and reliability analysis to quantify risks of insert recovery. Valid methods to verify in-situ
mooring rope integrity other than insert recovery and test.
A. Related Programs: 2006 MMS/OTRC/Industry JIP on Damaged Rope Testing, (2) MMS sponsored
project: Evaluate Accuracy of Polyester Subrope Damage Detection Performed by ROVs Following
Hurricanes just starting. (3) ARELIS program by DNV Norway, SIM testing program managed by
TTI Ltd, UK
B. Potential Funding sources for 20%: DeepStar, Industry JIP, or a combination thereof.
Perform Phase B testing with full-scale rope, and compare with Phase A results. Develop remaining life
models for synthetic fibers other than polyester (like HMPE). Results on polyester should form good basis.
time .
BUSINESS INCENTIVE AND THEME (Why invest?): Riser Life-Cycle Integrity Management Heavy
walled riser and flowline integrity in deepwater systems are susceptible to fatigue cracks due in part to
metocean conditions, temperature cycling, and corrosion pitting. To properly assure integrity of these systems
during production operations, a means for detecting and sizing fatigue cracks is essential. Current riser and
flowline designs are expected to be conservative. However, the industry is designing for conditions outside of
the design experience (e.g., XHPHT, ultra-deepwater, high currents, etc.) making the need for proper
inspection and integrity assurance. This work would best be described as science leading to an enabling
technology for inspection.
OBJECTIVE: The objective of this work is to develop an ultrasonic technique for detecting and sizing cracks
in risers and flowlines. Current methods, such as Magnetic Flux Leakage, are not capable of this due to the
heavy wall. Conventional Ultrasonic techniques, such as TOFD, for crack detection and sizing have been
found to be inadequate for seeing cracks in both tension and compression. Note that, in order to detect and
size cracks in flowlines, free swimming tools (pigs) would be necessary. Therefore, the technique identified as
suitable for crack detection and sizing would be incorporated into a free swimming inspection tool.
DELIVERABLES: Ultrasonic technique capable of detecting and sizing cracks in risers and flowlines.
Incorporation of this technique into a free swimming tool.
SCOPE OF WORK (Work plan & schedule): A phased approach is proposed for this work:
1. Feasibility and Concept (12 months)
a. Ultrasonic technique for detection and sizing cracks
b. Incorporation of technique in free swimming tool
2. Detailed engineering (12 months) Completion Date:
3. Tool building and operations (12 months) 4Q2010
VALUE: Improved reliability and uncertainty reduction of subsea systems.
CONTRACTING PLAN: It would be expected that all development would be performed and owned by a third
party inspection contractor. Teaming contractors with different expertise in ultrasonics and pigging would be
preferred, but may not be feasible.
RELATED PROGRAMS (Linked Projects, JIPs & partners):
Understanding the performance of high strength materials would further enable development of such reserves by making
them more economical. The fatigue performance data of high strength materials is non existent. Development of such data
would allow designers to use the high strength materials and thus enabling development of these fields. This proposal is
thus considered to be of an enabling technology theme.
OBJECTIVE:
The objective of this program is to develop fatigue data for High Strength Steels (such as X-80, X-100, C-110, Q-125, C-
125, V-140), Titanium (such as Grade 29 and newer alloys) and carbon fiber wrapped pipe (steel and titanium liner) riser
materials. The test matrix will be designed to reflect various production environments and different types of riser
configurations such as SCRs, dry tree risers, drilling and completion risers. The results from these tests will help qualify
these materials. The test program will also establish data for designers, enabling the use of high strength materials in
offshore environments. The tests will also be conducted on intermediate scale and full scale specimens and under more
realistic variable amplitude loading spectra consistent with service loading conditions. Such data is non-existent and would
establish validity of strip specimen results used in current practice. The sour service tests for intermediate and full scale
specimens will help in establishing the correct scaling parameters for strip specimen results. This will be an evolution from
DELIVERABLES:
1) Phase 1 results detailing fatigue crack growth rates and SN curves for materials tested.
2) Phase 2 results of SN curves for intermediate scale pipe materials tested.
3) Phase 3 results of SN curves for full scale pipe materials tested.
Phase 1: This phase will address fracture toughness, crack growth and S-N curve tests on strip specimens of materials
listed above (except carbon wrapped pipe). The samples will be tested in air, seawater (with CP charging), sour service
conditions and other production environments to simulate the conditions for drilling and production riser systems. Effect of
corrosion inhibitors would also be included. Both smooth and notched specimens would be used. 18 months
Phase 2: This phase will address SN Curve tests on intermediate scale pipe models for the successful materials and
environments selected from Phase 1 tests. The intermediate scale model tests will be welded as well as threaded
connectors as appropriate for the selected materials. The objective of the tests is to establish the validity of strip specimen
results of SN curves and to study the scaling effects. 18 months
Phase 3: This phase will address SN curve tests on full scale samples for materials selected from Phase 2. Full scale tests
will be conducted on welded (X-80 and X-100) as well as threaded connectors as applicable for selected materials. The
objective of these tests is to develop an appropriate scaling approach and to validate the results of Phase 1 and Phase 2.
18 months
Some of the tests in Phase 2 and Phase 3 will also be conducted using a variable amplitude loading spectrum to reflect the
service loads on risers in offshore environments.
Completion Date:
4.5 years
VALUE:
The prequalification of high strength materials for risers would enable development of several of the deepwater, high
pressure, high temperature and sour/corrosive reservoirs. These fields currently can not be developed with existing
technology and require expensive and long development programs. The results of this program will help all the operators to
develop such reservoirs and reduce the development time. The qualification work will also reduce the risks involved in
developing such reservoirs. Thus the value of this program is considered to be tremendous.
CONTRACTING PLAN:
The program will be bid out to qualified testing labs.
Therefore, in the case of a single HP drilling riser for Spar or TLP based drilling operations, this is considered
an enabling technology, in that it can keep the pipe wall thicknesses and riser pipe materials within the
practical/accepted manufacturing capabilities, without the need for untested higher strength steels and large
bore threaded connectors. For production risers in both dry and wet tree options, wherein T&C connectors or
all welded joints would be required, this is considered an enhancement of technology by allowing the use of
lower yield steel pipe materials which are suitable to welding and sour service.
The business case for pursuing this technology lies in being able to perform dry tree Spar or TLP based
drilling and sidetrack operations, which lead to substantial savings over comparable deepwater MODU
operations with the differential approaching $400-$500K per day, or up to $50MM on a single 100 day well.
Additionally, safe, reliable, and lighter weight production risers for both wet and dry tree solutions help reduce
platform and life cycle costs.
Shell, BP and industry have conducted several composite related laboratory-scale programs which address
the fundamental issues of materials selections and manufacturing processes as related to composite risers.
Most recently, Shell has completed a program to design high pressure hybrid risers (composite over wrapped
steel casing risers) with an ID ranging from 14.5 to 19. A 14.5 ID riser rated for 15000 psia working
pressure and 10,000 ft water depth was selected for manufacturing feasibility study and design verification
test. Both burst and bending fatigue tests were conducted, and verified a design life in excess of 20 years.
It is the intent of this program to work with the industry to move the technology out of the laboratory and
demonstrate viability through one or more field trials.
OBJECTIVE:
The focus of this project is on development and field trial of a light-weight drilling/completion riser (a few riser
joints, not the entire string) with the following attributes:
Inner diameter of 14 to 19 inches
Water depth capability in excess of 10,000 feet
Operating pressure rating in excess of 15,000 psia
Provide a 50% reduction in the in-water weight of a comparable steel riser.
The purpose of this project is to determine, through large scale tests, if carbon fiber wrapped steel riser pipe
(steel/composite hybrid) is suitable for long-term use in the harsh environment of deep water offshore. In
specific, it will establish design methodology and end termination issues, cost effective wrapping
method/manufacturing process, and address handling, storage and impact energy absorption capacity, along
with long-term durability and fitness for purpose for drilling and production riser applications.
Industry participants will further define the functional performance requirements (dimension, load, thermal,
etc.) during execution of the first task
DELIVERABLES:
PHASE I
1. Function performance requirements of the drilling/completion riser.
2. Comparative evaluation of various options for lightweight drilling/completion riser.
3. Path to resolve any regulatory issues and concerns.
4. Candidate riser for development and field trial.
5. Design methodology, including load sharing between steel pipe and carbon fiber, end
termination/interface design verified with the results of burst tests.
6. Cost effective wrapping method/manufacturing process, including comparative cost benefit analysis
including auto-frettage pre-stressing process vs. minimal tension required to effectively wrap, plus end
termination manufacturing/fabrication process.
7. Test results of handling, storage, and impact energy.
8. Test results of long term degradation due to environment, and associated design factors to be included in
the design.
9. Proof of concept through design, fabrication and laboratory testing to meet functional performance
requirements.
PHASE II
10. Fabricate full scale hybrid riser joints for field trial
11. Field trial results of candidate riser and comprehensive post deployment materials testing
12. Final report
PHASE I
1. Work with industry participants to define functional performance requirements with respect to potential
field trial candidate(s)
2. Perform comparative evaluation of various options for light-weight riser, including the composite
architecture (hoop wrap only pressure enhancement, or hoop+axial for enabling pressure and tension
capacity)
3. Select riser candidate for development and field trial
4. Resolve regulatory issues and concerns
5. Design and fabricate short length full diameter riser joints for proof of concept testing
PHASE II
6. Confirm field trial candidate(s)
7. Fabrication and acceptance testing of field trial joint(s)
8. Conduct field trial(s)
Completion Date:
Tasks 1-5: 18 months
Tasks 6-9: TBD, pending field
VALUE:
Light-weight riser with high pressure capability is both an enhancing and enabling technology for ultra-
deepwater high-pressure fields. It is envisioned that the technology that will be developed for the drilling /
completion riser can be easily translated for other riser applications such as DVA production risers.
Composite risers will allow brownfield structures additional tiebacks with minimal additional loading, thereby
enhancing production rates. Greenfield structures will benefit from reduced loads imparted by the composite
riser, resulting in either decrease of overall structure requirements, or an increase in the topside payload
capacity.
As an example, the differential loaded day rate of a 5th generation MODU and dry tree spar drilling unit is
currently running about $500,000/day. Many of the new developments in the GoM will have well depths of
25,000 or greater resulting in 100 day wells for drilling and 60 days for completion. Being able to use the
less expensive spar drilling rig on a 10 well development program would result in savings of more than
$500MM dollars
CONTRACTING PLAN:
Use competitive bidding process to obtain skilled and capable 3rd party contractor(s) to perform the work and
solicit potential suppliers to bring such a system to market. Industry 20% (TBD) can come from a JIP of
operators and suppliers. Shell has already invested in this system development. The intent is to offer one of
deepwater facilities as a candidate for the field trial.
1. NIST-ATP Composite Production Riser JIP (circa 1995 2000). JIP conducted design and testing of
composite production riser for 6000ft water depth. No field trial was conducted.
2. CompRiser JIP (circa 1997 2001) field trial on Heidrun TLP. Statoil has carried out successfully field
tests with one composite marine drilling riser joint on the Heidrun TLP platform (1300ft water depth and
4000psia). The field trial confirmed the ability of composite materials to withstand functional performance
requirements demanded from a medium-pressure marine drilling riser.
3. Composite Choke & Kill lines, various initiatives from 1987 through present. Limited field trials to date.
4. US-DoE Magnolia Production Riser JIP (circa 2002-2005). JIP conducted design and testing of composite
production riser for 4700ft water depth and 10,000psia. No field trial to date.
5. Composite Riser for High Pressure and Deep Water Applications (2005) joint effort between Shell,
General Dynamics, and Lincoln Composites to design, fabricate and proof of concept testing of a
drilling/completion riser suitable for 10,000ft water depth and 10,000 20,000 psi pressure capability.
6. Hoop wound pipes for risers and choke and kill line IFP concept.
Prior programs have addressed the fundamental issues of materials selection (reinforcing fiber type and
matrix material), fiber architecture (hoop, axial, and bias ratios), manufacturability, autofrettage, metal-
composite interface, and delivered requisite performance milestones (static, fatigue, thermal, and shock).
These programs have all culminated in qualification of the design and manufacturing methodology, through
both short and long-term laboratory testing verification.
However, most of the aforementioned programs did not progress beyond proof of concept testing in the
laboratory. Only one program has conducted field trials - a specific and unique titanium/composite
application of a low/medium pressure marine drilling riser rated for 1300ft water depth.
Through this RPSEA program, success of the planned field trials / demonstrations using a few riser joints will
facilitate the acceptance and deployment of composite riser joints throughout the entire riser string.
The logical next step will be to seek industry co-operation to deploy an entire riser string of composite joints,
for ultra deepwater drilling and completion.
OBJECTIVE:
To define the potential and gaps for developing a dry tree semi or similar to a feasible and competitive floater
solution for GOM in 8,000 ft water depth and moderate to large payloads. This study will explore use of
conventional technologies to the extent possible, such as hull form, riser hull interface, tensioning options,
riser configurations and riser materials. The study will explore tradeoffs such as:
Semi draft for possibility of quayside integration
Deep draft semi that allows use of standard tensioning technology (motions comparable to spar)
Topsides installation options such as quayside versus near-shore floatover versus offshore lift
The study will identify gaps and challenges associated with each option including equipment limitations,
fabrication, transportation, installation, well-bay layout and HSE considerations. The study is expected to
move the technology to TRL 3.
DELIVERABLES:
1. Design basis
2. Work shops and meetings with intermediate results presentation
3. Final report and presentation to DeepStar/RPSEA
Phase 2
1. Front end engineering for single concept
2. +/-15% cost estimate
3. Finalize qualification plans for new or extended technologies.
CONTRACTING PLAN:
Work will be awarded to a primary contractor with EPCI experience. Subcontracts for specific portions, e.g.,
model tests, will be handled by the prime contractor.
proposal).
OBJECTIVE:
Key XHPHT (extremely high pressure and high temperature) technology development in deepwater has
become increasingly demanding. For the high pressure drilling riser typically used with a surface BOP,
pressures are up to 22.5 ksi. Riser design methodology and fabrication capabilities for pipe structures,
connectors, flexible jumpers, plus global environmental load criteria have to be carefully re-thought. The CTR
intends to enhance the relevant technologies and develop a feasible, economical, and reliable system for the
XHPHT drilling riser. The following tasks have been identified:
DELIVERABLES:
- Final report, including new design methodology, code change recommendation, and case study;
- Design recommendation for high strength steel and titanium XHPHT riser;
- System design configuration for XHPHT drilling riser;
- Prototypes and test data
requirements. Also, perform testing to provide data to support the new methodologies and work with the
MMS and API to enhance GoM regulations and recommended practices (MMS, API).
Completion Date:
12/31/2008
VALUE:
The XHPHT drilling riser design will enable drilling for those XHPHT wells which are not feasible with current
X-80 steel risers.
CONTRACTING PLAN:
Use RPSEA's standard contracting procedures
BUSINESS INCENTIVE AND THEME (Why invest?): With drilling vessel day rates in the range $500k -
$800k, large down-time costs are incurred in high current areas as contractors and operators wait on weather
to run, retrieve or simply to proceed with connected drilling operations. Platform drilling operations incur
similar costs in high-current regions. In such cases, it is not sufficient to simply mitigate VIV with helical
strakes, which carry a drag penalty with them. Devices must be available that not only mitigate VIV, but also
reduce drag. Examples of such devices are (but are not limited to) fairings, tailfins and splitters. Some such
devices are already available, but little is publicly known about their hydrodynamic performance. In addition,
even if it can be shown that a VIV/drag reduction device performs well hydrodynamically, such a device may
be difficult and time-consuming to handle, store, run and retrieve and this can offset the savings offered by an
increased operability window. Further, any such devices must be structurally robust enough to handle the
forces of being run through the splash zone. Thus, significant cost savings could be gained by the industry
by developing a VIV/drag reduction device that not only acceptably meets key hydrodynamic performance
criteria, but is also structurally sound, compact as possible and quickly installable.
This CTR falls under the themes of Improved Design and Analysis Methods Riser VIV and Optimized Field
Development Concepts for Improved Economics Installation and could be considered enabling in situations
where high current would have otherwise prohibited drilling operations.
OBJECTIVE: Design a VIV mitigation device that also reduces drag that: (a) performs hydrodynamically; (b)
is structurally robust; (c) is lightweight and compact; (d) is easy to handle, store and install; (e) is resistant to
(or its performance is insensitive to) marine fouling.
DELIVERABLES: (a) A proven prototype design that is ready for mass production and implementation in the
field. (b) Installation, handling and storage procedures suitable for operations.
CONTRACTING PLAN: Scope of work would be submitted for competitive bidding and would ideally include
a multi-disciplinary team consisting of expertise from among drilling contractors, hydrodynamicists, VIV
mitigation manufacturers, structural/mechanical designers, material scientists.
9. Data analysis plan to process, analyze, document, and archive the data for storage and distribution.
Regular meetings will be held with DeepStar or JIP representatives for review & feedback. Consultations will
be held with VIV specialists and subcontractors providing specialty work to support the project. Phase 1
would seek to develop as complete a plan & budget as possible and make all major technical decisions
regarding the execution of the project in Phase 2.
Completion Date:
6 - 9 month from
initiation for Phase 1
VALUE:
Value of this project is predicated on the overall value of have a high quality data set that will allow calibration
and validation of accurate design tools for VIV design. DS/RPSEA sponsored a VIV Forum (2/07) to help
update the riser/VIV program. A high Re and high L/D test program was identified as a critical step in the
validation of VIV design methods and to guide project designers.
CONTRACTING PLAN:
Issue an RFP for this test program with Phase 1 industry funds provided by DS for the experimental design
and planning, with a milestone before going on to Phase2. The CTR has been formulated around a tow test,
ensuring access to controlled current profiles and a short test duration. However, alternative approaches will
be considered in response to the RFP. This could include a long term monitoring of a riser (SCR?) from a
fixed installation, or other scheme to achieve the same goal of better understanding the behavior of prototype
risers in an offshore environment. Due to the tailor nature of the design and likely transient availability of the
offshore equipment, Phase 2 would proceed as soon as DS/RPSEA approved the plan from Phase 1 and the
industrial funds are available for RPSEA 4:1 matching.
Ph1 $160k
RPSEA Matching Funds
Ph2 $6,400k
OBJECTIVE:
Validate floating system global analysis techniques and model testing verification for ultra-deep
water depths.
Improve design, predictive, and life-management tools for the hull global analysis, and analysis of
moorings and risers using full-scale measured data.
Develop hybrid systems using real-time, full-scale measurements combined with analytic tools to
monitor and predict remaining life of components.
DELIVERABLES:
Final Report including results, conclusions and recommendations from the validation and calibration of design
analysis methods/tools, and recommendations for establishing hybrid systems (real time full scale
measurements combined with analytic tools to monitor responses and predict remaining life, and results of
the comparisons between selected platforms.
VALUE:
Hurricanes Katrina and Rita caused storm loads on deepwater floating systems that were in excess of then
existent design conditions.
The Shell Mars deepwater production system, the largest producing system in the Gulf of Mexico, delivering
160,000 boe/d, was shut in for 9.5 months to repair damage from Hurricane Katrina. During that downtime,
crews of some 500 people per day participated in repair operations to bring Mars back on line.
Improvement of global analysis tools can result in improved operational reliability, reduced downtime, and the
associated deferred production.
CONTRACTING PLAN:
Use competitive bidding to select the best contractor.
Composite materials offer the attractive properties of light weight for high strength and stiffness, good
corrosion and excellent fatigue resistance that make them ideal candidates for use in deepwater. This
technology will benefit the offshore industry in terms of reducing topside riser payloads as well as installation
and handling loads that makes it both an enhancing and enabling technology for future deepwater
applications.
Composite carbon fiber tubes with a thermoplastic matrix are currently being developed within the frame of
the 3C-Partnership with Soficar, Freyssinet and Doris Engineering. Soficar has developed a special machine
to fabricate the composite thermoplastic tube as a continuous process, Freyssinet is responsible for the
design and fabrication of the end connectors that are fitted to the composite tube and DORIS Engineering is
responsible for the design of the tube itself. A 6" high performance composite tube has already been
designed and manufactured for pressures corresponding to a water depth of 3000 m, and the promising
results of the tests will be presented at OTC 2007.
To extend the range of tubes for future applications and further develop this technology, it is proposed to
fabricate and test a 3 tube with its connectors in a first phase, followed by a 10 tube for a specific
deepwater application in the second phase.
OBJECTIVE:
The main objective of this project is to bring composite thermoplastic tubes from the development phase to a
stage where a full size prototype section could be tested in the field for a real application. To reach this
objective, the program has been broken into two phases as follows:
PHASE I
Design and fabrication procedures for tube and connectors
- Design of 3" composite tube
- Verification of limiting fiber laying angles less than 25 and greater than 67
- Fabrication procedure, detailed engineering for tube and end terminations
PHASE II
Design and fabrication procedures for 10 composite tube:
- Design of 10 tube using previous conclusions for a specific application
- Fabrication procedure & detailed engineering for tube and end terminations
Fabrication of 10 composite tube (Total of 3No. 12 m sections)
Fabrication of end connections to fit to the tube (Total 6 No. terminations)
Tests: - Material test (Tomography, metrology)
- collapse tests with end caps
- tensile tests with connectors
- burst tests with connectors
Completion Date:
Phase I: Dec. 2008
Phase II: Dec. 2010
VALUE:
This project is aimed at bringing composite carbon thermoplastic tube technology into the offshore industry
for deepwater and ulta-deepwater applications. It represents an attractive alternative to existing steel tube
solutions because steel is heavy and sensitive to corrosion and fatigue. The fabrication process developed by
Soficar allows composite tubes to be manufactured in continuous lengths of 100m or more, reducing the
number of connections required and hence the overall cost and weight of a system.
The range of sizes proposed includes 3", 6" & 10" ID tubes and the possibility to design the tubes for a
range of different pressures and mechanical requirements will allow many different applications to be
considered in future deepwater and ultra deepwater developments, including lighter riser systems for floating
production platforms, drilling and well intervention units as well as hybrid riser tower solutions.
The value of lighter riser systems for floating UDW support structures is estimated to be several $100MM on
a single development
CONTRACTING PLAN:
This project follows a 6 year R&D program supported by the 3C-Partners, with the help of Total. For the
design and fabrication of the tubes and end connections this CTR is intended to be sole sourced. The testing
and analysis for a future application could be performed under RPSEA's standard contracting procedures.
RELATED PROGRAMS (Linked Projects, JIPs & partners):
This CTR is not related to any previous DeepStar project. This project will benefit from the 3C-Partnership
between SOFICAR, FREYSSINET and DORIS Engineering who have developed this technology over the
past 6 years with the support of the French CEP&M and TOTAL.
WHAT NEXT (Potential future work to advance/deploy technology)?
Upon completion of Phase I of this project, it is anticipated that the information provided will be sufficient to
confirm the technology could be used for an industrial application offshore. The 3" prototype created in
Phase I will also be used as basic knowledge for other applications.
At the end of Phase II it is anticipated that a full size prototype system could be installed in the field as a pilot
test.
Technology Readiness Level (TRL) for this project technology. TBD
Colleagues,
We would like to thank everyone for your interest in CTR 840OO VIV Analysis and
Modeling Program. In this brief note we would like to clarify some possible
misconceptions concerning the scope and emphasis of the CTR and encourage you to
support this DS/RPSEA program with a favorable vote. The two points that are probably
worth address are (a) the scope and (b) the funding strategy.
Work Scope
The CTR addresses the important analysis phase of DeepStars VIV experimental
program under CTR 8402. The high L/D experiments conducted off of Miami were
highly successful and revealed many new aspects associated with VIV and VIV
suppression. In order to reap the benefits of this effort, the data needs to be interpreted,
models upgraded or created and the resulting capabilities made available for use. We
have explicitly merged ideas from some other proposals. The following attempts to
clarify our primary Task objectives:
VIV Physics: where possible, additional high quality datasets from the 2006
Miami tests will be included to help expand the database and be made available to
the community of investigators pursuing VIV modeling approaches (see second
bullet). In addition, at least one operator would commit to making available full-
scale riser response data with current profiles to investigators for the purpose of
making substantial inroads toward quantifying the distinctions between model-
scale, single-tube test pipes and prototype-scale risers with ancillary equipment
and auxiliary lines. More operators would certainly be welcome to contribute
their full-scale data to the database.
VIV Modeling: numerous VIV models exist and/or are under development, both
empirical and CFD. Our aim is to be able to evaluate and possibly assist with their
optimization, e.g. parameter selection through system identification, stochastic
models for loading in suppressed regions, etc. This effort needs to be selective,
but is not linked to a single model or procedure. It is rather open to, and proposals
would be invited from, the community of VIV investigators who would like to
utilize the data to benchmark their analysis approach. We recognize that multiple
approaches to the analysis and prediction of VIV type behavior are needed.
One of the benefits of the leverage permitted by the RPSEA program is that we should be
able to take a broader look at models appropriate for the various stages of design and
analysis, thereby permitting a better understanding of the industrys capabilities and
assisting with upgrades.
In conclusion, we have adjusted the wording of the CTR to clarify the scope covering the
issue discussed above. We recommend support of the proposed DeepStar-RPSEA
program (CTR 840OO) and the active involvement in the CTR steering committee of
those interested in important topic.
If you have any suggestions or concerns, please feel free to contact us.
Michael Tognarelli
BP, Michael.Tognarelli@bp.com.
OBJECTIVE:
Using the high L/D data from the 7402/8402 offshore tests and operator-contributed full-scale measurements
as the primary datasets, the project will (a) develop a high quality case matrix suitable for software verification
and distribution, (b) characterize the responses to fully understand the VIV behaviors, (c) develop advanced
analysis techniques and models specific to VIV and customize tools for riser analysis, (d) develop guidelines
and user guidance.
DELIVERABLES:
Provide (a) benchmark datasets suitable for distribution to the community of investigators of VIV analysis
methods, (b) a detailed analysis report on high L/D VIV behavior based on the recent Deepstar tests, (c)
suitable progress reports and tutorial presentations ,(d) benchmark reports on existing and novel VIV
prediction tools, (e) next-generation VIV prediction tools
Completion Date:
~2 yrs for phase 1.
Multiyear program.
VALUE:
Data is of little value to deepwater operators unless the data is effectively vetted, extracted, compiled and
made available to the VIV community. The value of the high quality data obtained by DeepStar and others will
not be realized unless the data is analyzed in depth, repackaged and distributed to industry, software
developers and academics for easy and rapid use. As a key part of the vetting process, to the greatest extent
possible, model-scale data must be compared to full-scale measurements to gauge its reflection of reality.
This analysis phase (part 2) is therefore essential.
CONTRACTING PLAN:
This critical program should have the industry portion of the funds provided by DeepStar. Bidders should
include an option to subcontract with MIT to assist with data transfer and experiment interpretation, as
required. The primary datasets will be the DeepStar tests from Phase VII and VIII and full-scale data
contributed by BP. It may be possible to include additional, high quality datasets in the analysis. This could
significantly enhance the work and will be recognized in the bid evaluation.
OPB occurs when two interconnected links are forced to rotate with respect to one another. As alternating
chain links are orthogonal to one another, during this rotation one link will be in the plane of bending and the
other out of the plane of bending. The out of plane link having a low inertia against bending will be seeing
bending stresses leading to OPB fatigue.
SBM who supplied the Girassol buoy has been actively carrying out testing to better identify the OPB
phenomenon with a view to putting in place design procedures to safeguard chain mooring systems against
this type of failure. It is clear the phenomenon becomes more pronounced when mean tensions are increased
making deepwater systems the most vulnerable to these failures. Results of short-term tests performed in the
SBM laboratory have clearly demonstrated the fatigue mechanism. Some of this testing has been published
at several conferences and we attach the 2005 OTC paper on this subject.
The short-term testing and Finite Element Analyses (FEA) have been used to formulate a basic procedure,
which can be used to prevent OPB fatigue failures. These procedures are thought to give overly conservative
fatigue predictions. To improve this fatigue prediction long-term fatigue testing and further FEA is presently
ongoing at the SBM laboratory and offices to yield better procedures.
The OPB chain fatigue can place existing and future deepwater moorings at risk of failure. To identify existing
systems and prevent future systems from OPB risk, SBM proposes to carry out sufficient long-term test work
and FEA to put in place approved design practices for OPB.
Currently a group of sponsors have formed a JIP consisting of 6 oil companies, 6 contractors and 6
classification societies. Current funding totaling $775,000.
OBJECTIVE:
The main objectives of this work will be:
- To improve our knowledge regarding OPB of chain-links and validate, by further testing and
analysis, the OPB chain-link stress relationship implemented by SBM after the Girassol chain
failures.
- Generate S-N curves for chain links subjected to OPB.
DELIVERABLES:
The deliverable will be:
- Reports containing stress measurements and fatigue performance of 4 different chain sizes.
- Chain OPB stress relationships.
- S-N curves to be used for OPB fatigue calculation.
- Develop a specific test rig for fatigue test of large (up to 124 mm diameter) chain-links in OPB.
- S-N curve determination.
- Write API RP for OPB.
Completion Date:
36 months
VALUE:
The main value of this work will be to improve the safety of the deepwater mooring systems as a failure can
have major consequences regarding safety, environment and costs.
CONTRACTING PLAN:
Sole source CTR to SBM for project management, subcontractors SES for the testing and PRINCIPIA for the
FEA work.