For nuclear weapons storage facilities, all sentry booth or
gatehouse designs shall be in accordance with NAVFAC P-272~ NAVFAC Drawing 1404126, ~ Sectitv ~ sDe& we~ ~. The NAVFAC Definitive Drawing is considered the minimum design and construction criteria for such facilities and are mandatory for facility certification.
4.3.1 A sentry booth or gatehouse will be provided for all
entrance gates that are manned by security personnel on a full or part-time basis. They should be located as close as possible to entry gates to permit personnel inside the booth or gatehouse to maintain constant surveillance over the entrance and approaches. In addition, site layout should allow for vehicle inspections or search without causing undue traffic backups. Figure 20 depicts an ideal entry control point, locations, and roadway clearances. Explosives safety criteria contained in NAVSEA OP 5, Volume 1, Ammunit~ E>:~losives Ash ore, Safetv Reau&@ ens for ~a. Storin~ ProducG J@nova tion, and Shirmin- must be considered in siting sentry booths and gatehouses at explosive component storage areas.
The entry control facility for nuclear weapons storage facilities
is part of the perimeter security system and is the point from which personnel and vehicle control, and badge exchange operations are conducted. The personnel entry gate and access route shall be arranged and constructed to ensure that personnel pass the entry controller or badge exchange point and enter the area singly under the positive cont~ol of the security force (remotely operated gate, door, or turnstile controlled from within the gate house). See Figure 21 for a typical entry control facility for special weapons storage facility.
4.3.2 ~. As previously discussed, a thorough site
analysis and review of operational requixernents for the area involved must be accomplished prior to initiating design of sentry booths or gatehouses. NAVFAC P-80, ~V ~ provides general spacing criteria and should be followed when designing sentry booths and gatehouses for other facilities. A typical site-built gatehouse is shown in Figure 31. Some basic considerations are provided in the following subparagraphs to assist the designer.
4.3,2.1 $tmcture Size. When determining structure size consider the
number of personnel that will be assigned duzing normal operations, and the electronic and electrical equipment (e.g., communications equipment and gate controls) requirements. The mechanical support equipment (HYAC), storage space, and space provided for such equipment in addition to security personnel space allocations should also be determined. The surface area of any required counter or work space must be added to the overall floor space requirements for the structure.